SOP 3 - ID Packages 1.pdf

  • View
    228

  • Download
    6

Embed Size (px)

Transcript

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    01 PILING (ALL PROVISIONAL) - NOT APPLICABLE PILING (ALL PROVISIONAL) - NOT APPLICABLE

    To Collection: CostX Vincent Tan Associates 1/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    01 PILING (ALL PROVISIONAL) - NOT APPLICABLE (Continued)

    COLLECTION

    Page 1/1:

    01 PILING (ALL PROVISIONAL) - NOT APPLICABLECarried to Summary:

    CostX Vincent Tan Associates 1/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    02 WORK BELOW LOWEST FLOOR FINISHES - NOT APPLICABLE

    02 WORK BELOW LOWEST FLOOR FINISHES - NOT APPLICABLE

    To Collection: CostX Vincent Tan Associates 2/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    02 WORK BELOW LOWEST FLOOR FINISHES - NOT APPLICABLE (Continued)

    COLLECTION

    Page 2/1:

    02 WORK BELOW LOWEST FLOOR FINISHES - NOTAPPLICABLECarried to Summary:

    CostX Vincent Tan Associates 2/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    03 STRUCTURAL FRAME AND UPPER FLOOR - NOT APPLICABLE

    03 STRUCTURAL FRAME AND UPPER FLOOR - NOT APPLICABLE

    To Collection: CostX Vincent Tan Associates 3/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    03 STRUCTURAL FRAME AND UPPER FLOOR - NOT APPLICABLE (Continued)

    COLLECTION

    Page 3/1:

    03 STRUCTURAL FRAME AND UPPER FLOOR - NOTAPPLICABLECarried to Summary:

    CostX Vincent Tan Associates 3/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    04 ROOF TRUSSES - NOT APPLICABLE

    04 ROOF TRUSSES - NOT APPLICABLE

    To Collection: CostX Vincent Tan Associates 4/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    04 ROOF TRUSSES - NOT APPLICABLE (Continued)

    COLLECTION

    Page 4/1:

    04 ROOF TRUSSES - NOT APPLICABLECarried to Summary:

    CostX Vincent Tan Associates 4/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    05 EXTERNAL WALLS - NOT APPLICABLE

    05 EXTERNAL WALLS - NOT APPLICABLE

    To Collection: CostX Vincent Tan Associates 5/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    05 EXTERNAL WALLS - NOT APPLICABLE (Continued)

    COLLECTION

    Page 5/1:

    05 EXTERNAL WALLS - NOT APPLICABLECarried to Summary:

    CostX Vincent Tan Associates 5/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    06 EXTERNAL WALL FINISHES - NOT APPLICABLE

    06 EXTERNAL WALL FINISHES - NOT APPLICABLE

    To Collection: CostX Vincent Tan Associates 6/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    06 EXTERNAL WALL FINISHES - NOT APPLICABLE (Continued)

    COLLECTION

    Page 6/1:

    06 EXTERNAL WALL FINISHES - NOT APPLICABLECarried to Summary:

    CostX Vincent Tan Associates 6/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    07 WINDOWS - NOT APPLICABLE

    07 WINDOWS - NOT APPLICABLE

    To Collection: CostX Vincent Tan Associates 7/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    07 WINDOWS - NOT APPLICABLE (Continued)

    COLLECTION

    Page 7/1:

    07 WINDOWS - NOT APPLICABLECarried to Summary:

    CostX Vincent Tan Associates 7/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    08 ROOF COVERING - NOT APPLICABLE

    08 ROOF COVERING - NOT APPLICABLE

    To Collection: CostX Vincent Tan Associates 8/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    08 ROOF COVERING - NOT APPLICABLE (Continued)

    COLLECTION

    Page 8/1:

    08 ROOF COVERING - NOT APPLICABLECarried to Summary:

    CostX Vincent Tan Associates 8/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    09 RAINWATER INSTALLATION - NOT APPLICABLE

    09 RAINWATER INSTALLATION - NOT APPLICABLE

    To Collection: CostX Vincent Tan Associates 9/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    09 RAINWATER INSTALLATION - NOT APPLICABLE (Continued)

    COLLECTION

    Page 9/1:

    09 RAINWATER INSTALLATION - NOT APPLICABLECarried to Summary:

    CostX Vincent Tan Associates 9/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    10 INTERNAL WALLS AND PARTITION

    BRICK WALLS Common clay brick; in cement mortar ( 1:6 ) with plasticiser; including reinforced concrete stiffeners and extended reinforcement welded back to column/stiffener reinforcement at every second course and bonding ties as shown on the drawing, described in the specification or as otherwise necessary and mesh reinforcement at every fourth course and including damp proof course

    A 115mm thick 155 m2

    B 300mm thick 23 m2

    GYPSUM BOARD PARTITION Design, supply and fix; dry partition complete with 12.5mm thick "Boral" gypsum board complete with 80kg/m3 rock wool insulation including all additional work in ends, angles, intersections and abutment, timber/metal stud and all other necessary support to manufacturer's approval

    C 150mm thick 335 m2

    Design, supply and fix; dry partition complete with 12.5mm thick "Boral" gypsum board including all additional work in ends, angles, intersections and abutment, timber/metal stud and all other necessary support to manufacturer's approval

    D 150mm thick (CEO's room) 39 m2

    E ANY OTHER ITEMS i) .................................... ii) ................................... iii) ..................................

    To Collection: CostX Vincent Tan Associates 10/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    10 INTERNAL WALLS AND PARTITION (Continued)

    COLLECTION

    Page 10/1:

    10 INTERNAL WALLS AND PARTITIONCarried to Summary:

    CostX Vincent Tan Associates 10/2

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    11 DOORS

    SPECIAL CONTRACTOR'S DESIGNDED ALUMINIUM GLAZING SYSTEM Notes

    Prices for Aluminium glazing system (curtain walling, window, door and the like) shall include for the complete installation including all supports, fixing accessories, matching hardware, ironmongeries, sub-frame, glass, louvre, glazing beads, gaskets, silicon, expansion and other joints, fixing back to structure. The Tenderer's design submission must be complete with full specification, type of Aluminium glazing system, thickness and type of glass, thickness of frame, specification for powder coating, drawings for extrusion section, and all necessary details to fulfill the tender.

    Prices for Aluminium glazing system work shall include for all necessary design work, mock ups, wind load testing and structural integrity testing and Professional Engineer's calculations and endorsement, obtaining all necessary approvals and associated associated cost there of, preparation of shop drawings and subsequent submittal to Architect for approval. No work shall start on site unless the above requirement of wind load testing and structural integrity testing and Professional Engineer's calculations and endorsement have been approved by the Architect/Structural Engineer. Shop drawings submitted by the Contractor for approval must show location, type and size of supporting framework and must clearly indicate method of fixing of supports shown on the Architect's drawings which are indicative only and have no design intent. Shop drawings must be approved by the Architect before commencement of work on site.

    The tenderer shall be required to carry out a sample mock-up of Aluminium glazing system at site before acceptance of tender by the Employer. This shall facilitate the Employer for selection of the curtain walling. The tenderer shall bear all cost to comply with this mock-up requirement including the cost of subsequent removal of mock-up from site if the tender is not successful.

    To Collection: CostX Vincent Tan Associates 11/1

  • Item Description Quantity Unit Rate Total

    Project: BELLWORTHBuilding: ID PACKAGE 1

    Details: SOP 3 (ADD.1)

    11 DOORS (Continued)

    FIXED GLASS PANEL Design, fabricate, supply and install complete in position fixed glass panel, complete with all matching hardware; ironmongeries such as heavy-duty hinges, lockset, stay, handles, fastener, etc, glazing beads and gaskets; and including glass, setting blocks including building frames in waterproof mortar (1:3 ) and pointing frames with approved sealant.