20
SEMS Auditing: An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham Philip Emanuel, Lead Auditor Michelle Duncan, Lead Auditor September 11, 2013

SEMS Auditing: An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

  • Upload
    thad

  • View
    39

  • Download
    1

Embed Size (px)

DESCRIPTION

SEMS Auditing: An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham Philip Emanuel, Lead Auditor Michelle Duncan, Lead Auditor. September 11, 2013. About M&H. M&H Established in 1978 More than 250 engineering and technical professionals - PowerPoint PPT Presentation

Citation preview

Page 1: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

SEMS Auditing: An I3P Auditor’s PerspectiveSummary/Analysis of Findings To Date

Kevin Graham

Philip Emanuel, Lead Auditor

Michelle Duncan, Lead AuditorSeptember 11, 2013

Page 2: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

│2│

About M&H

M&H• Established in 1978

• More than 250 engineering and technical professionals

• Offices in Houston and Lafayette

• First I3P to conduct SEMS audit (Directed)

• More than 2 dozen SEMS audits completed or in process

Our Services

• Regulatory Compliance

• Project Management

• Design Engineering

• Information Technology

• Maintenance Management

• Technical Documentation

Page 3: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Our Approach to SEMS Auditing

│3│

M&H Presentation Photo Caption

Three types of Audits1. Commissioned Contractor Audits

2. Gap Analysis

• No Audit Plan, Final Report, or CAP submitted to BSEE

3. Formal I3P Audit

Based on COS SEMS Audit Protocol• Some items reorganized into separate questions

• Placeholder for Operator-specific requirements not required by Subpart S or API RP75

Page 4: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Three Phases (Gap Analysis/I3P)

Phase I:

• Corporate-level documentation; program documents/procedures

• Conducted at M&H offices

Phase II:

• Program implementation

• Conducted at Operator’s corporate office/shorebase location

Phase III:

• Program implementation (facility-specific)

• Site visit to each facility identified in Audit Plan

Page 5: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Number of Protocol Requirements by Element/Phase

No of Requirements (Full Protocol)

Element Phase I Phase II Phase III Total Percent

1 - General 33 16 0 49 11.92%

2 - Safety and Environmental 9 21 0 30 7.30%

3 - Hazard Analysis 5 25 6 36 8.76%

4 - Management of Change 17 5 0 22 5.35%

5 - Operating Procedures 23 3 2 28 6.81%

6 - Safe Work Practices 21 16 7 44 10.71%

7 - Training 12 18 1 31 7.54%

8 - Assurance of Quality and Mechanical Integrity 34 4 6 44 10.71%

9 - Pre-Startup Review 8 0 0 8 1.95%

10 - Emergency Response and Control 4 15 0 19 4.62%

11 - Investigation of Incidents 3 10 0 13 3.16%

12 - Audit of SEMS Program Elements 27 40 0 67 16.30%

13 - Records and Documentation 2 15 1 18 4.38%

NA - Operator-Specific 1 0 1 2 0.49%

Total 199 188 24 411 100.00%

Percent 48.42% 45.74% 5.84% 100.00%  

Page 6: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Number of Protocol Requirements by Element

Page 7: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Number of Protocol Requirements by Element/Phase

Page 8: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Our Sample (Data Set)

16 Separate Audits• Includes Gap Analysis and/or Formal I3P Audits

• Gap Analysis Audits: 4• 2 of these subsequently accepted by BSEE as

meeting formal audit requirements• I3P Audits: 12

• 3 of these were BSEE-Directed• 1 of these utilized an Operator-defined protocol (not

the COS Protocol)• 1 of these included only Phase I and II• Included both production and drilling (where

appropriate)

Page 9: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

No of Findings (Deficiencies) by Element/Phase

No of Requirements where Findings Occurred

Phase I Phase II Phase III Total Percent

1 - General 17 5 0 22 11.89%

2 - Safety and Environmental 6 2 0 8 4.32%

3 - Hazard Analysis 2 12 2 16 8.65%

4 - Management of Change 13 4 0 17 9.19%

5 - Operating Procedures 21 1 1 23 12.43%

6 - Safe Work Practices 15 1 6 22 11.89%

7 - Training 10 8 0 18 9.73%

8 - Assurance of Quality and Mechanical Integrity 13 2 6 21 11.35%

9 - Pre-Startup Review 2 0 0 2 1.08%

10 - Emergency Response and Control 1 4 0 5 2.70%

11 - Investigation of Incidents 3 1 0 4 2.16%

12 - Audit of SEMS Program Elements 16 5 0 21 11.35%

13 - Records and Documentation 2 1 1 4 2.16%

NA - Operator-Specific 1 0 1 2 1.08%

Total 122 46 17 185 100.00%

Percent 65.95% 24.86% 9.19% 100.00%  

Page 10: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

No of Findings (Deficiencies) by Element/Phase

Page 11: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

No of Findings (Deficiencies) by Element/Phase

Page 12: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

No of Findings (Deficiencies) by Element/Phase

Page 13: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Occurrence of Findings by Phase/Element – Difficulty Ranking

Rate at Which Findings Occurred Element/Phase Difficulty (Findings) RankingPhase I Phase II Phase III Total PH I Rank PHII Rank PHIII Rank Overall Rank

1 - General 51.52% 31.25% NA 44.90%

9 6 NA

6

2 - Safety and Environmental 66.67% 9.52% NA 26.67%

7 10 NA

10

3 - Hazard Analysis 40.00% 48.00% 33.33% 44.44%

10 3 5

7

4 - Management of Change 76.47% 80.00% NA 77.27%

5 1 NA

2

5 - Operating Procedures 91.30% 33.33% 50.00% 82.14%

3 5 4

1

6 - Safe Work Practices 71.43% 6.25% 85.71% 50.00%

6 12 3

4

7 - Training 83.33% 44.44% 0.00% 58.06%

4 4 6

3

8 - Assurance of Quality and Mechanical Integrity 38.24% 50.00% 100.00% 47.73%

11 2 1

5

9 - Pre-Startup Review 25.00% NA NA 25.00%

12 13 NA

12

10 - Emergency Response and Control 25.00% 26.67% NA 26.32%

12 7 NA

11

11 - Investigation of Incidents 100.00% 10.00% NA 30.77%

1 9 NA

9

12 - Audit of SEMS Program Elements 59.26% 12.50% NA 31.34%

8 8 NA

8

13 - Records and Documentation 100.00% 6.67% 100.00% 22.22%

1 11 1

13

NA - Operator-Specific 100.00% NA 100.00% 100.00%        

Page 14: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Element 5 - Operating Procedures:Most Common Deficiencies

1. Failure to adequately address:

a. “Simultaneous Operations”

b. “Temporary Operations”

c. “Any lease or concession stipulations established by recognized governmental authority”

d. “Continuous and periodic discharge of hydrocarbon materials, contaminants, or undesired by-products into the environment is restricted by governmental limitations”

e. “Raw materials used in operations and the quality control procedures used in purchasing these raw materials”

2. Consideration of human factors associated with format, content, and intended use of operating procedures

3. Failure to include job title and reporting relationship of the person(s) responsible for each of the facility’s operating areas

4. Failure to consistently implement operating procedures

Page 15: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Element 4 - Management of Change:Most Common Deficiencies

1. MOC procedures fail to address:

a. Duration of the change, if temporary

b. Necessary time period to implement changes

c. Communication of the proposed change and the consequences of that change to appropriate personnel

2. Employees not adequately informed of the change prior to startup of the process or affected part of operation

3. Employees not trained in the change prior to startup of the process of affected part of operation

4. Where MOC results in a change in operating procedures, such changes not documented/dated

Page 16: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Element 7 - Training:Most Common Deficiencies

1. Refresher training not provided to maintain understanding of and adherence to current operating procedures

2. Failure to develop procedures for evaluating whether personnel possess the required knowledge and skills to carry out their duties and responsibilities, including startup and shutdown

3. Failure to develop and implement qualification criteria for operating and maintenance personnel

4. Failure of training program to address operating procedures

Page 17: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Element 6- Safe Work Practices:Most Common Deficiencies

1. Failure to consider human factors in development of safe work practices

2. No work authorization or “permit-to-work” system implemented for tasks involving lockout and tagout of electrical and mechanical energy sources

3. Failure to include provisions in permit-to-work system for adequate communication of work activities to shift changes and replacement personnel

4. Failure to include contractors in permit-to-work communications

5. Failure to develop and implement safe work practices to control the presence, entrance, and exit of contract employees in operation areas.

Page 18: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

Element 8- Assurance of Quality/Mechanical Integrity:Most Common Deficiencies

1. Failure to document for each inspection/test performed of equipment/systems:

a. Name, position, and signature of the person who performed the inspection/test

b. Date of inspection/test

2. Failure of Mechanical Integrity procedures to address modification of existing equipment and systems and failure to ensure that procedures are modified for the application for which they will be used

3. Failure of testing, inspection, calibration, and monitoring programs for critical equipment to include:

a. Documentation of completed testing and inspection

i. Pressure vessel testing/inspection documentation not maintained for life of equipment

ii. All other documentation not retained for a minimum of 2 years or as needed

b. Appropriate auditing procedures to ensure compliance with the program

Page 19: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

General Notes and Other Observations

• Most common findings in “other” elements

a. Failure to analyze/critique emergency response drills for the purpose of identifying and correcting weaknesses (Element 10 – Emergency Response)

b. Failure of the supervisor of the person in charge of the task to approve the JSA prior to commencement of the work (Element 3 – Hazards Analysis)

• Management commitment/involvement led to fewer findings

• Key variable in determining time/cost required to conduct audit has been quality of “Document/Records Management System” – not size of Operator company or number of facilities.

Page 20: SEMS Auditing:  An I3P Auditor’s Perspective Summary/Analysis of Findings To Date Kevin Graham

General Notes and Other Observations

• The more robust the MOC program/process, the fewer program deficiencies

• Level of BSEE involvement/participation in audits has varied

• Competing mindsets: Is this about compliance? Or is this about management systems?

• No clear definition/approach yet in verifying knowledge/skills

• Greater focus on the “E” in SEMS is coming