Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
1
CHAPTER-1
INTRODUCTION
M/s Bravo Sponge Iron Pvt. Ltd. has existing 1x95 TPD & 1x100 TPD DRI kiln producing
62,400 TPA Sponge Iron for sale village- Mahuda, P.O- Rukni, Puruliya District of West
Bengal
1.0 Importance of the project to the country and region
TMT rod and bar products are normally used in constructional/structural work so
products have demand for development of infrastructure of a country.
Steel is a basic commodity for all industrial activity and its consumption marks industrial
prosperity. The steel industry has tremendous forward and backward linkages in terms
of material flow, income and employment generation.
Steel is a core industry and thus its demand is strongly linked to the overall economic
activity of the nation. Given the inherent long-term potential of the Indian economy and
its cyclical nature, the long-term prospects of the steel industry are fairly comfortable.
The demand and production has been growing at a healthy rate for the last few years
and the forecast for the next decade and half is also very promising.
It has been estimated by certain major investment houses such as Credit Suisse that
India’s steel consumption will continue to grow at 16 % rate annually fuelled by demand
for construction projects worth US $1 trillion. The scope for raising the total consumption
for steel is huge, Per capita consumption of steel at current levels is about 65 kg. As a
comparison per capita steel consumption in China is 430 kg and the world steel
consumption per capita average is 180 kg.
By 2020-21 the demand at 7 % and 8 % GDP growth is estimated to be 123 million tons
and 137.5 million tons respectively. Taking a mean figure of 130 million ton, there is a
need of 65 million ton in 10 years time. This translates into an average growth
requirement of about 10 million tons per year.
Ministry of steel has projected that steel capacity in the country is likely to be 124.06
million tons by 2011-12. Further based on the status of MOUs signed by private
producers with various State Govt., it is expected that India’s steel capacity would be
nearly 293 million tons by 2020.
1.1 Global Steel Scenario:
Steel is a key driver of the world's economy. The industry directly employs more than
two million people worldwide, with a further two million contractors and four million
people in supporting industries. In 1950-India and China had same level of per capita
consumption of steel. But then India remained mostly stagnant whereas China went
about Industrialization and increased its production as well as consumption. However
India improved between 1997 to 2003, but steel then per capita steel has remained very
low in comparison to China.
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
2
In 2007 World steel output reached 1343.5 million metric tons and showed a growth of
7.5% over previous year.
China remained World’s largest crude steel producer in 2007 producing 489.00 million
metric tons and USA 97.20. India occupied 5th position producing 53.10 million metric
tons for the second consecutive year.
In 2013 the world crude steel production reached 1606 million tons and showed a
growth of 3% over 2012. (Source: World Steel Association or WSA)
China remained the world’s largest crude steel producer in 2013 (779 mt) followed by
Japan (111 mt), the USA (87 mt) and India (81 mt) at the 4th position.
WSA has projected Indian steel demand to grow by 3.3% in 2014 as compared to
global steel use growth of 3% and Chinese growth of 3.1%. For 2015, further
recovery is projected for world (3.3%) and India (4.5%) and a slowing down for China
(2.7%).
Per capita finished steel consumption in 2013 is estimated at 225 kg for world and
515 kg for China.
1.2 Domestic Steel Scenario:
The Indian steel industry has entered into a new development stage from 2007-08,
riding high on the resurgent economy and rising demand for steel.
Rapid rise in production has resulted in India becoming the 4th largest producer of
crude steel and the largest producer of sponge iron or DRI in the world.
As per the report of the Working Group on Steel for the 12th Plan, there exist many
factors which carry the potential of raising the per capita steel consumption in the
country, currently at 59.2 kg. These include among others, an estimated
infrastructure investment of nearly a trillion dollars, a projected growth of
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
3
manufacturing from current 8% to 11-12%, increase in urban population to 600
million by 2030 from the current level of 400 million, emergence of the rural market
for steel currently consuming around 10 kg per annum buoyed by projects like Bharat
Nirman, Pradhan Mantri Gram Sadak Yojana, Rajiv Gandhi Awaas Yojana among
others.
At the time of its release, the National Steel Policy 2005 had envisaged steel
production to reach 110 million tons by 2019-20. However, based on the assessment
of the current ongoing projects, both in Greenfield and Brownfield, the Working Group
on Steel for the 12th Plan has projected that the crude steel steel capacity in the
county is likely to be 140 mt by 2016-17 and has the potential to reach 149 mt if all
requirements are adequately met.
The National Steel Policy 2005 is currently being reviewed keeping in mind the rapid
developments in the domestic steel industry (both on the supply and demand sides)
as well as the stable growth of the Indian economy since the release of the Policy in
2005.
The liberalization of industrial policy and other initiatives taken by the Government have
given a definite impetus for entry, participation and growth of the private sector in the
steel industry. While the existing units are being modernized/expanded, a large number
of new steel plants have also come up in different parts of the country based on modern,
cost effective, state of-the-art technologies. In the last few years, the rapid and stable
growth of the demand side has also prompted domestic entrepreneurs to set up fresh
Greenfield projects in different states of the country.
Crude steel capacity was 102 mt in 2013-14 and India, the 4th largest producer of crude
steel in the world, has to its credit, the capability to produce a variety of grades and that
too, of international quality standards. The country is expected to become the 2nd largest
producer of crude steel in the world by 2015-16, provided all requirements for creation
of fresh capacity are adequately met.
Further based on the status of MOUs signed by private producers with various State
Govt., it is expected that India’s steel capacity would be nearly 293 million tons by 2020.
[Source: Ministry of Steel]
Importance of various units
DRI KILN
Sponge iron is the metallic form of iron and Scarp substitute produced from reduction of
iron oxide below the fusion temperature of iron ore (15350C) by utilizing hydrocarbon
gases or carbonaceous fuels as coal. The reduced product having high degree of
metallization exhibits a honeycomb structure, due to which it is named as sponge iron.
As the iron ore is in direct contact with the reducing agent throughout the reduction
process, it is often termed as direct reduced iron (DRI).
IF
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
4
The various types of Induction Furnaces used for Steel making are medium frequency
and high frequency. Mild steel, Stainless Steel and low and high alloy Steel can be made
from these furnaces. Raw materials used are DRI, Pig Iron & Scarp. Charge is heated by
eddy current.Alloying elements are added as per the requirement and the induction
furnaces are provided with matching billet casters.
Rolling Mill:
Steel Billets/blooms from Billet Caster are cut to desired sizes and either fed to hot
rolling mill for processing or transferred to raw material shed stored. Cold Billets are
transferred to roller table and pushed through the Reheating furnaces which are heated
and soaked up to 11500C
The Billets/blooms are then processed through roughing mill, intermediate mills and
finishing mills to get the finished rolled products. Re heating of Billets will be done in
reheating furnace by burning surplus BF gas. Then rolled products are cropped & caught
in required commercial length by hot saws.
Location Map of project site
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
5
Satellite imagery of location-BRAVO Sponge Iron pvt. Limited
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
6
Justification of the project
The company produces steel Billets in its existing unit which is a semi finished product
and unless same are converted to marketable products, the project is less profitable.
Again TMT Bar has high market demand for its utilization in construction work. Hence
expansion of Bravo Sponge Iron Pvt Ltd is justified.
Undoubtedly the development of this industrial project will give rise to the production of
finished products like construction material which is in demand. In the meanwhile
generation of various wastes would also take place from the project and there by
environmental degradation is anticipated. However the use of advanced technology and
proper management, planning and application of meticulous Environment management
plan, shall substantially reduce environmental problems and the project shall becomes
acceptable as it leads to socio-economic development of the region.
Authorization
M/s. BRAVO Sponge Iron Pvt. Limited has entrusted M/S Global Experts, a NABET
accredited “A” Grade Environment consultant Bhubaneswar for preparation of TEFR for
their expansion project.
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
7
In accordance to the scope of work, M/s. Global Experts team visited the project site at-
At-Mahuda, P.O- Rukni, in Puruliya District of West Bengal. During their visit the team
collected information on site and availability of infrastructure facilities like raw materials,
water, power and transportation facilities available for the existing unit and space
available for expansion. The representative of M/s. Bravo Sponge iron Pvt. Limited
accompanied Global Experts team during visit to their site.
ACKNOWLEDGEMENT
GLOBAL EXPERTS, Bhubaneswar expresses its deep gratitude to management of M/s.
Bravo Sponge Iron Pvt. Limited for entrusting the assignment of making report and
providing all documents required for submission of form-1 and TEFR and for the active
interest and cooperation extended by the concerned officials of M/s Bravo Sponge Iron
Pvt Ltd.
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
8
CHAPTER-2
SITE AND INFRASTRUCTURE
2.1 SITE LOCATION
A Plant is set up at a place, where men, machinery and material are brought together to
manufacture the product. The success and failure of an Industry greatly depends on its
location. Therefore location must be based on careful consideration of all the factors that
are essentially needed for successful running of an Industry which may provide
maximum advantage. The most important factors on which the selection of site depends
are 1) Proper Geological region, 2) Appropriate location in the region.
The location of an Industry is determined by following factors.
a) Availability of Raw materials nearby
b) Availability of Industrial vacant land for Industry and its expansion in future.
c) Availability of water needed for the Industry.
d) Availability of power.
e) Nearness to market.
f) Availability of Labor.
g) Good transport facility.
h) Suitable climate and Topography.
Location of the proposed project site fulfils all the above conditions to a large extent.
The site is located at At- Mahuda, P.O-Rukni in the district Puruliya of West Bengal The
plant location and Latitude 230 32' 53.49" N & Longitude 860 32' 49.70" E.
2.2 LAND
The company has already acquired 19.69 acres land and running the existing plant,
vacant space in it will be utilized to accommodate expansion project. The total land use
will be as follows.
LAND USE PATTERN
Sl.N
o.
FACILITIES AREA IN ACRES
1 Plant Facilities 5.50
2 Office Admin Building Canteen 0.25
3 RMH & Storage 1.50
4 Dispatch & Parking Bay 0.75
5 Green belt 6.50
6 Water Storage 0.10
7 Internal Roads 0.60
8 Fuel Storage 0.05
9 Solid Waste Disposal 1.75
10 Vacant Space 2.69
TOTAL 19.69
(As provided by Project Proponent)
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
9
All raw materials are proposed to be received through Rail and in dump trucks and
unloaded in the raw material receiving yard. Sufficient space is earmarked to cater to the
needs of all the units of the plant. Different plant units will be laid out considering the
need of optimized earthwork, rational material flow, economy of operations and the
space requirements for rational development.
The general layout of the proposed plant has been developed keeping in the view the
following factors:
Smooth & uninterrupted flow of materials in accordance with the technological
requirements
Contours & gradient of the site
Optimum lead for transport of materials & for service lines
Predominant wind direction
Logistic approach in location of technological units as well as service facilities
Safety clearances & statutory provisions
The major consideration that has been given for making layout is given below.
The storage facility and raw material & isolating areas have been located near the
main processing area. But care has been taken to see that expansion will not be
hampered in future.
The processing areas are situated at the centre of plant so that all other required
material can be easily available; the area of processing has been such that
movement of worker & flow of material within the processing unit, location of
equipment & their maintenance easy.
The storage facility has been nearer to the processing area so that the production
flows from department to storage easy. A space has been reserved for loading &
unloading of product.
Proper regard has been shown in placement of each of services like the
distribution of water, power refrigeration unit & electricity.
Adequate green belt in 33% of total land within the plant boundary and on the periphery
of the proposed project will be developed to reduce pollution load on environment as it
acts as a sink of dust and noise pollution load.
Connectivity Project area is 0.5 km from SH-12, 0.5 km from SH-8 and 28 km from
NH-60A
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
10
CHAPTER-3
PROCESS DESCRIPTION
PROCESS DESCRIPTION
M/s Bravo Sponge Iron Limited has an existing running unit producing Sponge Iron for
sale for external consumption. The Project Proponent now proposes expansion of this
unit to enhance the capacity of the unit by backward and forward integration. Project
configuration and product mix has been given below.
PROJECT CONFIGURATION
SL
NO
FACILITY CONFIGURATION CAPACITY PRODUCT ENDUSE
Existing
1 DRI kiln 1x100 TPD
1x95 TPD
62,400 TPD Sponge Iron Use in IF
Expansion
2 DRI 1x350 TPD
1x100 TPD
1,44,000 TPD Sponge Iron Use in IF
3 IF 4x15 T 2,09,313 TPA Hot Metal Use in CCM
4 CCM Matching 2,03,033 TPA Billet Use in RM
5 Rolling Mill 600 TPD 1,92,000 TPA TMT Bar/
Rod
Sale
6(a) CPP WHRB 11.5 MW Power Internal Use
6(b) CPP AFBC 6.5 MW Power Internal Use
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
11
FLOW SHEET
Raw material requirement (Existing + Expansion)
Sl.No Material Quantity in TPA Source
1 DRI Grade Iron Ore 2,99,280 Jharkhand/ Odisha
2 Lime stone / Dolomite 820 TPA Local purchase/ M.P
3 Coal(DRI) 2,72,450 TPA Eastern Coal Field
4 Coal(AFBC) 30,000 TPA Eastern Coal Field
5 Pig 22,500 TPA Local purchase
6 Scarp 12,000 Local purchase
Power requirement for the unit inclusive of existing
UNIT CONSUMPTION IN MW
DRI 3.2
IF & CCM
9.0
Rolling mill 2.0
Power plant internal consumption 1.8
Lighting & Auxiliary 2.0
Total power requirement 18.0
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
12
Power requirement 18.00 MW
Captive power generation 18.00 MW
Power to be purchased Nil
WATER REQUIREMENT (Existing+Proposed)
UNIT TOTALMAKE UP m3/Day
DRI 315
IF 120
ROLLING MILL 150
POWER PLANT(Air Cooled) 600
Drinking & Sanitation 30
Green Belt 20
TOTAL 1235
Water requirement for the proposed project comes to about. 1,235 m3/day.
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
13
CHAPTER-4
ENVIRONMENTAL MANAGEMENT PLAN
Industries do pollute the environment. Nevertheless industrial growth has been receiving
tremendous boost all over the world. Over 60-75% of the pollution in the world is related
to industrial production and consumption of fossil fuel and the developed countries have
the major share in it. The present global model of development for prosperity is directly
linked to industrial growth and hence even the developing countries have to initiate
industrial development for their progress, although most of them are lagging far behind
the others.
AIR ENVIRONMENT
Sl.
No Section/Unit Operation
Emission
released waste
generated
Types of
pollution
Pollution
control
measures
1. Raw Material
and scrap
Handling
Stock, crushing,
screening,
conveyor transfer
& charging etc.
Fugitive dust
emission
Air pollution
Noise pollution
Bag filter & 35m
stack
2 DRI kilns Reduction of
pellet/iron ore
with lime and coal
Particulate
matter,CO2, SO2
and NOX
Heat & Air
pollution
WHRB, ESP and
high stack
4 SMS (IF)&
Billet casting
Unit
Melting of pig, hot
metal, scrap &
Ferro Alloys using
O2 & lime. Casting
of refined liquid
steel in moulds of
billet
Water vapor Waste
water containing
iron scales, CO2,
Oil & grease from
scrap. EOF and LF
slag.
Air, thermal ,
Water & soil
pollution
Water scrubber,
settling pond,
Fume extraction
scrubber and
Bag house with
55m stack
5 AFBC Generation of
Steam from coal
and waste heat
from BF and
Coke-oven
TSP, CO2, SO2,
NOx and
generation of fly
and bed ash
Air pollution
Land pollution
Flue gas Lime
scrubber , ESP
& stack
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
14
Water environment
SOLID WASTE AND ITS MANAGEMENT
Solid waste in the form of dust, slag, scrap and ash will be generated from this Steel
plant and shall pollute the environment unless managed properly. Following solid waste
will be generated from the proposed project. Mitigation measure is given below.
Solid waste Quantity in TPA Mitigation measure
Char 41,280 TPA Use in AFBC
IF Slag 33,500 TPA To be used in Land fill
Fly Ash (WHRB) 38,105 Sold to Cement Plant & Brick
Manufacturing
Fly Ash (AFBC) 36,105 TPA Sold to Cement Plant & Brick
Manufacturing
Bottom Ash 5,687 TPA Cement Plant/ Land facilities
Rain water Harvesting
M/s Bravo Sponge Iron Pvt. Ltd will go for rain water harvesting from the project area to
reduce consumption of fresh water make up and specially to meet lean season deficit of
river water.
The average annual rain fall of the project area is about 1445 mm=1.45m
Total project area is19.69 acres=67,460.98m2.
Hence with 50% loss towards evaporation & percolation about 48,638.66m3 of rain water
can be harvested per annum and stored in Rain water harvesting pond. Rain water
harvested can meet the plant requirement of about 40 days.
Sl.
No Section/Unit Operation
Emission
released waste
generated
Types of
pollution
Pollution
control
measures
1 SMS (IF)&
Billet casting
Unit
Melting of pig,
hot metal, scrap
& Ferro Alloys
using O2 & lime.
Casting of refined
liquid steel in
moulds of billet
Water vapor Waste
water containing
iron scales, CO2,
Oil & grease from
scrap. IF and LRF
slag.
Water & soil
pollution
Water
scrubber,
settling pond,
scrubber
2. AFBC Generation of
Steam by
burning coal,
Dolchars for use
in Turbo
generator
generation of fly
ash slurry
Water & soil
pollution by
leaching
Ash settling
pond with
impervious
bottom
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
15
Greenbelt
Green belt has already been developed in about 33% area of the total land and it has
been developed all around the plant boundary and by the side on internal roads. This will
serve as dust sink of the project and will not allow the excess sound level of project to
go out. Local species of trees having good canopy area will be selected for developing
green belt in consultation with forest department.
NOISE POLLUTION MANAGEMENT
The noise pollution management will be taken up in following manner
By selecting low noise generating equipment, which would have below 85 dBA at 1m
distance. This is taken care at the equipment design stage.
By isolating the noise unit from the working personnel’s continuous exposure by
providing acoustic aids for plant personnel.
Use of PPE like ear muff etc.
By administrative & safety measures, providing noise level monitoring, remedial
measures, providing noise safety appliances.
The noise impact on the surrounding environment during the construction phase will
be within acceptable limits. The operation of high noise generating equipment shall
be restricted during the night time.
Various measures proposed to reduce noise pollution include reduction of noise at
source, provision of acoustic lagging for the equipment and suction side silencers,
selection of low noise equipment and isolation of noisy equipment. The plant
personnel in noisy area will be provided with high noise reduction aid such as ear
muffler & also the duration of exposure of the personnel will be limited as per the
norms.
Thick green belt development is planned for the attenuation of noise pollution and to
maintain ambient noise quality within the statutory limit
Carbon Credit Opportunities through CDM activities
Carbon credit is a “generic term to assign a value to a reduction or offset of greenhouse
gas emissions, usually equivalent to one ton of carbon dioxide equivalent (CO2-e).
The Waste heat from DRI Kiln shall be utilized for the generation of of electrical power
through Waste Heat Recovery Boiler (WHRB). This power generation would have
required Tons of coal per hour. 11.5 MW power generations from WHRB can save about
54,761 Tons per annum of coal burning as thus atmospheric emission of pollutants will
be reduced. With a saving of these amounts of coal shall reduce the CO2 emission. These
activities shall make the company to eligible for availing carbon credit facilities.
Cost towards Environment Management
At least 4% of total project cost i.e. about 6.2 crores will be spent towards Environment
pollution control with which ESP, Bag filter, Tailing pond and ash pond etc will be
installed along with other plant machineries.
CHAPTER-5
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
16
ESTIMATATION OF PROJECT COST AND TIME SCHEDULE
PROJECT COST DISTRIBUTION:
Facilities Estimated Project Cost (LAKHS)
Land & Site development 60.00
Civil Buildings 350.00
Structure Buildings 526.00
Plant machinery & Electrical 12,500.00
Erection & installation 500.00
Waste Heat cleaning System 350.00
Miscellaneous Fixed Assets 100.00
Contingencies 240.00
Engineering & Consultancy Charges 108.00
Working Capital 900.00
Total Amount 15,634
Project schedule
It is expected that after getting EC tenders will be floated for equipments and other
activities and establishment and commissioning will be completed in 3yr of time.
Employment opportunities
For the proposed project activities skilled and unskilled manpower will be needed. This
will temporarily increase the employment opportunity. Secondary jobs are also bound to
be generated to provide day-to-day needs and services to the work force. This will also
temporarily increase the demand for essential daily utilities in the local market.
The manpower requirement for the proposed project will generate some permanent jobs
and secondary jobs for the operation and maintenance of plant. This will increase direct /
indirect employment opportunities and ancillary business development to some extent
for the local population. This phase is expected to create a beneficial impact on the local
socio-economic environment.
Techno Economic Feasibility Report of M/s Bravo Sponge Iron Pvt Ltd.
At: Mahuda P.O- Rukni in Purliya district of West Bengal
Global Experts
17
About 350 people will get direct employment in various grades. This figure includes
employment in technical, operation, maintenance, finance, commercial, personnel and
general administration.
ESC (Enterprise Social Commitment)
The company will utilize Rs.8 crores i.e.5% of total project cost of Rs 157 crores towards
ESC activities, this fund shall be utilized over a period of 5 years of profitable production.
The allocation of fund will be mainly based on public demand during Public Hearing and
socio-economic study of the project area.
The project has several beneficial impacts which will obviously improve the socio-
economic conditions of the locality.
Those are mainly
Improvement in infrastructure facilities
Improved business opportunity
Direct & indirect Employment opportunity
Revenue generation to central & state government.
Allocation of 5 % of the project cost towards the ESC
When there will be and industry there will be some negative impact whatever small it
may be due to implementation of pollution control system and management.
When the same is superimposed with the project benefits that include employment,
trade & business opportunity, infrastructure development, greenbelt development and
peripheral development, which trickle down to lower strata of population the TIS (Total
Impact Score) comes out to be positive indicating the clear acceptability of the project.