ID Task Name Duration Start Finish Predecessors 0 Basement Apartemen One East Surabaya 395 days Wed 29/04/15 Tue 01/11/16 1 Pekerjaan Soldier Pile 177 days Wed 29/04/15 Thu 31/12/15 3 Tiang Bentonite 71 days Wed 29/04/15 Wed 05/08/15 4 Pengeboran 22 days Wed 29/04/15 Thu 28/05/15 5 Pengecoran 71 days Wed 29/04/15 Wed 05/08/15 4FF+0.33 days 6 Tiang Beton Bertulang 111 days Wed 29/04/15 Wed 30/09/15 7 Pengeboran 22 days Thu 09/07/15 Fri 07/08/15 5FF+2 days 8 Pembesian 111 days Wed 29/04/15 Wed 30/09/15 4SS 9 Pengecoran 109 days Wed 29/04/15 Mon 28/09/15 7FF+0.33 days 11 Tiang Bentonite 90 days Wed 29/04/15 Tue 01/09/15 12 Pengeboran 28 days Wed 29/04/15 Fri 05/06/15 4SS 13 Pengecoran 90 days Wed 29/04/15 Tue 01/09/15 12FF+0.3 days 14 Tiang Beton Bertulang 177 days Wed 29/04/15 Thu 31/12/15 15 Pengeboran 28 days Tue 28/07/15 Thu 03/09/15 13FF+2 days 16 Pembesian 177 days Wed 29/04/15 Thu 31/12/15 4SS 17 Pengecoran 141 days Wed 29/04/15 Wed 11/11/15 15FF+0.33 days 18 Pekerjaan Capping Beam 8 days Fri 01/01/16 Tue 12/01/16 22 Pekerjaan Bored Pile 361.67 da... Mon 15/06/15 Tue 01/11/16 24 Pengeboran 41 days Fri 04/09/15 Fri 30/10/15 15 25 Pembesian 218 days Fri 01/01/16 Tue 01/11/16 16 26 Pengecoran 100 days Mon 15/06/15 Mon 02/11/15 24FF+0.33 days 28 Pengeboran 34 days Fri 04/09/15 Wed 21/10/15 15 29 Pembesian 184 days Fri 01/01/16 Wed 14/09/16 16 30 Pengecoran 82 days Tue 30/06/15 Thu 22/10/15 28FF+0.33 days 31 Galian Basement 51 days Thu 22/10/15 Fri 01/01/16 H2 H1 H2 H1 H2 H1 2015 2016 2017 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 1 Project: Basement Apartemen On Date: Thu 30/04/15

Sequencing 1

Embed Size (px)

DESCRIPTION

sequencing basement

Citation preview

  • ID Task Name Duration Start Finish Predecessors

    0 Basement Apartemen One East Surabaya

    395 days Wed 29/04/15

    Tue 01/11/16

    1 Pekerjaan Soldier Pile 177 days Wed 29/04/15 Thu 31/12/153 Tiang Bentonite 71 days Wed 29/04/15 Wed 05/08/154 Pengeboran 22 days Wed 29/04/15 Thu 28/05/155 Pengecoran 71 days Wed 29/04/15 Wed 05/08/15 4FF+0.33 days6 Tiang Beton Bertulang 111 days Wed 29/04/15 Wed 30/09/157 Pengeboran 22 days Thu 09/07/15 Fri 07/08/15 5FF+2 days8 Pembesian 111 days Wed 29/04/15 Wed 30/09/15 4SS9 Pengecoran 109 days Wed 29/04/15 Mon 28/09/15 7FF+0.33 days

    11 Tiang Bentonite 90 days Wed 29/04/15 Tue 01/09/1512 Pengeboran 28 days Wed 29/04/15 Fri 05/06/15 4SS13 Pengecoran 90 days Wed 29/04/15 Tue 01/09/15 12FF+0.3 days14 Tiang Beton Bertulang 177 days Wed 29/04/15 Thu 31/12/1515 Pengeboran 28 days Tue 28/07/15 Thu 03/09/15 13FF+2 days16 Pembesian 177 days Wed 29/04/15 Thu 31/12/15 4SS17 Pengecoran 141 days Wed 29/04/15 Wed 11/11/15 15FF+0.33 days18 Pekerjaan Capping Beam 8 days Fri 01/01/16 Tue 12/01/1622 Pekerjaan Bored Pile 361.67 da... Mon 15/06/15 Tue 01/11/1624 Pengeboran 41 days Fri 04/09/15 Fri 30/10/15 1525 Pembesian 218 days Fri 01/01/16 Tue 01/11/16 1626 Pengecoran 100 days Mon 15/06/15 Mon 02/11/15 24FF+0.33 days28 Pengeboran 34 days Fri 04/09/15 Wed 21/10/15 1529 Pembesian 184 days Fri 01/01/16 Wed 14/09/16 1630 Pengecoran 82 days Tue 30/06/15 Thu 22/10/15 28FF+0.33 days31 Galian Basement 51 days Thu 22/10/15 Fri 01/01/16

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 1

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    33 Zona A 20 days Thu 22/10/15 Thu 19/11/1535 Zona B 22 days Thu 22/10/15 Mon 23/11/1539 Zona A 15 days Mon 23/11/15 Mon 14/12/1541 Zona B 17 days Mon 23/11/15 Wed 16/12/1545 Zona A 5 days Wed 16/12/15 Wed 23/12/1547 Zona B 12 days Wed 16/12/15 Fri 01/01/1649 Pekerjaan Pile Cap 19 days Wed 23/12/15 Tue 19/01/1651 Pekerjaan Lantai Kerja 1 day Wed 23/12/15 Thu 24/12/15 4652 Pembesian 6 days Wed 23/12/15 Thu 31/12/15 4653 Bekisting 2 days Thu 31/12/15 Mon 04/01/16 5254 Pengecoran 1 day Mon 04/01/16 Tue 05/01/16 5356 Pekerjaan Lantai Kerja 1 day Thu 31/12/15 Fri 01/01/16 5257 Pembesian 6 days Thu 31/12/15 Fri 08/01/16 5258 Bekisting 2 days Fri 08/01/16 Tue 12/01/16 5759 Pengecoran 1 day Tue 12/01/16 Wed 13/01/16 5861 Pekerjaan Lantai Kerja 1 day Fri 01/01/16 Mon 04/01/16 5662 Pembesian 6 days Fri 01/01/16 Mon 11/01/16 5663 Bekisting 2 days Mon 11/01/16 Wed 13/01/16 6264 Pengecoran 1 day Wed 13/01/16 Thu 14/01/16 6366 Pekerjaan Lantai Kerja 1 day Mon 04/01/16 Tue 05/01/16 6167 Pembesian 6 days Mon 04/01/16 Tue 12/01/16 6168 Bekisting 2 days Tue 12/01/16 Thu 14/01/16 6769 Pengecoran 1 day Thu 14/01/16 Fri 15/01/16 6871 Pekerjaan Lantai Kerja 1 day Tue 05/01/16 Wed 06/01/16 6672 Pembesian 6 days Tue 05/01/16 Wed 13/01/16 6673 Bekisting 2 days Wed 13/01/16 Fri 15/01/16 72

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 2

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    74 Pengecoran 1 day Fri 15/01/16 Mon 18/01/16 7376 Pekerjaan Lantai Kerja 1 day Wed 06/01/16 Thu 07/01/16 7177 Pembesian 6 days Wed 06/01/16 Thu 14/01/16 7178 Bekisting 2 days Thu 14/01/16 Mon 18/01/16 7779 Pengecoran 1 day Mon 18/01/16 Tue 19/01/16 7880 Pekerjaan Raft Foundation 15 days Thu 07/01/16 Thu 28/01/1685 Pekerjaan Pelat Lantai Dasar Basement 34 days Fri 08/01/16 Thu 25/02/1687 Pekerjaan Lantai Kerja 1 day Fri 08/01/16 Mon 11/01/16 8188 Pembesian Kolom 2 days Mon 11/01/16 Wed 13/01/16 8789 Pemasangan Bekisting 1 day Wed 13/01/16 Thu 14/01/16 8890 Cor kolom 1 day Thu 14/01/16 Fri 15/01/16 8991 Pembesian Slab 4 days Wed 13/01/16 Tue 19/01/16 8892 Pembesian Dinding 2 days Tue 19/01/16 Thu 21/01/16 9193 Pemasangan Bekisting Slab 1 day Tue 19/01/16 Wed 20/01/16 9194 Cor Slab 1 day Wed 20/01/16 Thu 21/01/16 9395 Pemasangan Bekisting Dinding 1 day Thu 21/01/16 Fri 22/01/16 9296 Cor Dinding 1 day Fri 22/01/16 Mon 25/01/16 9598 Pekerjaan Lantai Kerja 1 day Thu 21/01/16 Fri 22/01/16 9499 Pembesian Kolom 2 days Thu 21/01/16 Mon 25/01/16 92

    100 Pemasangan Bekisting 1 day Mon 25/01/16 Tue 26/01/16 99101 Cor kolom 1 day Tue 26/01/16 Wed 27/01/16 100102 Pembesian Slab 4 days Mon 25/01/16 Fri 29/01/16 99103 Pembesian Dinding 2 days Fri 29/01/16 Tue 02/02/16 102104 Pemasangan Bekisting Slab 1 day Fri 29/01/16 Mon 01/02/16 102105 Cor Slab 1 day Mon 01/02/16 Tue 02/02/16 104106 Pemasangan Bekisting Dinding 1 day Tue 02/02/16 Wed 03/02/16 103

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 3

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    107 Cor Dinding 1 day Wed 03/02/16 Thu 04/02/16 106109 Pekerjaan Lantai Kerja 1 day Tue 02/02/16 Wed 03/02/16 105110 Pembesian Kolom 2 days Tue 02/02/16 Thu 04/02/16 103111 Pemasangan Bekisting 1 day Thu 04/02/16 Fri 05/02/16 110112 Cor kolom 1 day Fri 05/02/16 Mon 08/02/16 111113 Pembesian Slab 4 days Thu 04/02/16 Wed 10/02/16 110114 Pembesian Dinding 2 days Wed 10/02/16 Fri 12/02/16 113115 Pemasangan Bekisting Slab 1 day Wed 10/02/16 Thu 11/02/16 113116 Cor Slab 1 day Thu 11/02/16 Fri 12/02/16 115117 Pemasangan Bekisting Dinding 1 day Fri 12/02/16 Mon 15/02/16 114118 Cor Dinding 1 day Mon 15/02/16 Tue 16/02/16 117120 Pekerjaan Lantai Kerja 1 day Fri 12/02/16 Mon 15/02/16 116121 Pembesian Kolom 2 days Mon 15/02/16 Wed 17/02/16 120122 Pemasangan Bekisting 1 day Wed 17/02/16 Thu 18/02/16 121123 Cor kolom 1 day Thu 18/02/16 Fri 19/02/16 122124 Pembesian Slab 4 days Wed 17/02/16 Tue 23/02/16 121125 Pembesian Dinding 2 days Wed 17/02/16 Fri 19/02/16 121126 Pemasangan Bekisting Slab 1 day Tue 23/02/16 Wed 24/02/16 124127 Cor Slab 1 day Wed 24/02/16 Thu 25/02/16 126128 Pemasangan Bekisting Dinding 1 day Fri 19/02/16 Mon 22/02/16 125129 Cor Dinding 1 day Mon 22/02/16 Tue 23/02/16 128130 Pekejan Lantai 3A 37 days Thu 25/02/16 Mon 18/04/16132 Pekerjaan Lantai Kerja 1 day Thu 25/02/16 Fri 26/02/16 127133 Pembesian Kolom 2 days Fri 26/02/16 Tue 01/03/16 132134 Pemasangan Bekisting 1 day Tue 01/03/16 Wed 02/03/16 133135 Cor kolom 1 day Wed 02/03/16 Thu 03/03/16 134

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 4

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    136 Pembesian Slab 4 days Tue 01/03/16 Mon 07/03/16 133137 Pembesian Dinding 2 days Mon 07/03/16 Wed 09/03/16 136138 Pemasangan Bekisting Slab 1 day Mon 07/03/16 Tue 08/03/16 136139 Cor Slab 1 day Tue 08/03/16 Wed 09/03/16 138140 Pemasangan Bekisting Dinding 1 day Wed 09/03/16 Thu 10/03/16 137141 Cor Dinding 1 day Thu 10/03/16 Fri 11/03/16 140143 Pekerjaan Lantai Kerja 1 day Wed 09/03/16 Thu 10/03/16 139144 Pembesian Kolom 2 days Thu 10/03/16 Mon 14/03/16 143145 Pemasangan Bekisting 1 day Mon 14/03/16 Tue 15/03/16 144146 Cor kolom 1 day Tue 15/03/16 Wed 16/03/16 145147 Pembesian Slab 4 days Tue 15/03/16 Mon 21/03/16 145148 Pembesian Dinding 2 days Mon 21/03/16 Wed 23/03/16 147149 Pemasangan Bekisting Slab 1 day Mon 21/03/16 Tue 22/03/16 147150 Cor Slab 1 day Tue 22/03/16 Wed 23/03/16 149151 Pemasangan Bekisting Dinding 1 day Tue 22/03/16 Wed 23/03/16 149152 Cor Dinding 1 day Wed 23/03/16 Thu 24/03/16 151154 Pekerjaan Lantai Kerja 1 day Wed 23/03/16 Thu 24/03/16 150155 Pembesian Kolom 2 days Thu 24/03/16 Mon 28/03/16 154156 Pemasangan Bekisting 1 day Mon 28/03/16 Tue 29/03/16 155157 Cor kolom 1 day Tue 29/03/16 Wed 30/03/16 156158 Pembesian Slab 4 days Mon 28/03/16 Fri 01/04/16 155159 Pembesian Dinding 2 days Mon 28/03/16 Wed 30/03/16 155160 Pemasangan Bekisting Slab 1 day Fri 01/04/16 Mon 04/04/16 158161 Cor Slab 1 day Mon 04/04/16 Tue 05/04/16 160162 Pemasangan Bekisting Dinding 1 day Wed 30/03/16 Thu 31/03/16 159163 Cor Dinding 1 day Thu 31/03/16 Fri 01/04/16 162

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 5

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    165 Pekerjaan Lantai Kerja 1 day Tue 05/04/16 Wed 06/04/16 161166 Pembesian Kolom 2 days Wed 06/04/16 Fri 08/04/16 165167 Pemasangan Bekisting 1 day Fri 08/04/16 Mon 11/04/16 166168 Cor kolom 1 day Mon 11/04/16 Tue 12/04/16 167169 Pembesian Slab 4 days Fri 08/04/16 Thu 14/04/16 166170 Pembesian Dinding 2 days Fri 08/04/16 Tue 12/04/16 166171 Pemasangan Bekisting Slab 1 day Thu 14/04/16 Fri 15/04/16 169172 Cor Slab 1 day Fri 15/04/16 Mon 18/04/16 171173 Pemasangan Bekisting Dinding 1 day Tue 12/04/16 Wed 13/04/16 170174 Cor Dinding 1 day Wed 13/04/16 Thu 14/04/16 173175 Pekerjaan Lantai 2 25 days Tue 12/04/16 Tue 17/05/16177 Pembesian Kolom 2 days Tue 12/04/16 Thu 14/04/16 170178 Pemasangan Bekisting Kolom 1 day Thu 14/04/16 Fri 15/04/16 177179 Cor Kolom 1 day Fri 15/04/16 Mon 18/04/16 178180 Pembesian Slab 4 days Thu 14/04/16 Wed 20/04/16 177181 Pembesian Dinding 2 days Thu 14/04/16 Mon 18/04/16 177182 Pemasangan Bekisting Slab 2 days Wed 20/04/16 Fri 22/04/16 180183 Cor Slab 1 day Fri 22/04/16 Mon 25/04/16 182184 Pemasangan Bekisting Dinding 1 day Mon 18/04/16 Tue 19/04/16 181185 Cor Dinding 1 day Tue 19/04/16 Wed 20/04/16 184187 Pembesian Kolom 2 days Mon 18/04/16 Wed 20/04/16 181188 Pemasangan Bekisting Kolom 1 day Wed 20/04/16 Thu 21/04/16 187189 Cor Kolom 1 day Thu 21/04/16 Fri 22/04/16 188190 Pembesian Slab 4 days Wed 20/04/16 Tue 26/04/16 187191 Pembesian Dinding 2 days Wed 20/04/16 Fri 22/04/16 187192 Pemasangan Bekisting Slab 2 days Tue 26/04/16 Thu 28/04/16 190

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 6

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    193 Cor Slab 1 day Thu 28/04/16 Fri 29/04/16 192194 Pemasangan Bekisting Dinding 1 day Fri 22/04/16 Mon 25/04/16 191195 Cor Dinding 1 day Mon 25/04/16 Tue 26/04/16 194197 Pembesian Kolom 2 days Thu 28/04/16 Mon 02/05/16 192198 Pemasangan Bekisting Kolom 1 day Mon 02/05/16 Tue 03/05/16 197199 Cor Kolom 1 day Tue 03/05/16 Wed 04/05/16 198200 Pembesian Slab 4 days Mon 02/05/16 Fri 06/05/16 197201 Pembesian Dinding 2 days Mon 02/05/16 Wed 04/05/16 197202 Pemasangan Bekisting Slab 2 days Fri 06/05/16 Tue 10/05/16 200203 Cor Slab 1 day Tue 10/05/16 Wed 11/05/16 202204 Pemasangan Bekisting Dinding 1 day Wed 04/05/16 Thu 05/05/16 201205 Cor Dinding 1 day Thu 05/05/16 Fri 06/05/16 204207 Pembesian Kolom 2 days Wed 04/05/16 Fri 06/05/16 201208 Pemasangan Bekisting Kolom 1 day Fri 06/05/16 Mon 09/05/16 207209 Cor Kolom 1 day Mon 09/05/16 Tue 10/05/16 208210 Pembesian Slab 4 days Fri 06/05/16 Thu 12/05/16 207211 Pembesian Dinding 2 days Fri 06/05/16 Tue 10/05/16 207212 Pemasangan Bekisting Slab 2 days Thu 12/05/16 Mon 16/05/16 210213 Cor Slab 1 day Mon 16/05/16 Tue 17/05/16 212214 Pemasangan Bekisting Dinding 1 day Tue 10/05/16 Wed 11/05/16 211215 Cor Dinding 1 day Wed 11/05/16 Thu 12/05/16 214216 Pekerjaan Lantai 2A 21 days Tue 10/05/16 Wed 08/06/16218 Pembesian Kolom 2 days Tue 10/05/16 Thu 12/05/16 211219 Pemasangan Bekisting Kolom 1 day Thu 12/05/16 Fri 13/05/16 218220 Cor Kolom 1 day Fri 13/05/16 Mon 16/05/16 219221 Pembesian Slab 4 days Thu 12/05/16 Wed 18/05/16 218

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 7

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    222 Pembesian Dinding 2 days Thu 12/05/16 Mon 16/05/16 218223 Pemasangan Bekisting Slab 2 days Wed 18/05/16 Fri 20/05/16 221224 Cor Slab 1 day Fri 20/05/16 Mon 23/05/16 223225 Pemasangan Bekisting Dinding 1 day Mon 16/05/16 Tue 17/05/16 222226 Cor Dinding 1 day Tue 17/05/16 Wed 18/05/16 225228 Pembesian Kolom 2 days Mon 16/05/16 Wed 18/05/16 222229 Pemasangan Bekisting Kolom 1 day Wed 18/05/16 Thu 19/05/16 228230 Cor Kolom 1 day Thu 19/05/16 Fri 20/05/16 229231 Pembesian Slab 4 days Wed 18/05/16 Tue 24/05/16 228232 Pembesian Dinding 2 days Wed 18/05/16 Fri 20/05/16 228233 Pemasangan Bekisting Slab 2 days Tue 24/05/16 Thu 26/05/16 231234 Cor Slab 1 day Thu 26/05/16 Fri 27/05/16 233235 Pemasangan Bekisting Dinding 1 day Fri 20/05/16 Mon 23/05/16 232236 Cor Dinding 1 day Mon 23/05/16 Tue 24/05/16 235238 Pembesian Kolom 2 days Fri 20/05/16 Tue 24/05/16 232239 Pemasangan Bekisting Kolom 1 day Tue 24/05/16 Wed 25/05/16 238240 Cor Kolom 1 day Wed 25/05/16 Thu 26/05/16 239241 Pembesian Slab 4 days Tue 24/05/16 Mon 30/05/16 238242 Pembesian Dinding 2 days Tue 24/05/16 Thu 26/05/16 238243 Pemasangan Bekisting Slab 2 days Mon 30/05/16 Wed 01/06/16 241244 Cor Slab 1 day Wed 01/06/16 Thu 02/06/16 243245 Pemasangan Bekisting Dinding 1 day Thu 26/05/16 Fri 27/05/16 242246 Cor Dinding 1 day Fri 27/05/16 Mon 30/05/16 245248 Pembesian Kolom 2 days Thu 26/05/16 Mon 30/05/16 242249 Pemasangan Bekisting Kolom 1 day Mon 30/05/16 Tue 31/05/16 248250 Cor Kolom 1 day Tue 31/05/16 Wed 01/06/16 249

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 8

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    251 Pembesian Slab 4 days Mon 30/05/16 Fri 03/06/16 248252 Pembesian Dinding 2 days Mon 30/05/16 Wed 01/06/16 248253 Pemasangan Bekisting Slab 2 days Fri 03/06/16 Tue 07/06/16 251254 Cor Slab 1 day Tue 07/06/16 Wed 08/06/16 253255 Pemasangan Bekisting Dinding 1 day Wed 01/06/16 Thu 02/06/16 252256 Cor Dinding 1 day Thu 02/06/16 Fri 03/06/16 255257 Pekerjaan Lantai 1 21 days Wed 01/06/16 Thu 30/06/16259 Pembesian Kolom 2 days Wed 01/06/16 Fri 03/06/16 252260 Pemasangan Bekisting Kolom 1 day Fri 03/06/16 Mon 06/06/16 259261 Cor Kolom 1 day Mon 06/06/16 Tue 07/06/16 260262 Pembesian Slab 4 days Fri 03/06/16 Thu 09/06/16 259263 Pembesian Dinding 2 days Fri 03/06/16 Tue 07/06/16 259264 Pemasangan Bekisting Slab 2 days Thu 09/06/16 Mon 13/06/16 262265 Cor Slab 1 day Mon 13/06/16 Tue 14/06/16 264266 Pemasangan Bekisting Dinding 1 day Tue 07/06/16 Wed 08/06/16 263267 Cor Dinding 1 day Wed 08/06/16 Thu 09/06/16 266269 Pembesian Kolom 2 days Tue 07/06/16 Thu 09/06/16 263270 Pemasangan Bekisting Kolom 1 day Thu 09/06/16 Fri 10/06/16 269271 Cor Kolom 1 day Fri 10/06/16 Mon 13/06/16 270272 Pembesian Slab 4 days Thu 09/06/16 Wed 15/06/16 269273 Pembesian Dinding 2 days Thu 09/06/16 Mon 13/06/16 269274 Pemasangan Bekisting Slab 2 days Wed 15/06/16 Fri 17/06/16 272275 Cor Slab 1 day Fri 17/06/16 Mon 20/06/16 274276 Pemasangan Bekisting Dinding 1 day Mon 13/06/16 Tue 14/06/16 273277 Cor Dinding 1 day Tue 14/06/16 Wed 15/06/16 276279 Pembesian Kolom 2 days Mon 13/06/16 Wed 15/06/16 273

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 9

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    280 Pemasangan Bekisting Kolom 1 day Wed 15/06/16 Thu 16/06/16 279281 Cor Kolom 1 day Thu 16/06/16 Fri 17/06/16 280282 Pembesian Slab 4 days Wed 15/06/16 Tue 21/06/16 279283 Pembesian Dinding 2 days Wed 15/06/16 Fri 17/06/16 279284 Pemasangan Bekisting Slab 2 days Tue 21/06/16 Thu 23/06/16 282285 Cor Slab 1 day Thu 23/06/16 Fri 24/06/16 284286 Pemasangan Bekisting Dinding 1 day Fri 17/06/16 Mon 20/06/16 283287 Cor Dinding 1 day Mon 20/06/16 Tue 21/06/16 286289 Pembesian Kolom 2 days Fri 17/06/16 Tue 21/06/16 283290 Pemasangan Bekisting Kolom 1 day Tue 21/06/16 Wed 22/06/16 289291 Cor Kolom 1 day Wed 22/06/16 Thu 23/06/16 290292 Pembesian Slab 4 days Tue 21/06/16 Mon 27/06/16 289293 Pembesian Dinding 2 days Tue 21/06/16 Thu 23/06/16 289294 Pemasangan Bekisting Slab 2 days Mon 27/06/16 Wed 29/06/16 292295 Cor Slab 1 day Wed 29/06/16 Thu 30/06/16 294296 Pemasangan Bekisting Dinding 1 day Thu 23/06/16 Fri 24/06/16 293297 Cor Dinding 1 day Fri 24/06/16 Mon 27/06/16 296298 Pekerjaan Lantai 1A 21 days Thu 23/06/16 Fri 22/07/16300 Pembesian Kolom 2 days Thu 23/06/16 Mon 27/06/16 293301 Pemasangan Bekisting Kolom 1 day Mon 27/06/16 Tue 28/06/16 300302 Cor Kolom 1 day Tue 28/06/16 Wed 29/06/16 301303 Pembesian Slab 4 days Mon 27/06/16 Fri 01/07/16 300304 Pembesian Dinding 2 days Mon 27/06/16 Wed 29/06/16 300305 Pemasangan Bekisting Slab 2 days Fri 01/07/16 Tue 05/07/16 303306 Cor Slab 1 day Tue 05/07/16 Wed 06/07/16 305307 Pemasangan Bekisting Dinding 1 day Wed 29/06/16 Thu 30/06/16 304

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 10

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    308 Cor Dinding 1 day Thu 30/06/16 Fri 01/07/16 307310 Pembesian Kolom 2 days Wed 29/06/16 Fri 01/07/16 304311 Pemasangan Bekisting Kolom 1 day Fri 01/07/16 Mon 04/07/16 310312 Cor Kolom 1 day Mon 04/07/16 Tue 05/07/16 311313 Pembesian Slab 4 days Fri 01/07/16 Thu 07/07/16 310314 Pembesian Dinding 2 days Fri 01/07/16 Tue 05/07/16 310315 Pemasangan Bekisting Slab 2 days Thu 07/07/16 Mon 11/07/16 313316 Cor Slab 1 day Mon 11/07/16 Tue 12/07/16 315317 Pemasangan Bekisting Dinding 1 day Tue 05/07/16 Wed 06/07/16 314318 Cor Dinding 1 day Wed 06/07/16 Thu 07/07/16 317320 Pembesian Kolom 2 days Tue 05/07/16 Thu 07/07/16 314321 Pemasangan Bekisting Kolom 1 day Thu 07/07/16 Fri 08/07/16 320322 Cor Kolom 1 day Fri 08/07/16 Mon 11/07/16 321323 Pembesian Slab 4 days Thu 07/07/16 Wed 13/07/16 320324 Pembesian Dinding 2 days Thu 07/07/16 Mon 11/07/16 320325 Pemasangan Bekisting Slab 2 days Wed 13/07/16 Fri 15/07/16 323326 Cor Slab 1 day Fri 15/07/16 Mon 18/07/16 325327 Pemasangan Bekisting Dinding 1 day Mon 11/07/16 Tue 12/07/16 324328 Cor Dinding 1 day Tue 12/07/16 Wed 13/07/16 327330 Pembesian Kolom 2 days Mon 11/07/16 Wed 13/07/16 324331 Pemasangan Bekisting Kolom 1 day Wed 13/07/16 Thu 14/07/16 330332 Cor Kolom 1 day Thu 14/07/16 Fri 15/07/16 331333 Pembesian Slab 4 days Wed 13/07/16 Tue 19/07/16 330334 Pembesian Dinding 2 days Wed 13/07/16 Fri 15/07/16 330335 Pemasangan Bekisting Slab 2 days Tue 19/07/16 Thu 21/07/16 333336 Cor Slab 1 day Thu 21/07/16 Fri 22/07/16 335

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 11

    Project: Basement Apartemen OnDate: Thu 30/04/15

  • ID Task Name Duration Start Finish Predecessors

    337 Pemasangan Bekisting Dinding 1 day Fri 15/07/16 Mon 18/07/16 334338 Cor Dinding 1 day Mon 18/07/16 Tue 19/07/16 337

    H2 H1 H2 H1 H2 H1 H22014 2015 2016 2017

    Task

    Split

    Milestone

    Summary

    Project Summary

    External Tasks

    External Milestone

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    Deadline

    Progress

    Page 12

    Project: Basement Apartemen OnDate: Thu 30/04/15