Upload
phungnhan
View
219
Download
0
Embed Size (px)
Citation preview
भारत सरकार
GOVERNMENT OF INDIA
विद्युत मंत्रालय
MINISTRY OF POWER
कें द्रीय विद्युत प्राविकरण
CENTRAL ELECTRICITY AUTHORITY
दविण िते्रीय विद्यतु सवमवत SOUTHERN REGIONAL POWER COMMITTEE
छब्बीसवीीं बैठक की कार्यवतृ
MINUTES OF THE 26TH MEETING
बेंगलूरु BENGALURU
Minutes of the 26th Meeting of SRPC held on 20th December 2014 1 of 73
CONTENTS
1. INTRODUCTION ............................................................................................................................... 3
2. CONFIRMATION OF THE MINUTES OF 25th
MEETING OF SRPC ..................................... 4
3. UPCOMING TRANSMISSION SYSTEM ..................................................................................... 4
4. RANSMISSION LINES APPROVED IN 37th
MEETING OF SCPSPSR .............................. 31
5. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE& UMPP .............................. 32
6. NEW PROJECTS OF STATE SECTOR & IPP ........................................................................... 38
7. COAL STOCK POSITION IN THERMAL STATIONS OF SOUTHERN REGION .......... 39
8. SIMHADRI STPS – SCHEDULES FOR 12-10-2014 TO 25-10-2014 ..................................... 41
9. EMERGENCY RESTORATION SYSTEM (ERS) ..................................................................... 43
10. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR......................... 44
11. STUDY GROUP OF SLDCs TO ASSESS TTC/ATC AND OPERATIONAL
PLANNING ........................................................................................................................................ 47
12. SEMs ON ALL FEEDERS FOR SECTIONAL LOSSES ........................................................... 48
13. IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION ........................................... 49
14. REVIEW OF PERFORMANCE OF ULDC SCHEME ............................................................... 57
15. PENDING ARREARS PAYMENT BETWEEN BENEFICIARY STATES IN SR ............... 59
16. OUTSTANDING DUES BETWEEN WR & SR ......................................................................... 60
17. UNIFORM RATE OF CHANGE OF FREQUENCY RELIEF SCHEME ............................... 60
(df/dt) TO BE ADOPTED THROUGHOUT THE COUNTRY ................................................. 60
18. SPS FOR OVERLOADING OF 400 kV KOLAR – HOSUR LINES ....................................... 61
19. DETAILS OF PENDING REMEDIAL MEASURES DISCUSSED AND FINALIZED
IN PCC ................................................................................................................................................ 61
20. WHEELING CHARGES PAYABLE BY GOA TO KARNATAKA ....................................... 62
21. UTILIZATION OF TERTIARY WINDING OF ICTS FOR AUXILIARY POWER
SUPPLY IN SUBSTATIONS ......................................................................................................... 62
22 PROCUREMENT OF 500 MVA ICT AS SPARE INSTEAD OF 315 MVA ICT
APPROVED UNDER RAMAGUNDAM TRANSMISSION SYSTEM .................................. 62
23. PROCUREMENT OF 3x125 MVAR REACTORS INSTEAD OF 3 x 50 MVAR
REACTORS APPROVED UNDER RAMAGUNDAM TRANSMISSION SYSTEM .......... 63
24. CONVERTING FIXED LINE REACTORS INTO SWITCHABLE LINE REACTORS
IN OVER COMPENSATED LINES. ............................................................................................. 63
25. CERC ORDER ON UPCL POWER EVACUATION ISSUE .................................................... 64
Minutes of the 26th Meeting of SRPC held on 20th December 2014 2 of 73
26. RE-CONSTITUTION OF THE VALIDATION COMMITTEE UNDER REGULATION
7(1)(g) (SHARING OF INTER STATE TRANSMISSION CHARGES AND LOSSES)
REGULATIONS, 2010..................................................................................................................... 64
27. UTILIZATION OF PSDF TO DEVELOP INTER- STATE TRANSMISSION SYSTEM
TO RELIEVE TRANSMISSION CONSTRAINTS..................................................................... 64
28. EARLY COMMISSIONING OF 765 kV VEMAGIRI-KHAMMAM-HYDERABAD-
WARDHA TRANSMISSION SYSTEM FOR THE ENHANCEMENT OF INTER
REGIONAL TRANSMISSION CAPACITY BETWEEN NEW GRID AND SR. ................. 65
29. PUBLISHING THE RESULTS OF SYSTEM STUDIES BY CTU IN COMPLIANCE
WITH REGULATION 20 OF THE CERC (GRANT OF CONNECTIVITY, LONG
TERM AND MEDIUM TERM OPEN ACCESS) REGULATIONS, 2009. ............................ 65
30. DIFFERENCE IN COMPUTATION OF CAPACITY CHARGES OF NTPC
STATIONS AS PER CERC REGULATIONS (2014-19) .................................................... 66
31. KPTCL DENYING NOC FOR OPEN ACCESS FOR POWER CONTRACTED FROM
UDUPI POWER CORPORATION LTD. ...................................................................................... 67
32. DOUBLING OF 110 KV KONAJE-MANJESHWARAM S/C FEEDER ................................ 67
33. PROVISION OF ADDITIONAL SPACE IN SRPC SECRETARIAT / OTHER CIVIL
WORKS .............................................................................................................................................. 67
34. S3 REGION TO BE FORMED BY BIFURCATING S2 AND ATC TO BE
CALCULATED FOR S2-S3 REGION BY FOLLOWING THE N-1 CONDITION IN
400 kV UDUMALPET – PALAKKAD D/C LINES .............................................................. 68
35. GRID OPERATION .......................................................................................................................... 68
36. DEMAND VARIATION (Peak Vs Off-peak) .............................................................................. 69
37. FREQUENCY OF OPERATION OF SOUTHERN GRID ......................................................... 71
38. URTDSM (PMU) PROJECT IN SOUTHERN REGION ........................................................... 71
39. DRAWAL POINTS OF COASTAL ENERGEN ......................................................................... 71
40. PAYMENT OF TRANSMISSION CHARGES & OPENING OF LC FOR DRAWAL OF
START UP POWER DURING COMMSSIOING PERIOD BY GENERATING
STATIONS ......................................................................................................................................... 72
41. AUDITING OF ACCOUNT - ANNUAL SUBSCRIPTION FOR CONDUCTING
VARIOUS COMMITTEE MEETINGS OF SRPC ...................................................................... 72
42. DATE & VENUE OF THE NEXT SRPC MEETING ................................................................. 73
43. VOTE OF THANKS/PLACING ON RECORD CONTRIBUTIONS ....................................... 73
Minutes of the 26th Meeting of SRPC held on 20th December 2014 3 of 73
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
MINUTES OF THE 26th
MEETING OF SRPC HELD AT
VISAKHAPATNAM ON 20th
DECEMBER 2014
1. INTRODUCTION
1.1 The 26th
Meeting of Southern Regional Power Committee was held at Visakhapatnam
on 20th
December 2014. The list of participants is furnished at Annexure-I.
1.2 Shri R.P.Sasmal, Director (Operations), PGCIL welcomed all Members to the 26th
Meeting of SRPC. He stated that it was a great pleasure hosting the SRPC Meeting at
Visakhapatnam. He thanked all constituents for the continued support and confidence
reposed in PGCIL. He also informed that on 10th
December 2014, Government of India
had issued a Circular for implementing the much awaited 6,000 MW Raigarh –
Pugalur HVDC project by PGCIL. He hoped that in this Meeting, SRPC would look
into the problems being faced in execution of transmission schemes. Transmission
system was required to be implemented, keeping in view anticipated growth for the
next 10 to 15 years. In the recent past there had been substantial improvement in the
SR transmission system especially after synchronization with NEW grid.
1.3 Shri S.R.Bhat, Member Secretary, SRPC welcomed all the Members and delegates to
the Meeting. He extended a special welcome to Shri G.Kumar Naik, Chairperson,
SRPC & MD, KPTCL. He also thanked Shri R.P.Sasmal, Director (Operations),
PGCIL and the entire team of PGCIL for the excellent arrangements for the conduct of
the Meeting.
1.4 Shri G.Kumar Naik, Chairperson, SRPC& MD, KPTCL welcomed all the Members to
the Meeting and thanked Director (Operations), PGCIL for the nice arrangements. He
noted that in the SRPC Meeting, various coordination issues of Southern Region were
being deliberated and the way forward to resolve these challenges was being evolved.
The concerns of all constituents on various issues could be further deliberated in this
Meeting and consensus could be arrived at. He stated that the contribution of Shri K.
Gnanadesikan, erstwhile Chairman, TNEB required special mention for providing
inspiration and guidance during his association with SRPC forum.
1.5 SRPC welcomed the following new Members:
Shri M. Maheshwar Rao, MD, KPCL
Dr M. Saikumar, Chairman, TANTRANSCO
Shri D. Prabhakar Rao, CMD TSTRANSCO & TSGENCO
Minutes of the 26th Meeting of SRPC held on 20th December 2014 4 of 73
1.6 SRPC also placed on record the excellent services rendered by the following outgoing
Members:
Shri K. Gnanadesikan, Chairman, TANTRANSCO
Shri S. A. M Rizvi, CMD, TSTRANSCO
Shri Ritesh Kumar Singh, MD, KPCL
Shri K. Vikraman Nair, Director (Tr & SO), KSEB
2. CONFIRMATION OF THE MINUTES OF 25th
MEETING OF SRPC
The Minutes of the 25th
Meeting of Southern Regional Power Committee held on 26th
July 2014 held at Chennai were confirmed.
3. UPCOMING TRANSMISSION SYSTEM
3.1 Perspective Transmission Plan for Twenty Years (2014-2034) – Highlights
3.1.1 MoP in association with CEA, CTU and POSOCO had brought out the Perspective
Transmission Plan for 20 Years (2014-34) and following are the highlights:
Load generation balance shows that deficit in Southern Region is about 13,000 to
19,100 MW at the end of 13th
Plan (2021-22) conditions.
Summary of Inter- Regional Transmission Capacity Corridor towards SR is given
below:
Transmission Element Transmission Capacity in MW
Existing
12
th Plan
addition
End of
12th
Plan
13th
Plan
addition
Total
Balimela-Upper Sileru 220kV S/c 130 130 130
Gazuwaka HVDC back-to-back 1000 1000 1000
Talcher-Kolar HVDC bipole 2000 2000 2000
Upgradation of Talcher-Kolar HVDC
Bipole
500 500 500
Angul - Srikakulam 765kV D/c line 4200 4200 4200
Angul - Srikakulam 765kV D/c line (2nd) 4200 4200
EAST-SOUTH 3630 4200 7830 4200 12,030
Chandrapur HVDC back-to-back 1000 1000 1000
Kolhapur-Belgaum 220kV D/c 260 260 260
Ponda – Nagajheri 220kV D/c 260 260 260
Raichur - Sholapur 765kV S/c line (PG) 2100 2100 2100
Raichur - Sholapur 765kV S/c line (Pvt.
Sector)
2100 2100 2100
Narendra - Kolhapur 765kV D/c (ch at
400kV)
2200 2200 2200
Wardha - Nizamabad 765kV D/c line 4200 4200
Raigarh - Pugalur +/- 800kV, 6000 MW
Bi-pole
6000 6000
Warora Pool - Warangal 765kV D/c line 4200 4200
WEST - SOUTH 5720 2200 7920 14400 22,320
Minutes of the 26th Meeting of SRPC held on 20th December 2014 5 of 73
ISTS drawal requirement of each State in 2021-22 had been assessed as follows :
State 2013-14 2021-22
Demand
Met
MW
Peak
Demand as per
EPS
Increment
Load
State
Generation
Despatch
Import
requirement
through
ISTS
%ge of
Peak
AP 6318 15933 9615 9697 6236 39%
Karnataka 9223 18403 9180 7763 10640 58%
Kerala 3573 6093 2520 1119 4974 82%
TN 12825 29975 17150 13053 16922 56%
Telangana 6844 17261 10417 3949 13312 77%
State wise annual peak demand for SR constituents is as given below :
State/UT 14th
Plan (as per 18th
EPS) 2026-27
15th
Plan (as per 18th
EPS) 2031-32
Estimate for
2033-34
AP/Telangana 51601 74818 86805
Karnataka 25396 34720 39346
Kerala 8150 10903 12249
TN 43044 59827 68248
Puducherry 787 940 1009
Southern Region 1,18,764 1,65,336 1,88,730
Load generation balance shows the import assessment for Southern Region in different
scenarios as given below :
Generation Scenario 14
th Plan
(2026-27)
15th
Plan
(2031-32)
2033-34
Scenario I
(Normal Generation as per
plan / resource availability)
3356-20607 19631-41539 27002-51249
Scenario II
(Less gas met through imported
coal with respect to Scenario I)
+507-20607 10165-41538 27002-51249
Requirement for Major Transmission Corridors had been assessed as given below :
13th
Plan
(2021-22)
14th
Plan
(2026-27)
15th
Plan
(2031-32)
2033-34
ER/NER-SR 12000 15000 30000 40000
WR-SR 22000 25000 35000 40000
SR-Sri Lanka 500 1000 1000
Minutes of the 26th Meeting of SRPC held on 20th December 2014 6 of 73
3.1.2 For coordinated development process aiming at perspective optimization in meeting
growth targets, it was thought appropriate that State Transmission Utilities prepare their
State Electricity Plans appropriately, focusing on specific requirements of the
concerned State. In Petition No SM/011/2014 before Hon’ble CERC, it had been
stipulated that CTU and STUs shall coordinate with each other and other agencies so
that implementation of ISTS and associated downstream/upstream ISTS is carried out
in a matching time frame so that no asset remains stranded or underutilized and the
intended purpose of the scheme was realized.
3.1.3 The following had been noted in the TCC Meeting:
In earlier Meetings, it had been suggested that a ‘Big Picture’ be
deliberated in SRPC forum which would help in assessment of bottlenecks
and ensure timely corrective actions. MoP in association with
CEA/CTU/POSOCO had come up with Perspective Transmission Plan for
coming two decades. The plan was under draft stage and comments had
been sought. The need for coordinated development by CTU and STU had
been highlighted for optimal planning and utilization of transmission
assets. In a recent petition before Hon’ble CERC, the issue regarding
stranded assets due to non-completion of downstream assets was being
heard. Proof of coordination and action taken by the concerned utilities
had been sought. Section 38 (2) and Section 39 (2) of the Electricity Act
clearly demarcate the responsibility of CTU and STU in the process.
CTU had stated that the projected ISTS import requirements for the states
was quite high and varying between 39% and 82%. Regional Demand
which was currently around 38,500 MW was expected to rise by 50,000
MW and reach about 87,500 MW by 2021-22. By 2026 -27, the demand
of SR was expected to rise to 1, 19,000 MW (about current all India
demand). An action plan with concerted efforts was therefore required,
considering the quantum jump in demand and various bottlenecks likely in
development of the transmission system. CTU had suggested constitution
of a Task Force in this regard.
KPTCL had observed that KPTCL was planning 1,000 Km of 400 kV
transmission lines. It was noted that the Tables projected pertained to the
likely LGBR considering requirement as per EPS figures and anticipated
availability as per proposed generation addition etc. The difference
between requirement and local availability indicated the level of
dependence on ISTS in bridging the gap.
TSTRANSCO had stated that state generation dispatch for the year 2021-
22 appeared to be on the lower side. The State Government was having
ambitious plan for generation additions and the drawal from ISTS could
be of the order of about 9,640 MW. It was suggested to TSTRANSCO that
they may convey revised projected figures to CEA at an early date.
SRLDC had observed that state network too was required to be built in a
coordinated manner with ISTS for effective and full utilization.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 7 of 73
MS, SRPC had said that the Plan had been prepared with due consultation
and inputs from the state utilities. However, States could immediately
convey their comments to CEA in event of changes. As suggested by
PGCIL, a Task Force could be constituted which would validate data;
finalize action plan to achieve the desired results and sort out any
coordination issue between CTU/STU/Generators.
After deliberation, it had been noted that sustained coordination was
required between CTU and STU to achieve the desired results. It was
therefore agreed to form a Task Force at the level of Chief Engineers to
study and validate the LGBR projections, Inter Regional Import
requirements, ISTS requirements etc. Task Force would also assess the
intra state transmission system requirement (keeping in view the planned
network). CTU agreed to be associated with this Task Force.
3.1.4 In the Meeting MS, SRPC said that critical issues that could arise in the future in
respect of upcoming transmission system had been highlighted in the Agenda. The
ISTS import requirement assessed was quite high and varied between 39 % and 82 %.
SR demand was expected to rise to about 82,000 MW by 2021-22 and 1,19,000 MW
by 2026-27. Sustained coordinated effort at regional level was therefore essential in
view of the projected quantum jump. Issue of stranded assets on account of non-
availability of downstream systems had been raised in a few petitions and Hon’ble
CERC had sought the action plan. In this regard it had been decided that a Task Force
be formed at the level of Chief Engineer. This mechanism would help develop ISTS
and intra state transmission system in a coordinated manner ensuring better utilization.
3.1.5 Chairperson, SRPC stated that transmission bottlenecks should not come in the way of
smooth evacuation. Surplus generation available in different regions had to be made
available to needy consumers. He suggested that the Task Force as proposed be
formed to study the matter.
3.1.6 After deliberation, SRPC agreed to form a Task Force at level of Chief Engineer to
study and validate the LGBR projections, Inter Regional Import requirements, ISTS
requirements etc. Task Force would also assess the intra state transmission
requirements.
3.2 Associated Transmission System in respect to 765 kV Raichur-Sholapur lines
3.2.1 Additional ATC ( as on date) between WR - SR on account of this link was around
350 (1,100-750 ) MW.
3.2.2 TANTRANSCO vide letter dated 29th
November 2014 (Annexure- II) had stated that
status of remaining lines comprising associated transmission system in WR & SR for
765 kV Raichur-Sholapur 2 x S/C line may be deliberated. The probable quantum of
Minutes of the 26th Meeting of SRPC held on 20th December 2014 8 of 73
power increase in WR-SR corridor due to commissioning of new lines in WR & SR
had also been proposed to be discussed.
3.2.3 KSEB vide letter dated 8th
December 2014 (Annexure-III) had stated that status of
lines likely to relieve S1-S2 congestion be discussed in the Meeting. Suitable action
plan may be evolved for early commissioning of the same, including time frame.
3.2.4 The following had been noted in the TCC Meeting:
Updated status of commissioning of the planned (18 Nos.) transmission elements
in WR and SR for proper utilization of 765 kV Raichur-Sholapur line is as follows:
Sl.
No.
Name of
Transmission
Element
Exe.
Agency
Date as
noted in
CEA
Mtg. held
on
09.09.13
Expected
date Remarks Comments
1. Aurangabad-
Pune 400 kV
D/C
Reliance Dec. 2013 Completed
2. Parli-Pune 400
kV D/C
Reliance Dec. 2013 Completed
3. Raipur-Wardha
765kV D/C
PGCIL May 2014 Nov. 2014 Commissioned
on 15.11.2014
Delayed forest clearance
4. Raipur 765/400
kV S/S
PGCIL Dec. 2013 Completed It is a pooling station.
Interconnecting links
Commissioned
5. Wardha-
Aurangabad
765kV D/C
PGCIL July 2014 Commissioned
in July 2014
One Circuit
Commissioned on 01-07-
2014 against severe
RoW constraints
6. Aurangabad
765/400 kV S/S
PGCIL July 2014 Completed in
July 2014
Interconnecting
network in progress:
400 kV Aurangabad-
Padghe (expected in
June 2015), 400kV
Aurangabad-Boisar
(expected in March
2015), 400 kV Padghe -
Padghe (Kudus)
(expected by June 2015),
MSETCL to take up
commissioning of
Padghe (Kudus) S/S by
June 2015
Minutes of the 26th Meeting of SRPC held on 20th December 2014 9 of 73
7. Sholapur-Pune
765 kV S/C
PGCIL Oct.2014 Jan-2015 Pune s/s
critical. Line
being planned
for
commissioning
earlier
bypassing Pune
through
contingency.
Severe RoW
problem.
Sever RoW Problem.
Line is being charged
through Parli by
bypassing Pune S/S
which is expected by
March 2015
8. Pune 765/400 kV
S/S
PGCIL Oct. 2014 March 2015 Civil work
under progress
Land acquisitioned
delayed, Expected
commissioning by March
2015, Civil works and
erection activity in
progress
9. Gooty-
Madhugiri 400
kV D/C
PGCIL June 2014 March 2015 Critical RoW
problems faced
towards
Karnataka end
Hold continues at 10
locations in District
Tumkur. Stringing has
been stopped since Feb
2014
10. Madhugiri
400/220 kV S/S
PGCIL June 2014 March 2015 Erection under
progress
Downstream network not
available
11. Madhugiri-
Yelahanka 400
kV D/C line
PGCIL June
2014 March 2015 Severe Row
Problem
Severe RoW problem at
Tumkur (30 Loc),
Bangalore Rural (35 Loc)
and Bangalore Urban (10
Loc)
12. Raichur-
Kurnool 765
kV S/C
PGCIL Aug-
2014 Commissioned
on 21.06. 2014
13. Kurnool
765/400 kV
S/S
PGCIL Aug-
2014 Commissioned Downstream network
ready
14. Kurnool-
Thiruvalam
765 kV D/C
PGCIL Nov.201
4 Commissioned
on 27.11.2014
Downstream network
ready
15. Thiruvalam
765/400 kV
S/S
PGCIL Nov
2014 765 kV by
Feb 2015
400kV
Commissioned 765 kV by Feb 2015
16. Vijayawada-
Nellore 400 kV
D/C
PGCIL Nov.
2014 March.
2015
RoW problem
being faced at
Krishna Dist.
(49 Loc) &
Guttur Dist (23
Loc)
RoW continuing , efforts
being made including the
Power Secretries meet in
SR Chaired by Union
Power Secretary
Minutes of the 26th Meeting of SRPC held on 20th December 2014 10 of 73
17. Nellore-
Thiruvalam
400 kV D/C
PGCIL Nov.201
4 Commissioned
on 14.04.2014
18. Thiruvalam-
Melakottaiyur
400 kV D/C
PGCIL Nov.201
4 July 2014 Commissioned
on 24.07.2014
PGCIL had expressed concern that though 400 kV Gooty - Madhugiri D/C line
would come up , the downstream system at Madhugiri as well as Yelahanka may
not be ready by that time. Stringing on 11-12 towers was pending on Gooty-
Madhugiri lines on account of local compensation issue. Once compensation
issues are finalized by Karnataka Govt. the pending works could be completed.
SRLDC had stated that the utilities were anticipating increase in ATC with
commissioning of new elements. However, in the event downstream system at
Madhugiri and Yelahanka did not come up in the matching time frame, it would
not be possible to enhance the ATC.
KPTCL had informed that Compensation issues were under consideration of the
Govt. of Karnataka and would be settled within 3 months. Complete downstream
evacuation from Madhugiri and Yelahanka had been planned. 220 kV D/C
evacuation lines had been planned from Madhugiri . Initially at Madhugiri, about
500 MVA of evacuation would be possible by July 2015. With regard to
Yelahanka, KPTCL Board had decided that complete evacuation would be
through UG Cable ( 6 kms) since O/H lines were not feasible. 1,500 MVA of
evacuation was planned from Yelahanka and KPTCL was going for adequate
capacity cables despite the high cost involved. It could take 6 to 8 months for the
evacuation system at Yelahanka to come up. Madhugiri and Yelahanka
downstream system would come up in stages from June/July 2015.This factor
would need to be considered while declaring ATC/TTC for different corridors.
CTU had informed that the NEW Grid to SR ATC could be increased by 900
MW with commissioning of 765 kV Sholapur – Pune S/C line, 400 kV Gooty-
Madhugiri-Yelahanka D/C line and downstream system at Madhugiri and
Yelahanka by March 2015. It was clarified that presently Madhugiri substation
would be charged at 400 kV level. With generation addition etc subsequently,
charging at 765 kV level could be planned. Contingency arrangement of
bypassing Pune S/S would be in place by March 2015. ATC from S1-S2 would
be enhanced in stages with commissioning of 765 kV Salem – Madhugiri line,
400 kV Mettur- Thiruvalam D/C lines, 400 kV Mysore – Kozhikode D/C lines
and 400 kV Somanahalli – New Salem D/C lines . ATC would also depend on
the commissioning of KKNPP (2,000 MW), NTPL (1,000 MW), NLC TS-II
Expn (500 MW), BHAVINI (500 MW) and NTECL Vallur 3rd
Unit (500 MW)
etc. Earlier during May 2014 TN, Kerala, CTU & CEA were associated in
studying ATC/TTC computations. A participative approach with mutually
acceptable collective assumptions was required to be adopted to finalize
TTC/ATC computation, especially since spatial distribution of loads etc was
involved.
TANTRANSCO had informed that 400 kV Thiruvalam - Mettur D/C line was
stuck up at 7 locations (out of 799 locations) and they were planning to
commission the same by January 2015, five months ahead of schedule. The failed
Minutes of the 26th Meeting of SRPC held on 20th December 2014 11 of 73
transformer at Thiruvalam had been replaced by a new transformer and the same
would be commissioned within 10 days.
MS, SRPC had stressed on the need for participative approach in finalization of
ATC/TTC. The same needed to be backed up with technical rationale and
assumptions on a collective basis. Some issues had been raised regarding
ATC/TTC of CTU and of POSOCO. However, it could be kindly appreciated
that the horizons and assumptions in this regard were different.
KSEB had suggested that the studies be periodically undertaken with
participation from the utilities.
It was agreed that the Study Group would also look into various ATC related
issues with commissioning of lines and Generation. CTU agreed to associate with
the Study Group.
3.2.5 In the Meeting, CTU informed that additionally around 900 MW of power could be
transmitted from NEW grid to SR with the commissioning of new elements by March
2015. ED, SRLDC pointed out that additionally Thiruvalam-Mettur and Somanahalli –
Salem lines as well as downstream system at Madhugiri & Yelahanka S/S was needed
to be in place for enhancement in ATC.
3.2.6 MS, SRPC said that it had been agreed that a Study Committee would look into
ATC/TTC related aspects. A number of issues had been raised on TTC/ATC
computations of CTU & NLDC. However, it could be kindly appreciated that the
horizons, assumptions etc were different for both the studies.
3.2.7 COO, CTU informed that certain MTOA Applications had been received in regard to
which action was required to be completed by 10th
January 2015. Preliminary studies
had been carried out in this regard. She suggested that a Meeting of SR constituents be
held shortly to arrive on a consensus for the ATC between S1-S2.
3.2.8 After deliberations, it was agreed that a Meeting would be conducted on 29th
December
2014 at Bengaluru to look into the ATC issues. MS, SRPC requested CTU to kindly
furnish the study results in advance to the constituents so that the participants could
come prepared for the Meeting. CTU agreed to furnish the details of load flow studies
to the constituents in advance.
3.2.9 ED, SRTS-I informed that during the last one and half years, PGCIL had completed
more than 10 major elements in SR. In respect of Gooty -Madhugiri line, 10
foundations and around 75 Km of stringing was left which could have been completed
as committed. There was demand for stringing corridor to be paid, which was not in
accordance with provisions of the Indian Telegraph Act 1885. Compensation issue had
been taken up with Government of Karnataka at the highest level. Local State
Minutes of the 26th Meeting of SRPC held on 20th December 2014 12 of 73
Administration at Madhugiri had informed that unless corridor issue was settled,
stringing could not be carried out. On 7th
July 2014, the local Administration had issued
an Order covering the stringing corridor payment which was around Rs.16 Crores.
Petition had been filed with Hon’ble CERC in this regard and order was awaited. Gooty
-Madhugiri line was transiting 15 Kms in Karnataka and another 15 Kms is Andhra
Pradesh before reentering Karnataka. Farmers in AP were demanding higher
compensation not only for Gooty - Madhugiri line but also for lines coming in other
parts of Andhra Pradesh (Vijayawada – Nellore, Vijayawada area etc.). Once directions
were received on the pending Petitions, works would be taken up.
3.2.10 MS, SRPC said that KPTCL had informed that from Madhugiri S/S, around 500 MW
of evacuation would be possible by July 2015 while evacuation from Yelahanka
substation would be through underground cable. He added that the downstream
system needed to be in place for proper utilization of ISTS.
3.2.11 Director (Tr.), KPTCL informed that tender for Madhugiri evacuation system had been
floated, opened and was in the finalization stage. Regarding evacuation at Yelahanka,
after commissioning of cable (tender to be floated) the 220 kV substation would be
back charged upto 400/220 kV Yelahanka substation of PGCIL. In case 400 kV S/S
and upstream was charged by PGCIL by that time, power could be drawn.
3.2.12 MD, TANTRANSCO informed that Mettur-Thiruvalam line would be commissioned
by January 2015.
3.3 Status of upcoming Inter-Regional links
3.3.1 Narendra-Kolhapur 765 kV D/C line
Transmission
Element
Implement
-ing
Agency
Line
length
(ckm)/
MVA
Capacity
Sch. COD Ant
COD/
Act
COD
Constraints/ Remarks
Kolhapur-
Narendra (New)
765 kV D/C line
(initially charged at
400 kV)
PGCIL 376 April’15 Dec’15
Completion matching
with Kudgi S/S (Land
acquired in Feb’14).
Efforts being made to
complete in 2014-15.
LILO of both circuits
of Kolhapur –
Mapusa 400 kV D/C
line at Kolhapur
PGCIL 90 April’15 Dec’15
Completion matching
with S/S. Efforts being
made to complete in
2014-15.
Narendra (New) –
Narendra (Existing)
400 kV (quad) D/C
line
PGCIL 354 April’15 Dec’15
Completion matching
with S/S. Efforts being
made to complete in
2014-15.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 13 of 73
Kolhapur 765/ 400
kV S/S (GIS)
(initially charged at
400 kV)
PGCIL April’15 Dec’15
Award placed in
Feb’14. Engg. & Civil
works under progress.
Narendra (New) 765/
400 kV S/S (GIS)
(initially charged at
400 kV)
PGCIL April’15 Dec’15
Award placed in
Mar’14. Land acquired
in Feb’14. Civil works
under progress.
Extn. at Narendra
(Existing) 400/ 220
kV S/S
PGCIL April’15 Dec’15
Award placed in
Mar’14. Engg. in
progress.
Kudgi TPS –
Narendra (new) 400
kV 2xD/C Line
M/s Kudgi
Transmissi
on
Limited
(L&T
Infrastruct
ure
Developm
ent
Projects
Ltd.)
Feb’15 Dec’15
Completion matching
with Narendra-
Kolhapur line.
Narendra (new) -
Madhugiri 765 kV
D/C Line
Dec’15 Sept’16
Madhugiri - Bidadi
400 kV D/C (quad)
Line
Dec’15 Sept’16
3.3.1.1 The following had been noted in the TCC Meeting:
SRLDC had pointed out that Kudgi generation would get stranded in case 400
kV Kudgi-Narendra (New), Narendra (New) – Madhugiri and Madhugiri -
Bidadi lines get delayed. There could be issues relating to drawal of Startup
Power as well.
NTPC and KPTCL had clarified that startup power was being arranged
through 220 kV system of KPTCL and the system was in advanced stage of
commissioning.
3.3.1.2 The Committee noted the above.
3.3.2 Wardha - Nizamabad 765 kV D/C line
Transmission
Element Implement-ing Agency
Line
length
(ckm)/
MVA
Capacity
Sch.
COD
Ant
COD/
Act
COD
Constraints/ Remarks
Wardha-Nizamabad
765 kV D/C line PGCIL 250
Wardha – Raipur PS
765 kV D/C line PGCIL 713 Dec’15
Commissioned on 15-11-
2014
Extn. of Raipur 765
kV S/S PGCIL Dec’15 Completed
Minutes of the 26th Meeting of SRPC held on 20th December 2014 14 of 73
Extn. of Wardha 765
kV S/S PGCIL Dec’15 June’15
Engg. & Civil Works
under progress
Wardha –
Aurangabad 765 kV
D/C line
PGCIL 701 Dec’15 July’14
Extn. of Aurangabad
765 kV S/S PGCIL Dec’15 Feb’15 Completed
Extn. of Wardha 765
kV S/S PGCIL Dec’15 Feb’15
Award placed in June’13.
Engg., supply, civil works
& erection are under
progress
Nizamabad-
Maheshwaram PG
(Hyderabad) 765 kV
D/C line
PGCIL 250
Nizamabad-
Dichipalli 400 kV
D/C line
PGCIL
Nizamabad-
Yeddumailaram
(Shankarapalli) 400
kV D/C line
This line along with
“Maheshwaram PG -
Mahboobnagar 400 kV
D/C line” was
recommended for
implementation through
tariff based competitive
bidding (TBCB) route.
Project was recommended
to GoI for notification
Maheshwaram PG
765/400 kV, 2x1500
MVA S/S
PGCIL
Nizamabad 765/400
kV, 2x1500 MVA
S/S
PGCIL
3.3.2.1 In the TCC Meeting, CTU had informed that regarding 765 kV Wardha- Nizamabad
D/C lines, tenders had been floated.
3.3.2.2 In the Meeting, POWERGRID informed that the line from Wardha to Dichipally was
under the scope of PGCIL while Nizamabad – Sankarapalli under TBCB route.
TSTRANSCO requested that the Nizamabad – Sankarapalli line be executed by
POWERGRID in view of its criticality.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 15 of 73
3.3.3 WR-SR 6000 MW HVDC Bipole Link [Raigarh (Chhatisgarh) -Pugalur/Trichur
(TN/KER)]
Transmission Element Imple-
menting
Agency
Line
length
(ckm)/
MVA
Capacity
COD
Constraints/ Remarks
Sch. Ant /
Act
WR-SR HVDC Bipole Link
[Raighar (Chhatisgarh) - Pugalur
(Tamil Nadu)]
PGCIL
The scheme was
originally designed for
import of 4000 MW and
put up before SCPSPSR-
36 for approval. However,
to cater to the huge import
requirement of power, the
Committee suggested that
studies for 6000 MW
capacity and additional
strengthening be carried
out and put up for
discussion in the next
Standing Committee (37th)
meeting.
Accordingly the scheme
has been modified and
discussed in SCPSPSR-
37, when KSEB requested
to construct this link as a
multi-terminal HVDC
with one Inverter station
of 4000 MW at Pugalur
and another Inverter
station of 2000 MW
capacity at Madakathara
in Kerala by extending the
same HVDC up to
Madakathara to enable it
to import power from
outside.
It was decided that the
same would be explored
and finalized in the next
meeting of SCPSPSR.
Raigarh (existing) - Raigarh (HVDC
Stn) –400 kV 2xD/C (quad) lines
6000 MW, HVDC Terminal Station
at Raigarh 6000
6000 MW, HVDC terminal Station
at Pugalur (or alternatively (i) with
4000 MW HVDC terminal, and (ii)
2000 MW HVDC terminal at
Madakathara, and inter-connection
with existing 400 kV AC Substation
at Madakathara.
6000
Raigarh (HVDC Stn) -
Pugalur(HVDC Stn) 6000 MW, +/-
800 kV HVDC bipole.
Pugalur HVDC station-Pugalur
existing S/S 400 kV D/C(Q) Line
Pugalur HVDC station-Arasur S/S
400 kV D/C (Q) line with 80 MVAR
switchable line reactor at Arasur end.
Pugalur HVDC station-Thiruvalam
S/S 400 kV D/C (Q) line with 80
MVAR switchable line reactor at
both ends
Pugalur HVDC station-
Edayarpalayam S/S400 kV D/C (Q)
line with 63 MVAR switchable line
reactor at Edayarpalayam end
Edayarpalayam S/S-Udumalpet
S/S400 kV D/C (Q) Line
400/230 kV, 2x500 MVA,
Edayarpalayam S/S with 2x125
MVAR bus reactors. 2x500
Minutes of the 26th Meeting of SRPC held on 20th December 2014 16 of 73
The matter regarding proposed HVDC link between Raigarh - Pugalur had been discussed
in the 25th
Meeting of SRPC. After discussions it had been felt prudent to recommend to
Ministry of Power that this proposed link be developed by Power Grid Corporation at the
earliest. Only Power Grid Corporation had the desired technical and financial expertise to
take up the project in a timely manner. Accordingly, Chairperson, SRPC vide letter dated
25th
September 2014 (Annexure-IV) had taken up the matter with Secretary (Power),
Government of India.
3.3.3.1 The following had been noted in the TCC Meeting:
PGCIL had appraised the forum about the different configurations and
technology options for Multi-Terminal HVDC Link. Decision on the
configuration and technology option was critical. In one option, the voltage
level from Pugalur to Madakathara could be brought down thereby
considerably reducing the RoW requirement. Use of cable partially in
Kerala portion could also be contemplated. On a query it was informed that
this would be the third link of +/- 800 kV, the first being from North East to
Agra and the second one from Champa to Kurukshetra.
KPTCL had suggested that usage of Covered Conductor could be explored
which would help considerably reduce the RoW requirement on the Pugalur
- Madakathara Section.
It was agreed that PGCIL would circulate different technology
options/configurations for consideration. The matter would be further
deliberated in the Standing Committee on Power System Planning.
3.3.3.2 In the Meeting, Director (O), PGCIL said that HVDC system upto Pugalur (6,000 MW)
would be implemented by PGCIL. He however observed that construction of
transmission lines within Kerala was rather difficult. PGCIL had been stuck up with one
line in Kerala for the past 7 years or so. He suggested that Kerala may take care of
evacuation within the state. Kerala could also consider transmission through cable for
which the technology would be different. PGCIL would place the Order for the HVDC
station (at Trichur) but execution would be after completion of line by Kerala. PGCIL
would not like to jeopardize the HVDC link because of transmission constraints in
Kerala.
3.3.3.3 Chief Engineer (Tr.), KSEB informed that they were exploring all possibilities and
within one or two weeks, the option may get finalized. Reducing voltage from 800 kV
to 266 kV and bringing in a new line at 266 kV level was one option. All possible
options would be considered and in case required KSEB may also take up construction
of the line. He requested full support from PGCIL in the design and engineering
aspects.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 17 of 73
3.3.3.4 Director (O), PGCIL said any option proposed by KSEB would need to be put up to
Standing Committee for further deliberations. He added that N-1 contingency had
already been factored in and 6,000 MW of power would be available even after outage
of one block.
3.3.3.5 Director (Tr.), KPTCL suggested that on account of severe RoW issues in Kerala, the
proposed terminal at Trichur could instead be located at Mysore. The power deficit
northern part of Kerala could then be fed from Mysore. He stated that system studies
could help decide the location of the terminal.
3.3.3.6 Chief Engineer (Tr.), KSEB observed that the terminal location at Trichur had already
been frozen and should not be reopened.
3.3.3.7 MD, TANTRANSCO stated that 4,000 MW of power evacuation at Pugalur end was
needed to be ensured, irrespective of location of the other landing point.
3.3.3.8 CTU pointed that the scheme (landing point etc) had already been deliberated and
agreed in the 37th
Standing Committee on Power System Planning.
3.3.3.9 The Committee observed that the scheme / technology option etc. would be finalized by
the Standing Committee.
3.3.4 Angul - Srikakulam PS 765 kV D/C line
Transmission
Element
Implementing
Agency
Line
length
(ckm)/
MVA
Capacity
COD
Constraints / Remarks
Sch.
Ant /
Act
Angul - Srikakulam
PS 765 kV D/C line
PGCIL
552
Jun'15 Jun'15
Processing of forest
case very slow at state
govt. level; Critical.
Extn. 765/400 kV
Angul Sub station PGCIL
1x1500
Jun'15 Jun'15
Engineering, Civil works
under progress.
765 kV D/C Angul-
Jharsuguda line PGCIL
570
Dec'15 Dec'15
RoW being faced
765 kV D/C
Jharshuguda-
Dharamjayagarh line
PGCIL 230 Dec'15 Dec’15
Award placed in
May’14. Foundation
commenced from
Sept’14.
Extn. of 765/ 400 kV
Angul SS PGCIL
Dec'15 Dec’15
Award placed in Aug,13.
Engineering & Civil
works under progress
Minutes of the 26th Meeting of SRPC held on 20th December 2014 18 of 73
Extn. of 765/ 400 kV
Jharshuguda SS PGCIL
Dec'15 Dec’15
Award placed in Aug,13.
Engineering & Civil
works under progress
Extn. of 765/ 400 kV
Dharamjaigarh SS PGCIL
Dec'15 Dec’15
Award placed in Aug,13.
Engineering & Civil
works under progress
Srikakulam P P-
Vemagiri- II Pooling
station 765 kV D/C
line
M/s Vizag
Transmission
Limited
(A subsidiary
of PGCIL)
30.08.2
016 July’16 Under implementation
Srikakulam Pooling
Station 765/ 400 kV,
2x1500 MVA PS (400
kV - AIS & 765 kV –
GIS)
PGCIL 2x1500 Jun'15 Jun'15 Engineering, Civil works
& supply under progress.
Srikakulam Pooling
Station – Garividi 400
kV (Quad) D/C line
with 80 MVAR
switchable line reactor
at Garividi end.
PGCIL
The line has been
approved as ISTS
scheme for
implementation in
SCPSPSR-37.
400/220 kV S/S at
Maradam (Garividi) APTRANSCO
Tenders will be called
for shortly
Behrampur-
Gazuwaka 400 kV
D/C line
M/s Talcher
Transmission
Company
Limited
(Subsidiary of
M/s Reliance
Power
Transmission
Company
Limited)
290 CERC ROP (for
18.11.2014) enclosed
CEA letter 17.11.2014 :
No physical progress
visible on ground.
The scheme needed to be
implemented without any
further delay
Talcher II –
Behrampur 400 kV
D/C line
220
Talcher II- Rourkela
400 kV D/C Quad
line
161
Behrampur 400/220
kV, 2x315 MVA S/S 2x315
3.3.4.1 The following had been noted in the TCC Meeting:
APTRANSCO had stated that 400 kV Srikakulam – Garividi D/C line needs
to be expedited.
CTU had informed that this line is under TBCB route and APTRANSCO
could recommend it to be executed by PGCIL, if so desired.
Regarding Talcher-II back up scheme, it was noted that a Petition in this
regard was being heard by Hon’ble CERC.
3.3.4.2 In the Meeting, TSTRANSCO stated that possibility of drawing power by Telangana
through Angul- Srikakulam line needed to be examined. CTU clarified that an inter-
regional line would generally help increase the ATC, irrespective of its actual
Minutes of the 26th Meeting of SRPC held on 20th December 2014 19 of 73
connectivity in this region. Increase in Drawal capability of any utility may however
depend on the quantity of additional access granted to it.
3.3.4.3 CTU informed that evacuation schemes had been discussed and finalized in a
comprehensive manner in the 37th
Meeting of Standing Committee. Hyderabad was
getting well connected to Wardha and Warora, while evacuation beyond Vemagiri to
Chilkalurupeta/Cuddapah was through the TBCB route.
3.3.4.4 APTRANSCO suggested that CTU may take up execution of 400 KV Srikakulam –
Garividi line. They informed that they would take up the matter with Empowered
Committee regarding execution by CTU of this line keeping in view the urgency.
3.3.5 Warora Pool – Warangal 765 kV D/C line
Transmission
Element
Implementing
Agency
Line
length
(ckm)/
MVA
Capacity
COD
Constraints / Remarks
Sch.
Ant /
Act
Warora Pool –
Warangal 765 kV
D/C line
This line has been
approved as additional
inter-regional link for
importing power into
Southern Region, and
recommended for
implementation in
Southern Region’s
Standing Committee on
Power System Planning in
its 37th
meeting held on
31.07.2014
Warangal (New) –
Hyderabad 765 kV
D/C line
Warangal (New) –
Warangal (existing)
400 kV (quad) D/C
line.
Warangal (New) –
Chilakaluripeta 765
kV D/C line
Warora 765/400 kV,
2x1500 MVA S/S PGCIL 2x1500
Warangal (New)
765/400 kV, 2x1500
MVA S/S
PGCIL 2x1500
Minutes of the 26th Meeting of SRPC held on 20th December 2014 20 of 73
3.3.5.1 In the TCC Meeting, CTU had informed that the scheme was discussed in the
Empowered Committee and is coming through TBCB route.
3.3.5.2 In the Meeting, CMD, TSTRANSCO requested that Warora – Warangal Line be
kindly expedited. ED, SRTS-I, PGCIL clarified that the lines were to be executed
under TBCB route. It was also noted that matter regarding Vemagiri – Khammam –
Hyderabad line was before Hon’ble CERC.
3.4 Status of upcoming links having impact on S1-S2
3.4.1 Following is the updated status of the links having impact on S1-S2 ATC:
Sl.
No. Transmission Element Schedule Remarks
1 400/230 kV Thiruvalam S/S and
associated LILOs
Both the ICTs and LILOs
completed by October 2014.
2 400 kV Thiruvalam - Melakottaiyur Commissioned on
24.07.2014
3 400 kV Somanahalli- New Salem June. 2015
Approval for enhanced
compensation is awaited from
CC,PGCIL
4 400 kV Pugalur- Kalavindapattu Both ckts commissioned
5 765 kV Kurnool-Thiruvalam Commissioned on
27.11.2014
6 400 kV Mettur- Singarapet- Thiruvalam Jan. 2015
7 LILO of Kolar- Sriperumbudur at
Thiruvalam Commissioned in March
2014
8 400 kV Mysore-Kozhikode May. 2015 Held up due to ROW issue.
9 400 kV Mangalore (UPCL ) -Kasargode-
Kozhikode
Approved by Standing
Committee & SRPC. KPTCL
stated that they had furnished
load flow studies and their
comments keeping in view of
2000 MW HVDC link at
Madakathara and hence the
necessity of the line to be
reexamined. KSEB, CTU &
SRLDC stated that the line
was absolutely essential.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 21 of 73
3.4.2 It had been noted that CTU had not been specifying the ATC of S1 – S2 corridor.
CTU/POSOCO were to appraise the forum of the schedule of release of ATC.
TANTRANSCO vide letter dated 29th
November 2014 (refer Annexure-II) had stated
that the present status of erection work of lines to relieve S1-S2 corridor congestion
may please be discussed. In addition, Karnataka had to cater their Yerandahalli load of
80 MW from Somanahalli itself. It had also been stated that though SPS on 400 kV
Hosur-Salem D/C line had been provided by Tamil Nadu, the ATC had not been
increased. Further, due to drawal of KSEB, the flow on 400 kV Kolar-Hosur D/C line
was always maintained high.
3.4.3 The following had been noted in the TCC Meeting:
KPTCL had stated that with regard to proposed UPCL-Kozhikode line,
they had furnished their comments, keeping in view the planned 2,000 MW
HVDC terminal at Madakathara. It had been opined that the scheme needed
to be justified technically before looking into any commercial issue.
SRLDC had stated that the UPCL-Kozhikode line was necessary from the
reliability point of view. Under PoC regime, transmission charges would be
borne by the concerned utility using the system. CTU stated that the
scheme had been planned keeping in view comprehensive perspective LGB
scenario. PGCIL also observed that presently there was no N-1 reliability
for the UPCL plant. This link would thus improve reliability under N-1
contingency. They also informed that a site survey had been carried out
recently with the participation of CEA. MS, SRPC noted that the scheme
had been agreed in the Standing Committee and also by SRPC.
KSEB had observed that all concerned issues had been studied and
subsequently only the scheme had been approved. The line was absolutely
necessary for connectivity to North Kerala. Two more units were also
likely to come up in the UPCL complex; hence the requirement of the line
is more justified.
Regarding Thiruvalam- Mettur line, MD, TANTRANSCO informed that
the line was held up at 14 towers due to NGT clearances. They were
hopeful of getting the line through by January 2015.
3.4.4 In the Meeting, ED, SRTS- II, PGCIL informed that order regarding enhanced
compensation in respect of 400 kV Somanahalli- New Salem line was awaited.
PGCIL Management would take a suitable decision in this regard.
3.4.5 MD, TANTRANSCO stated that shut down of 45 days in respect of Somanahalli –
Salem line could be allowed during wind season in TN (after April / May 2015).
3.4.6 Director (Tr.), KPTCL informed that in view of the changed scenario ( HVDC at
Trichur), a letter had been addressed in respect of UPCL- Kasargode – Kozhikode
line.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 22 of 73
3.4.7 ED, SRLDC said that from the reliability point of view UPCL- Kasargode –
Kozhikode line was highly essential.
3.4.8 Chief Engineer (Tr.), KSEB said that the proposed link (UPCL- Kasargode –
Kozhikode) would help KPTCL also in smooth evacuation of power from UPCL,
even under outage of UPCL- Hassan line. He added that joint inspection with
participation of CEA had already been carried out. Additional units were also being
planned in UPCL. Space for 400 kV substation at Mylatti had been identified. No
RoW constraints were anticipated in the Kerala portion of the line. The scheme had
already been approved in Standing Committee. He stated that KSEB was not aware of
KPTCL letter in this regard and requested for a copy of the same.
3.4.9 RoW of 400 kV Mysore-Kozhikode D/C line
3.4.9.1 In the 25th
Meeting of SRPC the following had been noted:
KSEB had stated that the completion of 400 kV Mysore-Kozhikode
(Areakode) D/C line is urgently required since Northern Kerala was facing
acute power shortage. Due to forest clearance and RoW disputes, the line
work was held up in Karnataka. 400 kV line works in Kerala and
construction of 400 kV substation at Areakode had been completed and kept
idle for want of this line.
KPTCL had informed that Karnataka State Government had constituted an
Expert Committee to examine alternative possibilities for this line. The
Committee had almost finalized the Report which was expected to be
submitted shortly.
3.4.9.2 In the 101st OCC Meeting on 11
th November 2014, SR-II, PGCIL had informed that
the works on this line had resumed. The status may please be appraised by
POWERGRID. Petition No. 120/MP/2014 was heard by Hon’ble CERC on 13th
November 2014. The Commission had reserved order in the petition.
3.4.9.3 The following had been noted in the TCC Meeting:
PGCIL had informed that they had resumed work with support of State
Govt. In case conducive environment persisted, they would complete this
line by June 2015.
KSEB had stated that the line was extremely critical for North Kerala.
They suggested that PGCIL may deploy multiple agencies to expedite the
works.
KPTCL had assured that they would continue to support PGCIL for
completion of works on this line.
3.4.9.4 In the Meeting, CE (Tr. & SO), KSEB reiterated that Mysore – Kozhikode line was
needed to be commissioned at the earliest, since northern part of Kerala was facing
acute constraint.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 23 of 73
3.5 Other upcoming Intra-regional transmission elements
3.5.1 Updated status of other critical upcoming lines is given below:
Sl.
No. Transmission Element Schedule Remarks
1 765 kV Salem- Madhugiri December
2015
Severe RoW problem near
Madhugiri.
2 400kV Krishnapattanam- Chittoor March 2015 APTRANSCO was requested to
expedite commissioning to
avoid evacuation constraints.
SRLDC had stated evacuation
should be restricted to 800 MW.
3 400kV Almathy-Thiruvalam D/C line Jan.2015 ROW issues at 17 locations.
4 400 kV Edamon-Kochi Held up due to RoW issue.
KSEB informed that GO for
compensation is awaited. KSEB
was requested to settle the
compensation issues within one
month to enable PGCIL to
initiate works.
3.5.1.1 In the TCC Meeting, regarding Krishnapattanam - Chittoor, APTRANSCO had
informed that they would commission the planned evacuation system by March
2015. SRLDC had stated that during the interim period, evacuation had to be
restricted to 800 MW from Krishnapattanam JV.
3.5.1.2 The Committee noted the above.
3.5.2 400 kV Edamon-Kochi line
3.5.2.1 In the 25th
Meeting of SRPC, the following had been noted:
POWERGRID had filed a petition before Hon’ble CERC seeking
provisional tariff on the expenditure incurred on construction of Edamon -
Cochin 400 kV D/C (Quad) line till 31.03.2014 and adjudication of dispute
between the petitioner and Govt. of Kerala with regard to the compensation
determined by the latter in terms of Section 67 (4) of the Electricity Act.
Hon’ble CERC had issued RoP in respect of Petition No. MP/083/2014
(date of hearing 17th
June 2014) wherein the following was stated:
“(d) Under the circumstances, the petitioner finds no way to complete the
Projects and seeks recovery of expenditure already incurred in a suitable
manner. “
KSEB had informed that it had been decided that additional compensation
of about Rs. 341 Crores would be borne by the Government of Kerala. They
were in discussion with PGCIL to work out the schedule and works were
likely to commence by mid-August 2014.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 24 of 73
3.5.2.2 In the 101st OCCM, KSEB had informed that they are extending all support for the
early completion of Tirunelveli- Kochi line in Edamon – Kochi portion. KSEB had
already taken up the task of liaisoning and a senior Executive Engineer has been
assigned the dedicated task.
3.5.2.3 Petition No. MP/083/2014 was heard by Hon’ble CERC on 13th
November 2014. The
Commission had reserved order in the Petition.
3.5.2.4 The following had been noted in the TCC Meeting:
PGCIL had expressed concern that despite several Meetings, assurance on
compensation issues being settled by Kerala Govt etc. there had virtually
been no progress at ground level. Around one and half year ago, PGCIL
had stated that they were ready to abandon this line and that KSEB could
take over and execute the pending works.
KSEB had informed that the G.O. of Kerala Govt. on enhanced
compensation was awaited and the same was expected within a month.
KSEB assured that RoW issues would be settled enabling PGCIL to take
up the works.
KSEB was again requested to settle the compensation issues within one
month in the interest of speedy completion of pending works.
3.5.2.5 In the Meeting, ED, SRTS-II, PGCIL informed that it was becoming extremely
difficult for PGCIL to continue with the project. They were willing to wind up the
project or else Kerala could take over the line.
3.5.2.6 On a query from Chairperson, SRPC on compensation, CE, KSEB informed that
compensation at higher rate amounting to Rs.321 Crores would be paid by
Government of Kerala for tower foot print as well as corridor also. Steps had been
initiated and once GO is issued, compensation issue would get settled.
3.5.3 400 kV Trichur-Kozhikode line (Madakkathara- Areakode)
The following had been noted till 25th
Meeting of SRPC:
KSEB had stated that this line had already been approved as Regional
System Strengthening Scheme. North Kerala would benefit since 400 kV
supply could be availed either from Udumalpet or from Mysore for all the
400 kV substations in Kerala. Multi circuit & multi-level circuit was their
requirement for surrender of corridor.
PGCIL had sought utilization of existing 220 kV Madakkathara-
Malaparamba-Areakode S/C feeder. There was no possibility of
surrender of RoW of KSEB line presently since energy security of
Malabar region was involved. Line works could be taken up only after
commissioning of the 400 kV Mysore-Kozhikode line. PGCIL had been
requested to initiate the process so that construction could commence
immediately after 400 kV Mysore-Kozhikode line was commissioned.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 25 of 73
3.6 Transmission Constraints Requiring Attention
Following constraints had been noted in various fora:
Overloading of Hiriyur- Nelamangala D/C & Jindal‐BTPS S/C Line
Till parallel lines are developed KPTCL to restrict upstream
generation and downstream load.
Prioritizing and expediting commissioning of the transmission system
planned for Yermarus TPS .
Early Commissioning of 220 kV Hiriyur ‐ Gowribidanur D/C line
under construction by KPTCL would help in relieving this line to
some extent.
In the TCC Meeting the KPTCL had informed the following:
Out of 120 Km of 220 kV Hiriyur – Gowribidanur line, 118 Km had
been completed and test charged from the other end. Out of 436
locations 434 locations foundation have been completed while 429
towers had been completed. The completion was being followed up
and the line is expected in January 2015.
JWSEL is executing 400 kV S/S at Bellary which would be handed
over to KPTCL. Tenders finalized for 400 kV Bellary – Madhugiri
line (200 Km). Schedule for completion is 24 months with incentive
clauses for early commissioning. For 400 kV Bellary – Yeramarus
line, tenders would be shortly floated
400 kV Chikanayakanahally – Bellary (JSWEL) would be taken up
once the land acquisition for Chikanayakanahally S/S is finalized
The Committee noted the above.
Hinduja Evacuation
Till the ATS is developed total injection at Vemagiri to be restricted
to 600 MW.
In the TCC Meeting, APTRANSCO had informed that the
evacuation scheme was expected in about 8 Months. They assured
that injection from the Vemagiri complex would be restricted to
600 MW till evacuation system is in place.
The Committee noted the above.
Overloading of 230 kV and below system in TN during high wind
season also leading to low voltages
Identified evacuation lines to be developed by TANTRANSCO to be
prioritized and expedited.
Provision of Under Voltage Relays (UVR) to be ensured.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 26 of 73
The following had been noted in the TCC Meeting:
TANTRANSCO had informed that Kanarpatty S/S would be
commissioned by next year, while Kayathar S/S had been
commissioned. The situation had eased to some extent with the
commissioning of Kayathar S/S. Besides substantial wind presence,
2,000 MW of solar project were also coming up in the state. Hence,
as a comprehensive measure, network strengthening at 400 kV and
230 kV was planned. Under kfW scheme, various 400 kV and 230
kV network strengthening schemes were under execution. 15
number of capacitor bank had also been planned to be installed
shortly to address under voltage issue.
SRLDC had pointed out that since wind generation had come down
the situation had presently eased. With wind generation picking up
from May 2015 onwards, there could be evacuation constraints
coupled with low voltages. It was also suggested that TN may
kindly furnish full details of the schemes along with schedule of
commissioning dates. TANTRANSCO agreed to furnish the same.
The Committee noted the above
Once S1-S2 lines are in place the loading on 400 kV Salem‐Udumalpet
would be a concern
400 kV Mettur‐ Thiruvalam line to be expedited
In the TCC Meeting, TANTRANSCO had informed that Mettur-
Thiruvalam line would be commissioned by January 2015.
The Committee noted the above
Overloading of Khammam‐Nagarjuna Sagar S/C line
400 kV D/C line between Khammam and Nagarjuna Sagar to be
expedited.
The following had been noted in the TCC Meeting:
TSTRANSCO had stated that presently there was no overloading
of Khammam- Nagarjunasagar S/C line.
SRLDC had clarified that this was a future anticipated constraint.
PGCIL had informed that 400 kV Khammam - Nagarjunasagar
line (under TBCB) would come up in the first quarter of 2016.
The Committee noted the above.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 27 of 73
Overloading of 400/220kV 500 MVA ICTs at Somanahalli 2 Nos.&
Radialization of Lines
Redistribution/ reconfiguration of 220 kV transmission lines around
these substations is required.
The following had been noted in the TCC Meeting:
KPTCL had informed that comprehensive plan for Bengaluru
(7,500 MW) has been envisaged and had been approved by the
Board. Presently the load met was about 2,700 MW out of 5,600
MVA capacity. About Rs.1,100 Crore had been earmarked for the
strengthening works.
Tender had been finalized for strengthening Somanahalli - Peenya
section and they were planning to complete it within one year.
The Committee noted the above
Overloading of 400/220kV 315MVA ICTs at Mysore‐ 2Nos.
Strengthening at 220 kV level around Mysore is required. This needs
to be planned by KPTCL. 500 MVA ICT expected by 2017 (award
placed in September 2014).
In the TCC Meeting, PGCIL was requested to expedite the
commissioning. PGCIL agreed to prioritize and expedite the
commissioning of the ICT.
The Committee noted the above
Overloading of 400/220kV 315MVA ICTs at Kalvindapattu‐2 Nos
Commissioning of newly planned substations at Thiruvalam and
Sholinganallur would help 500 MVA ICT expected by 2017. ( award
placed in September 2014)
In the TCC Meeting, PGCIL was requested to expedite the
commissioning. PGCIL agreed to prioritize and expedite the
commissioning.
In the Meeting SRTS-II, PGCIL informed that order had been placed and they
would try to expedite commissioning to the extent possible.
Overloading of 400/220kV 315MVA ICTs at Trichur‐ 2Nos and
Palakkad‐ 2Nos
Loading of ICTs at Trichur would ease after Mysore-Kozhikode 400
kV line. 3rd
ICT at Trichur (315 MVA) was commissioned on 31st
October 2014.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 28 of 73
In the TCC Meeting, it was noted that the situation may get
mitigated after commissioning of 400 kV Mysore-Kozhikode
lines. In the meanwhile KSEB was suggested to take steps to
avoid any overloading of the ICTs at Trichur and Palakkad.
The Committee noted the above
400 kV Udumalpet – Palakkad D/C lines are heavily loaded during
high drawal by KSEB
This could limit the drawal by Kerala in future.
The following had been noted in the TCC Meeting:
Udumalpet - Palakkad lines were violating N-1 criteria in certain
occasions.
KSEB was requested to take steps to avoid overloading of
Udumalpet - Palakkad D/C line. There should be no overdrawal
during N-1 contingency.
The Committee noted the above.
400/220 kV 315 MVA ICTS at Gazuwaka are overloaded
The following had been noted in the TCC Meeting:
PGCIL had suggested that the 315MVA ICTs be replaced with
500 MVA ICTs on account of space constraints. The 315 MVA
ICTs could be utilized as regional spare.
TCC had recommended for up-gradation of 2x315 MVA ICTs to
2x500 MVA along with associated bay equipment. Two 315
MVA ICTs would be utilized as regional spare.
The Committee approved up-gradation of 2x315 MVA ICTs to 2x500 MVA along
with associated bay equipment. Two 315 MVA ICTs would be utilized as regional
spare.
Loading on 220 kV Kadakola –Kaniampetta lines
In the 101st OCCM (held on 11.11.2014) KPTCL had informed that
there had been loss of elephant life due to electrocution close to this
corridor. Keeping the various issues in mind, the loading was needed
to be restricted to 120 MW on this line.
KSEB categorically stated that any further reduction in the power
flow through this line would result in perpetual load shedding in
Northern Kerala and cannot be agreed upon. Special maintenance for
the line had already been discussed in earlier SRPC Meetings.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 29 of 73
It was agreed that loading upto 150 MW would continue and the issue
would be put up to TCC.
The following had been noted in the TCC Meeting:
KPTCL had informed that they had assessed the requirement for
intermediate towers at critical locations and tenders would be
called shortly. KPTCL would share the corridor details with
KSEB..
Similarly, KSEB had also been suggested to assess and furnish
corridor details in their portion.
KSEB had stated that they would also examine the issues in
coordination with KPTCL. They agreed to furnish the details
within one month time. In the meantime, flow on the line would
be allowed upto 150 MW. It was also pointed out that any
shutdown of this line could only be agreed after commissioning of
400 kV Mysore-Kozhikode line. KSEB agreed to restrict the
loading below 150 MW in all instances.
It was noted that the issue would be deliberated in a Meeting to be
held on 9th
January 2014 at PCKL.
In the Meeting, CE, KSEB informed that there was no clearance issue in Kerala
portion of the line.
KPTCL suggested that OCR at 150 MW could be activated to restrict the flow.
KSEB assured that flow would be restricted to 150 MW and OCR was not
required.
220 kV Sharavathy –Talaguppa lines over loading
In the TCC Meeting, KPTCL had informed that reconfiguration
works would be completed within 3 months
The Committee noted the above.
Strengthening of Hyderabad downstream system
The following had been noted in the TCC Meeting:
TSTRANSCO had informed that a number of lines and
substations had been planned in the Hyderabad area for
augmentation purposes.
SRLDC had requested that these details be shared by
TSTRANSCO. TSTRANSCO agreed to furnish the details.
TSTRANSCO informed that 9 nos 220 KV substations were
planed around Hyderabad.
The Committee noted the above.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 30 of 73
Rayalaseema TPP – Chinakampally lines overloading
In the TCC Meeting, APTRANSCO had informed that 3rd
D/C
line would be commissioned by end February 2015.
The Committee noted the above.
Nellore ICT Overloading
In the TCC Meeting, APTRANSCO had informed that 3rd
ICT
would be commissioned within 3 months’ time.
The Committee noted the above.
Additional ICT at Vijayawada
The following had been noted in the TCC Meeting:
APTRANSCO had requested for expediting the commissioning of
additional ICT at Vijayawada.
PGCIL had informed that the Order for 3rd
ICT at Vijayawada had
been placed and they would expedite the commissioning.
The Committee noted the above.
Overloading of Hosur-Shoolagiri
The following had been noted in the TCC Meeting:
TANTRANSCO had informed that approval has been accorded for
2nd
circuit of Hosur – Shoolagiri. Approval was under progress for
Uddanapalli S/S (near Hosur).
KPTCL had informed that system strengthening was under progress
and they would be able meet the load from their end without
depending on Hosur by July 2015.
The Committee noted the above.
PST at Kothagudem
In the TCC Meeting, TSTRANSCO had informed that the Phase
Shifting Transformer (PST) has been synchronized on 1st
December 2014 with objective of relieving the 220 kV network
and injecting more power into 400 kV network.
The Committee noted the above.
3.7 Closing of Upper Sileru-Balimela Line
3.7.1 In the 25th
SRPC Meeting it had been agreed that the Upper Sileru- Balimela Line be
closed again on an experimental basis. Apprehensions of AP would be addressed
including those relating to quick exchange of codes.
3.7.2 SR constituents were ready for trial operation and the line was closed from AP end.
In the 99th
OCC it had been agreed to have a trial operation on 19th
September 2014.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 31 of 73
In the 101st OCC Meeting, APTRANSCO had informed that temporary
reconfiguration (Upper Sileru-Pendurthi) carried out due to “Hud Hud” cyclone, the
exercise would not be possible till the original system is restored.
3.7.3 In the TCC Meeting, APTRANSCO had informed that normalization works would
take about 10 days. There were some issues with Railways which had been sorted out.
Subsequently, trial operation could take place on the Upper Sileru – Balimela line.
3.7.4 In the Meeting, MS, SRPC said that the line was needed to be closed at the earliest and
that the matter was also being reviewed by MoP. He noted that 150 MW flow on this
line had been considered as import capability towards SR in the Perspective Plan.
3.7.5 The Committee noted the above.
4. TRANSMISSION LINES APPROVED IN 37th
MEETING OF SCPSPSR
4.1 The 37th
Meeting of Standing Committee on Power System Planning of Southern
Region (SCPSPSR) was held on 31st July 2014. The Minutes of the Meeting along
with Corrigendum is enclosed as Annexure-V.
4.1.1 TCC had recommended the Schemes (along with the Corrigendum) as agreed in the
37th
Meeting of Standing Committee on Power System Planning of Southern Region
(SCPSPSR) held on 31st July 2014 for approval.
4.1.2 The Committee approved the Schemes (along with the Corrigendum) as agreed in the
37th
Meeting of Standing Committee on Power System Planning of Southern Region
(SCPSPSR) held on 31st July 2014.
4.2 Evacuation System for Ultra Mega Solar Park (1,000 MW) in AP
4.2.1 The following had been noted in the TCC Meeting:
PGCIL had appraised the forum about the urgent evacuation need for 1,000
MW Ultra-Mega Solar Park in Anantapur District of Andhra Pradesh since
gestation period for Solar Park was quite short (PGCIL Agenda at
Annexure-VI). This important prestigious renewable project was being
followed up at the highest level. Under Phase-I, evacuation for 250 MW was
being planned. Tender for S/S had already been issued and the same for
transmission line package was under process. The complete scheme would
be taken up with Standing Committee for ratification. The proposed
transmission scheme is as under:
Minutes of the 26th Meeting of SRPC held on 20th December 2014 32 of 73
Phase-I
Establishment of 3 x 500 MVA, 400/220 kV Substation at NP Kunta.
LILO of 400 kV Kadapa-Kolar S/c Line at NP Kunta.
1 x 125 MVAR Bus Reactor at NP Kunta along with +- 100 MVAR
STATCOM.
Phase-II
NP Kunta – Kadapa 400 KV D/C line.
LILO of 765 kV Kurnool – Thiruvalam D/C at Kadapa*
Up gradation of Kadapa S/s at 765 kV with 2 x 1500 MVA, 765/400 kV
transformation capacity*
2 x 240 MVAR Bus Reactors at 765 kV Kadapa S/s*
* Already approved in the 37th
SCPSPSR as System Strengthening
Scheme XXIV in SR being implemented by POWERGRID.
KSEB had enquired whether this scheme would curtail the margin for S-2
constituents in any manner. CTU had clarified that this scheme would only
help in making more power available at the mouth of S-2 region.
TCC had recommended the scheme for approval, subject to necessary
ratification of the Standing Committee on Power System Planning.
4.2.2 The Committee approved the scheme, subject to necessary ratification of the Standing
Committee on Power System Planning.
5. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE& UMPP
5.1 NTPC- Kudigi TPS Stage-I (3x800 MW)
5.1.1 In the 24th
& 25th
Meeting of SRPC, the following had been noted:
NTPC had informed that synchronization of Unit-I was expected during
September 2015 and Unit-II during March 2016.
KPTCL had informed that chunk of land for Stage-II had been identified
near Stage-I. NTPC could expedite activities relating to Stage-II also.
NTPC had informed that they were in the process of firming up coal
requirements/availability and subsequently other activities could be taken
up.
NTPC had informed that on 5th
July 2014 there had been a law & order
incident involving disruption. Works had come to a standstill. Though the
State Government was extending full support, the workmen were yet to
come back. The concerned agencies were being asked to get the workmen
back to site. In such a scenario, it would be difficult to estimate the effect of
this disruption on the project schedule.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 33 of 73
5.1.2 The following had been noted in the TCC Meeting:
NTPC had informed that Unit-I synchronization was planned for
February 2016 while CoD was expected by April 2016. CoD of Unit –II
was expected subsequently after 6 months.
CTU had informed that AP DISCOMs (undivided) were having share of
418 MW. After reorganization, revised application for LTA needed to be
furnished by NTPC/AP /Telangana.
TSTRANSCO had informed that sharing percentage as per the AP
Reorganization Act 2014 holds good for any project under construction
also. They would ensure the needful in coordination with NTPC.
Director (Grid & Tr), APTRANSCO had stated that any sharing would
need to be carried out as per the Reorganization Act 2014.
5.1.3 The Committee noted the above.
5.2 NLC-Neyveli TS-II Expansion (2x 250 MW)
5.2.1 In the 25th
Meeting of SRPC, the following had been noted:
NLC had informed that BHEL had committed synchronization of Unit-1 by
mid-August 2014. CoD of Unit-I was expected during August 2014 and
CoD of Unit-II during September 2014.
NLC had again filed a Petition for extension of injection of infirm power
until 31st March 2015. The delay in commissioning was affecting S1-S2
ATC also.
5.2.2 In the 26th
Meeting of Commercial Sub- Committee of SRPC held on 21st November
2014, NLC had informed that CoD of Units I & II are expected by December 2014.
5.2.3 In the TCC Meeting, NLC had informed that bulk of the issues relating to Heat
Exchanger and Refractory works had been resolved. CoD of Unit –I was expected by
first week of January 2015. Unit II was also in advanced stage of commissioning and
CoD of the unit was also expected by end January 2015.
5.2.4 The Committee noted the above.
5.3 NLC - New Thermal Power Project (2x 500 MW) at Neyveli
5.3.1 The following had been noted in the 25th
Meeting of SRPC:
NLC had informed that CoD of Unit-I & Unit –II was expected by October
2017 & April 2018 respectively.
5.3.2 In the TCC Meeting, NLC had informed that there was no change in the schedule.
5.3.3 The Committee noted the above.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 34 of 73
5.4 NPCIL-Kudankulam Nuclear Power Project (KKNPP) Stage-I (2x1000 MW)
5.4.1 Following had been noted in the 25th
Meeting of SRPC:
NPCIL had filed Petition before Hon’ble CERC praying that they be
permitted injection of infirm power to the grid till declaration of CoD of
KKNPP Unit-1 or 22.10.2014, whichever is earlier.
NPCIL had informed that final phase of pre CoD tests were continuing.
Unit-I was under shutdown as per AERB requirements and CoD of the unit
was expected by end of August 2014. Synchronization of Unit- II was
planned by December 2014 and CoD by March 2015.
5.4.2 Subsequently, NPCIL had filed Petition (Petition No. 408/MP/2014) seeking permission
of Hon’ble CERC to continue injection of infirm power in Southern Grid till declaration
of COD of Unit-I or 22nd
January 2015, whichever is earlier. Hon’ble CERC vide order
dated 10.11.2014 had allowed extension of time for injection of infirm power into the
grid for commissioning tests including full load test of unit up to 22.1.2015.
5.4.3 MoP vide letter dated 10th
November 2014 (Annexure-VII) had allocated 50 MW
unallocated power of Second Unit (1000 MW) of KKNPP to Telangana. This is to be
implemented from the date of commercial operation of the unit.
5.4.4 The following had been noted in the TCC Meeting:
NPCIL had informed that Unit- I was running at 1,000 MW and CoD was
expected before 22nd
January 2015. Unit –II was planned to be critical by
end April 2015 while synchronisation was planned by July 2015.
PCKL had observed that the allocation to Telangana needed to be
ascertained since AP & Telangana were not the original beneficiaries of the
project.
MS, SRPC had clarified that allocation of unallocated power was at the
discretion of MoP.
5.4.5 The Committee noted the above.
5.5 BHAVINI- Kalpakkam PFBR (500 MW)
5.5.1 In the 24th
/ 25th
Meeting of SRPC, the following had been noted:
TANTRANSCO had informed that tender in respect of Kancheepuram S/S
had been finalized and the substation was expected to be ready by
September 2014.
Reactor could go critical by September 2014 and power injection was
expected by November 2014.
5.5.2 In the 26th
Meeting of Commercial Sub-Committee of SRPC held on 21st November
2014, BHAVINI had informed that the unit would be commissioned during March
2015.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 35 of 73
5.6 NTECL - NTPC & TNEB Joint Venture - Vallur STPS Unit- III (500 MW)
5.6.1 The following had been noted in the 25th
Meeting of SRPC:
NTECL had informed that all activities except CHP had been completed
and they were putting best efforts to complete balance works by August
2014. As abundant precaution, NTECL had approached Hon’ble CERC
seeking permission for infirm power injection up to 15th
October 2014.
5.6.2 Subsequently, Hon’ble CERC vide order dated 25.08.2014 had allowed extension of
time for injection of infirm power into the grid for the commissioning tests including
full load test of Unit-3 up to 15.10.2014 or actual date of commercial operation,
whichever is earlier. Further vide Order dated 17.10.2014, Hon’ble CERC in Petition
No. 392/MP/2014 had allowed extension of time for injection of infirm power into the
grid for the commissioning tests including full load test of Unit up to 31.12.2014 or
actual date of commercial operation, whichever is earlier.
5.6.3 In the 26th
Meeting of Commercial Sub- Committee of SRPC held on 21st November
2014, NTECL had informed that CoD of Unit III is expected by December 2014.
5.6.4 In the TCC Meeting, NTECL had informed that most of the issues had been resolved
and CoD was expected before 31st
December 2014.
5.6.5 The Committee noted the above.
5.7 NLC Tamil Nadu Power Limited (NTPL - JV Company of NLC & TANGEDCO)
at Tuticorin (2x500 MW)
5.7.1 The following had been noted in the 25th
Meeting of SRPC:
NLC had informed that the unit was in the final phase of commissioning.
CoD of Unit-I expected by August 2014 & CoD of Unit- II expected by
September 2014.
5.7.2 In the 26th
Meeting of Commercial Sub- Committee of SRPC held on 21st November
2014, NLC had informed that CoD of Unit - I is expected by December 2014 and Unit-
II by February 2015.
5.7.3 In the TCC Meeting, NLC had informed that they had received ‘Consent to Operate’
pending forest clearance. Synchronization of Unit-I was planned during January 2015
while CoD was scheduled by February 2015. Unit –II CoD was scheduled by March
2015.
5.7.4 The Committee noted the above.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 36 of 73
5.8 Krishnapattanam UMPP (6x660 MW)
5.8.1 In the 25th
Meeting of SRPC, APTRANSCO had informed that the matter was before
Hon’ble CERC as well as Hon’ble Delhi High Court. It was understood that Hon’ble
CERC had asked Reliance Power to first settle the matter before High Court and revert
back. The Developer had sought a Meeting with the procurers. TN had requested AP to
kindly continue to take the lead and arrange a Meeting at the earliest. APTRANSCO
had assured that a Meeting would be called at the earliest.
5.8.2 In the TCC Meeting, APTRANSCO had informed that a Meeting with Developer and
Procurers was conducted on 21st August 2014. A Consultant had been appointed to look
into commercial, financial and legal issues. Report of the Consultant was expected
within one month time which would be shared with other Procurers.
5.8.3 The Committee noted the above.
5.9 Cheyyur UMPP (4000 MW)
5.9.1 In the 25th
Meeting of SRPC, it had been noted that the project had now been revived.
RfQ had been issued and project developer (M/s Coastal Tamil Nadu Power Ltd. - SPV
of PFC) had applied for LTA to CTU.
5.9.2 In the TCC Meeting, TANTRANSCO had informed that Request for Qualification
(RfQ) document was opened on 20.11.2013. Request for Proposal (RfP) documents
were scheduled to be opened on 22.12.2014. The 1st Unit would expected to be
commissioned in 42 months from zero date (2018-19) and the subsequent units would
be commissioned at the interval of six months.
5.9.3 The Committee noted the above.
5.10 Schedule of synchronizing/commissioning of the new projects of NTPC, NLC, NPCIL,
BHAVINI, and Joint Venture & UMPP is furnished below:
Station Unit Installed
Capacity
MW
Scheduled date of
synchronizing /
commissioning
Remarks
NTPC
Kayamkulam I, II,
III
1050/
1950
12th
Plan Gas supply by 2014. Kerala
requested for 500 MW. TN &
Puducherry would consider after
knowing the tentative tariff. AP &
KAR DISCOMs were not willing to procure the power.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 37 of 73
Kudgi TPS
Stage-I
I,I,
III
3x800=
2400
Unit-I :
synchronization by
February 2016
(CoD by April
2016)
Unit-II: CoD by
October 2016
Construction activities in
progress. Evacuation issues
needed to be addressed.
NLC
Neyveli-II Expn. I 250 1st week of January
2015
Injection of infirm power sought
up to March 2015
II 250 End of January
2015
New Thermal
Power Project
I 500 October 2017
II 500 April 2018
Sirkali TPP I, II,
III
3x660 From GoI approval
Unit I – 52 months
Unit II – 58 months
Unit-III – 64
months
PPA has been signed. Fuel
imported coal. Approval of
Feasibility Report was awaited
from NLC Board.
NPCIL
Kudankulam
Stage-I
I 1000 CoD by 22nd
January 2015
Synchronized on 22nd
October
2013. Reached 1000 MW
generation level.
II 1000 Synchronization by
July 2015
Work in progress
BHAVINI
Kalpakkam
(PFBR)
I 500 March 2015
NTECL ( NTPC & TNEB JV)
Vallur STPS I 500 Original schedule:
February 2011
CoD on 29.11.2012
II 500 Original schedule:
August 2011
CoD on 25.08.2013
III 500 December 2014 Synchronized on 28.02.2014
NTPL (JV Company of NLC & TANGEDCO)
Tuticorin I 500 Original schedule:
40 months after
LOA
Anticipated
schedule:
February 2015
LOA signed on 28.01.2009
Unit ready for synchronization.
II 500 Original schedule:
45 months after
LOA
Anticipated
schedule:
March 2015
LOA signed on 28.01.2009
Unit ready for synchronization.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 38 of 73
UMPP
Krishnapattanam 3960
(6x660)
The developer had stopped the
works at site and the project may
get delayed. Meeting of
Developer & Procurers was held
on 21.08.2014. Consultant
report was awaited.
Cheyyur 4000 42 months from
Zero Date (2018-
19). Subsequent
units at six months
interval.
Site finalized during meeting of
CMs held on 04.08.08. RfQ had
been issued and project
developer (M/s Coastal Tamil
Nadu Power Ltd. which is SPV
of PFC) had applied for LTA to
CTU. RfP would be opened on
22.12.2014.
6. NEW PROJECTS OF STATE SECTOR & IPP
6.1 Following are major thermal plants coming up in Southern Region during 12th
Plan :
Sl
No.
Name of project Located in Owner Capacity
in MW
Remarks
1 Krishnapattnam JV Andhra Pradesh State 1600 U-I: Dec.14
U-II: Mar 16
2 Rayalaseema TPS ST-IV Andhra Pradesh State 600 Aug. 16
3 Meenakshi PH-II Andhra Pradesh IPP 700
4 Simhapuri PH-II Andhra Pradesh IPP 150
5 East Coast Energy
Thermal Andhra Pradesh IPP 1320 AP : 300 MW
6 Thermal Powertech. Andhra Pradesh IPP 1320 AP : 500 MW.
PPA signed.
7 NCC Krishnapattnam Andhra Pradesh IPP 1320 AP : 250 MW
8 Hinduja State IPP, Vizag Andhra Pradesh IPP 1050 Mar 2015
9 Bellary TPS U-3 Karnataka State 700 Mar 2015
10 Yeramarus TPS Karnataka State 1600 Mar 2015. No
connectivity at 400 kV
level for startup power
11 Edlapur Karnataka State 800
12 Coastal Energen Tamil Nadu IPP 1200 U-I: Trial run would
be over in few days
U: By April 2015
13 Ind-Barath Power Tamil Nadu IPP 660
14 IL&FS Tamil Nadu IPP 1200 New Environmental
Clearance under
process
15 Kakatiya TPP ST-II Telangana State 600 August 2015.
16 Singareni Telangana IPP 1200 U 1Oct 2015
U2 Dec 2015
Minutes of the 26th Meeting of SRPC held on 20th December 2014 39 of 73
6.2 The following had been noted in the TCC Meeting:
KPCL had requested startup power for Yeramarus TPS by tapping 400
kV Raichur – Gooty lines of PGCIL.
KPTCL had informed that startup power for KPCL’s Yeramarus unit
was required at 400 kV level. Tapping/LILO of Raichur - Gooty lines
had been suggested and the matter taken up with CTU.
SRLDC and PGCIL had opined that such type of scheme may not be
feasible as per Regulations. Margins available for downward transfer of
power may also get affected in case other evacuation lines did not come
up and this is used as injection of power also.
It was noted that Hon’ble CERC was already hearing a Petition
regarding LILO arrangements.
KPCL was suggested to take up the matter with the Standing Committee.
SRLDC had stated that Unit 3 of Bellary TPS should come with the
required evacuation system.
6.3 In the Meeting, KPCL requested startup power for Yeramarus TPS from ISTS as an
interim measure, since the plant was in urgent need for startup power to meet certain
deadlines. 400 kV switchyard was ready along with station transformer. The planned
evacuation line (STU) was yet to be commissioned.
6.4 Director (Tr.), KPTCL informed that the time line had been recently been advanced
and existing ISTS line (400 kV Raichur – Gooty lines) was closer to the plant.
6.5 The Committee observed that 400 kV Raichur – Gooty line was a vital link for import
of power from NEW grid. Besides, there were protection issues etc that were
involved, Petition regarding LILO arrangement etc was already before Hon’ble
Commission. KPCL was therefore advised to take up the matter appropriately with
the Standing Committee on Power System Planning.
7. COAL STOCK POSITION IN THERMAL STATIONS OF SOUTHERN REGION
7.1 Coal stock position had remained critical in APGENCO stations, Simhadri,
Ramagundam, RTPS, BTPS and at NTECL station during the period under review.
Chairperson, SRPC vide letter dated 01st August 2014 (Annexure-VIII) addressed to
Secretary (Power) had taken up this matter.
7.2 The following had been noted in the TCC Meeting:
It was noted that the coal stock position at Vijayawada, Rayalaseema, Raichur
& Tuticorin Thermal Stations remained critical. NTECL was also having
critical coal stock position and Unit-III was also coming up.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 40 of 73
NTPC had informed that presently coal stock at Ramagundam and Simhadri
was adequate for 12 & 16 days of generation respectively. NTECL was facing
some problems in the pipe conveyor which was out for the past 8 to 9 days or
so. The same was likely to come back before 20th
December 2014. Coal for 3rd
Unit had been tied up and once ‘Consent for Operation’ is received MCL would
commence the supply. Blending with imported coal was being carried out.
However, the realization from MCL for Vallur remained at around 70 % only.
TSTRANSCO had stated that the coal stock position especially in CGS needed
to be augmented keeping in view the peak months ahead.
7.3 In the Meeting, GM (S & M), MCL informed that on account of enhanced coal
production in MCL, the generating plants were in receipt of more coal as compared to
previous year. The offtake of coal had increased to 86 MT as compared to 76 MT last
year. However, sufficient Railway wagons were not available and there was stagnation
also in some sections. He also mentioned that as per MoEF guidelines, for 1st January
2015 to June 2016, all power plants had to ensure that they maintained weighted average
ash content of 34 % on a quarterly average basis. In this regard, power plants need to
make their own arrangements with the help of nearby washeries etc. so as to maintain
ash content as stipulated. Most of the plants had represented that they were maintaining
34 % through blending with imported coal etc. However, MoEF had stipulated that
during movement itself the average ash content must be within 34 %.
7.4 It was noted that the issue of 34% ash content had been discussed in earlier SRPC
Meeting wherein it was observed that with blending of imported coal, power plants
could ensure ash content as stipulated.
7.5 MCL informed that materialization for Vijayawada was about 60 % till November 2014
which had increased to 73 % during December 2014 (upto 17th
) KPCL, Raichur
materialization was more than 100 %. NTECL, Vallur materialization was 64% up to
November 2014 and had gone up to around 78 % during December 2014 (upto 17th
).
NTPC Simhadri materialization was around 72% while that of Kaniha was around 95 %.
There was adequate coal stock ,and facility for daily loading 50 rakes at Talcher and 35
rakes at Ib valley existed with MCL. However, they were getting only 37 rakes in
Talcher and 24 rakes in Ib. He requested the generating companies to take up this
matter with Railway. 100 % offer to the generating plants was being made by MCL as
per the plan.
7.6 TSGENCO opined that a dedicated corridor was required in view of number of thermal
plants coming up in the Region. The requirement for indigenous as well as imported coal
would only increase in the future.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 41 of 73
7.7 APGENCO expressed concern that only 65% of ACQ was being received by APGENCO
plants. In view of the poor coal stock in the stations, the only recourse would be to shut
down the units in the event of any unforeseen disruption in the coal transportation.
7.8 NTECL mentioned that both MCL and Railways jointly need to identify measures to
ensure adequate coal supply to plants which would in turn ensure power to end
consumers. 85 % PLF could not be maintained with just 65-70 % coal availability.
Hence, MCL & Railways could have a joint Meeting to address the issue appropriately..
7.9 Regional ED (South), NTPC said that Simhadri was requesting coal supply more than
ACQ. However, the supply was only around 65 % of the ACQ itself.
7.10 GM (S& M), MCL stated that request for coal more than ACQ was to be furnished in
the appropriate format.
7.11 Chairperson, SRPC suggested that the issues regarding coal transport be again taken up
with MoP keeping in view the long term sustainability of thermal plants.
7.12 After deliberations, the following was agreed:
Chairperson, SRPC would once again take up the issues regarding dedicated
Railway corridor, strengthening of stagnated sectors, automated signaling
system etc. with MoP.
A joint Meeting with MCL and Railways at Bhubaneshwar could be arranged.
8. SIMHADRI STPS – SCHEDULES FOR 12-10-2014 TO 25-10-2014
8.1 ‘Hudhud’ cyclone had affected generation in Simhadri STPS complex on account of
outages of major evacuation lines. Due to outage / limitations in the transmission
system, SRLDC had regulated generation from Simhadri STPS in real time based on the
line loadings etc. A Meeting of APSLDC, TSSLDC, SRLDC, NTPC & SRPC
Secretariat was held on 05th
November 2014 in NTPC, Secunderabad to discuss issues
relating to schedules of Simhadri STPS for the period from 12.10.2014 to 25.10.2014
(Record Notes of discussions available at www.srpc.kar.nic.in/website/
2014/meetings/special/rcn05-11-14.pdf).
8.2 The matter was further deliberated in the 26th
Meeting of Commercial Sub-Committee
held on 21st November 2014. After deliberations, the following had been agreed:
Revision of Generation schedules of Simhadri STPS to actual generation for all
time blocks from block No.34 of 12th
October 2014 to block No.88 of 25th
Minutes of the 26th Meeting of SRPC held on 20th December 2014 42 of 73
October 2014. Scheduled drawal of beneficiaries of Simhadri STPS Stage-II
would also be revised accordingly.
Revision of Generation schedules of Talcher STPS Stage-II for the blocks 39 to
61 for 12th
Oct 2014 with actual.
Exemption from Hon’ble CERC needs to be obtained by AP SLDC in respect
of control area of Simhadri STPS Stage-I.
In respect of schedules of Simhadri STPS Stage-I, APSLDC, TSTRANSCO &
NTPC to discuss and settle the matter separately.
In order to consider matter regarding deemed DC, NTPC needs to document
details of problems faced in synchronization of units. Coal stock position
during 12th
October to 25th
October 2014 also needs to be furnished.
Details would be put up to ensuing TCC/SRPC for kind consideration.
8.3 Subsequently NTPC vide letter dated 25th
November 2014 (Annexure-IX) had
furnished the details.
8.4 The following had been noted in the TCC Meeting:
PCKL had opined that this appeared to be a ‘Force Majeure’ condition under
‘Act of God’ and deemed DC could not be allowed. APTRANSCO stated
that the provision of the Regulations needed to be followed. KSEB observed
that deemed DC could be allowed for this case. TANTRANSCO observed
that this being a genuine ‘Force Majeure’ condition, the same could be
accepted as a onetime measure. TSTRANSCO stated that deemed DC of
past month (excluding any planned outages) could be allowed. SRPC
Secretariat opined that as per Regulations, this was a ‘Uncontrollable
Parameter’ which could be compensated during Truing Up Exercise in
accordance with CERC (Terms & Conditions of Tariff) Regulations. It was
also pointed out that this was liable to be quoted as precedence for any ‘Act
of God’ instances in future.
NTPC had stated that this was an ‘Act of God’ and deemed DC should be
allowed as natural justice. Fixed charges were recoverable at 83% availability
and Simhadri II was likely to cross 83% availability by year end. The issue
was more relating to ‘Principle’, since there would be no financial gains or
loss either to any of the beneficiaries or to NTPC. Payment of Incentive was
based on PLF and not on availability. NTPC also pointed out that similar
clause for deemed availability existed in respect of transmission elements.
Further, during transmission constraints (like Talcher-Kolar pole tripping)
deemed DC was already being accorded to Talcher – II units. A similar
treatment was being sought in this instance.
After deliberation, TCC had recommended that Deemed DC be allowed for
Simhadri II for the period from 12th
October 2014 to 25th
October 2014 as a
“one time” measure without citing this precedence in future. Deemed DC for
the affected period would be based on the average DC of Stage-II Units for
the period 5th
October to 11th
October, excluding any planned outage. The
following was also agreed:
Revision of Generation schedules of Simhadri STPS Stage-II to
actual generation for all time blocks from block No.34 of 12th
October 2014 to block No.88 of 25th
October 2014. Scheduled
Minutes of the 26th Meeting of SRPC held on 20th December 2014 43 of 73
drawal of beneficiaries of Simhadri STPS Stage-II would be revised
accordingly.
Revision of Generation schedules of Talcher STPS Stage-II for the
blocks 39 to 61 for 12th
Oct 2014 with actual.
Exemption from Hon’ble CERC was needed to be obtained by AP SLDC in
respect of control area of Simhadri STPS Stage-I (scheduling aspects).
8.5 The Committee approved the following:
Deemed DC for Simhadri STPS Stage-II for the period from 12th
October
2014 to 25th
October 2014 as a “one time” measure without citing this
precedence in future. Deemed DC for the affected period would be based on
the average DC of Stage-II Units for the period 5th
October to 11th
October,
excluding any planned outage.
Revision of Generation schedules of Simhadri STPS Stage-II to actual
generation for all time blocks from block No.34 of 12th
October 2014 to block
No.88 of 25th
October 2014. Scheduled drawal of beneficiaries of Simhadri
STPS Stage-II would be revised accordingly.
Revision of Generation schedules of Talcher STPS Stage-II for the blocks 39
to 61 for 12th
Oct 2014 with actual.
9. EMERGENCY RESTORATION SYSTEM (ERS)
9.1 Need for ERS had been felt during the recent “Hud Hud” Cyclone. In this regard CEA
had taken a Meeting on 10th
November 2014. In the Meeting it was noted that PGCIL
was having 2 ERS (1 at Vijayawada & 1 at Bangalore) in Southern Region. KPTCL had
also reported availability of ERS. APTRANSCO was planning to procure ERS.
9.2 Requirement of ERS is mandated as per Regulation 22 of CEA (Grid Standards)
Regulations 2010 as given below:
“Each transmission licensee shall have an arrangement for restoration of transmission
lines of 400 kV and above and strategic 220 kV lines through the use of Emergency
Restoration System in order to minimize the outage time of the transmission lines in case
of tower failures.”
9.3 PGCIL vide letter dated 4th
December 2014 (Annexure-X) had stated that considering
the massive cyclone that had hit Andhra Pradesh in October 2014 disrupting power
supply over considerable areas, the earlier proposal of procurement of ERS substations
be reconsidered, to take care of any such contingencies in future.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 44 of 73
9.4 The following had been noted in the TCC Meeting:
APTRANSCO had informed that tenders for 2 sets of ERS of 10 towers each
had been floated.
TSTRANSCO had informed that procurement of 1 set of ERS was under
process.
KPTCL had informed that they were having 2 set of ERS (10 towers each).
KSEB was requested to procure at least 1 set of ERS to comply with the
Regulations. KSEB enquired whether it could be funded through PSDF.
APTRANSCO informed that in the recently held Meeting on ERS at CEA it
had been pointed out that funding through PSDF may not be possible.
TANTRANSCO had informed that procurement of 2 sets of ERS was under
process.
TCC recommended for procurement of one set of 400/220/33 kV ERS
Substation for Southern Region by POWERGRID. It was also suggested that
PGCIL may endeavor to get it funded through PSDF.
9.5 Director, APTRANSCO informed that 400 kV ERS towers could also be deployed at
lower voltages also. Considering the vast extent of 400 KV network available, it would be
prudent to go for procurement of 400 KV ERS system. .The Cost for 16-17 towers ERS
was about Rs 23 Crores.
9.6 In the Meeting, on a query regarding funding from PSDF, it was clarified that as noted in
the Meeting taken by CEA on 10th
November 2014, utilities would need to procure ERS
from their own funding.
9.7 The Committee approved procurement of one set of 400/220/33 kV ERS Substation for
Southern Region by POWERGRID. PGCIL would endeavor to get the same funded
through PSDF.
10. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR
10.1 The status of implementation of Bus / Line Reactors / Dynamic Compensation
approved in the Standing Committee / SRPC pending for commissioning by the SR
constituents are furnished below:
Entity Bus Name Status REMARKS
KPCL Raichur TPS
By March 2015.
Foundation issues
in Switchyard.
Reactor is ready.
As identified in the 22nd
Standing
Committee Meeting on Power
System Planning of SR and as
approved in the 4th SRPC Meeting
held on 7th June 2007
KPTCL
Hoody By May 2015
Davanagere By January 2015
Nelamangala By May 2015
Talaguppa By March 2015
Guttur Line Reactor By April 2015 Shifted from Hoody
Minutes of the 26th Meeting of SRPC held on 20th December 2014 45 of 73
Entity Bus Name
Capacity
in
MVAR
Approve
d in Type Remarks
PGCIL
Vijayawada 2x125
20th
SRPC/
34th
SC
Bus
Likely
commission
ing during
December
2015-March
2016
Nagarjuna Sagar 125
21st
SRPC/
34th
SC
Bus
Narendra 125
21st
SRPC/
34th
SC
Bus
Hyderabad 125 21st SRPC
Gooty 125
22nd
SRPC /
36th
SC
Bus
Hassan 125
36th
SC
Bus
Khammam 125 Bus
Narendra (New) 125 Bus
Trivandrum 125 Bus
Nellore (Existing) 125 Bus
Yelahanka 2x63 Bus
Nellore PS on NPS-
Gooty Line
2x63
(37th
SC) Line
Narendra–Madhugiri
D/C at each end 4x63 Line
APTRANSCO
Vemagiri 80/125
21st
SRPC/
34th
SC
Bus By Feb
2015
Vemagiri 125
36th
SC
Bus
By Dec
2015 Kurnool 125 Bus
Kalpakka 125 Bus
TSTRANSCO
Mamidipalli 125 Bus
By June
2016
Gajwel 125 Bus
Sankarapalli 125 Bus
Mehboob Nagar 125 Bus
NPCIL
Kaiga 2 x125
Bus
TCC
suggested
implementi
ng 2x 125
MVAR in
line with
SC
decision.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 46 of 73
PGCIL had informed that the reactor at Hyderabad had been dropped in view of the
STATCOM being planned at Hyderabad. It had been suggested that PGCIL may revert
back with ratification/approval of Standing Committee in this regard.
10.2 The following had been noted in the TCC Meeting:
TSTRANSCO had informed that 125 MVAR reactor at Malkaram had been
planned. However, PGCIL was planning to convert the line reactor of
Malkaram-Hyderabad line (at Hyderabad) as switchable line reactor. Hence,
need for the reactor at Malkaram needed to be ascertained. In case not
required, TSTRANSCO would divert the same to some other high voltage
node. CTU stated that they would revert back after studying the same.
Regarding 2 x 125 MVAR, reactors at Kaiga, NPCIL had stated that they were
agreeable for one reactor and approval process had been initiated. Regarding
2nd
reactor they had sought clarifications from CTU and reply was awaited.
CTU had clarified that necessary technical justification had already been
furnished to NPCIL. Further, the Standing Committee had already approved
2x125 MVAR reactors at Kaiga. SRLDC reiterated that NPCIL, Kaiga should
initiate action for both the reactors. TCC had suggested that Kaiga implement
the recommendations of the Standing Committee at the earliest.
10.3 Dynamic Compensation (Approved in 36th
SC)
Entity Bus Name
SC
MVA
GVA /
KA
Dynamic
Compensation
(STATCOM)
Mechanically
Switched
Compensation
(MVAR) Remarks
Reactor Capacitor
PGCIL
Hyderabad 18.4/
26.5
+ 200 MVAR 2x125 1x125
2015-16 Udumalpet 19.4/
28.0
+ 200 MVAR 2x125 1x125
Trichy 12.5/
18.0
+ 200 MVAR 2x125 1x125
10.4 Construction of 400 kV Vijayawada-Nellore Ckt-III & IV lines under system
strengthening was underway. Along with this, 2 reactors of 63 MVAR at Nellore and
2 reactors of 50 MVAR at Vijayawada are envisaged for both the lines. The reactors
were ready for commissioning at both the ends. During discussions in the OCC
forum it was proposed to utilize above reactors at both the stations even before the
lines are commissioned. SRLDC had opined that utilization of these reactors would
help in containing the high voltage and thus help system operation. In this regard,
letter dated 18th
September 2014 (Annexure-XI) had been addressed to the SRPC
Members.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 47 of 73
10.5 In the TCC Meeting, PGCIL had suggested that a regional pool of spare bay equipment
be maintained in view of natural calamities taking place.
10.6 The Committee noted the above.
11. STUDY GROUP OF SLDCs TO ASSESS TTC/ATC AND OPERATIONAL
PLANNING
11.1 Need for having quality node wise data from constituents for optimal utilization of
transmission assets has been felt in various forums. Having a dedicated study group in
SLDCs for TTC/ATC/Operational Planning would help in addressing this issue to a
large extent. Procedure for Relieving Congestion In Real Time Operation mandates
SLDC to assess the TTC/TRM/ATC on its inter-state transmission corridor considering
meshed intra-state corridor for exchange (import/export) of power with ISTS. In
addition, SLDCs are also to designate Main and Alternate Officers as Reliability
Coordinator(s). The need for having dedicated system group in each utility and Load
Despatch Centres for operation planning had also been discussed in MoP Meeting held
on 11th
March 2014 to discuss Task Force Report on Power System Analysis Under
Contingency.
11.2 A Meeting of the Study Group of the SLDCs was held on 20th
October 2014 (Minutes
available at www.srpc.kar.nic.in/website/2014/meetings/special/rnsldc 20-10-14.pdf).
Manpower crunch had been highlighted by most of the SLDCs to handle these
additional responsibilities effectively. AP & Telangana SLDCs were yet to form a Study
Group at the SLDCs. Subsequently a workshop was also organized by SRLDC on 20th
November 2014.
11.3 Considering lower temperature limit (less than 45⁰C) for ATC computation (Kolar-
Hosur D/C line) was under examination of NRCE.
11.4 The following had been noted in the TCC Meeting:
MS, SRPC had informed that draft guidelines which included ambient
temperature based TTC, SPS etc. had been prepared and were under
circulation. All constituents except AP & Telangana had furnished the data
for TTC purpose. Further, Main & Alternate Reliability Coordinators were
to be nominated by each SLDC as per provision of the Congestion
Regulation.
APTRANSCO & TSTRANSCO expressed that there were manpower issues
on account of bifurcation. Therefore, they required some more time for
streamlining the activities. SRLDC/SRPC/other constituents suggested that
one or two Officers could be nominated to carry out the mandated activities.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 48 of 73
SRLDC had pointed out that SLDCs were raising issue of manpower
shortage and this needed to be highlighted in the SRPC Meeting.
After deliberation, the following was agreed:
AP & Telangana SLDCs would communicate the nominations.
SRLDC would guide/assist AP and Telangana SLDCs in arriving
node-wise data for two months period and subsequently AP &
Telangana SLDCs would take over the exercise.
TCC had recommended strengthening of SLDCs in terms of
manpower.
Main & Alternate Reliability Coordinators to be nominated at each
SLDC. It was noted that NLDC and SRLDC had the same in place.
11.5 In the Meeting, ED, SRLDC suggested that AP & Telangana may entrust the works to
suitable available Officers for the purpose. However, in the absence of node wise data,
the existing practice of ATC/TTC computations would be continued by SRLDC.
11.6 Chairperson, SRPC noted that other states had identified Officers who were able to
submit the required data. Similarly, AP & Telangana could also kindly identify one or
two Officers to carry out the above activities.
11.7 CMD, TSTRANSCO assured that they would arrange necessary action in this regard.
11.8 APTRANSCO also assured that they would ensure needful action.
12. SEMs ON ALL FEEDERS FOR SECTIONAL LOSSES
12.1 SRLDC had put this issue to Commercial sub- Committee of SRPC as follows:
“As per CEA (Installation and operation of meters) Regulations, 2006 and
Amendment thereof,
7.1 At one end of the line between the sub-stations of the same licensee, and
at both ends of the line between sub-stations of two different licensees.
But in the backdrop of increased complexities in Transmission network, a need is felt
for installing the SEMs on both ends of all the feeders of same licensees also
irrespective of ownership. This will help in computing Sectional Loss at each bus and
identify the metering deficiencies and under-recordings. Commercial Committee may
please approve the proposal so that CTU can do the needful. ”
12.2 This issue had been discussed in the 25th
Meeting of Commercial Sub-Committee of
SRPC. After deliberations, Commercial Sub- Committee had agreed in principle, but
observed that installation of SEMs on all feeders involved considerable cost implications
etc. Hence it was agreed that the details of SEMs requirement etc would be furnished by
SRLDC so that the matter could be put up to TCC/SRPC for consideration.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 49 of 73
12.3 SRLDC letter dated 17th
December 2014 furnishing the details of transmission lines
where SEMs ( 51 nos) are to be installed is at Annexure-XII
12.4 The following had been noted in the TCC Meeting:
MS, SRPC had said that SRLDC was facing a number of issues relating to
timely receipt of data, validation of data etc. As highlighted by SRLDC,
provision of the SEMs would help in computing Sectional Loss at each bus
and also in identification of metering deficiencies and under-recordings. The
total cost would be around Rs 10 lakhs.
TCC had recommended the scheme for approval. SEMs would be provided
by respective utilities. Cost of SEMs which would be provided by PGCIL,
would be shared as per the existing sharing mechanism.
12.5 The Committee approved installation of SEMs by respective utilities on both ends of
all the feeders of same licensees as per Annexure XII. Cost of the SEMs would be
shared as per the Regulations.
13. IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION
13.1 Automatic Demand Management Schemes
13.1.1 Automatic Demand Management Scheme in line with clause 5.4.2 (d) of the IEGC
was to be provided by all the constituents by 1stJanuary 2011.SRLDC & SRPC
Secretariat had pointed out that automated scheme was to be in place to meet
Regulatory requirements.
13.1.2 The following is the status update on the action finalized in the 25th
Meeting of SRPC:
In compliance of Order dated 22nd
February 2014 of CERC in respect of
Petition No. 120/2011, it was learnt that TANTRANSCO had finalized
the scheme and communicated to P&C Wing for implementation. Since
considerable time had lapsed, the scheme needed to be in place at the
earliest. Other Constituents (other than KSEB) also needed to put the
ADMS in place.
Scheme in TN yet to be implemented. In 101st OCCM TN had
informed that the scheme would be completed by December 2014.
The logic would take care of sudden withdrawal of wind
generation also.
KPTCL had informed that 350 MW loads had been identified for ADMS.
Initially the loads would be tripped manually, but within a period of three
months, the same would be automated.
Scheme in Karnataka yet to be implemented. In the 101st OCCM
Karnataka SLDC had informed that the scheme would be completed
by December 2014.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 50 of 73
AP & Telangana had informed that the new upgraded SCADA system
was likely to be in place by October 2014 and ADMS would be
subsequently implemented.
Scheme in AP & Telangana yet to be implemented. In the 101st
OCCM AP &TS SLDCs had informed that the scheme would be
completed by March 2015.
KSEB had informed that the scheme (320 MW) had already been
implemented.
New Scheme (which would replace the old implemented scheme) at
11 kV was being implemented.
13.1.3 The following had been noted in the TCC Meeting:
APTRANSCO & TSTRANSCO had informed that ADMS would be taken
up after completion of SCADA up-gradation works expected in March
2015. It may take around 2-3 months’ time after completion of SCADA
up-gradation works.
KPTCL had informed that existing SCADA had facility of tripping at
66/110/220 kV level from the SLDC. The scheme would be under trial
operation upto 31st March 2015. Subsequently, it would be put in regular
operation from 2nd
April 2015. DISCOMs were also being involved and
trippings sought to be carried out at 11 kV level so as to mitigate large
scale interruptions to consumers.
TANTRANSCO had informed that they would implement the scheme
along with the new SCADA ( February 2015). SRLDC/SRPC pointed out
that ADMS/Contingency Scheme for Tamil Nadu was further mandated in
a CERC Order. As per the Order, monthly status report was also to be
submitted. Hence, TN needed to complete this scheme at the earliest. The
scheme should also take care contingency of sudden withdrawal of wind
generation.
13.1.4 The Committee noted the above.
13.2 Inadequate UFRs and df/dt reliefs
13.2.1 Issue regarding inadequate relief through UFRs and df/dt relays had consistently been
raised by SRLDC & SRPC Secretariat. SRLDC had also reported the issue under
clause 1.5 of IEGC on a number of occasions. SRPC Secretariat had taken up the
matter with Constituents for necessary compliance. On 19th
December 2013,
Hon’ble CERC had issued its Order in respect of Petition No 263/MP/2012. It had
directed that SR constituents identify additional feeders and install UFR and df/dt
relays to ensure relief as decided by SRPC from time to time. SLDCs had also been
directed to map the relays on the SCADA system within three months of issuance of
the Orders.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 51 of 73
13.2.2 Visible relief of the states is as follows :
AUFR, df/dt feeders Percentage relief realization w.r.t. SCADA monitored
October 2014 August 2014
MAX MIN AVG MAX MIN AVG
AP 58% 15% 40% 109% 50% 82%
TS 123% 39% 77%
KAR 75% 16% 55% 83% 7% 59%
KER 106% 52% 74% 80% 23% 48%
TN 69% 21% 53% 74% 47% 60%
SR 87% 49% 70% 80% 47% 65%
Except Kerala and Puducherry all the other constituents were yet to
implement the additional feeders
All the constituents were yet to complete 100% SCADA mapping. KSEB
had approached CERC for time extension for complete the activity.
13.2.3 In the 24th
Meeting of TCC SLDCs had been requested to examine the matter in
consultation with the Discoms. Endeavour to improve the relief figures by about 20 %
(at least up to 70 %) would be ensured by the next SRPC Meeting.
The issue is being regularly monitored in the OCCM but there was no
significant improvement from the earlier visible relief.
13.2.4 The following had been noted in the TCC Meeting:
Updated status of the visibility and installation with respect to the
recommended quantum was presented (Annexure-XIII). It was noted that
since last Meeting of TCC, KPTCL had improved both visibility as well as
quantum of UFR. However, the visible relief was still hovering in the range
of 60 -70%.
After deliberation, the following was agreed:
States would increase SCADA relief visibility to at least 75% by 1st
March 2015. SRLDC would continue monitoring at 10 days interval.
AP, Telangana and Tamil Nadu to implement the balance quantum
and achieve recommended quantum by 1st March 2015.
13.2.5 The Committee noted the above.
13.3 Low Voltage and installation of UV Relay/High voltage
13.3.1 Following is the status on the actionable points as discussed in the 24th
TCC Meeting:
KSEB had finalized the scheme which had been put to higher management
and approval was awaited.
Scheme was yet to be approved and implemented
SRLDC had said that this issue was being followed up since last couple of
years and they may be constrained to go for physical regulation measures
in low voltage areas.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 52 of 73
Scheme had been finalized and implemented
KPTCL had agreed to implement UV relay scheme. In addition steps
would also be taken to provide capacitor of adequate capacity at low
voltage nodes.
Scheme was yet to be approved and implemented
TANTRANSCO had stated that they would maintain the voltage levels
within limits at 230 kV level and below. It had been pointed out that loss
of wind generation had taken place due to low voltage scenario. States
were to maintain voltages within IEGC range and in case voltages are not
maintained, then UVR is to be provided as per IEGC.
IEGC/CEA Regulations mandate providing UV relays if need arises.
13.3.2 The following had been noted in the TCC Meeting:
SRLDC had expressed concern that despite earlier agreeing for the
implementation of UV Relays, KPTCL and TANTRANSCO had not shown
any progress in this regard. Installation of UVR was mandated in IEGC as
well as CEA Regulations.
MS, SRPC had said that the analysis of low voltage nodes had been carried
out. Some of the nodes like Gazuwaka, Palakkad, Somanahalli, Udumalpet,
Trichur etc. were facing low voltages at different periods. Activation of UV
feature in relays would only help strengthen the safety net and aid system
operation. In case in future, voltage profile improved on a sustained basis,
this feature could be recommended for disabling.
TANTRANSCO had informed that system strengthening and capacitor
installation had helped improve the voltage profile in the state and thus there
may not be any need for installation of UVR. However, TN would
implement/enable UVR at identified low voltage nodes.
KPTCL had pointed out that the voltage profile in and around Bengaluru had
improved due to rectification of faulty capacitor banks and also installation
of new capacitors. All zones were concentrating to improve voltage profile
at distribution level. SRLDC had pointed out that voltage at Somanahalli had
touched 378 kV a couple of days back. After discussions, KPTCL agreed
that to implement/ enable UV Relay. The same would under trial operation
upto 31st
March 2015 and would be implemented by 2nd
April 2015.
KSEB had informed that the scheme had been sanctioned by their
Management and the same would be implemented in about a months’ time.
PGCIL had expressed concern that number of failure of their equipment had
taken place due to sustained high voltage operation and delayed opening of
elements at high voltages. In case any pattern was known, it may be prudent
to take out elements a little earlier rather than switching it off at high
voltage. It was also suggested that analysis of high voltage nodes in the
Region could also be made in the next Meeting. This exercise would help in
assessment of additional reactor requirements and also focus on short term
operational measures to be undertaken.
13.3.3 The Committee noted the above.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 53 of 73
13.4 Restricted Governor Mode of Operation (RGMO)/FGMO of Generating Units &
MVAR Interchange
13.4.1 In the 25th
Meeting of SRPC, the following had been noted:
All GENCOs would endeavor to ensure RGMO response as mandated in
the Regulations.
Response would be analyzed further in a Special Meeting of Generators to
be held during August 2014.
Regarding MVAR, the constituents had been requested to kindly comply
the decisions taken in various Meetings in this regard.
A Meeting in this regard was held on 27.08.2014 (Minutes available
http://www.srpc.kar.nic.in/website/2014/meetings/special/
Minutes_RGMO.27.08.2014.pdf)
The response was minimal by most of the generators and there was
considerable scope of improvement.
Actionable points in respect of RGMO and MVAR finalized in the
Special Meeting needed to be implemented.
All the SLDCs to monitor the response of the generators in their
control area and take up the matter with respective SERC in case of
lack of response or inadequate response. (RoP dated 06.07.2014 on
Petition No.302/MP/2013)
13.4.2 The following had been noted in the TCC Meeting:
SLDC to take up the matter with concerned SERCs for non-performing Units
of their control area.
Each Genco to identify one station which would be monitored for RGMO
performance with the objective of improving the performance.
Other Units would also endeavor to improve their performance
SRLDC had stated that RGMO/FGMO status points should be made available
to SLDC/SRLDC.
A separate Committee had been formed by Hon’ble CERC to look into
associated issues with regard to implementation of RGMO/FGMO.
13.4.3 In the Meeting, the following generating stations were identified as Model Stations for
regular monitoring and improvement of RGMO/FGMO performance:
APGENCO - Vijayawada STPS
TSGENCO – Kothagudem 500 MW unit
KPCL – Raichur TPS (except unit-4)
TANGEDCO – North Chennai Stage-II
KSEB- Idukki HEP
All CGS, JSWEL – Torangallu and UPCL
13.4.4 It was noted that all other generators too needed to ensure RGMO response as
mandated in the Regulations.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 54 of 73
13.4.5 ED, SRLDC pointed out that RGMO status needed to be ensured to SLDCs/RLDCs.
Categorization of performance as negative response, inadequate performance and
adequate performance was already been carried out. With regard to Central Sector
Stations, this would be one criteria for certification of performance as per CERC Terms
& Conditions of Tariff Regulations. Also, the duration between any instance of
nonperformance to instance of next performance would be considered as non-
performance.
13.5 Low Voltage Ride Through (LVRT)
13.5.1 The following had been noted in the SRPC/TCC Meeting:
There had been 3-4 incidences of wind generation withdrawal of around
1,000 MW in the past one year. This was on account of non-availability of
LVRT feature which was a matter of great concern to grid security. Special
Meeting of Protection Sub-Group had been held in this regard on 08th
July
2014
TANTRANSCO had informed that the matter regarding provision of LVRT
features was being taken up with the wind developers. Data/information
could be jointly studied to assess the root cause for such incidents, whether it
could be attributed to variability or on account of non-availability of
LVRT/FRT features
KPTCL had informed that they were viewing the issue with concern since
about 70% of the wind mills in Karnataka Grid may not be equipped with
LVRT feature presently. They would take up the issue with wind developers.
Compliance in this regard could be planned only in a phased manner. Most of
the wind mills (about 95 %) were privately owned and commissioned over a
period of 6 to 8 years.
After deliberations, it had been decided that NLDC would carry out bilateral
discussions/study with Tamil Nadu.
13.5.2 Subsequently SRLDC had filed a Petition before Hon’ble CERC in this regard.
13.5.3 In the TCC Meeting, TANTRANSCO & KPTCL were requested to kindly initiate
necessary action in this regard.
13.5.4 The Committee noted the above.
13.6 Demand Estimation for Operational Purpose (Clause 5.3 of IEGC)
13.6.1 Each SLDC was to create mechanism and facilities to facilitate on-line demand
estimation of demand for daily operational purpose for each 15 minutes block by
01.01.2011. In this regard, following may kindly be noted as contained in Order dated
19th
December 2013 of Hon’ble CERC in Petition No. 249/250/251/MP/2012:
“We direct all STUs/SLDCs of the Northern Region, Southern Region and
Eastern Region to forecast their demand and make adequate arrangements
Minutes of the 26th Meeting of SRPC held on 20th December 2014 55 of 73
to avoid dependence on Unscheduled Interchange for meeting their demand
or for injecting short term surplus power, irrespective of the frequency.”
Load Forecasting tool meeting the regulatory requirement yet to be
developed by all the utilities.
A Meeting was held with GETCO SLDC so as to be acquainted of the load
forecasting being carried out in Gujarat. (Minutes available at http://www.srpc.kar.nic.in /website/2014/meetings/special/rnspl23-08-14.pdf)
13.6.2 SRLDC/SRPC Secretariat had expressed concern that Regulatory requirements had
not been met since the scheme was to be put in place by 01.01.2011. They had
requested all the constituents to initiate necessary steps in this regard.
13.7 Sudden Change in Demand / Frequency Excursion
13.7.1 In earlier Meetings, violation of Clause 5.2 (j) of the IEGC Regulations has been
highlighted. No user is to cause sudden variation in its load by more than 100 MW
without prior intimation to and consent of the RLDC. Similarly no user should reduce
the generating unit output by more than 100 MW without prior intimation to and
consent of the RLDC. Necessary action was sought in respect of demand and
generation management as well as power purchases, so that clause 5.2 (j) of IEGC
Regulations is not violated.
Another Meeting in this regard was held on 26th
September 2014 (Minutes
available at http://www.srpc.kar.nic.in/website/2014/ meetings/special/rn26-09-
14.pdf)
Constituents to initiate action as finalized in the Special Meetings.
13.7.2 SRLDC/SRPC Secretariat had expressed concern that despite regular follow up and
Special Meetings the Regulatory provisions were not being fully met and requested
for necessary compliance.
13.8 Arranging of interruptible loads in four groups
13.8.1 As per IEGC, to maintain the frequency within stipulated band and also to ensure
network security, interruptible loads are to be arranged in four groups of loads.
This was for the purpose of scheduled power cuts/load shedding, loads for
unscheduled load shedding, loads to be shed through UF relays, df/dt relays and
loads to be shed under any SPS Scheme. These loads are to be grouped in such a
manner that there was no overlapping between different groups of loads.
Existing schemes were not meeting the Regulatory requirement fully
and further action was required in this regard.
13.8.2 SRLDC/ SRPC Secretariat had requested for necessary compliance since regulatory
requirement were not being fully met.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 56 of 73
13.9 Follow up by MoP on implementation of corrective action
Ministry of Power had convened a Meeting to discuss various issues such as
implementation of corrective action based on 3rd
Party Audit of Substations,
implementation of RGMO, operation of Defense Mechanism, Ring Fencing of
SLDCs, formation of dedicated system studies group etc. In this regard,
Chairperson, SRPC had also addressed a letter dated 7th
August 2014 (Annexure-
XIV) to SRPC Members.
13.10 PSS Tuning
13.10.1 The need for PSS tuning of all major generators has been raised by SRLDC on
number of occasions in the recent past keeping in view the sustained oscillations of
high mode and poor damping. In the 25th
SRPC Meeting it was noted that in the
Meeting taken by Secretary (Power) on 11th
March 2014 to discuss the Task Force
Report, CTU had been entrusted the responsibility of PSS tuning. Keeping in view
the observations raised by PGCIL of not having the necessary expertise in
generator/governor technology, CTU had been suggested to suitably take up the
matter with MoP for further directions.
13.10.2 The following had been noted in the TCC Meeting:
In a Meeting held in MoP, the responsibility of PSS tuning had been
entrusted to CTU. Earlier too in the 25th
Meeting of SRPC, CTU had been
suggested to take up any issue in this regard appropriately.
CTU had assured that they would take up this issue appropriately.
13.10.3 The Committee noted the above.
13.11 Other Issues requiring kind attention of SRPC/ TCC
13.11.1 The following issues are being regularly followed up in the Sub-Committees of
SRPC, and merit kind attention:
Phase-I & Phase-II activities identified in Protection Audit needs to be
completed. Progress of the implementation needs to be submitted to
SRPC/SRLDC in a time bound manner.
Reactive Power Planning including at distribution level needs to be
submitted to CEA with a copy to SRPC Secretariat.
Information regarding tripping details with relay indications was needed to
be furnished in a timely manner.
Information regarding Cyber Security was to be furnished to Chief Engineer,
DPD, CEA, Sewa Bhavan, New Delhi-110066. Report on Physical
Security, other Mock Drills for CMP, Mock Drill for Black Start Restoration
is to be furnished to Chief Engineer, DMLF, CEA, Sewa Bhavan, New
Delhi-66. Copy of the report is to be sent to SRPC Secretariat
Minutes of the 26th Meeting of SRPC held on 20th December 2014 57 of 73
Tertiary Transformer at HVDC Bhadravathi was planned to be
commissioned by December 2014. Same needs to be commissioned as per
schedule since number of instances of pole blocking due to auxiliary supply
failure have been experienced.
Pollution mapping activities like installation of dummy insulators and six
reading within interval of 4 months are being undertaken.
Transmission elements outage planning to be done in a coordinated manner
and shutdown requests to be received by 3rd
of each month for the next
month.
13.11.2 The following had been noted in the TCC Meeting:
MS, SRPC had informed that in the 102nd
Meeting of OCC held on 10th
December 2014, CEA, NTPC, NHPC & PGCIL had made Presentation on
Cyber Security issues. NTPC, NHPC & PGCIL had been designated as
CERTs (Computer Emergency Response Teams) for Thermal, Hydro and
Transmission respectively. Director (IT), CEA had been nominated as Chief
Information Security Officer (CISO) for MoP. Critical issues were
highlighted during the Presentation. As an initial step, all the utilities were
requested to nominate one Chief Information Security Officer (CISO) for
Cyber Security at senior level.
All the constituents agreed to furnish the nomination of CISO to CEA &
Nodal CERT with a copy to SRPC Secretariat.
Regarding auxiliary power at Bhadravathi HVDC, PGCIL had confirmed
that the tertiary transformer would be commissioned by December 2014.
13.11.3 The Committee noted the above.
13.12. Protection Suite
13.12.1 In the Meeting, MS, SRPC informed that the need for procuring Protection Suite had
been deliberated in the Meetings of Protection Sub-Committee of SRPC. The
Protection Sub-Committee had noted that Protection Suite would be an important
tool. It was proposed that the Suite be procured through PSDF funding. He suggested
that all the states may kindly furnish their consent in this regard before the next
Protection Sub- Committee Meeting.
13.12.2 The Committee approved in principle the proposal for procurement of Protection
Suite through PSDF Funding.
14. REVIEW OF PERFORMANCE OF ULDC SCHEME
14.1 The issue is being followed up in the OCC Meetings. Following are the actionable
points in this regard:
Status of data, voice, internet communication and pending filed inputs as
discussed in the 101st OCC is enclosed as Annexure-XV.
Standby data channels from 400 kV S/S (SR1 & SR2) not made through.
Talcher-II data to be integrated in new SCADA system at SRLDC.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 58 of 73
Pending field inputs from KKNPP, MAPS and Kaiga GS to be ensured.
Pending field inputs from UPCIL stations to be ensured
14.2 In view of difficulty to communicate with Simhadri TPS and other important S/S
during “Hud Hud” cyclone, SRLDC had requested all utilities to maintain reliable
and redundant communication system in place. V-SAT communication may be
required from all critical generating stations, HVDC stations and 400 kV and above
substations.
14.3 APTRANSCO vide letter dated 17.12.2014 (Annexure-XVI ) had proposed
discussion on readiness of SRLDC control room with ALSTOM system and
providing ICCP data to SRLDC/SLDCs.
14.4 The following had been noted in the TCC Meeting:
TSTRANSCO had informed that data validation between SLDC & SRLDC
through ICCCP had been completed. The Service Agreement with M/s. GE
was terminating on 6th
January 2015. However, parallel operation of both the
systems was needed to be in place for three months.
APTRANSCO had informed that the trial run of the ICCP link between
SLDC and SRLDC was underway. The contract with M/s GE was needed to
be extended for three months till the new SCADA system stabilizes.
KSEB had informed that they had earlier agreed for one quarter extension of
the existing AMC and they were agreeable for another three months
extension.
It was agreed that AMC for the existing SCADA be extended for 3 Months
during parallel operation by the respective utilities. ED, SRLDC stated that
presently they were receiving as well as sending the ICCP data. Tuning was
needed to be carried out both by SRLDC and SLDC to ensure that the data is
correct.
MS, SRPC had highlighted the need for V-SAT and SAT Phone
communication keeping in view the communication issues faced during/after
the recent ‘Hud Hud ‘cyclone.
KPTCL had informed that CEA had called a Meeting on communication
issues wherein it was noted that V-SAT communication was the fastest. It
had been suggested to have V-SAT equipment at strategic locations which
could be moved to affected areas quickly.
NTPC had informed that they were getting one set of Satellite Phone at
SRHQ which could be deployed at any of their station.
After deliberations, constituents were suggested to ensure availability of V-
SAT/SAT Phones at strategic locations which would help in effective
communication during disasters.
14.5 The Committee noted the above.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 59 of 73
15. PENDING ARREARS PAYMENT BETWEEN BENEFICIARY STATES IN SR
15.1 The following had been noted in the 25th
Meeting of SRPC:
It was agreed that KPTCL/PCKL and TANTRANSCO would settle this
issue bilaterally. It was also agreed that AP, KPTCL/PCKL and KSEB
would settle the issues bilaterally
APTRANSCO had stated that it had already rejected the claims in respect of
frequency linked penalty/incentive scheme along with valid reasons. This
issue would be resolved bilaterally and was not to be included as agenda in
SRPC meeting.
KSEB/TANTRANSCO had stated that since this issue was not getting
resolved bilaterally, it had been brought to SRPC forum.
TANTRANSCO had stated that SRLDC was the designated agency for
frequency linked penalty/incentive scheme and hence it should provide
necessary data for settling this issue.
SRLDC had informed that in respect of frequency linked penalty/incentive
scheme SRLDC was not in a position to provide any data except for the
month wise summary of the payables and receivables. The hourly data and
computation were stored in floppies which became unusable over a period of
about 20 years. This had already been informed earlier.
Chairperson TCC had suggested that a separate Meeting be convened and
SRLDC provide necessary guidance in this regard.
15.2 Subsequently, this issue had been further deliberated in 25th
& 26th
Meeting of
Commercial Sub- Committee of SRPC.
15.3 TANTRANSCO vide letter dated 29th
November 2014 (refer Annexure-II) had stated
that KPTCL has to pay an amount of Rs.26,49,88,513/- to TANGEDCO towards
monetary compensation claims for the period from December 1998 to March 2001. It
had also been stated that status on the above be expedited by KPTCL, PCKL officials.
15.4 TANTRANSCO vide letter dated 29th
November 2014 (refer Annexure-II ) had also
stated that regarding frequency linked penalty/incentive scheme for
overdrawal/underdrawal of shares, APTRANSCO and KPTCL may furnish suitable
date for their visit to Chennai to participate in a Meeting to resolve the above issue.
Further, the Nodal Agency SRLDC had to forward the invoices sought by KPTCL on
the above issue.
15.5 KSEB vide letter dated 8th
December 2014 (refer Annexure-III) had stated that as on
31st March 2014, the net receivable amount form and KPTCL was Rs.16,09,87,736 and
from APPCC was Rs.15,61,13,679/-. It was also stated that question of limitation act
does not apply.
15.6 In the TCC Meeting, after deliberations, it was agreed that the issue would be
discussed bilaterally between the concerned states. Only in case of non-convergence,
Minutes of the 26th Meeting of SRPC held on 20th December 2014 60 of 73
the matter would be put up to the SRPC forum. A Meeting in this regard would be held
on 9th
Jan 2015 at PCKL office in Bengaluru.
15.7 The Committee noted the above.
16. OUTSTANDING DUES BETWEEN WR & SR
16.1 Meetings between WR & SR Constituents regarding outstanding payments in respect of
energy transactions between WR & SR for the period prior to January 2003 were held at
Mumbai & Bangalore. The sixth Meeting in this regard was held on 28th
October 2014
at Mumbai, where in the following was agreed:
WRLDC would verify the records and furnish the details to WRPC/SRPC
within 15 days regarding the amount transferred from WR UI Pool to WRTS
during the years 2003-04 & 2004-05.
An amount of Rs.1,80,89,611/- is to be transferred to SRTS.WRTS had
transferred Rs.14,57,444/- to SRTS. The balance amount would be transferred
as and when received from WR Constituents. SRTS would credit the amount
transferred by WRTS to SR Constituents towards transmission charges, under
intimation to SRPC.
WRTS and GUVNL would verify their records at the earliest. WRTS would
follow up with other Constituents for early settlement of the issue.
MSEDCL had informed that they had put up a note for approval of the
management for releasing the payment.
GUVNL had informed that as and when the amount is received from Tamil
Nadu and Karnataka, payment would be made to KSEB & Puducherry
proportionately.
CSPDCL had informed that they have to receive payment from Tamil Nadu &
Karnataka. TANTRANSCO and KPTCL to expedite the payment. There was no representation from MPPMCL in the Meeting.
16.2 TANTRANSCO vide letter dated 29th
November 2014 ( refer Annexure-II) had stated
that the status of transfer of amount to SR constituents be updated.
16.3 In the TCC Meeting, SRTS-II, PGCIL had informed that an amount of Rs 14,21,844
transferred by WRTS to SRTS had been passed on to the SR Beneficiaries. Balance
would also be passed on to the beneficiaries as and when the same was received from
WR.
16.4 The Committee noted the above.
17. UNIFORM RATE OF CHANGE OF FREQUENCY RELIEF SCHEME
(df/dt) TO BE ADOPTED THROUGHOUT THE COUNTRY
17.1 Revision of settings of df/dt relays was proposed on account of various reasons such as
integrated operation of NEWS grid, tightening of frequency band etc. TANTRANSCO
had opined that since National Grid is operated as single large grid at one frequency, the
Minutes of the 26th Meeting of SRPC held on 20th December 2014 61 of 73
settings to be adopted for load relief schemes such as df/dt etc. should be uniform
throughout the country.
17.2 TANTRANSCO vide letter dated 29th
November 2014 (refer Annexure-II) had stated
that the status on the above be deliberated.
17.3 The matter regarding revision of df/dt relay settings in Southern Region as well as
uniform settings of df/dt relays in all the Regions had been taken up with Member
Secretary, NPC vide SRPC letter dated 26th
September 2014. (Annexure-XVII)
17.4 In the TCC Meeting, it was noted that the issue had been referred to NPC for uniform
adoption throughout the country.
17.5 The Committee noted the above.
18. SPS FOR OVERLOADING OF 400 kV KOLAR – HOSUR LINES
18.1 SPS for overloading of 400 kV Kolar-Hosur lines were finalized in the PCC Meeting of
SRPC. The tentative cost for implementation of the proposed SPS scheme is about
Rs.12.5 lakhs. The time for completion of procurement, installation etc. is around 6 to
7 months. In this regard, copy of letter dated 20th
October 2014 from Power Grid is
enclosed as Annexure-XVIII . Since the requirement of the proposed SPS scheme is
felt even after 8 to 9 months, the implementation of this SPS scheme was proposed to
be approved.
18.2 TCC had recommended the implementation of SPS for approval.
18.3 The Committee approved the implementation of SPS for overloading of 400 kV Kolar-
Hosur lines
19. DETAILS OF PENDING REMEDIAL MEASURES DISCUSSED AND
FINALIZED IN PCC
19.1 Grid incidents are being analyzed and discussed in the monthly Meetings of Protection
Sub Committee. A number of visits by the Members of the Sub Group to analyze
major/recurring grid incidents had taken place. ( Guttur, Srisailam, Kadra/ Kodasalli
etc). Details of remedial measures etc to be complied with in accordance with the
discussions in the Protection Sub Committee is furnished at Annexure- XIX. The same
was needed to be expedited and implemented at an early date.
19.2 In the TCC Meeting, MS, SRPC had informed that remedial measures had been
compiled during the PCSC Meeting and Sub Group visits. He had requested that
recommendations may please be implemented at the earliest.
19.3 The Committee noted the above.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 62 of 73
20. WHEELING CHARGES PAYABLE BY GOA TO KARNATAKA
20.1 KPTCL vide letter dated 6th
December 2014 (Annexure-XX) had stated that the matter
regarding payment of wheeling charges by Goa to Karnataka for wheeling the CGS
share of power from Ramagundam be discussed.
20.2 TCC had noted that the matter was before Hon’ble CERC.
20.3 The Committee noted the above.
21. UTILIZATION OF TERTIARY WINDING OF ICTS FOR AUXILIARY
POWER SUPPLY IN SUBSTATIONS
21.1 PGCIL vide letter dated 4th
December 2014 (refer Annexure-X) had emphasized that
auxiliary supplies in EHV substation is critical for revival of service in contingencies.
It has therefore been proposed that constituents may consider utilization of tertiary
winding of ICTs, wherever available, in a substation for providing auxiliary supply.
21.2 The following had been noted in the TCC Meeting:
PGCIL had informed that they were using the tertiary winding of their ICTs
for auxiliary power supply in substations. As per CEA Regulations, two
reliable and redundant supplies in addition to DG were required and
utilization of tertiary winding would ensure reliable supply. They had
sufficient experience and confidence for active power loading of tertiary
winding. During recent “Hud Hud” cyclone reliable supply could have been
extended at the earliest using the 400 kV lines and tertiary winding.
KPTCL and TANTRANSCO had informed that there had been instances of
ICT failures in case of reactive loading and as a policy they were not
utilizing the tertiary winding.
After deliberation, TCC had recommended that utilization of tertiary
winding would be solely at the discretion of concerned utilities.
21.3 The Committee noted the above.
22 PROCUREMENT OF 500 MVA ICT AS SPARE INSTEAD OF 315 MVA ICT
APPROVED UNDER RAMAGUNDAM TRANSMISSION SYSTEM
22.1 PGCIL vide letter dated 4th
December 2014 (refer Annexure-X) had proposed
procurement of higher capacity ICT since it would be techno-economic in view of
future load growth. It had therefore been proposed to procure 1 No. 400 / 220 kV 500
MVA Transformer instead of 400 / 220 kV 315 MVA Transformer already approved.
22.2 The following had been noted in the TCC Meeting:
TSTRANSCO observed that 315 MVA ICT population was more in the
states and hence procurement of 315 MVA ICT may remain.
PGCIL had clarified that the foundation requirement would be maintained
the same. The reactance would be matched with the existing ICTs for parallel
Minutes of the 26th Meeting of SRPC held on 20th December 2014 63 of 73
operation (they had sufficient experience viz, Nagarjunasagar). With
increased growth rates etc PGCIL was going for 500 MVA ICTs and
difference of cost implication between 500 MVA ICT and 315 MVA ICT
was minimal.
TCC had recommended that 500 MVA ICT be procured instead of 315 MVA
ICT under Ramagundam Transmission System.
22.3 The Committee approved procurement for 500 MVA ICT instead of 315 MVA ICT
under Ramagundam Transmission System.
23. PROCUREMENT OF 3x125 MVAR REACTORS INSTEAD OF 3 x 50 MVAR
REACTORS APPROVED UNDER RAMAGUNDAM TRANSMISSION
SYSTEM
23.1 PGCIL vide letter dated 4th
December 2014 (refer Annexure-X) had stated that
addition of generation capacity and augmentation of Transmission System in the past
few years has led to increase in short circuit level of the system. Hence, in view of
system requirements and to meet any exigency in the event of failure of 50 MVAR
Reactors in future, it has been proposed that 3 x 125 MVAR Reactors be procured as
spare along with associated switching arrangements instead of 3 x 50 MVAR Reactors
already approved.
23.2 The following had been noted in the TCC Meeting:
SRLDC had noted that the short circuit MVA at nodes like Ramagundam,
Nagarjunasagar etc. had gone up. The impact of 125 MVAR reactor was
presently similar to that of 50 MVAR reactors at earlier short circuit levels. It
was technically justified to go for 125 MVAR reactors. PGCIL also endorsed
the views of SRLDC.
TCC had recommended for procurement of 3x125 MVAR reactors as spare
along with associated switching arrangements instead of 3x50 MVAR
reactors already approved.
23.3 The Committee approved procurement of 3x125 MVAR reactors as spare along with
associated switching arrangements instead of 3x50 MVAR reactors already approved
under Ramagundam transmission system.
24. CONVERTING FIXED LINE REACTORS INTO SWITCHABLE LINE
REACTORS IN OVER COMPENSATED LINES.
24.1 PGCIL vide letter dated 4th
December 2014 (refer Annexure-X) had stated that on
account of reduction in line length after LILO at certain nodes, some lines are being
over compensated with existing fixed Reactors. Hence, it had been proposed that fixed
line reactors on the following lines be converted to switchable line reactors:
Malkaram – Hyderabad-II Kurnool – Gooty Simhadri – Gazuwaka II
Minutes of the 26th Meeting of SRPC held on 20th December 2014 64 of 73
24.2 TCC had recommended for approval that the above line reactors be converted to
switchable reactors.
24.3 The Committee approved that fixed line reactors on the Malkaram – Hyderabad-II,
Kurnool – Gooty & Simhadri- Gazuwaka 400 kV lines be converted to switchable
reactors.
25. CERC ORDER ON UPCL POWER EVACUATION ISSUE
25.1 KSEB vide letter dated 8th
December 2014 (refer Annexure-III) had stated that the
cost of transmission system used by UPCL is being wrongly socialized among other
DICs. Follow up action in this regard had been sought to be reviewed.
25.2 In the TCC Meeting, it was noted that the issue was being heard by Hon’ble CERC.
25.3 The Committee noted the above.
26. RE-CONSTITUTION OF THE VALIDATION COMMITTEE UNDER
REGULATION 7(1)(g) (SHARING OF INTER STATE TRANSMISSION
CHARGES AND LOSSES) REGULATIONS, 2010.
26.1 KSEB vide letter dated 8th
December 2014 (refer Annexure-III) had stated that the
Validation Committee constituted under sharing regulations does not have adequate
representation at state level. This is creating difficulties in appraising state pertinent
issues by STU/DISCOMs before Validation Committee. It has hence been suggested
that Validation Committee may have at least one representative from each state. Till
that time, each state may be allowed to represent in the Validation Committee on
rotational basis.
26.2 In the TCC Meeting, MS, SRPC had informed that all the state/utilities were being
invited to the Meeting of Validation Committee.
26.3 The Committee noted the above.
27. UTILIZATION OF PSDF TO DEVELOP INTER- STATE TRANSMISSION
SYSTEM TO RELIEVE TRANSMISSION CONSTRAINTS.
27.1 KSEB vide letter dated 8th
December 2014 (refer Annexure-III) had stated that the
need for strengthening of ISTS in the country and to relieve the transmission
congestion and associated issues has been emphasized. It has been suggested that CTU
utilize the funds available in PSDF for constructing new transmission system for
providing relief to the congested regions. Further, congestion amount collected from
the utilities be segregated region-wise. Amount collected from each region may
preferably be utilized for developing the transmission system to relieve congestion of
that region.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 65 of 73
27.2 In the TCC Meeting, it was noted that segregation of fund region wise was not feasible
and the same had also been deliberated in various forums. Procedure for utilization of
funds had been clearly spelt out and each utility could apply as per their
requirement/assessment.
27.3 The Committee noted the above.
28. EARLY COMMISSIONING OF 765 kV VEMAGIRI-KHAMMAM-
HYDERABAD-WARDHA TRANSMISSION SYSTEM FOR THE
ENHANCEMENT OF INTERREGIONAL TRANSMISSION CAPACITY
BETWEEN NEW GRID AND SR.
28.1 KSEB vide letter dated 8th
December 2014 (refer Annexure-III) had suggested early
commissioning for enhancement of inter-regional transmission capacity between ER
and SR. The commissioning of these lines was also required for evacuating huge
generation potential in the Vemagiri area in Andhra Pradesh.
28.2 The following had been noted in the TCC Meeting:
TSTRANSCO had suggested revival of the Vemagiri-Khammam-
Hyderabad link since it would provide east to west connectivity.
CTU had clarified that the scheme had been suggested to be dropped in the
37th
SCPSCSR. However, the matter was being heard by Hon’ble CERC.
29 PUBLISHING THE RESULTS OF SYSTEM STUDIES BY CTU IN
COMPLIANCE WITH REGULATION 20 OF THE CERC (GRANT OF
CONNECTIVITY, LONG TERM AND MEDIUM TERM OPEN ACCESS)
REGULATIONS, 2009.
29.1 KSEB vide letter dated 8th
December 2014 (refer Annexure-III) had stated that CTU
has not been following provisions of the said Regulations. The result of system studies
has not been published in public domain nor the information notified as stipulated in
the approved procedure. Hence CTU has been requested to comply with the
procedures stipulated in the Regulation.
29.2 The following had been noted in the TCC Meeting:
KSEB had pointed out that as per the Procedure, CTU needed to publish
TTC/ATC for the coming 3 years along with the study results.
CTU had informed that as could be appreciated there was considerable
uncertainty in the commissioning of generating projects and number of lines
was held up due to RoW issues etc. There were a number of difficulties in the
assessment. The same had also been appraised to Hon’ble CERC. CTU was
adopting a consultative approach in this regard. Study results etc of LTA
Meeting, Special Meeting etc. were contained in the Agenda / Minutes and
were available in the public domain.
29.3 The Committee noted the above.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 66 of 73
30. DIFFERENCE IN COMPUTATION OF CAPACITY CHARGES OF NTPC
STATIONS AS PER CERC REGULATIONS (2014-19)
30.1 In the 24th
Meeting of TCC the following had noted:
KSEB vide letter dated 14th
July 2014 had invited reference to CERC Tariff
Regulation 2014-19 regarding payment of capacity charges to Thermal
Generating Station for a calendar month. It had been stated that all generators
have adopted calculation procedure in accordance with CERC Norms whereas
NTPC has adopted a different methodology for the same. The amount claimed
towards capacity charges by NTPC is more than the amount permissible as per
CERC Norms.
The issue would be first deliberated in the Commercial Sub-Committee.
30.2 Accordingly the issue had been deliberated in the 25th
Meeting of Commercial Sub-
Committee held on 22nd
August 2014. After deliberations, all other beneficiaries, except
KSEB were agreeable for the methodology currently being followed by NTPC.
30.3 KSEB vide letter dated 8th
December 2014 (refer Annexure-III) had stated that NTPC
had adopted a different methodology of their own for calculation of capacity charges
even when CERC has clearly prescribed a method. The amount claimed towards
capacity charges is often more than the amount permissible as per CERC norms.
30.4 The following had been noted in the TCC Meeting:
KSEB pointed out that the provision of Regulations was needed to be followed.
NTPC had stated that this was the common system being followed for all the
stations throughout the country. As can be seen, NTPC was not recovering
any additional amount. In case the suggested system was to be followed,
any post-facto change would result in changes in all the bills for all the
months.
All the other constituents observed that since NTPC was not recovering any
additional amount upto the month, they be allowed to continue with the
existing practice.
It was agreed that this issue would be put up to SRPC for a decision.
30.5 In the Meeting, CE (Tr. & SO), KSEB said that since all other beneficiaries were
agreeable to the methodology being followed by NTPC, KSEB too was agreeable for
the same.
30.6 The Committee noted and agreed for the above.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 67 of 73
31. KPTCL DENYING NOC FOR OPEN ACCESS FOR POWER CONTRACTED
FROM UDUPI POWER CORPORATION LTD.
31.1 KSEB vide letter dated 8th
December 2014 (refer Annexure-III) had stated that
KPTCL is denying NOC without any documentary support. Hence based on this
SRLDC had denied KSEB’s application. PPA for 18.5 MW RTC power had been
executed on 9th
April 2014. UPCL had stated that only 90% of the plant capacity is tied
up with ESCOMs of Karnataka and that the 18.5 MW offered to KSEB is not tied up
with any other utility.
31.2 In the TCC Meeting, MS, SRPC had informed that KSEB had filed a petition with
Hon’ble CERC. It would therefore be prudent to await the Order in this regard.
31.3 The Committee noted the above.
32. DOUBLING OF 110 KV KONAJE-MANJESHWARAM S/C FEEDER
32.1 KSEB vide letter dated 8th
December 2014 (refer Annexure-III) had stated that KSEB
was presently drawing 12 to 15 MW from 110 kV Konaje S/S of KPTCL. The issue
was deliberated in the 35th
SCPSPSR (19.02.2013). Till the 400 kV UPCL- Kasargode
line comes up the above lines could be converted to D/C which would enable more
power to North Kerala.
32.2 In the TCC Meeting, KPTCL had suggested that this issue be also deliberated in the
Meeting to be held at PCKL on 9th
January 2014.
32.3 The Committee noted the above.
33. PROVISION OF ADDITIONAL SPACE IN SRPC SECRETARIAT / OTHER
CIVIL WORKS
33.1 On account of increase in the number of Member Constituents in SRPC forum, and also
need to conduct a number of Meetings on various issues, it was found necessary to
enhance the available space in the SRPC Conference Hall. Certain other civil works /
modifications were also needed to be taken up in the building. Earlier too, certain
renovation works had been carried out through the good offices of Power Grid and
funding by the constituents. Necessary go ahead in this regard had been kindly sought.
33.2 TCC had observed that the number of member constituents had increased considerably.
It therefore recommended for approval of funding by the Constituents for the additional
space requirement/other civil works in the SRPC Secretariat.
33.3 The Committee approved the same in principle. Details would be put up in the next
Meeting of SRPC.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 68 of 73
34 S3 REGION TO BE FORMED BY BIFURCATING S2 AND ATC TO BE
CALCULATED FOR S2-S3 REGION BY FOLLOWING THE N-1 CONDITION
IN 400 kV UDUMALPET – PALAKKAD D/C LINES
34.1 TANTRANSCO vide letter dated 17.12.2014 (Annexure-XXI) had suggested present
S2 region has to be split into two regions namely S2 comprising of Tamil Nadu &
Puducherry and S3 comprising of Kerala alone.
34.2 The following had been noted in the TCC Meeting:
TANTRANSCO had suggested that S3 comprising of Kerala be carved out
keeping in view Grid security and overloading of 400 kV Udumalpet –
Palakkad D/C lines.
PGCIL had noted that in similar instances, separate areas had been identified
and the matter could be studied.
After deliberation, it was agreed that Study Committee could look into the
matter with participation from CTU & NLDC.
34.3 In the Meeting, it was agreed that this issue also would be deliberated in the Study
Committee Meeting with the participation of NLDC, CTU etc..
35. GRID OPERATION
35.1 Grid events/highlights during July 2014
400 kV Thiruvalam – Melakottaiyur ( Kalivanthapattu) D/C Line along with
associated bays under “ Transmission System associated with System
Strengthening of Southern Region XVIII” along with Communication Signal from
sending end to Receiving end, metering, telemetry and protection system had been
successfully charged on 24.07.2014 by PGCIL.
400 kV D/C line with Quad Moose ACSR from Kayathar 400 kV SS to Karaikudi
400 kV PGCIL SS line works completed. One circuit of 195 kms had been
radially test charged from Kayathar end with 63 MVAR 400 kV line reactor at
Kayathar on 04.07.2014 and tied with the grid on 26.07.2014 by TANTRANSCO.
400 kV D/C line from Pugalur 400 kV PGCIL SS to Kalivanthapattu 400 kV SS
line works completed. One circuit of 363.318 Kms had been test charged with 80
MVAR 400 kV line reactor at both ends and tied with grid on 23.07.2014 by
TANTRANSCO.
Conversion of existing 110 kV SC line on SC tower with Leopard conductor from
Loc 1(CBE SS)- 18 of 110 kV CBE O.K Mandapam feeder into 230 kV D/C line
tower with zebra conductor- Line energized on 16.07.2014 by TANTRANSCO
LILO of 230 kV Kayathar- Anuppankulam and 230 kV Kayathar – Pasumalai line
on MC towers at the proposed Kayathar 400 kV SS – Line energized on
19.07.2014 by TANTRANSCO.
Kayathar 400 kV SS was test charged on 04.07.2014 with 1 x 315 MVA ICT by
TANTRANSCO.
Thiruvalam 400 kV SS was test charged with 1 x 315 MVA ICT on 27.07.2014 by
TANTRANSCO.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 69 of 73
Coimbatore 400 kV SS was test charged with 1 x 100 MVA auto power transformer
on 16.07.2014 by TANTRANSCO.
Extension of 400/220 kV Thiruvalam S/Stn was commissioned in July 2014 by
PGCIL.
35.2 Grid events/highlights during August 2014
Andhra Pradesh, Kerala & Telangana were additionally allocated 200 MW, 76.83
MW & 100 MW from IGSTPS, Jhajjar of APCPL w.e.f. 1.8.2014 to 31.03.2015.
Operating procedure of SR was released by SRLDC.
Wind mills of capacity 4.7 MW had been added in Tamil Nadu.
35.3 Grid events/highlights during September 2014
Protection Committee Team visit to 400 kV Guttur S/S on 25th
& 26th
September
2014 to study repeated trippings.
Wind mills of capacity 4.9 MW had been added in Tamil Nadu.
MoP vide letter dated 29.09.2014 had allocated 50 MW unallocated power of first
unit (1000 MW) of Kudankulam APP to Andhra Pradesh from the date of
commercial operation of the unit. SRPC vide letter dated 07.10.2014 had
communicated the revised allocation to all the beneficiaries from the date of
commercial operation of the unit 1 of KKNPP.
35.4 Grid events/highlights during October 2014
Sincere cooperation extended by SR constituents during Hud Hud cyclone.
Protection System Analysis Group (PSAG-10) Meeting was held at Srisailam RB
on 14th
& 15th
October 2014 to address the grid disturbances at SRBPH.
200 MW power was additionally allocated to Andhra Pradesh from unallocated
quota of SR from 00 hours of 20th
October 2014 to 19th
November 2014.
35.5 Grid events/highlights during November 2014
Wind Mills of capacity 4.3 MW had been added in Tamil Nadu
35.6 Installation of Shunt Capacitors
The progress of installation of capacitors by the constituents during the year
2014-15 is furnished in the Table below:
(Figures in MVAR)
State Requirement
for 2014-15
Installed during the year 2014-
15 (till 30th
November 2014)
Andhra Pradesh 26.20 0.00
Karnataka 56.31 0.00
Kerala 10.00 0.00
Tamil Nadu 122.40 0.00
Installation of required capacitors works was sought to be completed early.
36. DEMAND VARIATION (Peak Vs Off-peak)
36.1 Issue regarding large variation between minimum and maximum demands has been
under the consideration of TCC/SRPC. The issue is also being discussed in the monthly
Meetings of OCC. Following was observed with regard to the period from July 2014 to
November 2014:
Minutes of the 26th Meeting of SRPC held on 20th December 2014 70 of 73
Description
Minimum to Maximum Demand Variation %
Andhra
Pradesh Telangana Karnataka Kerala
Tamil
Nadu Puducherry
Southern
Region
July 2014
Highest 29.89 25.14 33.17 46.16 27.72 32.82 29.90
Date 17th
4th 28th
21st 14
th 1
st 11
th
Lowest 2.55 11.69 14.74 28.89 12.03 13.66 10.68
Date 5th
2nd
4th
5th
20th
27th
5th
Average 19.03 18.20 27.13 40.28 20.03 21.69 16.94
August 2014
Highest 28.97 34.45 36.90 48.50 29.87 48.05 26.33
Date 6th
16th
25th
7th
25th
24th
30th
Lowest 10.36 16.15 18.32 36.42 13.19 13.96 11.25
Date 19th
13th
17th
22nd
3rd
5th
17th
Average 17.53 21.61 29.50 43.11 21.47 26.32 17.07
September 2014
Highest 25.16 33.93 36.55 47.38 28.57 33.78 28.33
Date 11th
16th
8th
1st 8
th 16
th 29
th
Lowest 2.91 13.20 20.20 31.44 8.25 15.40 11.72
Date 30th
18th
28th
27th
30th
2nd
27th
Average 15.06 20.99 29.07 40.40 19.73 25.78 17.80
October 2014
Highest 27.88 30.82 42.79 45.02 35.54 46.78 29.27
Date 12th
12th
27th
8th
24th
27th
28th
Lowest 9.20 15.94 18.82 30.49 9.38 14.68 8.15
Date 14th
17th
19th
5th
2nd
5th
2nd
Average 18.69 22.91 27.57 38.31 19.79 27.89 15.47
November 2014
Highest 22.11 30.19 38.16 47.90 29.22 40.85 26.13
Date 14th
27th
3rd
11th
20th
7th
17th
Lowest 11.29 14.27 19.57 33.61 14.66 25.53 16.67
Date 22nd
2nd
29th
23rd
2nd
16th
9th
Average 16.93 21.88 26.90 40.23 23.16 35.51 20.92
Note: Highest & lowest figures for the month have been computed based on the daily values.
36.2 In the TCC Meeting SRLDC had stated that the difference between maximum and
minimum demands were quite high and of the order of 5,000 - 6,000 MW. The same
was required to be minimized through appropriate demand side management in order to
avoid high voltage scenario.
36.3 Constituents were kindly requested to implement suitable DSM measures and also share
information with other constituents for mutual benefit.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 71 of 73
37. FREQUENCY OF OPERATION OF SOUTHERN GRID
37.1 The frequency of operation of the Southern Grid for the period under review is
furnished below:
Month
Percentage of time when frequency (Hz) was
Month
Avg.
freq. Less
than
49.5
49.5
to
49.7
49.7
to
49.9
49.9
to
50.0
50.0
to
50.05
50.05
to
50.20
More
than
50.20
Within
IEGC
range
49.9 to
50.05
July 2014 0.11 4.26 33.75 34.06 14.96 12.40 0.47 49.02 49.93
August 2014 0.08 4.47 36.67 32.74 15.10 10.62 0.32 47.84 49.92
September 2014 0.06 2.01 29.11 36.78 17.81 13.85 0.38 54.59 49.95
October 2014 0.00 1.62 25.57 34.00 18.38 19.73 0.70 52.38 49.96
November 2014 0.00 0.43 16.55 33.03 21.14 27.19 1.66 54.17 50.00
37.2 During the period under review, caution / violation messages (Annexure-XXII) were
issued to the constituents by SRLDC. Matter regarding overdrawal at low frequency by
some constituents is being regularly deliberated in the OCC forum. Utilities were
requested to kindly adhere to Regulations in this regard.
SRPC Noted the Following:
38 URTDSM (PMU) PROJECT IN SOUTHERN REGION
URTDSM project was planned to be completed within 24 months from the date of
award. A Meeting of the Coordinators of the utilities was held on 19th
September .2014
at SRPC, Bangalore. Installation and Training was likely to commence from December
2014.
39. DRAWAL POINTS OF COASTAL ENERGEN
In the 25th
Meeting of Commercial Sub-Committee held on 22nd
August 2014, it had
been agreed that energy accounting of drawal by Coastal Energen be based on the meters
at Madurai end on Madurai-Coastal line and meters at Coastal end on Coastal-NTPL
line. It had also been noted that energy accounting of startup power drawl by NTPL
would be based on the energy meters provided at NTPL end.
Minutes of the 26th Meeting of SRPC held on 20th December 2014 72 of 73
.
40. PAYMENT OF TRANSMISSION CHARGES & OPENING OF LC FOR
DRAWAL OF START UP POWER DURING COMMSSIOING PERIOD BY
GENERATING STATIONS
The matter was further deliberated in the 26th
Meeting of Commercial Sub-Committee
held on 21st November 2014. After deliberations, the following had been agreed:
Generators granted startup power drawal under DSM mechanism would be
advised to open LC in line with the methodology followed by PGCIL in the
GMR Energy Limited case.
As an interim arrangement, transmission charges from the generators
drawing startup power under DSM mechanism could be levied based on the
applicable withdrawal charges by taking approved withdrawal as the
weighted average of MW allocation granted by SRLDC. CTU would collect
the transmission charges based on RTA and RTDA. Disbursement of
amount collected would be carried out after obtaining clarification in this
regard.
41. AUDITING OF ACCOUNT - ANNUAL SUBSCRIPTION FOR CONDUCTING
VARIOUS COMMITTEE MEETINGS OF SRPC
In the 25th
SRPC Meeting, it was noted that the account in respect of annual subscription
for conducting of various Committee Meetings is operated by Chief Engineer, SLDC,
KPTCL. The account was proposed to be audited and the Audit Report submitted to
Chairperson, SRPC. The Committee had approved the above.
Accordingly, the Account had been audited and Audit Report submitted to Chairperson,
SRPC
Minutes of the 26th Meeting of SRPC held on 20th December 2014 73 of 73
42. DATE & VENUE OF THE NEXT SRPC MEETING
It was decided to hold the 27th
Meeting of SRPC in due course. Telangana kindly
agreed to host the next Meeting at Hyderabad.
43. VOTE OF THANKS/PLACING ON RECORD CONTRIBUTIONS
43.1 The Committee placed on record the excellent contributions to various forums of SRPC
of Shri R.V.Sundararaman, MD, TANTRASCO, Shri C.Kaliaperumal, Chief Engineer,
TANTRANSCO and also Shri N. Ravi Kumar, Executive Director, SRTS-II, PGCIL
who were due to superannuate shortly.
43.2 MD, TANTRANSCO thanked SRPC for providing necessary guidance and solving a
number of issues.
43.3 Chairperson, SRPC & MD, KPTCL thanked all the Constituents for meaningful
deliberations and arriving at consensus on a number of issues.
43.4 Member Secretary, SRPC thanked Chairperson, SRPC & MD, KPTCL for kindly
chairing the Meeting.
Sd/- Sd/-
(S.R. BHAT) (G. KUMAR NAIK) IAS
Member Secretary, SRPC Chairperson, SRPC & MD, KPTCL
******