24
Michael Paul, Andrea Kassahun Wismut GmbH, 09117 Chemnitz, Jagdschänkenstraße 29 The German Wismut Environmental remediation Programme – Status achieved and Challenges remaining Challenges and Best Practices in Metal Leaching and Acid Rock Drainage BC MEND 2013, Vancouver, December 4 - 5, 2013

The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

Michael Paul, Andrea KassahunWismut GmbH, 09117 Chemnitz, Jagdschänkenstraße 29

The German Wismut Environmental remediation Programme –Status achieved and Challenges remaining

Challenges and Best Practices in Metal Leaching and Acid Rock DrainageBC MEND 2013, Vancouver, December 4 - 5, 2013

Page 2: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

2

Introduction

1946 - 1990, SDAG Wismut in East Germany major foreign uranium supplier to the Soviet Union (~ 216,000 tonnes of U from 20+ deposits)

1990, U production terminated in the wake of the German reunification (45,000 employees)

Rigorous production philosophy, operation in densely populated areas

East German U industry left behind one of the most extensive uranium-mining legacies in the world

1991, start of the remediation program after abrupt closure

• German government as new company owner earmarked 6.6 bnEuro to fund the project (largest European environmental remediation programme)

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Page 3: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

3

Site setting and areal extent of the legacy

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Berlin

Germany

7 production complexes, with more than 1,000 objects:

• 5 Underground mines (~ 80 million m3 excavation volume)

• 1 open pit (~ 84 million m3)

• 2 Processing plants, 10 TMF, containing 160+ million m3 tailings

• 3,700 hectare operational areas with contaminated facilities

• 60+ Waste rock piles, containing 325 million m3 WR

Decommissioned Mine

Decommissioned Processing Plant

WISMUT Head Office

Page 4: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

4

Situation in 1990

Kapitel, Thema oder Verfasser

325 million m3 waste rock piles (1,540 ha contact area)

Page 5: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

5

Situation in 1990

Kapitel, Thema oder Verfasser

• 3,700 hectare contaminated operational areas:250,000 m3 demolition waste260,000 tonnes scrap

• 160 million m3 tailings

Page 6: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

6

Situation in 1990

Kapitel, Thema oder Verfasser

• 1 open pit: 84 million m3

• 5 underground mines (1,500 km mine workings),1 in-situ-leaching mine

Page 7: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

7

Remediation goals

Ensure public safety

Enable future land use

Minimize radiation risks and hazards

achieve individual effective dose for public: < 1 mSv/a

Reduce adverse effects to water resources

• minimize WR seepage, flood mines, pump & treat tailing seepage and mine drainage to meet regulatory standards (U, Ra, As, heavy metals, Fe, Mn, SO4)

Destigmatize regions affected by uranium mining

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Page 8: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

8

Main Activities

Dismantling of surface structures, decontamination and siteclean-up, disposal of contaminated material into containments

Safe closure of underground mines and controlled mine flooding

Tailings dewatering & stabilization

In-situ stabilization or Open Pit disposal of mine waste, segregation / conditioning of reactive mine waste

Vegetated soil covers on tailings and waste rock

Active water treatment and safe management of residues

Environmental monitoring & Maintenance

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Page 9: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

9

Main Activities

Dismantling of surface structures, decontamination and siteclean-up, disposal of contaminated material into containments

Safe closure of underground mines and controlled mine flooding

Tailings dewatering & stabilization

In-situ stabilization or Open Pit disposal of mine waste, segregation / conditioning of reactive mine waste

Vegetated soil covers on tailings and waste rock

Active water treatment and safe management of residues

Environmental monitoring & Maintenance

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Page 10: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

10

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Open pit disposal of mine waste

• ARD, 16 dumps

• Spatial concentration of waste rock in open pit

• 132 million m3 = 230 milliontonnes

• Transport capacity 10 million m3/a

• Necessary investment in powerful transport fleet (1993, 1995)

• Backfill concept includes zonationaccording to waste rock acid / neutralizing potential

1990

Open pit and importantWRD with volume (Mio. m3)

A 4

N

Page 11: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

11

Waste Rock relocation, 2006

0

2

4

6

8

10

12

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

SchutzdammHalde 4Halde PaitzdorfHalde ReustHalde 377Halde 370DiabashaldeNordhaldeHalde Schürfe 12/13Schmirchauer BalkonAbsetzerhaldeHalde Gessen

Annual relocation (million m3)

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Page 12: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

12

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Backfilling concept

Zone A: high acid potential / lime addition (saturated) Zone B: low acid potential (transition)Zone C: high neutralizing potential (unsaturated)

Page 13: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

13

Lichtenberg Pit, backfilled 2010

Waste concentration, reduction of environmental impacts, enable future land use

Lichtenberg Open Pit, 1991

Operation: 1958 – 1977 Remediation:1991 - 2010

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Remediation result

Page 14: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

14

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Vegetated soil covers Encapsulation of artificial landforms

Total area to be covered > 1,100 ha

Predominant use of natural soils

Object specific approach, cover thickness 0.5 – 2.5 m

Physical stability, reduction of environmental impacts, enable future land use

WRD #366, Aue, 1991 Volume 7.7 million m3

WRD #366, Aue, 2010Cover volume 370,000 m3

Page 15: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

15

Main Activities

Dismantling of surface structures, decontamination and siteclean-up, disposal of contaminated material into containments

Safe closure of underground mines and controlled mine flooding

Tailings dewatering & stabilization

In-situ stabilization or Open Pit disposal of mine waste, segregation / conditioning of reactive mine waste

Vegetated soil covers on tailings and waste rock

Active water treatment and safe management of residues

Environmental monitoring & Maintenance

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Page 16: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

16

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Tailing try in-situ stabilization • Total tailing volume 160 million m3

• Removal of surface water

• Dewatering of sludges

• Mechanical stabilization

• Cover and vegetation

TMF Culmitzsch1991 TMF Culmitzsch 2013

aera 250 hathickness 72 mvolume 85 million m³

temporary coverdrain drillspermanent cover

Page 17: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

17

Main Activities

Dismantling of surface structures, decontamination and siteclean-up, disposal of contaminated material into containments

Safe closure of underground mines and controlled mineflooding

Tailings dewatering & stabilization

In-situ stabilization or Open Pit disposal of mine waste, segregation / conditioning of reactive mine waste

Vegetated soil covers on tailings and waste rock

Active water treatment and safe management of residues

Environmental monitoring & Maintenance

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Page 18: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

18

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Closure of underground mines and water treatment

• Mine Schlema, 36 million m3

• Flooding 1991 - 2011

• Mine Königstein, 11 million m3

• Experimental fooding 1993 - 2000

• Flooding since 2001; stopped in 2012

Page 19: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

19

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Closure of underground mines and water treatment

• 7 water treatment plants (2 at TMF, 5 at flooded underground mines)

• mine flooding since 1991; water treatment since 1995

• Water treatment technology: modified or HDS lime precipitation / ion exchange

• Discharge limits for U, As, Ra, heavy metals, Fe, Mn, SO4

• German water legislation / european water frame work directive

• treatment capacity of individual plants100 - 700 m3/h (max. 1,200 m3/h)

• total throughput ~ 20 million m3 / a

• water treatment cost ~ 35 million € / a

Page 20: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

20

WISMUT Remediation ProgrammeStatus of Remediation Activities March 2013Underground

Surface Remediation Status

Mine workings abandoned 99 %

Backfilling of Mine Voids 99 %

Mine workings flooded 98 %

Stabilization of mine workings 94 %

Demolition of facilities 90 %

Contouring 93 %

Final capping 73 %

Reclaimed areas 74 %

Water treatment 53 %

Percent achieved*

* Based on the 2010 revision of the remediation programme

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Workremaining

TMF

planned until2040

Page 21: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

21

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Challenge: In-situ contaminant immobilizationC

once

ntra

tion

Time

Flooding Post-Flooding

Discharge limit

Page 22: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

22

Summary

Per 10/2013: Remediation of the legacies of uranium mining in East Germany to > 85 % successfully completed

• Total expenditures: 5.7 bn EURO

Sustainable limitation of radioactive and other emissions in compliance with permits

• Decrease of radionuclide discharge into surface wates by 90-99% (27.5 t U in 1989 → 2.4 t U in 2007)

Following land reclamation, some 1,150 ha sold or leased out of a total of ca. 3,700 ha appropriated land

Core remediation tasks to be completed by 2022

Long-term tasks dominated by water treatment, maintenance, and environmental monitoring planned until 2040

Michael Paul, Andrea Kassahun Wismut Programme BC MEND 2013, Vancouver, December 4-5 2013

Page 23: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

Challenges and Best Practices in Metal Leaching and Acid Rock DrainageBC MEND 2013, Vancouver, December 4 - 5, 2013

Page 24: The German Wismut Environmental remediation Programme ...bc-mlard.ca/files/presentations/2013-19-PAUL-ETAL-german-wismut... · The German Wismut Environmental remediation Programme

Challenges and Best Practices in Metal Leaching and Acid Rock DrainageBC MEND 2013, Vancouver, December 4 - 5, 2013