Space Shuttle Integration Lessons Learned

Embed Size (px)

Citation preview

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    1/84

    Space Shuttle IntegrationLessons Learned

    Bo Bejmuk

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    2/84

    2

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning

    Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned fromShuttle development &operations can reduce

    Constellation life-cycle costand development schedule,and result in more reliable

    and safer systems

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    3/84

    3

    8/31/2006

    Introduction

    Two types of Shuttle Program Lessons Learnedare addressed

    Problems How they were resolved and theirapplicability to Ares I

    Success Stories How they were achieved and theirapplicability to Ares I

    Lessons Learned are presented at a fairly highlevel

    Each can be expanded to any desired level of detail

    Top-level Lessons Learned from Zenit DerivedLaunch Systems Sea Launch are included

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    4/84

    4

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning

    Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned fromShuttle development &operations can reduce

    Constellation life-cycle costand development schedule,and result in more reliable

    and safer systems

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    5/84

    5

    8/31/2006

    System Integration Approach

    Shuttle Integration included:

    Configuration tradeoffs early in the development phase

    Mated system analysis and testing

    On the ground

    In flight

    Mated vehicle checkout requirements at the launch site

    Post flight data analysis

    Independent evaluation of all elements changes

    Definition and verification of system interfaces and interface

    parameters and associated documentation Integrated Hazard Analyses

    Integrated vehicle configuration management

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    6/84

    6

    8/31/2006

    System Integration Organization

    NASA was the Systems Integrator

    Boeing, (Rockwell) was the Systems Integrationcontractor

    The importance of integration was not fully appreciatedafter the initial development phase

    NASA revitalized System Integration twice during theShuttle Programs life

    After the Challenger accident After the Columbia accident

    Each time a strong leader was put in charge ofIntegration and the Integration resources wererevitalized

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    7/84

    7

    8/31/2006

    System Integration Organization

    (continued)Lesson

    It appears that the strength of Integration leadership

    is very important to the success of a program Integration should remain the watchful eye as the

    Program evolves to an operational status

    Continue flight data evaluation for the life of theProgram

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    8/84

    8

    8/31/2006

    Shuttle System Definitions &

    Corresponding Analyses

    1) Shuttle on Groundand Liftoff

    2) Post Liftoff Configuration 3) Boost Configuration

    Liftoff Loads Ground Winds Liftoff Clearances Acoustics ET Pressurization Main Propulsion System Avionics Sequencing & Timing Electrical Power Integrated Hydraulics Software Requirements Integrated Checkout

    Requirements

    Winds Aloft High Q Loads Heating Aero & Plume Flutter & Buffet Acoustics SRB Separation

    Control Stability & ControlAuthority

    ET Pressurization & MPS Integrated Hydraulics Software Requirements POGO

    High G Loads Heating Aero & Plume ET Pressurization & MPS Integrated Hydraulics Power Control Stability & Control

    Authority POGO Software Requirements ET Separation

    Evaluation of flight test results and the establishment of operationalboundaries for all flight phases

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    9/84

    9

    8/31/2006

    Shuttle Elements

    Ground Systems

    Solid RocketBoosters (SRB)

    External Tank

    Shuttle System

    Main Engines

    Orbiter*

    * Two cargo configurations analyzed 65K lbs and 0 lbs payloads

    Solid RocketMotor (SRM)

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    10/84

    10

    8/31/2006

    System Integration Support to Element

    Designers NSTS-07700 consisted of a series of requirements

    documents that were imposed on the elements System Integration analysis results were documented in

    Induced Environments Data Books and used by elementdesigners Loads

    Aerodynamics

    Aeroheating Plume heating

    Vibro acoustics

    Separations Main propulsion

    Other Technical panels were established early in the development

    cycle to provide a forum for the smooth interchange ofinformation between system integration and element experts

    The Systems Integration technical effort was iterative and

    involved several Design Cycles

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    11/84

    11

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning

    Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned fromShuttle development &operations can reduce

    Constellation life-cycle costand development schedule,and result in more reliable

    and safer systems

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    12/84

    12

    8/31/2006

    STS-1 SRB Ignition Overpressure (IOP)

    Problem

    SRB IOP measured at the vehicle exceeded the 3-sigma liftoffdesign environment

    Accelerations measured on the wing, body flap, vertical tail, andcrew cabin exceeded predictions during the liftoff transient

    Support struts for the Orbiters RCS oxidizer tank buckled

    Post flight analysis revealed that water spray designed tosuppress SRB IOP was not directed at the source of IOP

    Source of IOP was believed to be at the plume deflector

    STS-1 data analysis showed the primary source located

    immediately below the nozzle exit plane

    Tomahawk ignition transient used for preflight characteristicswere very different from that of the SRB

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    13/84

    13

    8/31/2006

    STS-1 SRB IOP (Continued)

    Corrective Actions Solution to the SRB IOP was treated as a

    constraint to STS-2

    IOP Wave Committee organized withparticipation of the NASA and the contractors

    A 6.4% model was modified to allow simulation ofsimultaneous ignitions of two SRBs with the firingof one motor only Add a splitter plate in the flame bucket

    A new scaling relation was developed based onblast wave theory

    A series of 6.4% scale model tests were conductedto evaluate various concepts of IOP suppression

    schemes Final fixes

    Redirected water spray for SRB IOP suppression

    toward the source of SRB IOP (Figure 1) Installed water troughs in the SRB exhaust duct

    Very significant IOP reduction was achieved (Fig. 2)

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    14/84

    14

    8/31/2006

    Figure 1: STS-1 and STS-2 SRB IOP

    Suppression Configuration

    STS-2 ConfigurationSTS-1 Configuration

    Water spray for STS-1was designed for IOPSource at flame deflector

    Water spray atThe flame deflectorand side pipesalong the duct

    Water spray at theside of duct deleted

    Water spray atthe crest of theflame deflector

    Water troughs cover theSRB duct inlet

    100,000 GPM of waterinjected into the SRBexhaust beneaththe nozzle exit plane

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    15/84

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    16/84

    16

    8/31/2006

    STS-1 SRB IOP (Continued)

    Lessons

    1. SRB Ignition is a powerful driver in liftoff environments

    2. System Integration, responsible for liftoff environmentdefinition, accepted the Tomahawk ignition test as asufficient simulation of SRB ignition IOP Did not fullyappreciate the effect of the differences between the SRBand the Tomahawk ignition characteristics

    3. SRB ignition transient for Ares I should benefit from postSTS-1 efforts on the Space Shuttle

    MLP configuration should be evaluated to account for a singleSRB

    If the SRB propellant shape or type is changed, the effect onIOP should be re-evaluated

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    17/84

    17

    8/31/2006

    Ascent Aerodynamics

    Problem Plume simulation used during the preflight wind tunnel test

    program was not adequately implemented

    Observed significant wing lift and vehicle lofting in STS-1 Measured strains showed negative structural margins

    Under-predicted ascent base pressures (base drag over-predicted) Temperature effects were not modeled in cold jet plume

    simulation parameters used during testingCorrective Actions The Post-flight tests using hot plume simulations improved

    base and forebody pressure predictions The ascent trajectory was changed to a flight with a greater

    negative angle of attack through High Q The negative angle reduced wing lift The negative angle had to be evaluated for Orbiter windows and

    the ET side wall pressures

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    18/84

    18

    8/31/2006

    Ascent Aerodynamics (continued)

    Lesson Although the hot plume re-circulation effect is less

    significant on an axis-symmetric vehicle, it shouldbe accounted for when defining pressure on thebase and aft portion of the vehicle

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    19/84

    19

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning

    Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management

    Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned fromShuttle development &operations can reduce

    Constellation life-cycle costand development schedule,and result in more reliable

    and safer systems

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    20/84

    20

    8/31/2006

    Structures

    Problem

    Throughout Shuttle development and the initial years ofoperations many costly structural modifications had to bemade to maintain the required 1.4 structural safety factor

    The Shuttle structure was designed for a 1.4 safety factor with noadditional margin to accommodate changes occurring during thedevelopment phase

    Corrective Actions

    As mathematical models and definitions of the environmentsmatured, resulting changes required many hardware changesto eliminate areas of negative margin (below a 1.4 safety factor)

    These hardware modifications were expensive and timeconsuming. Additionally, they increased workload at the launchsite

    This tedious activity ensured safe flights and compliance with thesafety factor requirement, however it created a significant impacton Shuttle operations

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    21/84

    21

    8/31/2006

    Structures (continued)Lessons

    If development time is short, structural margin

    management could be pursued to avoid costlyhardware changes as loads analyses mature

    A suggested approach could be as follows:

    Assign additional factor to be applied to the design loads forenvironments with the greatest uncertainties

    For example, gravity and pressure loads could have a factor of1.0 but dynamic and aero loads could have a factor of 1.2

    All factors would converge to 1.0 as a function of program

    maturity

    A method of structural margin management couldminimize costly hardware redesign, and program standdowns, but it may result in a somewhat heavier vehicle

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    22/84

    22

    8/31/2006

    Structures - Aero Elasticity

    Problem Flight data indicated a significantly higher buffet response of the

    vertical tail and body flap during ascent (at transonic speeds) The importance of buffet loads was not fully appreciated in the early

    Shuttle design (flutter was properly analyzed, safe boundaries wereestablished and stability was verified during flight)

    Corrective Actions

    Flight instrumentation and ascent photography were used tomeasure response in flight Ascent environments were updated to correspond to measured

    response The body flap critical design case was entry (thank goodness), no

    action was required since including buffet loads on ascent was stillenveloped by entry

    The vertical tail had sufficient margin to accommodate increased buffet

    loads

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    23/84

    23

    8/31/2006

    Structures - Aero Elasticity (continued)

    Lesson Even though the Ares I has a significantly simpler

    configuration, transonic buffet, particularly for thebulbous shape, should be addressed in the early loadsanalyses and test programs

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    24/84

    24

    8/31/2006

    Liftoff Loads Analyses

    Problem

    Shuttle liftoff (L/O) loads were very difficult to analyze

    Configuration complexity

    SRB Ignition Overpressure

    Twang during the SSME thrust buildup

    Vandenberg experience showed that loss of the MLP compliance significantlyincreased L/O loads

    Flexible washers were planned to restore compliance and avoid vehicle redesign

    ET/Orbiteraxial interface

    SRB

    Growth

    H2 TankCompliance

    Shuttle

    MLP

    Ares I

    SRB growthloads aretransmitteddirectly to 2nd

    stage potentiallycreating more

    sever L/O loads

    Common Shuttle/Ares I

    SRB grows 0.9 duringignition

    MLP deflectsdownward

    Forward interfacetranslates upward

    SRB growthloads aretransmitteddirectly toOrbiter thru H2Tank. H2 Tank

    providessofteningcompliance

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    25/84

    25

    8/31/2006

    Liftoff Loads Analyses (continued)

    Corrective Actions SRB ignition delayed until the SRB bending moment (due to

    SSME thrust buildup) was at zero Four independent support posts modeled in L/O

    simulations Monte Carlo method was incorporated Ground wind restrictions were implemented

    Lesson In spite of the relative configuration simplicity of the Ares I,

    L/O loads may be a significant design issue due to direct

    load path between the SRB and the upper stage

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    26/84

    26

    8/31/2006

    Structural Dynamics Testing

    Success Story

    Carefully developed Ground Vibration Test (GVT) program identifiedand facilitated correction of math model errors and precluded criticalproblems in-flight and potentially costly hardware redesign

    Disciplines benefiting from GVT included Loads, POGO, Flutter & FlightControl Analyses

    Building Block Approach

    Starting with element GVT

    Ending with full scale mated test at MSFC

    Scale Model GVT followed by full scale GVT The stiffening effects of the internal SRB chamber pressure were evaluated in a

    scale GVT

    Element GVTs

    SRB L/O & Boost Phase, & Burnout

    ET with various liquid levels Orbiter FREE-FREE & constrained at ET interface

    Mated GVTs

    Orbiter/ET Boost Phase

    4 Body mated, L/O, High Q, & SRB Burnout

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    27/84

    27

    8/31/2006

    Structural Dynamics Testing (Continued)

    Lesson

    Extensive investment into the Shuttle GVT Program can save

    money on Ares I

    Dynamic Characteristics of SRB Verified including:

    Liftoff, High Q and burnout configurations

    SRB/MLP Interface

    Dynamic response at rate gyro locations

    Dynamic interaction of SRB structure with visco-elastic propellant

    The effect of chamber pressure of the SRB dynamic properties

    Upper stage alone in Free-Free and constrained at SRBinterface configurations could be a sufficient and costeffective GVT for Ares I

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    28/84

    28

    8/31/2006

    Conversion of Static Test Article (STA)

    to the Flight OrbiterSuccess Story

    The Orbiter STA was originally intended for Orbiter structure strength

    demonstrations

    Planned to be subjected to ultimate loads

    Demonstration of 1.4 times limit load

    Very difficult to simulate combined thermal and mechanical loads

    Prior to test start, the decision was made to limit loading to limit plus loadlevel

    Test article was not stressed beyond yield This test was supplemented by component testing to 1.4 times limit loads in areas

    of low margin and sensitive joints

    The Orbiter test article was treated as flight hardware (configuration management,problem dispositions)

    Post test, the STA was converted to flight hardware and used as theChallengers airframe

    Lesson

    Thoughtful planning of the test hardware and transitioning it to flight status

    could result in significant cost savings

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    29/84

    29

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management

    Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduce

    Constellation life-cycle costand development schedule,and result in more reliable

    and safer systems

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    30/84

    30

    8/31/2006

    Ascent Flight Control System (FCS)

    Problem

    During Filament Wound Case SRB integrated vehicle analysisthe first structural mode was 1.7 Hz, compared to 2 Hz forbaseline vehicle

    Strong coupling with LOX slosh mode created (FCS) inadequatestability margin after liftoff

    Very difficult to filter out due to the proximity of frequencies forthe 1st bending, slosh and FCS closed loop modes

    Corrective Action

    The Program was cancelled, but the lesson remained

    Lesson

    Consider imposing minimum modal frequency on the launchvehicle to avoid coupling with slosh and control systemmodes

    May require stiffness requirements (in addition to strengthrequirement) for Stage I/Stage II interface hardware

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    31/84

    31

    8/31/2006

    Ascent Flight Control System (Continued)

    Success Story

    SRB rate gyros were incorporated into the Mated VerticalGround Vibration Test (MVGVT) test articles

    Large rotations were measured at the locations of the gyrosin low frequency modes

    Modal gains were large enough to cause potential loss ofvehicle due to FCS instability

    Corrective action was simple

    Stiffening the shelf on which gyros were installed

    Lesson

    Instrument every FCS sensor location preferably with flight-like sensors in future GVTs

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    32/84

    32

    8/31/2006

    Ascent Flight Control System (Continued)

    Success Story

    Conservative approach used in slosh baffle implementation

    STS-1 8 LO2 baffles

    STS-17 4 LO2 baffles SLWT 3 LO2 baffles

    Slosh baffles are easily removed, but difficult to add as theprogram matures

    Lesson Retain a conservative approach for slosh baffle

    implementation

    Avoids redesign to increase slosh damping

    Allows easy weight reduction as FCS stability is confirmed byflight data

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    33/84

    33

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management

    Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduce

    Constellation life-cycle costand development schedule,and result in more reliable

    and safer systems

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    34/84

    34

    8/31/2006

    Day-of-Launch I-Loads Update

    (DOLILU) EvolutionProblem

    The launch probability predictions for early Shuttle flights was lessthan 50%

    More than half of the measured winds aloft violated the vehicles certifiedboundaries

    Corrective Actions

    System Integration led the evolution from a single ascent I-load,through seasonal I-loads, alternate I-loads, and finally arriving at

    DOLILU

    This process extended over a 10+ year period (Figure 3)

    Concurrently the Program executed 3 load cycles (Integrated Vehicle

    Baseline Characterization - IVBC) combined with hardware

    modifications to expand vehicle certified envelopes (Figure 4) Current launch probability is well in excess of 95%

    Lesson

    Commit to a DOLILU approach during early development

    Significantly improves margins

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    35/84

    35

    8/31/2006

    Figure 3: Ascent Design Operations Evolution

    1975 1985 1995 2005

    50

    0

    100

    Med

    High

    Low

    Ope

    rations

    Overhea

    d

    Percen

    to

    fWin

    ds

    Violating

    Cert

    ifica

    tion

    (%)

    AnnualSeasonal

    MonthlyAlternate

    Day-of-Launch

    Lesson Learned: Reliance on Operations Processto Maintain Margin is Expensive

    Certification Violations

    Ascent OperationsOverhead

    Fi 4 D f L h I L d E l ti

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    36/84

    36

    8/31/2006

    Early FlightsSingle I-Loads

    Present FlightsDOLILU

    Qb

    3-Hour Wind

    Variation

    DOLILU drives toward center of QaQbenvelope and reduces winds violation to < 5%

    CertifiedEnvelope

    Ares I can benefit by starting with DOLILU or Adaptive Ascent Guidance

    Expanded CertifiedEnvelope

    Over 50% of winds

    violated certifiedenvelope

    Annual WindVariation

    Qa

    Qb

    Qa

    Figure 4: Day-of-Launch I-Loads Evolution(10 years +)

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    37/84

    37

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management

    Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduce

    Constellation life-cycle costand development schedule,and result in more reliable

    and safer systems

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    38/84

    38

    8/31/2006

    Avionics ArchitectureProblem

    Prevention of loss of vehicle/crew or mission due to avionicsfailures considering mission duration up to approximately 12 days

    Actions

    Dissimilar solutions (primary, backup and two fault tolerance inavionics hardware/software)

    Establishment of SAIL Simulation of hardware/softwareinteraction

    Four LRU Mid Value Select (MVS) implemented with appropriatecross strapping to ensure two fault tolerance

    The Redundancy Scheme was required to be test verified

    Two fault tolerance became an avionics system mainstay on the

    Shuttle OrbiterLesson

    The Orbiter system provided a reliable avionics system. For ashort duration, missions such as Ares I ascent suggested atradeoff to be performed between one and two fault tolerance.

    Overall system reliability could be used in the evaluation.

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    39/84

    39

    8/31/2006

    1st Stage (SRB)2nd StageSM

    Avionics Architecture (Continued)

    The Shuttle approach of two fault tolerance* was robust, but

    may be excessive for a boost only vehicle. The overallsystem reliability (for example 0.999) should driveredundancy requirements.

    * With some compromises

    Orion

    High TimeExposure

    Low TimeExposure Trade off study suggested: One vs.

    two fault tolerance on Booster A tailored level of fault tolerance

    could emerge as the best solution

    Establishing the Fault Tolerance Requirements is a PrimaryAvionics Cost Driver

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    40/84

    40

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management

    Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduce

    Constellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    M i P l i

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    41/84

    41

    8/31/2006

    Main Propulsion

    Problem Pressure oscillations upstream of the SSME first

    stage pumps were not fully appreciated and notincluded in the design environments

    This caused inadequate design resulting in fatigue of theH2 temperature probe located 18 upstream of pump

    Combined environments (vibroacoustics and pressureoscillations) also created fatigue cracks in the flowliners

    Neither were protected by screens

    Corrective Actions

    Eliminated temperature probe and switched LCC toupstream manifold measurement impact 2 monthsProgram stand down

    A massive analytical and test effort, resulting inpolishing flow liner slots, welding existing cracks andimplementing inspection after each mission impact

    4 months Program stand downLesson

    Based on Shuttle analytical and test experience,develop and incorporate pressure oscillations in theMain Propulsion System (MPS) hardware designenvironments

    M i P l i ( ti d)

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    42/84

    42

    8/31/2006

    Main Propulsion (continued)

    Problem

    Fill & drain valve shaft roller bearings failure in MainPropulsion Test Article (MPTA) spread debris throughout themain propulsion system.

    System did not contain debris screens due to pressure dropconcerns.

    Several other cases of debris were found in MPS during earlydevelopment phase

    Corrective Actions

    Pre-valve screens were implemented. However, locations ofthe screens were not optimal due to the existing hardwareconfiguration constraints

    Lesson

    Decision to protect engine inlet from debris using screensshould be made early in the MPS development

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    43/84

    43

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management

    Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    44/84

    44

    8/31/2006

    Flight Software Shuttle Experience

    Problem

    Concern over reliability of flight software (generic failure)during critical phases of flight

    Corrective Action

    Both Primary and Backup Flight Software were baselined inthe early stages of development

    Primary & Backup run independently on separate computers Backup was never engaged over the life of the Program and

    software reliability has improved since the ShuttleDevelopment timeframe

    Lesson For Ares I, Backup software is not recommended for ascent

    flight. However, for Orion, it should be considered for crewescape.

    Flight Software (Continued)

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    45/84

    45

    8/31/2006

    Flight Software (Continued)Problem

    Significant duplication of development andverification facilities on Shuttle

    Examples include:

    FSL, FCHL, SAIL (STS & GTS), SES, SMS,JAEL, KATS plus dozens of non-real-timeperformance verification tools

    These facilities played an important role but,once established, their existence perpetuated

    This created unnecessary cost drag on theProgram

    Lesson

    Manage Ground and Flight Software and

    avionics facilities on the Ares I Program topreclude unnecessary proliferation andduplication

    Force labs to terminate when their role is

    finished

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    46/84

    46

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management

    Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    Li ht i R i t

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    47/84

    47

    8/31/2006

    Lightning Requirements

    Problem

    The Shuttle started with strict requirements

    TPS could not be certified

    Avionics were difficult

    Corrective Actions

    Decision was made to transition to operationalrestrictions

    Field Mills & catenaries on ground

    Cloud cover restrictions before launch

    Years of unnecessary cost and effort prior todecision

    Lesson

    Starting with a fair weather vehicle may be acost effective approach

    Some avionics hardening could be worthwhile

    Crew escape should be considered for

    hardening

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    48/84

    48

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management

    Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    Flight Vehicle Instrumentation

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    49/84

    49

    8/31/2006

    Flight Vehicle Instrumentation

    Problem In spite of extensive analysis and testing, during the development phase,

    the flight vehicle frequently does not behave as predicted, as was the

    case with the Shuttle This could create a flight safety issue (Eg. SRB overpressure, aero

    ascent anomaly) Incorrect models, incorrect definition of the environments, incorrect

    assumptions

    Corrective Action The Program implemented a basic development flight instrumentation

    infrastructure Technical discipline experts stated their specific requirements late, after

    the vehicles were built

    Late definition of instrumentation created the necessity for aninvasive design and installation

    Program reluctance to accommodate late requirements Finally limited instrumentation implemented over several flights of

    Columbia Limited instrumentation was continued into the operations phase

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    50/84

    50

    8/31/2006

    Flight Vehicle Instrumentation (continued)

    Lesson Mandate design organizations to define requirements

    for flight instrumentation concurrently with systemdesign

    Emphasis of verification and addressing uncertaintiesmay result in easier implementation

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    51/84

    51

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management

    Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    52/84

    52

    8/31/2006

    RCS Thrusters

    The Orbiter has two bipropellant RCS systems

    Primary 870 lbs thrust used during

    ascent from SRB separation through entry

    Vernier 25 lbs thrust used on orbit for attitude adjustmentand maintenance

    Only applicable lessons learned from the Primarythrusters will be discussed

    Approximate thrust range of potential roll control Ares Ithrusters

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    53/84

    53

    8/31/2006

    RCS Thrusters (Continued)

    Problem

    The fuel valve seat extrusion caused leakage, leading to fail-

    off and deselect This was caused by a small oxidizer leak, which softened the

    valve seat

    Corrective Actions

    Adopted thruster chamber purge

    Developed a screening test and incorporated into the ATP

    Tightened leakage requirements for oxidizer valves

    Lesson

    For the bi-prop system, avoid Teflon fuel valve contaminationwith the Oxidizer

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    54/84

    54

    8/31/2006

    RCS Thrusters (Continued)Problem

    Thrust chamber combustion instability

    Acoustic resonance driven by high combustion chamber

    pressure oscillations Caused by pressurant Helium bubbles in the fuel system

    Corrective Actions

    Combustion stability screening added to hot fire ATP (Helium

    injection)

    Incorporated wire wrap around combustion chamber to shutdown the thruster at the onset of burn through

    Lesson

    Avoid pressurant gas in the propellant if possible (eg. Usebladders)

    Address combustion stability during the development andtest program

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    55/84

    55

    8/31/2006

    RCS Thrusters (Continued)

    Problem

    Thruster Columbium injector intergranular cracking

    Caused by residual stresses and inadequate rinsing of

    pre-weld etchant, coupled with high temperature (~600Degrees F) insulation bake-out

    Corrective Actions

    Eliminated pre-weld etch for new build

    Developed NDE to inspect for cracks at White SandsDepot and on vehicle

    Lesson

    Avoid processes or chemicals that would result withFluorine coming into contact with Columbium at

    temperatures above 500 Degrees F

    OUTLINE

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    56/84

    56

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation

    RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    Materials and Processes

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    57/84

    57

    8/31/2006

    Problem

    Flexible metal hoses, many of them

    Criticality 1, experienced damage,which caused leakage

    Each Orbiter contains 208 flexible hoses

    Ease of installation

    Effective strain isolation

    30 hoses were damaged and createdleaks over the Programs life

    M t i l d P ( ti d)

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    58/84

    58

    8/31/2006

    Materials and Processes (continued)

    Corrective Actions

    Educated workers on the vulnerability of flex hoses

    Implemented inspection and replacement with spares andalso substituted with rigid lines whenever practicable

    Could have caused Program stand down; was covered by theReturn to Flight schedule

    Lesson

    Try to avoid using metal flexible hoses, especially in hightraffic areas and incorporate hard protection wheneverpossible

    Educate workers and visitors on the vulnerability of flexhoses from the Programs onset

    OUTLINE

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    59/84

    59

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation

    RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    Risk Management

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    60/84

    60

    8/31/2006

    Problem Although risk was managed by good engineering practices, very

    little formal risk classification and management was employed Probabilistic Risk Analysis (PRA) was rarely used on the Shuttle

    Program

    Distrust of the methodology, lack of suitable data, Apollo experience Frequently funds were expended pursuing corrective action for

    extremely low probability threats no means to measureeffectiveness of a corrective action on the overall system reliabilityor safety

    Corrective Actions A 5X5 matrix risk classification was implemented on the Shuttle

    Program Up and down the organization, from individual technical disciplines to

    the Program Manager (Figure 5) PRA implemented on several technical projects

    Orbiter windows, debris, Kevlar Overwrapped tanks, MMOD

    Response to CAIB criticism

    Risk Management (continued)

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    61/84

    61

    8/31/2006

    Risk Management (continued)

    Lesson Formal risk management, including PRA, early in

    development could produce many cost savingsfeatures such as: Ensuring that system reliability drives redundancy

    requirements

    Prioritizing safety and reliability enhancements Identifying highest value initiatives

    Use competent PRA analysts Must have the data

    PRA does not replace good engineering

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    62/84

    OUTLINE

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    63/84

    63

    8/31/2006

    OUTLINE Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System

    Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation

    RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    Initial Naive Concept of Operations

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    64/84

    64

    8/31/2006

    Initial Naive Concept of Operations

    Operational Reality

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    65/84

    65

    8/31/2006

    Operational Reality

    NASA, KSC Photo, dated September 25, 1979, index number KSC-79PC-500

    Operational Cost Drivers

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    66/84

    66

    8/31/2006

    p

    Problem

    Insufficient definition of operational requirements duringdevelopment phase

    Concentration on performance requirements but not on operationalconsiderations

    Shuttle design organizations were not responsible for operational cost

    Very few incentives for development contractors

    Corrective Actions

    Very labor intensive (high operational cost) vehicle was developedand put into operations

    Lesson

    Must have the Concept of Operations defined

    Levy the requirements on contractors to support the Concept ofOperations

    Must have continuity and integration between designers, groundoperations, and flight operations requirements during thedevelopmental phase

    Operational Cost Drivers (Continued)

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    67/84

    67

    8/31/2006

    Problem The cost of reusability of complex, multifunctional, aging vehicle

    Every Orbiter function whether used or not on a given mission must

    be verified and checked out prior to flight

    Every function must also be monitored and failures managed to

    avoid a catastrophic event Reusability of aging complex systems requires ever increasing

    attention to maintain performance and safety

    Complex paper system touched by too many organizationsgoverns every step of the operation

    Early 1980s heritage

    Only limited streamlining over the life of the Program

    Lesson

    Complexity creates flight operational cost

    Minimize complexity Manual approach adds to operational cost

    Automate

    Realistically define operational life prior to development

    OUTLINE

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    68/84

    68

    8/31/2006

    Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation

    RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    Structural and Ascent Performance MarginManagement

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    69/84

    69

    8/31/2006

    Management

    Problem Unrealistic ascent performance requirements eliminated the

    possibility of effective margin management DOD insisted on 32K lbs polar orbit capability

    Equivalent to 65K lbs due East NASA needed DOD support of the Shuttle Program

    Continuous pursuit of the elusive 65K lbs due East ascentcapability precluded the possibility of holding back somestructural margin to avoid costly redesign changes as Programdevelopment matured

    Prior to performance enhancement program the Shuttle had anascent performance shortfall of ~10K lbs

    Actions Taken

    All priorities were subordinated to the quest for ascentperformance Very few features supported effective operations

    Costly structural modifications to maintain the required factor ofsafety were made

    Structural and Ascent Performance Margin

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    70/84

    70

    8/31/2006

    g

    Management (continued)Lesson Set realistic ascent performance requirements

    Hold back some margin to be used for problem areas

    Use factors on not well understood environments toprotect against costly design modifications as Programknowledge matures

    Transition to operations should be made consistent with

    vehicle operational capabilities imbedded in the design

    OUTLINE

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    71/84

    71

    8/31/2006

    Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation

    RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    Significance of Shuttle Lessons Learned

    G t SRB IOP2-Fault Tolerant Margin Mgmt.

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    72/84

    72

    8/31/2006

    Applica

    bility

    toA

    res

    I

    1

    2

    3

    4

    5

    1 2 3 4 5

    Significance to ShuttleLess Greater

    Less

    Greater SRB IOPAvionics

    Ops Cost Drivers

    Engine Inlet

    Screens

    Ascent Aero

    Anomaly

    MPS Pressure

    Oscillations

    RCS Combustion

    Instability

    RCS Inter-granular

    Cracking

    Flex Hoses

    Software

    Reliability

    Buffet

    DOLILU

    Liftoff Loads

    g g

    Risk Management

    Lightening

    Flex Modes

    Effects on FCS

    RCS Seat

    Extrusion

    S/W Verification

    Facilities

    Risk of Crew/Vehicle Loss

    Risk to Cost/Schedule

    Instrumentation

    RGAs in GVT

    GVTSTA as Flight

    Article

    Slosh Baffles

    OUTLINE

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    73/84

    73

    8/31/2006

    Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation

    RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned from

    Shuttle development &operations can reduceConstellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    Launch Platform

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    74/84

    74

    8/31/2006

    Courtesy of the Sea Launch Company

    Assembly and Command Ship

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    75/84

    75

    8/31/2006

    Courtesy of the Sea Launch Company

    Launch

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    76/84

    76

    8/31/2006Courtesy of the Sea Launch Company

    Sea Launch Zenit Derived Launch System

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    77/84

    77

    8/31/2006

    Major integration of existing and newelements

    Two stage Ukrainian Zenit

    3rd stage Russian Block DM

    New payload accommodation &composite fairing

    Modified semi-submersible oil drilling

    platform into a launch pad

    New command and control and rocketassembly ship

    System was built and brought to

    operational state in less than 3.5 years

    22 flights to date, 21 successful

    Courtesy of the Sea Launch Company

    Sea Launch Operations Integration of rocket stages

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    78/84

    78

    8/31/2006

    and payload at home port inLong Beach, CA

    Launches performed from the

    Equator, 154 degrees west(south of Hawaii)

    300405Totals

    40

    1405070

    80

    2005075

    Americans

    RussiansUkrainiansNorwegians

    Launch

    Team*

    Ground Processing

    Team

    * Launch Team is a subset of the Ground Processing Team; GroundProcessing team members that are not required to participate in launch atsea are sent back to their companies and are off the Sea Launch payroll

    Small Team performs ground checkout and launch

    Courtesy of the Sea Launch Company

    Lessons Learned from Sea Launch

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    79/84

    79

    8/31/2006

    Zenit extremely automated launch vehicle

    Very little interaction with crew during checkout, pre-launch, andflight

    Single string accountability, no duplications of effort (tosome extent driven by export compliance restrictions)

    Low operational cost benefited from original design criteriaof Zenit

    Rollout to pad, fuel and launch in 90 minutes

    Allows very little time for ground or flight crew involvement

    Imposes requirements for automatic processes

    OUTLINE

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    80/84

    80

    8/31/2006

    Introduction System Integration Approach Liftoff and Ascent Aerodynamics Structures Ascent Flight Control System Day-of-Launch I-Loads Evolution Avionics Architecture Main Propulsion Software Lightning Flight Instrumentation

    RCS Thrusters Materials and Processes Risk Management Operational Cost Drivers Margin Management Significance of Lessons Learned Other Applicable Lessons Learned

    Zenit Derived Launch System Sea Launch Delta IV Separate Briefing

    The Big Lesson

    Lessons learned fromShuttle development &operations can reduce

    Constellation life-cycle costand development schedule,and result in more reliable

    and safer systems

    The Big Lesson

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    81/84

    81

    8/31/2006

    At least 2 critical design flaws existed in the flightsystem through design, testing and flight testing

    Not detected or acknowledged as major problems

    A gap existed between actual and perceived state ofvehicle robustness and safety

    Although strong indications were present, neither thedesign nor the operations team identified the problem

    The Big Lesson (continued)

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    82/84

    82

    8/31/2006

    Big Lesson

    WE WERE NOT AS SMART AS WE THOUGHT WE WERE!

    Develop and maintain a strong integration team throughout theprogram life cycle

    Empower integration to challenge the elements and program onissues of design flaws and interaction between the elements

    Continuously monitor performance and safety throughout the transitionto operations and the operations phase

    Integration and element engineering should be staffed with the bestin their fieldinquisitive by nature, respected by peers andmanagement, and who have the courage to take on the Programregarding issues

    Transition to operations should be made consistent with vehicleoperational capabilities imbedded in the design

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    83/84

    83

    8/31/2006

    BACK-UP

    Seven Types of System Analyses will DefineInterstage Stiffness Requirements

  • 8/2/2019 Space Shuttle Integration Lessons Learned

    84/84

    84

    8/31/2006

    g q

    1.) Response to Ground Winds

    2.) Liftoff Loads and Clearances3.) Roll Control Authority

    4.)Transonic Buffet

    5.) FCS Flex Stability6.) High Q static Elastic Loads

    7.) High Q Response to Gust

    InterstageHardware