    SP SOLAR WIND SOLUTIONS

    SITE INSTALLATION AND SPECIFICATIONDOCUMENT: PART 10

    DC BACK UP GENERATOR

    D0273 48V 70A HYBRID POWER SUPPLY

    BROCHURE REV3

  • 8/8/2019 Sp Solar Wind Solutions

    2/32

    SP SOLAR WIND SOLUTIONS LM01/V08: PART 10

    Issued by

    SP Solar Wind Solutions (Pty) Ltd

    309 Derdepoort Road / Silvereike Tannery Industrial Park Unit 32 Sinoville

    Pretoria

    Copyright SP Solar Wind Solutions (Pty) Ltd All Rights Reserved.

  • 8/8/2019 Sp Solar Wind Solutions

    3/32

  • 8/8/2019 Sp Solar Wind Solutions

    4/32

  • 8/8/2019 Sp Solar Wind Solutions

    5/32

    Table of Content

    Table of Content5

    part 18

    Document Information8

    Introductions10

    1. Aim10

    2. Copyright10

    3. Issue Control10

    4. History10

    5. Glossary and Abbreviations10

    6. Keyword / Descriptor11

    Tool List13

    7. General13

    8. Safety13

    9. Special Tool14

    10. Instruments List14

    part 1015

    DC Back up Generator D0273 48V 70A HYBRID POWER SUPPLY BROCHURE REV317

    11. DESIGN PHILOSOPHY18

    12. Present Solution18

    13. Future Solution20

    14. Proposed Layout of Hybrid Solution21

    15. General21

  • 8/8/2019 Sp Solar Wind Solutions

    6/32

    16. Generator Specification22

    17. Operation Threshold Settings22

    18. System Specification24

    a. The Base Frame24

    b. The Unit Specifications24

    c. The Diesel Fuel Tank24

    d. Anti Vibration Mounting Rubbers24

    e. Engine25

    f. Noise Levels25

    g. Maintenance25

    h. Alternative Information Specification25

    i. Control25

    j. Canopy26

    k. Engine Operation as well as Engine Protection26

    i. Emergency Stop Pushbutton Alarm26

    ii. Engine Low Oil Pressure Alarm26

    iii. Start Failure Alarm26

    iv. Faulty Switch Position Alarm27

    v. Exhaust27

    vi. Alternator Abnormal Voltage.27

    l. Manual Operation27

    m. Alternator27

    n. Load Battery28

  • 8/8/2019 Sp Solar Wind Solutions

    7/32

    o. Documentation and Training28

    19. Photographs Of 48v 70a Hybrid Power Supply Prototype29

  • 8/8/2019 Sp Solar Wind Solutions

    8/32

    part 1

    Document Information

    Document SITE INSTALLATION AND SPECIFICATION DOCUMENT:

    Document number SP SOLAR WIND SOLUTIONS LM01/V08: PART 10

    Date created 05/10/2006

    Author G.B. Posthumus

    Technical writer G.B. Posthumus

    Last modified (date) 22/11/2006

    Last modified (by) Gerhard Posthumus

  • 8/8/2019 Sp Solar Wind Solutions

    9/32

  • 8/8/2019 Sp Solar Wind Solutions

    10/32

    Introductions

    1. Aim

    a. The aim of the document is define all equipment and civil used to produce this site.

    b. Ensure that safety is applied in all actions performed in the installation of thisequipment.

    c. State the technical specifications of this equipment regarding to the installation of the

    equipment.

    d. Indicate the wiring of the equipment.

    e. Supply technical drawings were applicable.

    f. Stipulated the step by step installation processes.

    g. To be applied as a training Document.

    2. Copyright

    a. All rights reserved. No part of this publication may be reproduced, transmitted, stored

    in retrieval system, or translated into any language in any form by any means, optical,electronic, recording, or otherwise, without the written permission of our company.

    b. We reserve the right to revise this manual and make changes to any or all parts at any

    time, without obligation to notify any person or entity of such revision and changes.

    3. Issue Control

    See Paragraph 4 History.

    4. History

    Issue Date Reason for Changes

    01 05/10/2006 New Specification

    02 21/10/2006 Add Astrabase mast and HCM information to specification

    5. Glossary and Abbreviations

  • 8/8/2019 Sp Solar Wind Solutions

    11/32

    a. BTS - Base Transceiver Station

    b. GSM - Global System Mobile

    c. Regulator Charge Controller Blue Sky

    d. LM Last Mile

    6. Keyword / Descriptor

    a. Container, BTS, Base Station

  • 8/8/2019 Sp Solar Wind Solutions

    12/32

  • 8/8/2019 Sp Solar Wind Solutions

    13/32

    Tool List

    7. General

    a. Spanners ring and open end, 8mm to 32mm.

    b. Shifter 28mm

    c. Pliers Combination.

    d. Screw driver set flat and star. (Full Set)

    e. Battery Drill/Screwdriver.

    f. Tech Screw 6 and 8mm by 25mm.

    g. Spirit Level.

    h. Ratchet set, 8mm to 32 mm.

    i. Ladder 6 foot x2.

    j. Balancing Rope x4.

    k. Pulley Times 2.

    l. Rope rigging.

    m. Side cutters small and big.

    n. Crimpers big and small.

    o. Heat Gun.

    p. Concrete Drill.

    q. Pop rivet gun.

    r. Torch.

    s. Rigging Spanners for mast.

    8. Safety

  • 8/8/2019 Sp Solar Wind Solutions

    14/32

    a. Safety Gloves.

    b. Grip Poles.

    c. Safety shoes.

    d. Safety harness.

    e. Hard hat.

    f. Fall Arrestor Equipment.

    g. Rigging Equipment.

    9. Special Tool

    a. Block and Tackle 7 meter chain.

    b. Solar Frame lifting tool.

    c. Rigging rope.

    d. Rigging Harness.

    10. Instruments List

    a. Multi Meter.

    b. Clamp meter.

    c. Heat detector.

    d. Wind Measurement.

    t. Digital camera.

    e. Label instrumentation.

  • 8/8/2019 Sp Solar Wind Solutions

    15/32

    part 10

  • 8/8/2019 Sp Solar Wind Solutions

    16/32

  • 8/8/2019 Sp Solar Wind Solutions

    17/32

    DC Back up Generator

  • 8/8/2019 Sp Solar Wind Solutions

    18/32

    D0273 48V 70A HYBRID POWER SUPPLY BROCHURE REV3

    11. DESIGN PHILOSOPHY

    a. For remote Base Transceiver Station (BTS) sites, where solar power is utilized tocharge a bank of 48V Batteries to power transmission equipment, the followingscenario usually applies:

    b. The BTS Radio Transmission equipment requires a 48V DC Power Source. As mains

    or grid power is usually not available on these remote sites, the power source utilizedis a battery bank. The battery bank uses solar power to recharge by utilizing a solar

    panel. Should the weather be overcast, the solar panel will be unable to recharge thebattery. For this reason, the typical battery is sized to store five days of energy.

    Depending on the site requirements, the typical battery bank is 48V, 2000Ah.

    c. A problem arises however, when the weather is overcast for more than five days, or if

    the window period for adequate sunlight is shortened due to seasonal rainfall. On theisolated occasions (probably 5 or 6 times per year) when this does occur, an alternate

    means of charging the batteries is required.

    12. Present Solutiona. The standard solution to this problem is relatively expensive and complex. One would

    usually use a standard Genset.

  • 8/8/2019 Sp Solar Wind Solutions

    19/32

    b. Then add to that a set of rectifiers to convert three phase 400V AC into a 55V DCFloat voltage. Then a special controller would be needed to monitor the state of the

    battery bank.

    c. By the time you have added all of these components, the end result is relatively

    expensive.

  • 8/8/2019 Sp Solar Wind Solutions

    20/32

    13. Future Solution

    We propose to do it a different way:

    a. The heart of the solution incorporates a standard 48Vdc wind turbine generatorsupplied by Kestrel Wind Turbines (Pty) Ltd that supplies battery charging energy.

    b. The generator being directly connected to the battery system is powered by a reliable

    air-cooled single cylinder diesel engine from a 750rpm half speed output shaft.

    c. The genset is designed in such a way that the fuel tank acts as a shelter for the genset,and no extra expensive housing is required.

    d. A Siemens LOGO! PLC controls the Genset, and monitors the state of the battery

    bank. If it is necessary to supplement the solar power recharging by using the

    generator, the controller will signal the generator to run for a pre-determined periodand charge the battery bank.

    e. The unit is designed for this purpose, and we anticipate it will only run a few times

    per year, when there has been a climatic reason for the Solar panels to be unable tocharge the batteries.

  • 8/8/2019 Sp Solar Wind Solutions

    21/32

    14. Proposed Layout of Hybrid Solution

    15. General

    a. A specially designed 48V DC Generator, that was specially designed by Kestrel Wind

    Turbines c.c. in South Africa, for use on Wind Turbines will be used.

    b. A modified version of this DC Generator to recharge the battery bank.

    c. A reliable air-cooled single cylinder engine with a half speed shaft that rotates at

    750RPM, to drive the DC generator will be used.

    d. At 650 Rpm the wind turbine is producing 3400 Watt.

    e. The output of this generator couples to the battery bank directly.

    f. The genset is designed in such a way that the fuel tank acts as a shelter for the genset,and no extra expensive housing is required.

    g. A Siemens LOGO! PLC controls the Genset, and monitors the state of the batterybank. If it is necessary to supplement the solar power recharging by using the

    generator, the controller will signal the generator to run for a pre-determined periodand charge the battery bank.

  • 8/8/2019 Sp Solar Wind Solutions

    22/32

    16. Generator Specification

    Engine:Kirloskar DA10, 7kW Single Cylinder Air Cooled Diesel

    Engine

    Alternator: Kestrel Wind Turbines c.c. DC Generator. 3.3kW, 70A 48VController: Siemens LOGO! PLC

    Control V: 12V DC

    Fuel Tank: 200 litres capacity

    Load Battery: 48V DC Typically 2000Ah

    Weight: 450Kg

    Size: 1.500 x 1.000 x 1.200m

    Fuel Consumption: 1.1l/hour

    a. Hybrid Genset dimensions:(H)1350mm x (D)1100 x (W) 1700.

    b. Canopy provider to provide canopy with at least the following dimensions, with at

    least 600mm access at the front and back for maintenance etc. That is (H) 1500 x (D)2300 x (W) 1700

    17. Operation Threshold Settings

  • 8/8/2019 Sp Solar Wind Solutions

    23/32

    Unit will start when battery voltage

    reaches this threshold:46V for 30 seconds

    Time unit will run for after start

    command is given:6 hours (programmable)

    Unit will stop on fault condition below

    this threshold:42V

    Unit will stop on fault condition above

    this threshold:60V for 2 seconds

    Unit will stop on fault condition above

    this threshold:58V for 15 minutes

  • 8/8/2019 Sp Solar Wind Solutions

    24/32

    18. System Specification

    a. The Base Frame

    i. The Base Frame for the Hybrid System is manufactured out of mild steel

    channel, and painted black.

    ii. The base frame includes lifting eyes at all 4 corners for ease of rigging andinstallation.

    iii. Anti corrosive base coat: A Raw metal primer is applied to aid in corrosion,and in correct paint application.

    b.

    The Unit Specificationsi. The unit is supplied without a canopy.

    ii. The unit is to be installed in the Tower's canopy/room/enclosure.

    iii. The genset dimensions are (H)1350mm x (D)1100 x (W) 1700.

    iv. The unit has access at the front and back - at least 600 mm either side for easy

    access for maintenance etc. Louvres must be provided to allow enough airflowacross the engine. (Louvres not supplied by Diesel Electric Services).

    v. You need a louvre 600x800 for air intake, and another louvre 600x800 for air

    removal.

    c. The Diesel Fuel Tank

    i. The diesel fuel tank has a 200 litre capacity, and is manufactured out of mildsteel plate.

    ii. A spill tray can be provided by customer request, however its not necessary on

    such a small set with such a small tank.

    d. Anti Vibration Mounting Rubbers

    i. The Engine has Anti Vibration Mounting Rubbers installed to dampen

    vibration transfer from the Engine to the base frame when the engine is running.

  • 8/8/2019 Sp Solar Wind Solutions

    25/32

    ii. The Anti Vibration Mounting Rubbers have a warrantee it for 1 year, but theyare designed to work for the life of the engine - 10 years.

    e. Engine

    The engine used is a Kirloskar DA10, 7kW Single Cylinder Air Cooled Diesel Engine.

    The engine has a warrantee of 2800 hours or one year, witch ever comes 1st.

    f. Noise Levels

    i. Noise Levels of Engine at 1 Meter on open Set are 90dBA.

    ii. Noise level on open set at 7 metres is 84dBA. the db of a closed canopy willdepend on the canopy design by the canopy manufacturer.

    g. Maintenance

    i. Engine Maintenance in very dirty environments, clean the air filter and oilfilter sieve. Every 50 hours.

    ii. Service every 500 hours, replace the oil, oil filters, fuel filters, and air filters.

    Check injectors etc.

    h. Alternative Information Specification

    i. This engine has a rotating shaft available running at half the engine speed.

    ii. The engine is coupled to the alternator via this half speed shaft.

    iii. The option to use a Lister Engine is not available.

    i. Control

    i. The Engine Control utilizes a Siemens LOGO! PLC.

    ii. The control utilizes 12V DC from the engine starting battery.

    iii. The unit is designed in such a way that the starting battery is charged from theload batteries by using a DC to DC converter, to ensure that the engine starting

    battery remains fully charged at all times. The LOGO! PLC controls Load BatteryMonitoring.

  • 8/8/2019 Sp Solar Wind Solutions

    26/32

    j. Canopy

    i. Canopy needs to be such that it provides protection to minimum if IP53

    ii. The engine supplier approved the configuration engine/canopy in terms of

    accessibility, air intake and exhaust location?

    iii. The unit is supplied without a canopy.

    iv. The unit is to be installed in the Tower's canopy/room/enclosure. T

    v. he genset dimensions are (H)1350mm x (D)1100 x (W) 1700. T

    vi. he unit has access at the front and back - at least 600 mm either side for easy

    access for maintenance etc. Louvres must be provided to allow enough airflowacross the engine. (Louvres not supplied by Diesel Electric Services).

    vii. You need a louvre 600x800 for air intake, and another louvre 600x800 for air

    removal.

    k. Engine Operation as well as Engine Protection

    Engine Operation as well as engine protection for the following conditions:

    i. Emergency Stop Pushbutton Alarm

    If the Emergency Stop Pushbutton is pressed, the engine will immediately stop, avisual LED on the control panel will indicate the particular alarm and the Potentialfree Common Alarm Contact will activate.

    ii. Engine Low Oil Pressure Alarm

    If a low oil pressure is detected while the engine is running, the engine willimmediately stop, a visual LED on the control panel will indicate the particular

    alarm, and the Potential free Common Alarm Contact will activate.

    iii. Start Failure Alarm

    Three start attempts are allowed once the engine is instructed to run. If the engine

    hasnt started after the third start attempt, a visual LED on the control panel willindicate the particular alarm and the Potential free Common Alarm Contact will

    activate.

  • 8/8/2019 Sp Solar Wind Solutions

    27/32

    iv. Faulty Switch Position Alarm

    If the control Switches on the control panel are not selected for Automaticoperation, a visual LED on the control panel will indicate the particular alarm, and

    the Potential free Common Alarm Contact will activate

    v. Exhaust

    (1) The engine is supplied without an exhaust. A new exhaust is fit

    (2) The manufacturer measurements on the carbon monoxide: TBA

    vi. Alternator Abnormal Voltage.

    (3) Should the voltage of the batteries exceed a pre-determined threshold, the

    unit will be instructed to stop charging, thus preventing any damage to thebatteries due to overcharging, and preventing any damage to the DC

    Generator due to an open circuit occurring.

    (4) The Load Batteries are at a nominal voltage of 48V. Please see section onOperation Threshold Settings.

    (5) These settings are the recommended settings, but can be changed by theoperator on site if so required.

    l.

    Manual OperationManual Operation of the System is available as an option if required.

    m. Alternator

    i. The alternator is a Kestrel 0404 48Vdc nominal 3kWdc (60A at 55Vdc) 70A

    maximum.

    ii. 12 Stage rectification DC, unregulated.

    iii. The Kestrel 0404 alternator is mounted directly onto the base frame.

    iv. A Special coupling between this and the engine is utilizes to minimise the

    vibration perceived by the alternator.

    v. The windings are coated to suite all weather conditions and the warrantee of

    the wind generator covers this as well. This includes Tropical conditions.

  • 8/8/2019 Sp Solar Wind Solutions

    28/32

    vi. 2 Year Warrantee

    n. Load Battery

    i. Load Battery: 48V DC Typically 2000Ah.

    ii. This is not part of our scope of supply, however the system is designed for abattery bank of this capacity, and if this capacity is reduced significantly, the

    operation of the system may not be optimal.

    o. Documentation and Training

    i. A full set of documentation including operation and maintenance manuals are

    provided with each hybrid system.

    ii. Although the documentation is comprehensive, training can be provided at our

    premises in at no charge if required.

    iii. To be provided within 2 weeks of placement of order.

  • 8/8/2019 Sp Solar Wind Solutions

    29/32

    19. Photographs Of 48v 70a Hybrid Power

    Supply Prototype

    Kestrel Wind Turbines 70 48V DC Generator Coupling between Engine and DC Generator

  • 8/8/2019 Sp Solar Wind Solutions

    30/32

    1 Cylinder Kirloskar Engine with half speed shaft

    Coupling between Engine and DC Generator

  • 8/8/2019 Sp Solar Wind Solutions

    31/32

  • 8/8/2019 Sp Solar Wind Solutions

    32/32

    Back view of our Hybrid Prototype

    Front view of our Hybrid Prototype