10
Techno-economic analysis of a CO 2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant Roberto Canepa a, * , Meihong Wang b a DIME sez.MASET, University of Genova, Via Montallegro 1,16145 Genova, Italy b School of Engineering, University of Hull, Hull HU6 7RX, UK highlights A post-combustion CO 2 capture plant model has been developed and has been extensively validated at pilot scale. Capture plant model has been scaled up to meet the requirement of a commercial 427 MW CCGT power plant. Sensitivity analysis has been conducted to reduce thermal energy requirement to 4.1 GJ/tonne CO 2 . Levelized cost of the electricity from CCGT power plant is increased by 47% when CO 2 capure process is added. article info Article history: Received 31 August 2013 Accepted 11 January 2014 Available online xxx Keywords: Process modelling Process simulation Gas turbine Combined cycle CCGT Post-combustion Carbon capture Techno-economic analysis abstract In this study, a combined cycle gas turbine (CCGT) power plant and a CO 2 capture plant have been modelled in GateCycle Ò and in Aspen Plus Ò environments respectively. The capture plant model is validated with experimental data from the pilot plant at the University of Texas at Austin and then has been scaled up to meet the requirement of the 427 MWe CCGT power plant. A techno-economical evaluation study has been performed with the capture plant model integrated with ue gas pre- processing and CO 2 compression sections. Sensitivity analysis was carried out to assess capture plant response to changes in key operating parameters and equipment design. The study indicates which parameters are the most relevant (namely absorber packing height and regenerator operating pressure) and how, with a proper choice of the operating conditions, both the energy requirement for solvent regeneration and the cost of electricity may be reduced. Ó 2014 Elsevier Ltd. All rights reserved. 1. Introduction 1.1. Background and motivations Carbon Capture and Storage (CCS) is regarded as an essential technology to meet greenhouse gases reduction goals [1]. CO 2 capture with chemical absorption using amine solvent is a proven and well established technology. Despite this, CO 2 capture from exhaust gas coming from a power plant poses many technical and economical challenges. Current CO 2 capture projects involve pilot plants on a scale much smaller than required to capture CO 2 from a commercially available power plant. In September 2012, Global CCS Institute has identied 75 large-scale integrated CCS projects (LSIP) running globally [2]. An LSIP is dened by Global CCS institute as a project involving the capture, transport and storage of CO 2 at a scale of at least 800,000 tonnes of CO 2 annually for coal-based power plants or at least 400,000 tonnes of CO 2 annually for other emission-intensive industrial facilities (including natural gas-based power generation). More than half of all projects started during 2012 are located in China, and all of these are investigating enhanced oil recovery (EOR) options as an additional source of revenue. Among these LSIPs only 16 are, however, currently oper- ating or in construction, for a global capture capacity of around 36 million tonnes per annum. These projects require investments of the order of dozens millions of Euros. It is expected that a full scale demonstration project for CO 2 capture would require over a billion dollars [3]. Accurate modelling of CO 2 capture plant, for the insight it can provide, is therefore a necessary intermediate step towards demonstrating full scale CO 2 capture. Both technical performance and costs are determinant factors to select optimal operating conditions. * Corresponding author. E-mail addresses: [email protected] (R. Canepa), [email protected] (M. Wang). Contents lists available at ScienceDirect Applied Thermal Engineering journal homepage: www.elsevier.com/locate/apthermeng 1359-4311/$ e see front matter Ó 2014 Elsevier Ltd. All rights reserved. http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014 Applied Thermal Engineering xxx (2014) 1e10 Please cite this article in press as: R. Canepa, M. Wang, Techno-economic analysis of a CO 2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant, Applied Thermal Engineering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

  • Upload
    meihong

  • View
    219

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

lable at ScienceDirect

Applied Thermal Engineering xxx (2014) 1e10

Contents lists avai

Applied Thermal Engineering

journal homepage: www.elsevier .com/locate/apthermeng

Techno-economic analysis of a CO2 capture plant integrated with acommercial scale combined cycle gas turbine (CCGT) power plant

Roberto Canepa a,*, Meihong Wang b

aDIME sez.MASET, University of Genova, Via Montallegro 1, 16145 Genova, Italyb School of Engineering, University of Hull, Hull HU6 7RX, UK

h i g h l i g h t s

� A post-combustion CO2 capture plant model has been developed and has been extensively validated at pilot scale.� Capture plant model has been scaled up to meet the requirement of a commercial 427 MW CCGT power plant.� Sensitivity analysis has been conducted to reduce thermal energy requirement to 4.1 GJ/tonne CO2.� Levelized cost of the electricity from CCGT power plant is increased by 47% when CO2 capure process is added.

a r t i c l e i n f o

Article history:Received 31 August 2013Accepted 11 January 2014Available online xxx

Keywords:Process modellingProcess simulationGas turbineCombined cycleCCGTPost-combustionCarbon captureTechno-economic analysis

* Corresponding author.E-mail addresses: [email protected] (R. Canep

(M. Wang).

1359-4311/$ e see front matter � 2014 Elsevier Ltd.http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Please cite this article in press as: R. Canepacombined cycle gas turbine (CCGT) power p

a b s t r a c t

In this study, a combined cycle gas turbine (CCGT) power plant and a CO2 capture plant have beenmodelled in GateCycle� and in Aspen Plus� environments respectively. The capture plant model isvalidated with experimental data from the pilot plant at the University of Texas at Austin and then hasbeen scaled up to meet the requirement of the 427 MWe CCGT power plant. A techno-economicalevaluation study has been performed with the capture plant model integrated with flue gas pre-processing and CO2 compression sections. Sensitivity analysis was carried out to assess capture plantresponse to changes in key operating parameters and equipment design. The study indicates whichparameters are the most relevant (namely absorber packing height and regenerator operating pressure)and how, with a proper choice of the operating conditions, both the energy requirement for solventregeneration and the cost of electricity may be reduced.

� 2014 Elsevier Ltd. All rights reserved.

1. Introduction

1.1. Background and motivations

Carbon Capture and Storage (CCS) is regarded as an essentialtechnology to meet greenhouse gases reduction goals [1]. CO2capture with chemical absorption using amine solvent is a provenand well established technology. Despite this, CO2 capture fromexhaust gas coming from a power plant poses many technical andeconomical challenges. Current CO2 capture projects involve pilotplants on a scale much smaller than required to capture CO2 from acommercially available power plant. In September 2012, Global CCSInstitute has identified 75 large-scale integrated CCS projects (LSIP)

a), [email protected]

All rights reserved.

, M. Wang, Techno-economilant, Applied Thermal Engine

running globally [2]. An LSIP is defined by Global CCS institute as aproject involving the capture, transport and storage of CO2 at a scaleof at least 800,000 tonnes of CO2 annually for coal-based powerplants or at least 400,000 tonnes of CO2 annually for otheremission-intensive industrial facilities (including natural gas-basedpower generation). More than half of all projects started during2012 are located in China, and all of these are investigatingenhanced oil recovery (EOR) options as an additional source ofrevenue. Among these LSIPs only 16 are, however, currently oper-ating or in construction, for a global capture capacity of around 36million tonnes per annum. These projects require investments ofthe order of dozens millions of Euros. It is expected that a full scaledemonstration project for CO2 capture would require over a billiondollars [3]. Accurate modelling of CO2 capture plant, for the insightit can provide, is therefore a necessary intermediate step towardsdemonstrating full scale CO2 capture. Both technical performanceand costs are determinant factors to select optimal operatingconditions.

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Page 2: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

R. Canepa, M. Wang / Applied Thermal Engineering xxx (2014) 1e102

1.2. Novel contributions of this paper

CO2 capture process is, with current available technology, a veryexpensive and energy-intensive process. Despite this, it is gainingattention among researchers and policymakers as a short-mid termsolution to contain carbon emissions from existing or yet to be builtfossil fuelled power plant. However, as usual for a substantially newtechnology (at least at the scale required for capturing CO2 frompower plants), much resistance remains, mainly due to the uncer-tainty connected to actual performance and costs. Therefore,accurate modelling constitutes a stepping-stone to increase confi-dence about CO2 capture process. In this perspective, rate-basedmodelling procedure adopted by the Authors constitute, whencompared to equilibrium based calculations, a superior solution interms of accuracy and sensitivity to changes in the operating pa-rameters. In addition to this pilot plants currently existing or, evenmore, large scale demonstration projects currently being built, arelimited in the range of parameters that can be changed. Captureplant modelling, if based on a rigorous and trusted modellingprocedure, can overcome this intrinsic limitation and following thisidea a wide sensitivity analysis has been conducted on the mainoperating and design parameters in order to identify optimalworking conditions, thus reducing uncertainty in thermal andeconomics characteristics of the process. Furthermore, combiningcapture plant commercial scale modelling with an extensive vali-dation campaign (over a wide range of L/G ratio and process con-ditions) constitute an emblematic element of novelty.Summarizing, the main novelties of this article are:

a. Extensive validation campaign of capture plant at pilot plantscale combined with commercial scale modelling andsimulation

b. Capture plant operating conditions and design parameterssensitivity analysis

2. Modelling of CCGT power plant

A commercial Combined Cycle Gas Turbine (CCGT) power plant,targeted to 427 MWe production (before capture) is modelled inGE’s GateCycle� software. GateCycle� software allows an accuratemodelling of design but also off-design power plant componentsoperation. The performance of the steam cycle sections, sized forthe reference non-capture case, is automatically scaled to take intoaccount the modified pressure and temperature they will face afterretrofitting to capture CO2.

The reference commercial CCGT power plant employs a heavyduty single shaft Ansaldo Energia AE94.3A gas turbine from whichexhaust gas is led to an unfired heat recovery steam generator(HRSG). The steam cycle consists of three pressure levels (124, 28and 4.5 bar respectively) with a reheat loop. The steam iscondensed in a condenser with outer water at 15 �C. Deaeration isattained in the deaerator, which operates at 4.5 bar, by using lowpressure steam. The condensate from the condenser is heated bymeans of a closed cycle loop in order to increase heat utilizationfrom flue gas as much as possible. All the parameters required forthe calculation comes from various sources: Ansaldo companyprivate communications, GateCycle� software library and commonpractice for large combined cycle power plants.

3. Integration between CCGT power plant and capture plant

An exhaust gas with mass flow rate of 702 kg/s is delivered toflue gas pre-processing and consequently capture sections.Applying post-combustion CO2 capture to a CCGT power plant re-quires minimal structural changes to the original cycle and is

Please cite this article in press as: R. Canepa, M. Wang, Techno-economicombined cycle gas turbine (CCGT) power plant, Applied Thermal Engine

therefore regarded as the best capture option for existing powerplants. Enough space should be provided for flue gas pipeline andcapture related sections (notably flue gas pre-processing, CO2capture and compression) which should be located in the vicinity ofthe power plant. The main connections between power plant andthe capture plant are as follows:

a. Flue gas pre-processing;b. Steam draw-off from the steam turbine in CCGT power plant to

feed the reboiler of the regenerator in the CO2 capture plant;c. Condensate return from capture plant to the power plant.

The first two processes result in a reduction of electricity outputfrom the CCGT power plant.

3.1. Flue gas pre-processing

Exhaust gases coming from the HRSG, before being sent to thecapture plant, need to be cooled down to 40e50 �C in order toimprove absorption and reduce solvent losses due to evaporation[4]. The cooling system consists of a direct contact cooler (DCC) inwhich a spray of water cools down flue gases to the desired tem-perature level.

This process has been modelled in Aspen Plus� environment byusing RadFrac block for the DCC, regarded as a two theoreticalstages tower with Rashig rings packing. Flue gases are cooled downto 40 �C by direct contact with a spray of water at 25 �C. During thecooling process water is recovered from the flue gas because ofcondensation. Finally, a blower increases the pressure of the cooledflue gases to a pressure above the atmospheric level, to balance thepressure losses in the capture plant. In Fig. 1, the entire Aspen Plus�

flowsheet for flue gas pre-processing is presented. Assuming ablower isentropic efficiency equal to 88.5%, compression powerrequirement has been found to be equal to 8896 kW.

3.2. Steam draw-off

The steam required by solvent regeneration in the reboiler isprovided by means of a steam bled from the IP/LP crossover. As aresult, the LP steam turbinewill see amajor reduction of steam flowrate, which will result in the reduction of both its efficiency andpower output. A throttled pressure configuration is used in thisstudy. Given the reducedmass flow rate going through the LP steamturbine, its inlet pressure would drop. To guarantee a sufficienttemperature (and thus pressure) for extraction, a valve has beenadded at IP/LP crossover. This adds pressure throttling losses to theefficiency penalty connected to reduced LP steam turbine massflow rate and efficiency.

To avoid solvent degradation due to high temperature, thesteam has to be cooled down to a temperature just above saturationwith a water spray. The waste heat resulting from this process hasbeen partially recovered by combining the steam with some of thecondensate coming from the reboiler. In this way steam draw-off isalso reduced. The remaining condensate is then returned to thecondenser.

4. Modelling of CO2 transportation and compression

At ambient condition, CO2 is a gas. At a temperaturebetween �56.5 and 31.1 �C, it may be turned into a liquid bycompressing it up to the corresponding liquefaction pressure. Thecritical point occurs at 73.825 bar and 31.4 �C. Above this criticalpressure (and at temperatures higher than 60 �C), only supercriticalor dense-phase liquid conditions exist. If the temperature andpressure are both above the critical point, supercritical conditions

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Page 3: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

Fig. 1. Aspen Plus� flowsheet for flue gas pre-processing section.

Table 1CO2 compression performance.

Parameter Value

CO2 mass flow rate [kg/s] 38.77Outlet pressure [bar] 110Intercooling temperature [�C] 35Polytropic efficiency (stage 1) [%] 85.5Polytropic efficiency (stage 2) [%] 85Polytropic efficiency (stage 3) [%] 84Polytropic efficiency (stage 4) [%] 78Water recovery [kg/s] 0.203Compressor power [kW] 11,225Compressor power [kJ/kgCO2] 289.51

R. Canepa, M. Wang / Applied Thermal Engineering xxx (2014) 1e10 3

are attained: CO2 no longer exists in distinct gaseous and liquidphases, but as a dense-phase with the density of a liquid but theviscosity of a gas. At pressures above, but temperatures belowcritical conditions, CO2 is a dense liquid, whose density increaseswith decreasing temperature. Captured CO2 has to be transportedto a suitable storage site: pipeline is themost economical method oftransport in the context of CCS (Refs. [5,6]). To allow an efficienttransportation, CO2 flow coming from capture plants has to becompressed above critical pressure. Indeed, managing of a two-phase system might be technically very hard to achieve and,moreover, a greater density allows a smaller, and thus cheaper,pipeline. A very important requirement is that pressure, all alongthe pipeline, should never drop below critical value. Thus CO2pipeline inlet pressure needs to be chosen according to a properpressure drop estimation along the pipeline. To cover great dis-tances, as it likely might be required for many power plants, anadditional intermediate boosting station should be provided. Inliterature [7] a lower limit pressure of 80 bar is usually suggested toguarantee a certain margin.

Pressure loss depends on many factors, such as the pipelinediameter and length, the roughness of the pipe and CO2 flow ve-locity. It might be calculated using the DarcyeWeisbach equation:

Dp ¼ 10�5fLDi

ravgv2avg2

(1)

Assuming a capacity factor, that is the ratio of nameplate powerfunctioning over the year, equal to 75% and 8766 h per year(averaging over leap years), a sizing requirement of 0.918 Mtonne/yr for the pipeline has been found. CO2 density is very dependenton pressure and temperature. Considering an average pipelinepressure equal to 95 bar and a ground temperature of 10 �C, CO2

density is equal to 810.8 kg/m3.Carbon steel pipes can be adopted thanks to the high degree of

control over the water content of the CO2 being transported. Thepipe has been chosen from existing tabled pipes [8]: a 10 inches(0.254 m) pipe with a 0.307 inches (7.80 mm) thickness has beenadopted. This gives an internal diameter equal to 0.238 m and avelocity of 1.07 m/s. With this assumptions, pressure loss over the

Please cite this article in press as: R. Canepa, M. Wang, Techno-economicombined cycle gas turbine (CCGT) power plant, Applied Thermal Engine

total assumed pipeline length (100 km), is calculated equal to17.0 bar. An inlet pressure equal to 110 bar gives a final dischargepressure of 93 bar and is thus sufficient to guarantee desiredtransport condition all along pipeline. If a greater distance had to becovered, pumping stations should be provided to raise CO2 pressureas needed.

The compression to 110 bar is achieved with a four stageintercooled centrifugal compressor modelled with Aspen Plus�.Water is removed during cooling process. PengeRobinson equationof state is used as a thermodynamic base model. In Table 1compressor assumptions and performance are given.

5. Modelling and simulation of capture plant

5.1. Methodology

Capture plant section model has been developed in Aspen Plus�

starting from Ref. [9], to which it can be referred for more details.Absorber and regenerator columns have been modelled using arate-based approach, which ensures higher reliability over equi-librium based one [10]. Electrolyte NRTL activity coefficient modelis used to account for liquid phase non-ideality, while the RedlicheKwong equation of state is employed for vapour. Both vapoureliquid equilibrium (VLE) and kinetic reactions are accounted for inthe columns. The following set of rate-controlled reactions has

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Page 4: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

Table 2Kinetic parameter for rate-controlled reactions.

Reaction K [e] E [cal/mol] Source

2 4.32Eþ13 13,249 Pinsent et al. [12]3 2.38Eþ17 29,451 Aspentech [13]4 9.77Eþ10 9855.8 Hikita et al. [14]5 3.23Eþ19 15,655 Hikita et al. [14]

R. Canepa, M. Wang / Applied Thermal Engineering xxx (2014) 1e104

been defined to represent monoethanolamine (MEA) reaction withCO2:

CO2 þ OH�/HCO3� (2)

HCO3�/CO2 þ OH� (3)

MEAþ CO2 þ H2O/MEACOO� þ H3Oþ (4)

MEACOO� þH3Oþ/MEAþ CO2 þ H2O (5)

They are governed by power law expressions which kineticcoefficients are given in Table 2. On the other hand, equilibriumconstants for equilibrium reactions are calculated from the stan-dard Gibbs free energy change. To reduce the solvent regenerationheat requirement, a cross heat exchanger is used to pre-heat therich solvent stream entering the regenerator column by usingcascade heat from the hot lean solvent stream coming from theregenerator itself. This would constitute a closed loop within theAspen Plus� flowsheet and therefore would require, rigorously, toprovide a tear stream for the cross heat exchanger. This has beenavoided by using two different heat exchanger for the hot (lean)and the cold (rich) side of the actual heat exchanger respectively.These heat exchangers are then linked together by a heat stream, toensure the same heat duty on the two sides. Being absorptionprocess favoured by low temperature, a cooler is needed to furtherdecrease lean solvent temperature. Solvent and water makeup arerequired to close the loop due to losses in vapour streams leavingboth the absorber and regenerator columns.

Fig. 2. Aspen Plus� flowshee

Please cite this article in press as: R. Canepa, M. Wang, Techno-economicombined cycle gas turbine (CCGT) power plant, Applied Thermal Engine

An extensive validation campaign has been conducted on cap-ture section. For this purpose, performance data from SeparationResearch Program (SRP) at the University of Texas at Austin pilotplant have been employed [11]. Then, capture plant has beenscaled-up to meet the requirement of the commercial scale CCGTpower plant. Aspen Plus� flowsheet for pilot plant is given in Fig. 2.

5.2. Model validation

The pilot plant is a closed loop absorption and stripping(regeneration) facility for CO2 removal from flue gas with 32.5 wt%aqueous MEA solution [11]. Two different kinds of packing havebeen adopted for the columns: Flexipac 1Y, a structured packingwith a specific area of 420 m2/m3 and IMTP no. 40, a random metalpacking with a specific area of 145 m2/m3. Out of the 48 experi-mental cases carried out in the test campaign, 12 cases were chosenfor validation to account for different liquid solvent to gas (L/G)molar flows ratios. Table 3 shows the process conditions for theconsidered cases. With reference to it, solvent loading is defined asthe (molar) ratio of CO2 to MEA. Therefore the lean loading is theloading of the (stripped) solvent stream entering the top of theabsorber column and the rich loading is the one of the solvent (inwhich CO2 has been captured) coming from the bottom of theabsorber column. In Table 4, the overall performance of the CO2capture plant model is reported. With reference to it, simulationresults are compared with the experimental results and with thoseobtained by Zhang et al. [10] from their Aspen Plus� model. Leanloading has been controlled by a design specification set in theregenerator column, and is not therefore a validation parameter. AllCO2 loadings available from pilot plant test campaign have beenobtained by means of an empirical equation resulting in a 10%uncertainty level. Taking this in consideration, all the rich loadingpredictions of the model can be considered satisfactory. Cases 47and 48 have the largest deviations among the selected cases, withan underestimation of the rich loading when compared with theexperimental results which is however within the uncertaintyrange. Interestingly, this is similarly found by Zhang et al. CO2capture level is always lower than the experimental results, which

t for capture pilot plant.

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Page 5: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

Table 3Process conditions for cases selected for validation.

Case 28 29 30 31 32 39 41 42 43 44 47 48

Lean solvent loading [mol/mol] 0.287 0.285 0.284 0.281 0.279 0.228 0.235 0.232 0.231 0.231 0.281 0.285Lean solvent flow rate [l/min] 81.92 54.93 54.89 40.58 40.73 83.24 56.71 56.86 39.33 39.44 30.13 30.13Lean solvent temperature [K] 313.1 312.9 313.2 313.57 313.71 313.2 313.3 313.5 313.26 313.3 313.3 313.4Flue gas flow rate [m3/min] 11 11.02 10.98 5.52 5.48 11.02 10.98 10.96 10.99 11.01 8.22 8.22Flue gas temperature [K] 321.1 324.1 324.7 322.4 319.71 328.4 325.5 325.8 326.66 324.7 332.4 329.1Flue gas pressure [kPa] 105.2 105.5 105.6 103.63 103.49 105 104.8 104.5 104.66 104.7 103.4 102.9Flue gas CO2 content [mol%] 16.54 16.18 17.08 17.41 17.66 16.89 17.11 16.98 16.96 16.8 18.41 17.63Regenerator pressure [kPa] 162.1 162 162 162.03 162.03 162 162 162 162.03 162 68.95 68.95Regenerator pressure drop [kPa] 1.48 0.55 0.6 0.02 0.02 1.48 0.65 0.67 0.1 0.1 0.37 0.41Regenerator feed temperature [K] 345.2 348.8 348.6 358.16 358.67 346.7 350.6 351.2 353.07 353 354.3 353.5Condenser temperature [K] 287.8 286.2 286 286.02 286.17 288.2 287.6 287.3 285.3 285.3 297.1 297.7Reboiler temperature [K] 388.1 387.3 387.4 386.86 386.68 389.8 389.3 389.3 389.3 389.3 366.3 366.4L/G [mol/mol] 7.4 5.0 5.0 7.5 7.4 7.9 5.3 5.4 3.7 3.7 4.6 4.6

R. Canepa, M. Wang / Applied Thermal Engineering xxx (2014) 1e10 5

is generally observed also in the model by Zhang et al. Only forcases 43 and 44, Zhang et al. reported an overestimation of the CO2removal rate. Reboiler duty is slightly underestimated by the AspenPlus� rate based model, but this is in accordance with CO2 capturerate estimation results. Zhang et al. (2009) studied stand-aloneabsorber performance only, so no reboiler duty estimation isgiven by them.

Temperature profile estimation is probably the most importantvalidation parameter. From temperature depends the kinetics ofabsorption, equilibrium phase, and fluid transport properties. Thebalance between the heat released from CO2 and MEA reaction andthe heat consumed in the process from various sources (like CO2stripping, water evaporation, heating of the streams and heat los-ses) produces a bulge in absorber temperature profile [15]. Theposition of this bulge is mainly connected to L/G ratio. When theliquid to gas ratio is low the bulgewill be located near the top of theabsorber and, conversely, when it is high it will be located near thebottom. In the case of CO2 capture for CCGT power plant, given thelow CO2 concentration in flue gases, the needed L/G ratio will likelybe low. In Ref. [10] three types of temperature profiles are identi-fied. Type A is a result of low L/G ratios and is represented, in thecurrent analysis, by Cases 43, 44, 47 and 48. Type B profile, resultingfrom medium L/G ratios, is represented by Cases 29, 30, 41 and 42.Finally, in the case of high L/G ratios (Cases 28, 31, 32 and 39), type Ctemperature profile is obtained. In Figs. 3e5 absorbers and re-generators temperature profiles provided by the rate-based modelare compared to experimental results for, respectively, Case 48 (lowL/G ratio), Case 42 (medium L/G) and Case 39 (high L/G). An

Table 4Model validation results.

Case Rich loading [mol/mol] CO2 capture level [%] Reboiler duty[MJ/hr]

Exp. Model Zhanget al.

Exp. Model Zhanget al.

Exp. Model

28 0.412 0.412 0.405 86 76 74 1317 109929 0.448 0.449 0.44 70 69 70 918 76630 0.453 0.455 0.452 70 68 64 918 77831 0.426 0.437 0.431 95 91 90 564 51732 0.428 0.438 0.432 95 91 90 548 52239 0.367 0.362 0.355 94 83 86 1497 136641 0.433 0.423 0.409 87 78 82 1087 90842 0.43 0.419 0.413 87 79 80 1087 92143 0.491 0.467 0.453 72 69 76 756 65544 0.492 0.466 0.45 72 69 76 754 65647 0.539 0.482 0.48 69 68 68 738 70148 0.537 0.480 0.481 69 69 65 775 662

Please cite this article in press as: R. Canepa, M. Wang, Techno-economicombined cycle gas turbine (CCGT) power plant, Applied Thermal Engine

excellent match between calculation results and experimental datahas been obtained and, consequently, the Aspen Plus� model reli-ability is thoroughly proven.

5.3. Scale-up and sensitivity analysis

Aspen Plus� is able to size packed column diameters based onthe desired approach to flooding on a specified stage, starting froma (user specified) fist-guess diameter. First-guess needed solutionhas been obtained using the procedure described by Lawal et al.[16]. This has provided the required number of columns and their(first-guess) diameters. The obtained results are presented in Fig. 6,in which absorber and regenerator diameters are represented as afunction of the columns number. Due to structural limitations,columns diameter should not exceed 12.2 m (i.e. 40 feet)(Refs. [16,17]). According to this limitation, a three-column absorberand one-column regenerator configuration was selected. A greaternumber of absorber would require larger capital costs and footprintwithout any major benefit. On the other hand one regeneratorcolumn is sufficient to strip all the rich solvent flow coming fromthe absorbers.

In order to lower the computational time, only one absorbercolumn has been modelled. Assuming the same performance for allthe absorber columns the output streams from the column (thevented stream and the rich solvent flow) have been opportunelymultiplied to take into account the actual number of columns. Inthis way regenerator performance can be taken in proper accountand the same happens for makeup calculation.

As a result of scale-up procedure columns number and (first-guess) diameter, as well as a reasonable solvent flow rate (and thusthe corresponding L/G ratio) have been obtained.

However, to model commercial scale capture plant many otherparameters are needed. Various design specifications or Calculatorblock have been assigned in order to ensure good capture plantperformance:

a. Lean solvent loading and temperature are user input;b. Lean solvent flow rate (and thus L/G ratio) is evaluated in order

to obtain, for the actual operating conditions the desired (90%)capture rate. It will mainly depends on user input lean loading.Scale-up procedure result is used to provide the needed first-guess solution;

c. Reboiler duty is defined in order to obtain the user input leanloading at regenerator outlet. This ensures that the solventcoming from the regenerator has, taking into account solventand water losses, the same loading than the one entering theabsorber;

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Page 6: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

Fig. 3. Temperature profile for Case 48 (low L/G ratio): (a) absorber and (b) regenerator.

R. Canepa, M. Wang / Applied Thermal Engineering xxx (2014) 1e106

d. Cross heat exchanger outlet temperature is calculated to ensureuser input heat exchanger approach temperature. An higherapproach temperature will correspond to a lower outlet tem-perature of the cold stream from the heat exchanger. As aconsequence, for a given lean loading target, an higher reboilerduty will be needed;

e. Lean solvent cooler heat duty is evaluated in order to ensure, atabsorber inlet, the user input lean solvent temperature;

f. Columns diameters are sized to obtain the desired floodingpercentage. However, to allow model convergence, a first-guessreasonable diameter has to be given. The other sizing-relevantparameter, the packing heights, are user input;

g. Columns pressure is user input. While absorber usually operatesat atmospheric pressure regeneration process is favoured bygreater pressures and its operating pressure will have to bechosen accordingly. Pressure drops have been assumed for boththe columns (5 kPa for the absorber and 20 kPa in theregenerator).

Considering pilot plant solvent concentration (32.5% aqueoussolutions of MEA) and columns packing, a baseline commercial-scale capture plant model has been developed, scaling it up fromthe pilot plant model. Absorber and regenerator column heights

Fig. 4. Temperature profile for Case 42 (medium

Please cite this article in press as: R. Canepa, M. Wang, Techno-economicombined cycle gas turbine (CCGT) power plant, Applied Thermal Engine

have been set equal to, respectively, 15 and 10 m. Cross heatexchanger approach temperature has been defined equal to 10 Kand regenerator pressure is 160 kPa. Most relevant user input pa-rameters have been undergone a sensitivity analysis (varying themfrom baseline case) in order to highlight their influence on captureplant performance and, notably, reboiler duty requirement.Reboiler duty, despite not being the only relevant parameter, issecurely the greatest contributor on techno-economic performanceof CCGT power plants with CO2 capture. In Table 5 the main resultsof this analysis are given. When sizing and designing the opera-tional parameters of a capture plant, absorber and regeneratorcolumns, on which mostly depend process economy and efficiency,need to be considered contextually to avoid to operate at a regionrequiring higher capital and operational expenditure. For thisreason, in Table 5 the influence of the lean loading has been alsoinvestigated to determine reasonable columns design in terms ofcapital costs and operational performance. When a low leanloading is specified (that is, a low CO2 concentration in the regen-erated solvent has been targeted) reboiler duty (and, consequently,steam draw off) required to strip the rich solvent of CO2 to thedesired lean loading will be larger but, on the other hand, given theincreased absorption capacity of the lean stream, the quantity ofsolvent required to attain the desired capture level is decreased.

L/G ratio): (a) absorber and (b) regenerator.

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Page 7: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

Fig. 5. Temperature profile for Case 39 (high L/G ratio): (a) absorber and (b) regenerator.

R. Canepa, M. Wang / Applied Thermal Engineering xxx (2014) 1e10 7

The contrary happens when an high lean loading is targeted. Forlean loading greater then approximately 0.250, reboiler dutyrequirement will increase slightly due to the sensible heat demandof the increased rich solvent flow rate. Therefore, while L/G ratioalways increases with increasing lean loading, reboiler duty willtypically present a saddle tendency with respect to this parameter.In the alreadymentioned Table 5, considering base-case, the impactof lean loading specification on sizing requirement, can be assessed.When L/G ratio is increased the absorber diameter, in order toobtain the desired flooding percentage, is increased as well. On theother hand regenerator flooding (and thus diameter) is mainlyconnected to reboiler duty requirement. However, from a processoptimization point of view, absorber columns will be among thetwo, given their larger number and size, the most determinantfactor.

Absorber packing height was increased from base-case captureplant (15 m). This would require greater capital and also O&M costsconnected to capture. By increasing the packing height and, as aconsequence, packing volume, absorption capacity is expectedto increase. From Table 5 it is clear the beneficial effect of anincrease of absorber packing height on thermal energy require-ment. Interesting is the fact that the optimal lean loading

Fig. 6. First-guess solution result: absorber and regenerat

Please cite this article in press as: R. Canepa, M. Wang, Techno-economicombined cycle gas turbine (CCGT) power plant, Applied Thermal Engine

(0.25 molCO2/molMEA) is almost unchanged from base-case. With25 m of absorber packing height reboiler duty requirement isdecreased, considering the optimal lean loading, by 31%. A furtherincrease of absorber packing height to 30 mwould only marginallyincrease this benefit (�33% in reboiler duty, if compared to base-case capture plant) and, on the other hand, would increasefurther capital and O&M costs. From column sizing point of view anincrease of absorber packing height is very relevant on, as easilyexpected, absorber requirement but, as well, it is a determinantfactor on regenerator sizing. This is mainly due to the lower reboilerduty requirement granted by an increase in the absorber height, onwhich, as previously shown, regenerator diameter is mainlyrelated. A packing height equal to 25 m ensures a reduction,compared to base-case, of 5% in absorber diameter and of 20% inregenerator one.

Regenerator operating pressure was changed from base-casecapture plant. Notably three different values of this quantitywhere considered: 160 kPa (base-case), 185 kPa and 210 kPa,assuming for everyone of them a pressure drop through theregenerator column equal to 20 kPa. Increasing operating pressurewould require greater pumping equipment along major pumpingoperating costs. From thermal point of view, an increase in

or diameters as function of the number of columns.

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Page 8: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

Table 5Sensitivity analysis results.

Lean load [mol/mol]

0.15 0.20 0.25 0.30

Base case a L/G [mol/mol] 1.14 1.42 1.92 3.18Abs. diameter [m] 10.5 10.7 11.1 11.7Reg. diameter [m] 11.1 10.1 10.1 11.4Reboiler duty [GJ/tonne] 9.60 6.99 6.27 6.97

Absorberheight [m]

30 L/G [mol/mol] 0.815 0.945 1.13 1.46Abs. diameter [m] 10.2 10.3 10.5 10.7Reg. diameter [m] 9.40 8.22 7.94 8.36Reboiler duty [GJ/tonne] 6.99 4.84 4.18 4.30

25 L/G [mol/mol] 0.834 0.973 1.19 1.60Abs. diameter [m] 10.2 10.3 10.5 10.8Reg. diameter [m] 9.51 8.34 8.11 8.68Reboiler duty [GJ/tonne] 7.14 4.98 4.34 4.56

20 L/G [mol/mol] 0.890 1.07 1.35 1.99Abs. diameter [m] 10.3 10.4 10.6 11.1Reg. diameter [m] 9.83 8.73 8.59 9.47Reboiler duty [GJ/tonne] 7.60 5.40 4.78 5.23

Regeneratorpressure[kPa]

210 L/G [mol/mol] 1.13 1.41 1.92 3.18Abs. diameter [m] 10.5 10.7 11.1 11.7Reg. diameter [m] 9.61 9.02 9.41 10.7Reboiler duty [GJ/tonne] 7.41 5.82 5.72 6.47

185 L/G [mol/mol] 1.14 1.41 1.93 3.18Abs. diameter [m] 10.5 10.7 11.1 11.7Reg. diameter [m] 10.3 9.46 9.71 11.0Reboiler duty [GJ/tonne] 8.35 6.29 5.95 6.68

Heaterapproach [K]

5 L/G [mol/mol] 1.13 1.42 1.92 3.18Abs. diameter [m] 10.5 10.7 11.1 11.7Reg. diameter [m] 11.2 10.2 10.3 11.7Reboiler duty [GJ/tonne] 9.54 6.93 6.17 6.66

Regeneratorheight [m]

20 L/G [mol/mol] 1.13 1.41 1.91 3.19Abs. diameter [m] 10.5 10.7 11.1 11.7Reg. diameter [m] 10.7 9.8 10.0 11.4Reboiler duty [GJ/tonne] 8.77 6.52 6.15 7.01

15 L/G [mol/mol] 1.13 1.42 1.91 3.19Abs. diameter [m] 10.5 10.7 11.1 11.7Reg. diameter [m] 10.9 9.89 10.0 11.4Reboiler duty [GJ/tonne] 9.04 6.68 6.18 7.00

a Absorber packing height: 15 m; regenerator pressure: 160 kPa; heaterapproach: 10 K; regenerator packing height: 10 m.

Table 6Commercial scale capture plant design and operational specification.

Parameter Value

CO2 capture level [%] 90CO2 captured [kg/s] 38.77Columns flooding [%] 65Lean loading [mol/mol] 0.200Rich loading [mol/mol] 0.477L/G [mol/mol] 0.97Reboiler duty [kW] 158,766Reboiler duty [GJ/tonne CO2] 4.1Lean solvent MEA concentration [wt%] 32.5Lean solvent temperature [K] 313Cross heat exchanger approach temperature [K] 10Absorber columns number [e] 3Absorber columns pressure [kPa] 105Absorber columns pressure loss [kPa] 5Absorber columns packing IMTP no. 40Absorber columns packing height [m] 25Absorber columns packing diameter [m] 10.3Regenerator columns number [e] 1Regenerator column pressure [kPa] 210Regenerator column pressure loss [kPa] 20Regenerator column packing Flexipack 1YRegenerator column packing height [m] 15Regenerator column packing diameter [m] 7.4

R. Canepa, M. Wang / Applied Thermal Engineering xxx (2014) 1e108

regenerator operating pressure corresponds to an increase indriving force and thus a beneficial effect on CO2 mass transfer ratethrough the regenerator column is expected. Thermal energyrequirement has been proven to decrease linearly with regeneratoroperating pressure. Notably with a pressure equal to 210 kPareboiler duty is lower by 9% if compared to base-case capture plant.While no effect on absorber diameter has been found, a regeneratorpressure equal to 210 kPa led to a 7% reduction in regeneratordiameter requirement. Again, the optimal lean loading is notsignificantly changed from base-case capture plant.

Cross heat exchanger provides pre-heating to the cold rich sol-vent by means of cascade heat from the hot lean solvent. So, adecrease in reboiler duty is expected when cross heat exchangerapproach temperature is decreased. On the other hand this wouldrequire larger heat exchanger surfaces and thus equipment costs.The beneficial effect on thermal energy requirement is however inpercent terms very limited. In correspondence to the optimal leanloading (0.250 molCO2/molMEA) reboiler duty decreases byapproximately 2% as the approach temperature decreases from 10 K(base case) to 5 K. Interesting is the fact that, even slightly, adecrease of this temperature difference led to an increase (2%) inregenerator diameter requirement. This is believed to be related tothe fact that, by decreasing approach temperature, the temperatureof the solvent entering the regenerator column will be affected(notably increased) and thus will be affected flooding capacity onbase (entering) stage on which column sizing depends.

Please cite this article in press as: R. Canepa, M. Wang, Techno-economicombined cycle gas turbine (CCGT) power plant, Applied Thermal Engine

As for absorber one, by increasing regenerator packing heightcolumn performance will be improved and equipment costsincreased. Reboiler duty is decreased by 1.5% from base-case bythe adoption of 15 m of packing. A further increase in columnpacking height doesn’t bring any significant benefits. Regeneratordiameter, in correspondence with the optimal lean loading (fromthermal energy requirement point of view), is only slightlydecreased (0.6%) from base-case. No effect on absorber diameterhas been proven.

6. Thermo-economic performance

Considering the sensitivity analysis previously shown it hasbeen possible to identify an improved set of capture plant oper-ating parameters. In Table 6 the main equipment design parame-ters are given. Columns packing heights and regenerator pressurehave been increased, given the great influence they have onreboiler duty requirement, while heat exchanger approach tem-perature has been left unchanged from base case capture plant,given its minor influence on thermal energy requirement. Such aconfiguration securely allows a reduction on reboiler dutyrequirement if compared to base case capture plant. As for thepreviously analyzed cases reboiler duty requirement shows asaddle tendency with respect to lean loading (see Fig. 7). Theminimal energy requirement condition (which was 0.250 molCO2/molMEA for base case) is here between 0.200 and 0.250 molCO2/molMEA of solvent lean loading. However, despite reboiler duty issecurely the most important thermal energy requirement of cap-ture plant (to which correspond the greatest efficiency penalty),net power production is not the only parameter which affects thecost of electricity. As already shown when the lean loading isincreased solvent flow rate is increased too. Thus, equipmentcapital cost and O&M costs are expected to be greater. For thisreason, in the already mentioned Fig. 7, the cost of electricity isalso depicted. Cost of electricity depends on both thermodynamicperformance and total annual revenue requirement (TRR) of theintegrated power plant and CO2 related sections (flue gas pre-processing, capture section and CO2 compression). Major detailson the integrated modelling and cost related assumptions aregiven in Ref. [18]. Considering the cost of electricity too as a

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Page 9: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

Fig. 7. Impact of lean loading on reboiler duty and cost of electricity at 90% capture level.

Fig. 8. Impact of lean loading on net power production and capture plant total capital requirement at 90% capture level.

R. Canepa, M. Wang / Applied Thermal Engineering xxx (2014) 1e10 9

decision parameter the optimal lean loading (see Table 6) has beenidentified equal to 0.200 molCO2/molMEA. To better understandthis, in Fig. 8 net power production and capture plant related totalannual revenue requirement as a function of lean loading areshown. It can be noted as, while net power plant power produc-tion is mainly dependent on reboiler duty (blower and CO2compression power requirement are unchanged), capture plantcapital annualized and O&M costs, represented by the TRRparameter, increase almost linearly with lean loading.

As a result, reboiler duty has been identified to be equal to4.1 GJ/tonne CO2. To satisfy this requirement a large amount ofsteam need to be extracted from power plant, considerablyreducing its thermal efficiency. Power plant net power productionis reduced, from 427 MW of no-capture case, to 368 MW, mainlydue to steam draw off. This, in combination with the capital andO&M costs connected to capture related sections, gives for the in-tegrated CCGT and capture plants a levelized cost of the electricityequal to 68 V/MWh, increased by 47% when compared to reference(no capture) power plant.

7. Conclusions

While the technology to capture CO2 from exhaust gas existsand is viable, it still needs to be deployed on commercial scalepower plant. This makes modelling and simulation an invaluabletool for investigating CO2 capture process integration at commer-cial scale. Very often capture process is simulated in a simplifiedway or not properly validated. Rate-based approach, as adopted forCO2 capture section, ensures a higher reliability over traditional

Please cite this article in press as: R. Canepa, M. Wang, Techno-economicombined cycle gas turbine (CCGT) power plant, Applied Thermal Engine

equilibrium based one. Experimental results from pilot plant fa-cility at the University of Texas at Austin represent an invaluablesource of insight on post-combustion capture by means of MEAsolvent. An extensive validation campaign based on these data hasallowed to thoroughly assess model validity. A sensitivity analysishas been conducted to prove how, with a proper choice of captureplant key operating parameters and equipment design, captureplant thermal energy requirement for solvent regeneration mightbe reduced to approximately 4 GJ/tonne CO2. It has been demon-strated as the most economical solution is not the one with thelowest thermal energy requirement, being capture plant relatedcosts also very relevant on the cost of electricity, and thus provingthe need to optimize capture plant from both the thermal andeconomical point of view.

Acknowledgements

Financial support for this study to the first author was providedby ANSALDO ENERGIA and is gratefully acknowledged.

References

[1] International Energy Agency (IEA), Energy Technology Perspectives, 2010.http://www.iea.org/publications/freepublications/publication/etp2010.pdf.

[2] Global CCS Institute, The Global Status of CCS, 2012. http://cdn.globalccsinstitute.com/sites/default/files/publications/47936/global-status-ccs-2012.pdf.

[3] H. Herzog, J. Meldon, A. Hatton, Advanced Post-combustion CO2 Capture,Clean Air Task Force, 2009, pp. 1e39.

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014

Page 10: Techno-economic analysis of a CO2 capture plant integrated with a commercial scale combined cycle gas turbine (CCGT) power plant

R. Canepa, M. Wang / Applied Thermal Engineering xxx (2014) 1e1010

[4] M. Wang, A. Lawal, P. Stephenson, J. Sidders, C. Ramshaw, Post-combustionCO2 capture with chemical absorption: a state-of-the-art review, Chem. Eng.Res. Des. 89 (9) (2011) 1609e1624.

[5] R. Svensson, M. Odenberger, F. Johnsson, L. Strömberg, Transportation systemsfor CO2 e application to carbon capture and storage, Energy Convers. Manage.45 (15) (2004) 2343e2353.

[6] S.M. Forbes, P. Verma, T.E. Curry, S.J. Friedmann, S.M. Wade, et al., Guidelinesfor Carbon Dioxide Capture, Transport and Storage, World Resources Institute,2008.

[7] C. Wildbolz, Life Cycle Assessment of Selected Technologies for CO2 Transportand Sequestration (Diploma thesis), Swiss Federal Institute of Technology,Zurich, 2007.

[8] Standards of the Tubular Exchanger Manufacturers Association, The TubularExchange Manufacturers Association Inc., Tarrytown, New York, 2007.

[9] R. Canepa, M. Wang, C. Biliyok, A. Satta, Thermodynamic analysis of combinedcycle gas turbine power plant with post-combustion CO2 capture and exhaustgas recirculation, Proc. Inst. Mech. Eng. Part E 227 (2) (2013) 89e105.

[10] Y. Zhang, H. Chen, C.C. Chen, J.M. Plaza, R. Dugas, G.T. Rochelle, Rate-basedprocess modeling study of CO2 capture with aqueous monoethanolaminesolution, Ind. Eng. Chem. Res. 48 (20) (2009) 9233e9246.

[11] R.E. Dugas, Pilot Plant Study of Carbon Dioxide Capture by Aqueous Mono-ethanolamine (MSE thesis), University of Texas at Austin, 2006.

[12] B.R.W. Pinsent, L. Pearson, F.J.W. Roughton, The kinetics of combination ofcarbon dioxide with hydroxide ions, Trans. Faraday Soc. 52 (1956) 1512e1520.

[13] Aspen Plus, Rate Based Model of the CO2 Capture Process by MEA Using AspenPlus, Aspen Technology Inc., Cambridge, MA, USA, 2012.

Please cite this article in press as: R. Canepa, M. Wang, Techno-economicombined cycle gas turbine (CCGT) power plant, Applied Thermal Engine

[14] H. Hikita, S. Asai, H. Ishikawa, M. Honda, The kinetics of reactions of carbondioxide with monoethanolamine, diethanolamine and triethanolamine by arapid mixing method, Chem. Eng. J. 13 (1) (1977) 7e12.

[15] H.M. Kvamsdal, G.T. Rochelle, Effects of the temperature bulge in CO2 ab-sorption from flue gas by aqueous monoethanolamine, Ind. Eng. Chem. Res. 47(3) (2008) 867e875.

[16] A. Lawal, M. Wang, P. Stephenson, O. Obi, Demonstrating full-scale post-combustion CO2 capture for coal-fired power plants through dynamicmodelling and simulation, Fuel 101 (2012) 115e128.

[17] M. Ramezan, T.J. Skone, N. Nsakala, G.N. Liljedahl, Carbon Dioxide Capturefrom Existing Coal-fired Power Plants, US Department of Energy e NationalEnergy Technology Laboratory, 2007. DOE/NETL-401/110907.

[18] R. Canepa, Analysis of Combined Cycle Power Plants with Post-combustionCO2 Capture, Including Turbomachinery Performance Estimation (Ph.D.thesis), Genova University, Italy, 2013.

Symbols

Dp: pressure loss [bar]f: Darcy friction factor [e]L: pipeline length [m]Di: pipeline internal diameter [m]ravg: average CO2 mass density [kg/m3]vavg: average CO2 velocity [m/s]

c analysis of a CO2 capture plant integrated with a commercial scaleering (2014), http://dx.doi.org/10.1016/j.applthermaleng.2014.01.014