91
Guru Nanak Dev Thermal Power Plant is a coal- based plant. The requirement of coal for four units based on specific fuel consumption of 0.60 kg / kWh. The conveying and crushing system will have the same capacity as that of the unloading system. The coal comes in as large pieces. This coal is fed to primary crushers, which reduce the size of coal pieces from 400mm to 150mm. Then the coal is sent to secondary crusher through forward conveyors where it is crushed from 150mm to 200mm as required at the mills. Then the coal is sent to boilers with the help of primary fans. The coal is burnt in the boiler. Boiler includes the pipes carrying water through them; heat produced from the combustion of coal is used to convert water in pipes into steam. This steam generated is used to run the turbine. When turbine rotates, the shaft of generator, which is mechanically coupled to the shaft of turbine, gets rotated so, three phase electric supply is produced. The basic requirements are:- INTRODUCTION

Thermal Power Plant Mechanical

Embed Size (px)

Citation preview

Page 1: Thermal Power Plant Mechanical

Guru Nanak Dev Thermal Power Plant is a coal-based plant. The requirement of

coal for four units based on specific fuel consumption of 0.60 kg / kWh. The conveying

and crushing system will have the same capacity as that of the unloading system. The

coal comes in as large pieces. This coal is fed to primary crushers, which reduce the size

of coal pieces from 400mm to 150mm. Then the coal is sent to secondary crusher through

forward conveyors where it is crushed from 150mm to 200mm as required at the mills.

Then the coal is sent to boilers with the help of primary fans. The coal is burnt in the

boiler. Boiler includes the pipes carrying water through them; heat produced from the

combustion of coal is used to convert water in pipes into steam. This steam generated is

used to run the turbine. When turbine rotates, the shaft of generator, which is

mechanically coupled to the shaft of turbine, gets rotated so, three phase electric supply is

produced.

The basic requirements are:-

♣ Fuel (coal)

♣ Boiler

♣ Steam turbine

♣ Generator

♣ Ash handling system

♣ Unit auxiliaries

INTRODUCTION

INTRODUCTION

Page 2: Thermal Power Plant Mechanical

Due to high rate of increasing population day by day, widening gap between power

demand and its availability was one the basic reason for envisaging the G.N.D.T.P. for

the state of Punjab. The other factors favoring the installation of the thermal power

station were low initial cost and comparatively less gestation period as compared to

hydro electric generating stations. The foundation stone of G.N.D.T.P. at bathinda was

laid on 19th November 1969, the auspicious occasion of 500th birth anniversary of great

Guru Nanak Dev Ji.

The historic town of bathinda was selected for this first and prestigious thermal

project of the state due to its good railway connections for fast transportations of coal,

availability of canal water and proximity to load center.

The total installed capacity of the power station 440MW with four units of

110MW each. The first unit of the plant was commissioned in September, 1974.

Subsequently second, third and fourth units started generation in September 1975, March

1978, and January 1979 respectively. The power available from this plant gives spin to

the wheels of industry and agricultural pumping sets.

BRIEF HISTORY OF PLANT

BRIEF HISTORY OF PLANT

Page 3: Thermal Power Plant Mechanical

R&M of GNDTP unit 1&2 has already been completed pending PG Test. R&M works of

unit 3&4 is underway to improve performance, enhance capacity and extend operating

life of the units. The present status of R&M works of GNDTP units is as under:

Unit I&II: - Against approved project Report of Rs. 229 Crores, Order was placed on

M/S NASL, New Delhi for major R&M works on Turnkey basis at a total of Rs.183

Crores.

Unit II: R&M works completed in October, 2005 (Pending attending to some deficiencies

by the firm). Average PLF achieved post R&M works is 87%.

Unit I: - R&M works completed and taken for normal operation in May, 2007(Pending

attending to some deficiencies by the firm). Average PLF achieved post R&M during

May’07 and June ’07 is 95.65%.

Unit III & IV: - Order for executing R&M works on Turnkey basis already placed on

M/S BHEL at a total cost of Rs. 465.36 Crores. 10% advance payment has been made to

M/S BHEL on 22/12/2006 and design and drawing work is in progress. As per Schedule,

work is to be completed in a phased manner upto July 2009. Apart from enhancing the

operating life and performance level of the units, it is also planned to upgrade the

capacity from 110 MW to 120 MW each resulting in total capacity addition of 20 MW.

R&M WORKS AT GNDTP, BATHINDA

R&M WORKS AT GNDTP, BATHINDA

Page 4: Thermal Power Plant Mechanical

The selection of site for Thermal Power Plant is more difficult compared to Hydro

Power Plant, as it involves number of factors to be considered for its economic

justification. The following consideration should be examined in detail before selection

of the site for the Plant. The location for plant should be made with full consideration not

only of the trends in the development and location but also the availability and location of

the cheapest source of primary energy:-

Availability of fuel

Ash disposal facilities

Space requirement

Nature of land

Availability of labour

Transport facilities

Public society problems

Development of Backward Area

SITE SELECTION

SITE SELECTION

Page 5: Thermal Power Plant Mechanical

G.N.D.T.P. won an award of Rs. 3.16 crores from Govt. of India for better

performance in 1983-84.

It achieved a rare distinction of scoring hart Rick by winning meritorious

productivity awards of Govt. of India, Ministry of Energy for year 1987, 1988 and

1989 due to its better performance.

It again won meritorious productivity awards during the year 1992-1993 and

1993-94 and has become entitled for the year 1996-1997 for better performance.

It also won awards for reduction in fuel oil consumption under Govt. of India

incentive scheme years from 1992-1993 (awards money for 1992, 1993 and 1994

already released for 1995, 1996 and 1997 under the consideration of Govt. of

India).

G.N.D.T.P. had achieved a generation of 2724240 LU’s (at a PLf of 70%) and

registering an oil consumption as low as 1.76ml/kwh during the year 1993-94 has

broken all previous records of performance since the inception of plant.

LANDMARK ACHIEVED

LANDMARK ACHIEVED

Page 6: Thermal Power Plant Mechanical

Guru Nanak Dev Thermal Plant, Bathinda, in addition to indirect contribution in various

facts of state economy, is also responsible for:-

Narrowing the gap between power demand and power availability of the state.

Providing employment potentials to thousands of workers.

Covering the backward surrounding area into fully developed Industrial

Township.

Providing additional relief to agricultural pumping sets to meet the irrigation

needs for enhancing the agriculture production.

Reliability and improvement in continuity of supply and system voltage.

Achieving cent percent rural electrification of the state.

CONTRIBUTION OF THE PLANT

CONTRIBUTION OF THE PLANT

Page 7: Thermal Power Plant Mechanical

PROJECT AREA:-

Power plant 238 acres

Ash disposal 845

Lake 180

Residential colony 285

Marshalling yard 256

Total area 1804

TOTAL COST: - Rs. 115 crores

STATION CAPACITY: - four units of 110MW.each

BOILER:-

Manufacturers B.H.E.L.

Maximum continuous rating (M.C.R.) 375 T/hr.

Superheater outlet pressure 139 kg/cm²

Reheater outlet pressure 33.8 kg/cm²

Final superheater/reheater temperature 540C

Feed water temperature 240C

Efficiency 86%

Coal consumption per day per unit 1400 tones (Approximate)

PLANT SALIENT FEATURESTHE PLANT

PLANT SALIENT FEATURESTHE PLANT

Page 8: Thermal Power Plant Mechanical

STEAM TURBINE:-

Manufacturers B.H.E.L.

Rated output 110 MW.

Rated speed 3000 r.p.m.

Number of cylinders three

Rated pressure 130 kg/cm²

Rated temperature 535C

Condenser vacuum 0.9 kg/cm²

GENERATOR:-

Manufacturers B.H.E.L.

Rated output

(Unit- 1 & 2) 125000KVA

(Unit -3 & 4) 137000KVA

Generator voltage 11000 volts

Rated phase current

(unit –1 & 2) 6560 Amps.

(unit –3 & 4) 7220 Amps.

Generator cooling hydrogen

BOILER FEED PUMPS:-

Number per unit two of 100% duty each

Type centrifugal

Rated discharge 445 T/hr.

Discharge head 1960 MWC.

Speed 4500 r.p.m.

Page 9: Thermal Power Plant Mechanical

CIRCULATING WATER PUMPS:-

Numbers for two units five of 50% duty each

Type mixed flow

Rated discharge 8600 T/hr.

Discharge head 24 MWC.

COOLING TOWERS:-

Numbers four

Water cooled 18000 T/hr.

Cooling range 10C

Height 120/12 metres

COAL PULVERISING MILLS:-

Numbers three per unit

Type drum-ball

Rated output 27 T/hr.

Coal bunkers 16 per unit

RATING OF 6.6 KV AUXILLIARY MOTORS:-

Coal mill 630 KW

Vapour fan 320 KW

C.W. Fan 800/746 KW

Coal crusher 520 KW

Page 10: Thermal Power Plant Mechanical

Primary air fan 320 KW

Forced draught fan 320 KW

Boiler feed pump 3500 KW

Induced draught fan 900/1000 KW

Condensate pump 175 KW

Page 11: Thermal Power Plant Mechanical

Coal received from collieries in the rail wagon is mechanically unloaded by

Wagon Tippler and carried by belt Conveyor System Boiler Raw Coal Bunkers after

crushing in the coal crusher. The crushed coal when not required for Raw Coal Bunker is

carried to the coal storage area through belt conveyor. The raw coal feeder regulates the

quantity of coal from coal bunker to the coal mill, where the coal is pulverized to a fine

powder. The pulverized coal is then sucked by the vapour fan and finally stored in

pulverized coal bunkers. The pulverized coal is then pushed to boiler furnace with the

help of hot air steam supplied by primary air fan. The coal being in pulverized state gets

burnt immediately in the boiler furnace, which is comprised of water tube wall all around

through which water circulates. The water gets converted into steam by heat released by

the combustion of fuel in the furnace. The air required for the combustion if coal is

supplied by forced draught fan. This air is however heated by the outgoing flue gases in

the air heaters before entering the furnace.

The products of combustion in the furnace are the flue gases and the ash. About

20% of the ash falls in the bottom ash hopper of the boiler and is periodically removed

mechanically. The remaining ash carried by the flue gases, is separated in the

electrostatic precipitators and further disposed off in the ash damping area. The cleaner

flue gases are let off to atmosphere through the chimney by induced draught fan.

The chemically treated water running through the water walls of boiler furnace

gets evaporated at high temperature into steam by absorption of furnace heat. The steam

is further heated in the super heater. The dry steam at high temperature is then led to the

turbine comprising of three cylinders. The thermal energy of this steam is utilized in

turbine for rotating its shaft at high speed. The steam discharged from high pressure

(H.P.) turbine is returned to boiler reheater for heating it once again before passing it into

the medium pressure (M.P.) turbine. The steam is then let to the coupled to turbine shaft

is the rotor of the generator, which produces electricity. The power from the generator is

pumped into power grid system through the generator transformer by stepping up the

voltage.

WORKING OF THERMAL PLANT

WORKING OF THERMAL PLANT

Page 12: Thermal Power Plant Mechanical

The steam after doing the useful work in turbine is condensed to water in the

condenser for recycling in the boiler. The water is pumped to deaerator from the

Page 13: Thermal Power Plant Mechanical

condenser by the condensate extraction pumps after being heated in the low pressure

heater (L.P.H) from the deaerator, a hot water storage tank. The boiler feed pump

discharge feed water to boiler at the economizer by the hot flue gases leaving the boiler,

before entering the boiler drum to which the water walls and super heater of boiler are

connected.

The condenser is having a large number of brass tubes through which the cold

water is circulated continuously for condensing the steam passing out sides the surface of

the brass tubes, which has discharged down by circulating it through the cooling tower

shell. The natural draught of cold air is created in the cooling tower, cools the water fall

in the sump and is then recirculated by circulating water pumps to the condenser.

Page 14: Thermal Power Plant Mechanical

BOILER FEED PUMP:-

As the heart is to human body, so is the boiler feed pump to the steam power plant. It is

used for recycling feed water into the boiler at a high pressure for reconversion into

steam. Two nos. 100% duty, barrel design, horizontal, centrifugal multistage feed pumps

with hydraulic coupling are provided for each unit. This is the largest auxiliary of the

power plant driven by 3500 KW electric motor.

The capacity of each boiler at GURU NANAK DEV THERMAL PLANT is

375 tones/hr. The pump which supplies feed water to the boiler is named as boiler feed

pump. This is the largest auxiliary in the unit with 100% capacity which takes suction of

feed water from feed water tank and supplies to the boiler drum after preheating the same

in HP-1, HP-2 and economizer. The delivery capacity of each boiler feed pump is 445

tones/hr. to meet better requirements corresponding to the various loads, to control steam

temperature, boiler make up water etc. The detailed particulars checking of protections

and inter locks, starting permission etc. are as below:-

Particulars of BFP and its main motor:-

BOILER FEED PUMP : - The 110 MW turboset is provided with two boiler feed

pumps, each of 100% of total quantity. It is of barrel design and is of horizontal

arrangement, driven by an electric motor through a hydraulic coupling.

Type 200 KHI

No. of stages 6

Delivery capacity 445 t/hr.

Feed water temperature 158C

Speed 4500 rpm

Pressure at suction 8.30 kg/cm²

Stuffing box mechanical seal

Lubrication of pump by oil under pressure

And motor bearing supplied by hydraulic coupling

Consumption of cooling water 230 L/min.

GENERAL DESCRIPTION

GENERAL DESCRIPTION

Page 15: Thermal Power Plant Mechanical

WATER TREATMENT PLANT:-

The water before it can be used in the boiler has to be chemically treated, since untreated

water results in scale formation in the boiler tubes especially at high pressure and

temperatures. The water is demineralised by Ion Exchange Process. The water treatment

plant has production capacity of 1800 Tonnes per day for meeting the make-up water

requirement of the power station.

COAL MILL:-

Coal Mill pulverizes the raw coal into a fine powder before it is burnt in the boiler

furnace. The pulverizing of coal is achieved with the impact of falling steel balls,

weighing 52.5 tonnes, contained in the mill drum rotating at a slow speed of 17.5 r.p.m.

The raw coal is dried, before pulverizing, with inert hot flue gases tapped from the boiler.

Three coal mills each with a pulverizing capacity of 27 T/hr. are provided for one unit.

INDUCED DRAUGHT FAN:-

Two nos. axial flow Induced Draught Fans are provided for each unit to exhaust ash

laden flue gases from boiler furnace through dust extraction equipment and to chimney.

The fan is driven by an electric motor through a flexible coupling and is equipped with

remote controlled regulating vanes to balance draught conditions in the furnace. The fan

is designed to handle hot flue gases with a small percentage of abrasive particles in

suspension.

CONTROL ROOM:-

The control room is the operational nerve center of the power plant. The performance of

all the equipments of the plant is constantly monitored here with the help of sophisticated

instrumentation and controllers. Any adverse deviation in the parameters of various

systems is immediately indicated by visual and audio warning and suitable corrective

action is taken, accordingly. The control room is air conditioned to maintain the desired

temperature for proper functioning of the instruments.

Page 16: Thermal Power Plant Mechanical

SWITCH YARD:-

Electricity generated at 11 KV by the turbo-set is stepped-up by unit transformers to

132/220 KV for further transmission through high tension lines to Maur, Muktsar,

Malout, N.F.L., Sangrur and Ludhiana. Transmission of power to grid is controlled

through 7 nos. 220 KV and 15 nos. 132 KV. Air Blast Circuit Breakers along with their

associated protective systems.

WAGON TIPPLER:-

The coal received from the collieries, in more than 100 rail wagons a day, is unloaded

mechanically by two nos. wagon tipplers out of which one serves as a standby. Each

loaded wagon is emptied by tippling it in the underground coal hopper from where the

coal is carried by conveyor to the crusher house. Arrangements have been provided for

weighing each rail wagon before and after tippling. Each tippler is capable of unloading

6-8 rail wagons of 55 tonnes capacity in an hour.

CRUSHER HOUSE:-

Coal unloaded by the wagon tippler is carried to crusher house through conveyors for

crushing. Two nos. hammer type coal crushers are provided, which can crush coal to a

size of 10 mm. The crushed coal is then supplied to Boiler Raw Coal Bunkers. The

surplus coal is carried to coal storage area by series of conveyors. Crushing of coal is an

essential requirement for its optimum pulverizing and safe storage.

COOLING TOWERS:-

Cooling Towers of the power plant are the land mark of the Bathinda City even for a far

distance of 8-10 kilometers. One cooling tower is provided for each unit for cooling

18000 tones of water per hour by 10C. cooling towers are massive Ferro-concrete

structure having hyperbolic profile creating natural draught of air responsible for

achieving the cooling effect. Cooling tower is as high as 40 storey building.

Page 17: Thermal Power Plant Mechanical

BOILER:-

It is a single drum, balanced draught, natural circulation, reheat type, vertical combustion

chamber consists of seamless steel tubes on all its sides through which water circulates

and is converted into steam with the combustion of fuel. The temperature inside the

furnace where the fuel is burnt is of the order of 1500C. The entire boiler structure is of

42meter height.

BOILER CHIMNEY:-

The flue from the boiler, after removal of ash in the precipitators, are let off to

atmosphere through boiler chimney, a tall ferro-concrete structure standing as high as the

historic Qutab Minar. Four chimneys, one for each unit, are installed. The chimney is

lined with fire bricks for protection of ferro-concrete against hot flue gases. A protective

coating of acid resistant paint is applied outside on its top 10 meters.

CIRCULATING WATER PUMP:-

Two nos. of circulating water pumps provided for each unit, circulate water at the rate of

17200 T/hr. in a closed cycle comprising of Turbine Condenser and Cooling Tower. An

additional Circulating Water Pump provided serves by for two units. The water

requirement for bearing cooling of all the plant auxiliaries is also catered by these pumps.

Page 18: Thermal Power Plant Mechanical

Since G.N.D.T.P. units are primarily coal fired units so each boiler is

provided with closed milling circuits to pulverize the raw coal which is

received from coal conveying system after coal crushes before it is fired in

the furnace. The necessity of pulverizing the coal is to be ensuring its

maximum possible combustion in the furnace. The coal data for units are: -

COAL DATA UNITS 1 & 2 UNITS 3 & 4

Type of Coal

Net Calorific Value

Moisture

Ash Content

Volatile Matter Incombustible

Inlet of Coal

Bituminous

4300 Kcal/kg

10 %

30 %

24 %

10 mm

Bituminous

4727 Kcal/Kg

7.5 %

32 %

27 %

20 mm

Raw coal of maximum size 10 mm – 20 mm is pulverized in the milling

circuit and the output from the mill is fine coal. Milling circuits of the

following main constituents: -

COAL MILLING PLANT

COAL MILLING PLANT

Page 19: Thermal Power Plant Mechanical

1. Raw Coal Bunkers (R.C. Bunkers).

2. Raw Coal Chain Feeders.

3. Drum Mill or Coal Mill.

4. Classifiers.

5. Cyclone Separator.

6. Vapour Fan.

7. Pulverized Coal Bunkers (P.C. Bunkers).

COAL MILL

Page 20: Thermal Power Plant Mechanical

RAW COAL BUNKER:-

Each of three raw coal bunkers is fabricated from the sheet metal and is well stiffened all

around. The storage capacity of each raw coal bunker is about 500 tones. There are four

outlet gates with each bunker. The gates are electrically operated from site. In case of

failure of the electric motors the gate can be hand operated from site. At a time only one

gate opening is suffices but should be changed so that there is no pilling within the

bunker.

RAW COAL CHAIN FEEDER:-

The raw coal chain feeder transports coal from raw coal bunker to the inlet chute leading

to the pulverized/coal mills. There is a double link chain of high tensile strength steel,

which moves on wheels and sweeps the raw coal falling over the top of the raw coal

chute of the mill. The height of the coal bed in the chain feeder can be adjusted manually

by means of lever operated damper. The maximum and minimum heights of the coal bed

are 200mm and 120mm respectively. The signaling equipment indicates the absence of

coal flow in the feeder, which is annunciated in the unit control board (U.C.B.). The main

shaft on the driving end is connected to the driving unit, consisting of variator, a gear box

and a motor all mounted as a single unit. The chain wheel on the driving end shaft is

provided with a shear pin, which will shear off and disconnect the driving mechanism if

there is any overload on the feeder. The speed of the chain feeder is regulated

automatically/remotely by actuating the control spindle of the variator through a

servomotor. A pump for circulating the oil in the gear box of variator is an integral part of

variator driven by a separator motor. Some of the technical data about the raw coal chain

feeder is given here:-

1. Output of the chain feeder 10-45 tonnes/hr.

2. Speed variations 0.0503-0.151m/sec.

3. Main motor 7.5kW, 415V, 50Hz.

4. Oil pump motor 0.05kW, 220V

5. Operating motor of each gate 3HP, 415V and 50Hz.

Page 21: Thermal Power Plant Mechanical

DRUM MILL:-

Each mill consists of single compartment drum, bearings driving motor, coal inlet

and discharge piping, ball change and lubricating equipment for mill bearings. Mill drum

is fabricated from thick steel plates and is supported on to the anti-friction bearings. The

mill is driven by an electric motor of capacity 630kW, 990 rpm, 6.6kV through a

reduction gear, which reduces the speed to 17.5 rpm. The ball charge for the mill consists

of the three different sizes of forged steel balls detailed as below. The capacity of each

mill is 27 T/hr. in case of unit 1 & 2 and 28 T/hr.

1. 40mm diameter 22500 kg

2. 50mm diameter 20000kg

3. 60mm diameter 10000kg

4. Total Ball Charge 52500kg

During operation only 60mm diameter balls are added is approx. 500 kg per week

and the guiding factor is the amperage of the coal mill, normally it should be 66-ampere

approx. at full load and when it falls below the above value ball charging of the mill is

carried out. Lubricating system consists of the oil tank, gear pump, oil cooler and base

frame to mount all these equipments. Gear pump is driven by an electric motor of rating 1

H.P., 415 V, 1440 rpm. Suction side of the gear pump is connected to the tube oil tank

and the delivery side is connected to inlet of the oil cooler and after cooling oil goes to

the bearings. The oil from the bearings is cooled to the required temperature in the cooler

by the means of plant bearing cooler water.

CLASSIFIER:-

The classifier is fabricated from the steel plates. It is an equipment that separates fine

pulverized coal from the coarser pieces. The pulverized coal along with the carrying as

well as drying medium (flue gas) strikes the impact plate in the classifier and the coarser

pieces get separated due to the change in the direction of flow and go back to mill. The

stream then passes to the outlet branch of the classifier through an adjustable telescopic

tube. At the outlet adjustable vanes are provided to change the size of coal when required.

Page 22: Thermal Power Plant Mechanical

CYCLONE SEPARATOR:-

The centrifugal type cyclone separator consists of two cyclones made up of welded

sheets. It is equipment in the milling plant, which serves for separating the pulverized

coal from the vapours i.e. carrying medium. The pulverized coal gets stored in the

pulverized coal bunkers and vapours go to suction of vapour fan. At the bottom of the

cyclone separator a rotary valve (Turnikete) is provided to transport coal from cyclone

separator to P.C. bunker on the worm conveyor as the case may be.

VAPOUR FAN:-

Pulverized coal bunker is welded from thick steel sheets and has a capacity of 4 hours

coal consumption at maximum continuous rating of the boiler. The whole bunker is

insulated externally. The carbon-dioxide blanketing system has been provided in the P.C.

bunker to prevent fire hazards inside the bunker. The while storage bunker is divide into

four parts namely A, B C & D. Further four coal feeders are taken out from each bunker

leading to each corner of the furnace.

CRUSHING OF COAL:-

When coal reaches the plant, normal size of coal is about 500mm. After unloading the

coal from the rake is fed to primary crusher, which reduces the size to 120mm. Then coal

is fed to secondary crusher which reduces the size to 25mm and this coal goes to bunker

with the help of conveyor belt from where coal finally goes to coal mill where coal is

transferred in form of pulverized coal. The coal is heated with the help of hot primary air.

We maintain the temperature of about 70C in coal mill. This temperature is maintained

with the help of cold air and a hot air damper.

USE OF OIL:-

Before the coal reaches the furnace, we preheat the furnace in order to remove the

moisture and raise the temperature of furnace, so that coal can catch fire easily without

any delay. This preheating of furnace is done with the help of oil. With burning of oil, we

maintain the temperature of furnace at 350C. we cut the oil supply after 350C because

oil is very costly. Source of oil for G.N.D.T.P., Bathinda is Mathura Oil Refinery. Other

Page 23: Thermal Power Plant Mechanical

use of oil is in bearing system for cooling. There are large number of bearings for plant.

For example bearing system of turbine. These bearings get heated upto high temperature,

which is dangerous. So we cool the bearing by circulating water in bearing.

COAL FEEDING AND COAL MILL:-

From the coal handling plant, coal comes in two belts namely 5A and 5B and then by

belts 6A and 6B coal comes in bunkers. Bunker capacity is 300 tonnes. Number of outlets

of bunker is three. First gate is opened for one hour and second and then third. If open the

one gate for long time, then coal will stop going to mill. That is why we open the gate

turn by turn.

RAW COAL CHAIN FEEDER:-

Raw coal chain feeder is just below raw coal bunker. It is a sliding chain which feed the

coal to mill. We can change the quantity of coal which is fed to mill in two ways.

By changing the speed of chain

By changing the depth of coal in chain

Speed of chain can be changed by adding a gear system to motor. We connect the

gear system with motor with a pin called shear pin. The prevent the overloading of motor

because when the coal quantity of coal on chain is greater than its capacity then the pin

will break and prevent the pin from overloading. Speed of Raw Coal chain is 2” to 6”/sec.

COAL MILL:-

These are mainly of two types:-

i) Ball Mills

ii) Bowl Mills

Ball Mills: - In Ball Mills there are steel balls which are revolving in horizontal

cylindrical drum. These balls are free from any shaft and balls are touching with each

other and with internal body of drum. These types of mills are at Bathinda Thermal Plant.

Page 24: Thermal Power Plant Mechanical

On the other hand, bowl mills part of the mill contain drive system i.e. it contains 6.6 kV

electric motor and gear system which translates the revolution about horizontal axis to

revolve about vertical axis. The revolving vertical axis contains a bowl about the driving

system. This bowl is fixed with driving and revolving with shaft. There are also three

rollers which are suspended at some inclination, so that there is a gap of few mm between

roller surface. These rollers are free to rotate about the axis.

Bowl Mills: - The coal is grinded and then fed into the mill at the center or near of

revolving bowl. It passes between the grinding ring in revolving bowl and rolls as

centrifugal force causes the material to travel towards the out perimeter of bowl. The

springs, which load the rolls, impart the necessary force for grinding. The partially

pulverized coal continue going up and down and over the edge of bowl.

Page 25: Thermal Power Plant Mechanical

The G.N.D.T.P. units are primarily coal-fired units and the coal consumption at

maximum continuous rating (M.C.R.) per unit is about 58 T/Hr. the coal used at

G.N.D.T.P. is of bituminous and sub-bituminous type and this is received from some

collieries of M.P. and Bihar. The designed composition of coal is as below:-

Type Bituminous Coal

Net calorific value 4300 kcal/kg

Moisture content in coal 10%

Ash content 30%

Volatile matter in combustibles 24%

Grind ability index 50 Hard Groove

The coal handling plant at G.N.D.T.P. has been supplied and erected by M/s

Elecon Engineering Company Limited, Vallabh Vidya Nagar, Gugarat. Coal is

transported from the coal mines to the plant site by Railways. Generally, the raw coal

comes by railway wagons of either eight wheels weighing about 75 to 80 tones each or

four wheels weighing about 35 to 40 tones each. The loaded wagon rake is brought by

railways main line loco and left on one of the loaded wagon tracks in the power station

marshalling yard. The main line loco escapes through the engine track. The station

marshalling yard is provided with 8 tracks. The arrangement of the tracks in the

marshalling yard is as follows:-

DESTINATION NO. OF TRACKS

Loaded wagons receiving tracks Four

Empty wagon standing tracks Three

Engine escape tracks One

COAL HANDLING PLANT (CHP)

COAL HANDLING PLANT (CHP)

Page 26: Thermal Power Plant Mechanical

UNLOADING OF COAL:-

In order to unload coal from the wagons, two Roadside Tipplers of Elecon make

are provided. Each is capable of unloading 12 open type of wagons per hour. Normally

one tippler will be in operation while the other will be standby. The loaded wagons are

brought to the tippler side by the loco shunters. Then with the help of inhaul beetle one

wagon is brought on the tippler table. The wagon is then tilted upside down and emptied

in the hopper down below. The emptied wagon comes back to the tippler table and the

outhaul beetle handles the empty wagons on the discharge side of the tippler. The tippler

is equipped with the integral weighbridge machine. This machine consists of a set of

weighing levers centrally disposed relative to tippler. The rail platform rests on the

weighing girders and free from rest of the tippler when the wagon is being weighed. After

weighing the loaded wagons is tipped and returned empty to the weighing girders and

again weighed. Thus the difference of the gross weight and the tare weight gives the

weight of the wagon contents. The tipplers are run by motors of 80 H.P. each through

gears only.

WAGON TIPPLER

The tippler is designed to work on the following cycle of operation:-

Tipping 90 seconds

Pause 5-12 seconds

Page 27: Thermal Power Plant Mechanical

Return 90 secondS

Weighing 30 seconds

Total 215-222 seconds

Allowing 85 seconds for wagon changing it will be seen that 12 eight-wheel wagons or

24 four-wheel wagons per hours can be tipped. However since the coal carrying capacity

is 500 tones per hour load of 12 wagons comes to 8 to 9 per hour.

DUST TRAPPING SYSTEM:-

The tippler is also provided with the dust trapping systems by which the dust nuisance

will be minimized. As the tippler rotates, a normally closed hopper valve opens

automatically and the discharged material passes through it into the hopper with its dust-

setting chamber, there is an air valve of large area, which opens, simultaneously with the

hopper valve. The object of this air valve is to blow back through the hopper valve into

the tipping chamber, which must occur if, the settling chamber were closed, it being

remembered that a large wagon contains some 240 cubic feet of material and that this

volume of dust air would be forced back at each tip if the hopper chamber were a “closed

bottle”. The air valve and the hopper valve are shut immediately on reversal of the tippler

and are kept shut at all times except during the actual discharge. The hopper valve is

operated by a motor of 10 H.P., 415 Volts and the air valve is operated by electro-

hydraulic thruster. Inlet valve consists of large number of plates sliding under the wagon

tippler grating. Coal in the wagon tippler hopper forms the heap and as such obstructs the

movement of sliding valve and damaging the plates. The inlet and outlet valves have

therefore been bypassed.

The unloaded material falls into the wagon tippler hopper (common to both

tipplers) having a capacity of 210 tones. The hopper has been provided with a grating of

300mm X 300mm size at the top so as to large size boulders getting into the coal stream.

There is also a provision of unloading the wagons manually into the MANUALLY

UNLOADED HOPPER of 110 tones capacity. Manually unloading will be restored to

while unloading coal from sick wagons or closed wagons.

Page 28: Thermal Power Plant Mechanical

MAGNETIC PULLEYS:-

On belt conveyor no. 4A and 4B, there have been provided high intensity

electromagnetic pulleys for separating out tramp iron particles/pieces from the main

stream of coal conveying. D.C. supply for the magnet is taken on 415 volt, 3 phase, 50

cycles A.C. supply system.

In addition to above high intensity suspension type electromagnets have also been

provided on belt conveyors 4A and 4B for separating out tramp iron pieces/particles.

RECLAIMING:-

If the receipt of coal on any day more than the requirement of the boilers, the

balanced material will be stocked via conveyor 7Aand 7B and through telescopic chute

fitted at the end of the conveyor. At the end of the chute one tele level switch is provided,

which automatically lifts the telescopic chute to a predetermined height every time. The

tele level switch is actuated by the coal pile. When the telescopic chute reaches maximum

height during operation, which will be cut off by limit, switch and stop the conveying

system. When the pile under the telescopic chute is cleared, the telescopic chute can be

independently lower manually by push buttons.

There are five bulldozers to spread and compact the coal pile. Bulldozers of Bharat Earth

Movers Limited Make are fitted with 250 H.P. diesel engines. Each bulldozer is able to

spread the crushed coal at the rate of 250 tones/hr. over a load distance of 60m the coal

can be stacked to a height of 6m the stockpile stores coal for about 45 days for four units

with an annual load factor of 0.66.

Whenever coal is to be reclaimed the bulldozers are employed to push the coal in

the reclaim hopper having a capacity of 110 tones. The coal from the reclaim hopper is

fed either 9A or 9B belt conveyor through vibratory feeders 8A and 8B.

CRUSHER HOUSE:-

The crusher house accommodates the discharge ends of the conveyor 4A, 4B receiving

ends of conveyor 5A, 5B and conveyor 7A and 7B, two crushers, vibrating feeders and

necessary chute work. There are two crushers each driven by 700H.P. electric motor, 3

Page 29: Thermal Power Plant Mechanical

phase, 50 cycles and 6.6 kV supply. The maximum size of the crushed coal is 10mm. The

capacity of each crusher is 500 tones/hr. one crusher works at a time and the other is

standby. From the crusher the coal can be fed either to the conveyors 5A, 5B or 7A, 7B

by adjusting the flap provided for this purpose. There is built in arrangement of bypassing

the crusher by which the coal can be fed directly to the conveyors bypassing crusher.

CONVEYOR BELT AND CRUSHER HOUSE

Page 30: Thermal Power Plant Mechanical

Boiler section

Page 31: Thermal Power Plant Mechanical

The steam generating unit is designed to meet the nominal requirements of 110MW turbo

generator set. The unit is designed for a maximum continuous rating of 375 tones/hr. at a

pressure of 139kg/cm2 and a steam temperature of 5400C. the reheated steam flows at

MCR 32H tones/hr. at the feed water temp at MCR is 2400C. The unit is a balance

draught dry bottom; single drum natural circulation, vertical water tube type, construction

with skin casing and a single reheat system. The furnace is arranged for dry ash discharge

and is fitted with burners located at the four corners. Each corner burner comprises coal,

vapour oil and secondary air compartments. The unit is provided with three ball mills and

arranged to operate with intermediate cool powder bunker. The steam super heater

consists of 4 stages Viz. Ceiling, convection, platen and final superheated. The ceiling

super heated forms the roof of the furnace and horizontal pass and finishes as the rear

wall of the second pass. The convection super heated is made up of horizontal banks

located in the second pass. While the platens are located at the furnace exit, the portion

above the furnace nose encloses the final superheated reheater are in two stages, first

stage is the triflux heat exchangers located in the second pass, which absorbs heat from

superheated steam as well as from the flue gases. The second stage is exit reheater

located in the horizontal pass as pendant tubular loops.

(a) The flue gas for drying the cool in the mills is tapped off after the triflux heat

exchangers. The damper located in the hot flue gases pipe leading to mill controls the

quantity. Control the circulating vapour of the mill entry effect temperature control.

Immediately after the triflux heat exchanger, the air heaters and economizers are located.

The air heater is in 2 stages.

(b) The hot air for combustion from air heater stage 2 is led into the common wind box

located on the sided of the furnace. 4 cool air mixed pipes from pulverized coal bounders

are connected to 4 cool burners’ nozzle at the corners. There will be totally 16 coal

nozzles. 4 located in each corner. Oil guns will be located in the secondary air nozzle for

coal burning. The turn down ratio of the guns will be so selected that it will be possible to

use them also for pulverized fuels flame stabilization while operating under load below

the control point.

(c) Take into consideration the high % age of ash and the relatively poor quality of coal

due regards has been paid to wide pitching the tubes and to the gas velocity across the

heating surface areas. In order to insure reliable and continuous operation sample sot

Page 32: Thermal Power Plant Mechanical

blowing equipment is provided. There are short retractable steam root blowers provide at

the top of furnace fully retractable rotary type blowers are located for cleaning of the

secondary super heater and final heater partly retractable steam blowers are arranged for

the horizontal reheater and super heaters in the second pass. The steam root blowers are

electrically operated.

(d) Root blowing nozzles using blow down from boilers drum are provide for the

cleaning of areas around the burners nozzles zone for dislodging of slag boulder if any in

the bottom ash hopper in the furnace.

(e) Two FD fans are provided per boiler. The FD fans are of the axial type driven by

constant speed motor. The regulation of quantity and pressure is done by inlet vane

control. The flue gases are sucked through the mechanical and electrostatic precipitators

by I.D. fans and delivered into the chimney. Two I.D. fans are provided for each boiler

and they are of the axial type driven by constant speed motors. Inlet vane control effects

the capacity change with reference to load. Both the I.D. and FD fans have been

dimensioned taking into account the minimum margins of 15% on volume and 32% on

pressure.

Specification

Manufacturer B.H.E.L

Maximum continuous rating 375tones/hr.

Super heater outlet pressure 139kg /cm2

Reheater outlet pressure 33.8 kg/cm2

Final super heater temperature 540 deg.c

Feed water temperature 240deg.c

Efficiency 86% (stage-1)

87% (stage-2)

Coal consumption per day 1500 tones

ASH SYSTEM

BOTTOM ASH SYSTEM

Page 33: Thermal Power Plant Mechanical

The ash deposited at the bottom of the furnace is collected in a water impounded hopper

where a continuous flow of water is maintained to limit the temperature of ash inside the

hopper. The bottom ash cleaning is done in every cycle of 8 hours. The bottom ash

system is local manually operated. On opening of feed gate ash is allowed to discharge

into a double roll linder grinder where it is grounded to smaller size, which can be

transported through the pipe line below the linker grinder there is a venturi which sucks

the ground ash the vaccum created at the venturi throat by the flow of high pressure water

tapped. Dawn stream of the discharge of the ash water pumps. The pressure recovered at

the end of venturi is adequate to convey the slurry to disposal area.

STEAM CYCLE

The design of the power cycle based on the modern concept, where a unit consists of a

steam generator with its independent firing system tied to the steam generation. The

steam generator is designed for maximum continuous rating of 375-tonnes/hr. and steam

Pressure of 139-kg/cm2 at temperature of 540C respectively. The steam generator is

designed to supply to a single reheat type condensing steam turbine with a 8 non

regulated extraction points of steam for heading the condensate and feed water. The

steam cycle can be classified into the following three divisions: -

a. Main steam (b) Reheat steam (c) extraction steam

(a)MAIN STEAM

Saturated steam from the steam generator drum is led to the super heater bank to heat if

up to 540C saturated steam from the drum is led to the ceiling super hearter (between

SHH1 and SHH2) from ceiling super steam goes to convection super heater (between

SHH2 and SHH3) the first regulated infection for at temperature takes place after

convection super heater (between SHH9 and SHH10). Before entry to final super heater

the steam is again at temperature by regulated injection. The steam is coming out from

the final super heater normally at a pressure of 139 kg/cm2

Page 34: Thermal Power Plant Mechanical

Temperature takes place after convection super heater (between SHH9 and SHH10).

Before entry to final super heater the steam is again at temperature by regulated injection.

The steam is coming out from the final super heater normally at a pressure of 139 kg/cm2

at a temperature of 540oC. This steam is feed to the control valve. In each of the two live

Page 35: Thermal Power Plant Mechanical

steam lines there is one turbine side main steam stop valve and one high pressure quick

closing valve along with two control valves.

(b) EXTRACTION STEAM

Steam for heating of the condenser and the feed steam is extracted from 8 non regulated

extraction points from the turbine. Heating is carried out in five stages of L.P. heaters,

one deareating heater and in two H.P. heaters extraction 1,2,3, is taken from L.P. turbine.

Extraction 4, 5, 6 and 7 are taken from M.P. turbine. Extraction 8 is obtained from C.R.H.

line first and second stage of heating is done by two sets of twin low-pressure heaters

mounted directly in the L.P. casing of the turbine. Extraction 3,4 and 5 are connected to

the deaereating heater placed above feed water storage tank 7 th and 8th extraction steam is

fed to the vertical H.P. heaters respectively.

(C) REHEAT STEAM

Exit steam from the H.P. turbine is taken back to the reheater section of the steam

generating unit. Reheating is done in two stages both by flue gas and by super heated

steam. The steam to be reheated is first pass through the triple-heated exchanger, where

super heated steam is used as the heating media. The steam is finally reheated in final

reheaters (RHH3) RHH4 and RHH5) suspended in the horizontal pass of the furnace.

Reheat steam at a normal pressure of 36.4 kg/cm2 at a temperature of 540 C respectively

is fed to the M.P. cylinder by two hot reheat steam pipes through strainers and combined

stop and interceptor valves. In each of the cold reheat steam lines from H.P. cylinder a

non-return valve is operated by oil pressure is provided.

MILLING CIRCUIT

The crushers crush the coal upto the dia of 20 mm. This coal comes to the raw coal

bunker through conveyer belts. This coal is fed into the ball mill through chain feeder,

operated by motor. In drum the steel balls are used to make it pulverized. At one end coal

Page 36: Thermal Power Plant Mechanical

enters the mill and from the other end pulverized coal is sucked by vapour fan. The

pulverized coal is used for burning in the furnace. On its way the p.c. (pulverized coal)

bunker, it goes from classifier and cyclone separator function of classifier is to use the

coal for burning coal which could not pass the classifier, is collected on the gravity

damper. When the weight of this coal is enough, gravity damper is opened because of the

weight of the coal and this coal goes back to mill through run back piping and is further

pulverized. In cyclone separator much finer particles of coal is stored in P.C. bunker

because of centrifugal force. This coal is fed to the P.C. bunker through the warm feeder.

Through warm feeder, we can collect the pulverized coal in any of the P.C. bunker.

Warm feeder runs with the help of motor and gearbox.

COAL PULVERIZING MILL

Coal mill pulverizes the raw coal into a fine powder before it is burnt in the boiler

furnace. The pulverizing of coal is achieved with the impact of falling steel balls,

weighing 52.5 tones contained in the mill drum rotating at a slow speed of 17.5 rpm. The

raw coal is dried before pulverizing with inert hot flue gases tapped from the boiler.

Three coal mills each having a pulverizing capacity of 27 tones per hours are provided

for one unit.

Specification

Numbers Three per unit

Type Drum ball

Rated output 30-32 tonnes/hr.

Page 37: Thermal Power Plant Mechanical
Page 38: Thermal Power Plant Mechanical
Page 39: Thermal Power Plant Mechanical

TURBINE SECTION

The turbine is the prime mover for the generator in the power plant Different

types of steam turbines used in thermal power plants, but the ones. Which

are used at G.N.D.T. P. are categorized as follows

S.No. Type of Turbine Turbine at G.N.D.T.P.

1. Horizontal/vertical Horizontal

2. Single/multi cylinder Multi cylinder

3. Condensing/non condensing condensing

4. Reheat/ non-reheat Reheat

5. Regenerative/non regenerative Regenerative

6. With by pas/without by pass with by pass (stage-1)

Without by pass (stage-2)

BASIC WORKING OF TURBINE

First of all the turbine is run on gear motor with the help of exciter. At that

time steam is kept on recirculating with the help of by pass valve. When the

pressure of steam is increased to on optimum level and turbine acquires a

particular rpm then steam is introduced in the H.P. (high-pressure) cylinder

first. The temperature of steam at entrance is 540C and pressure is about

139 Kg/cm2. After doing its work on the H.P. Turbine, the steam is taken out

for reheating rated temperature of steam at reheater inlet is 360 C. The

temperature of steam is increased upto 535C in the boiler shell and steam is

again introduced in M.P (Medium pressure) turbine. After M.P.turbine, the

steam is passed on to L.P. (Low-pressure) turbine. This process helps the

Page 40: Thermal Power Plant Mechanical

turbine to reach the speed of 3000 rpm. After L.P. turbine, the steam is

condensed in condenser, build below the turbine unit. The condenser

contains a number of brass tubes through which cooling out from L.P.

turbine it comes in contact with colder brass tubes then steam get

transformed into water. This water get collected in HOT WELL just below

the condenser. From here the hot water is again pumped with the help of

condensate pumps. The cooling water is used to condense steam gets heated

up and is cooled by falling from cooling tower. This completes the

processing of steam through turbine and condenser.

ROTOR OF TURBINE

All the rotors are manually by means of rigid coupling, including the rotors

of the generator. The speed of whole system of rotor lies in the following

ranges of the speed at the operating conditions: -

1900 to 2000 rpm Best noticed on the M.P. and L.P. rotors and generators.

2350 rpm Best noticed on H.P. rotor.

1. BEARING OF ROTORS

The axial load of the entire system of rotors is taken up by a double-sided

axial bearing located in the bearing stand between the H.P. and M.P casing.

These are two protections mounted near the axial bearing one hydro

chemical and one electromagnetic, which fouls the turboset during the non-

permissible movement of the rotor.

Page 41: Thermal Power Plant Mechanical

The rotors are placed on radial bearing which are machined to elliptical

shape. Further scrapping operations or change top and side clearances and

change in temperature of oil, influence the oil wedge and the position of the

journal bearing to maintain the same condition as existed during the initial

assembly.

In the lower half of bearing a hollow groove is provided in the babbit metal

through which oil the supplied through a drilled hole through H.P. jacking

oil pumps.

The high-pressure oil rotors are lifted in the bearing so that any scrapping of

the bearing is prevented.

2. TURBINE CASING

The high-pressure part of turbine is consisted of two-concentric horizontal

casing. Inner casing is connected in such a way to the other casing that it

enables to expand in all direction. The nozzles are attached to the inner

casing. The steam pipe is connected to the condensers and the condensers

are supported by springs. The casings are inter connected by the system of

guide keys through bearing pedestals in such a way that thermal expansion

of casing does not destroy the various parts of turbine.

The displacement-bearing pedestal between M.P. and H.P parts is measured

by the electromagnetic pick up. This valve is about of 15 mm to prevent

Page 42: Thermal Power Plant Mechanical

deformation at the casing. It is very important that sliding part clean

lubricated and free from hazard for connecting parts bolts elements. The

heating of bolts before tightening up and before the locking presents. The

flanges of M.P. and H.P. casings are designed to heat up by steam during the

starting up of turbo boost by which the difference in temperature between

the cylindrical position of the casing flanges and connected bolts is reduced

to limited deformation. The thermo couples are used for measuring

temperatures. The thermo couple is partially connected to the indicated

apparatus. Cooling fluid is generally used for reducing the temperature of

various parts.

Page 43: Thermal Power Plant Mechanical

3. REGULATION AND SAFETY EQUIPMENT FOR TURBINE

GOVERNING

The quality of steam entering in the turbine is regulated by the four

governing valves on the inlet to the M.P. part. The amount of opening at any

instant of these valves is controlled by the pressure of secondary oil, which

is indirectly depending on the primary oil pressure and directly depending

upon the spring force in the transformer during the stand still and during

starting of the turbo set. The pressure of primary oil is directly depending on

Page 44: Thermal Power Plant Mechanical

the speed of the set through the speed-sensing element. Operating the speed

changer or the normal speed changer can very the tension in the spring in the

transformer.

Thus make it possible to vary the speed before synchronizing. In case break

down of any equipment of the block the quick closing devices are provided

in the regulation system of the turbo set. H.P. quick closing valves

(H.P.Q.C) M.P. quick closing valves (M.P.Q.C) at return flap valves are

operated by either directly by the tripling lever or through the relay magnet

on the main relay which creates instantaneously loss of pressure of the quick

closing oil by the change of flow of oil inside the relay.

Distribution is used for checking the function of H.P.Q.C and M.P.Q.C

valves. The H.P. and M.P quick closing valves, the non return flaps and non

return extraction valves during normal operating condition have only two

positions one is fully opened another fully closed.

4. STEAM CYCLE

The design of the power cycle based on the modern concept, where a unit

consists of a steam generator with its independent firing system tied to the

steam generation. The steam generator is designed for maximum continuous

rating of 375-tonnes/hr. and steam Pressure of 139-kg/cm2 at temperature of

540C respectively. The steam generator is designed to supply to a single

reheat type condensing steam turbine with a 8 non regulated extraction

points of steam for heading the condensate and feed water. The steam cycle

can be classified into the following three divisions: -

(a) Main steam (b) Reheat steam (c) extraction steam

Page 45: Thermal Power Plant Mechanical

(a) MAIN STEAM

Saturated steam from the steam generator drum is led to the super heater

bank to heat if up to 540C saturated steam from the drum is led to the

ceiling super hearter (between SHH1 and SHH2) from ceiling super steam

goes to convection

Page 46: Thermal Power Plant Mechanical

Super heater (between SHH2 and SHH3) the first regulated infection for at

temperature takes place after convection super heater (between SHH9 and

SHH10). Before entry to final super heater the steam is again at temperature

by regulated injection. The steam is coming out from the final super heater

normally at a pressure of 139 kg/cm2 at a temperature of 540oC. This steam

is feed to the control valve. In each of the two live steam lines there is one

Page 47: Thermal Power Plant Mechanical

turbine side main steam stop valve and one high pressure quick closing

valve along with two control valves.

(b) EXTRACTION STEAM

Steam for heating of the condenser and the feed steam is extracted from 8

non regulated extraction points from the turbine. Heating is carried out in

five stages of L.P. heaters, one deareating heater and in two H.P. heaters

extraction 1, 2, 3, is taken from L.P. turbine. Extraction 4, 5, 6 and 7 are

taken from M.P. turbine. Extraction 8 is obtained from C.R.H. line first and

second stage of heating is done by two sets of twin low-pressure heaters

mounted directly in the L.P. casing of the turbine. Extraction 3, 4 and 5 are

connected to the deaereating heater placed above feed water storage tank 7 th

and 8th extraction steam is fed to the vertical H.P. heaters respectively.

(C) REHEAT STEAM

Exit steam from the H.P. turbine is taken back to the reheater section of the

steam generating unit. Reheating is done in two stages both by flue gas and

by super heated steam. The steam to be reheated is first pass through the

triple-heated exchanger, where super heated steam is used as the heating

media. The steam is finally reheated in final reheaters (RHH3) RHH4 and

RHH5) suspended in the horizontal pass of the furnace. Reheat steam at a

normal pressure of 36.4 kg/cm2 at a temperature of 540C respectively is fed

to the M.P. cylinder by two hot reheat steam pipes through strainers and

combined stop and interceptor valves. In each of the cold reheat steam lines

from H.P. cylinder a non-return valve is operated by oil pressure is provided.

Page 48: Thermal Power Plant Mechanical

5. Turbine Accessories and Auxiliaries

I. Surface condenser.

II. Steam jet air ejector

III. LP and HP heaters.

IV. Chimney steam condenser.

V. Gland steam condenser.

VI. Oil purifier or centrifuge.

VII. Clean oil pump with clean oil tank

VIII. Dirty oil pump with clean oil tank.

IX. Auxiliary oil pump with auxiliary oil tank

X. Starting oil pump.

XI. Emergency oil pump.

(I) SURFACE CONDENSER

Two surface condensers are used for condensing the steam which has

worked in the turbine. The coolant for condensing the steam is circulating

water which is inside the condenser brass tubes and steam is outside.

Technical data of Condenser

Cooling Area 3300 msq.

Number of brass tubes 6000

Circulating water required 7500 tonnes/hr.

Vacuum in the condenser 0.90 kg/cm sq.

Page 49: Thermal Power Plant Mechanical

(II) STEAM JET AIR EJECTOR

Starting ejector is used for quick evacuation of the turbo set during starting

whereas main steam jet air ejector is used to maintain Vacuum in the

condenser. It works on the principle of ‘VENTURI’ with steam working

media to eject air from the condenser.

(III) LP AND HP HEATERS

In regenerative system there is a steam of 5 LP heaters, one Deaereator, 2

HP heaters. All LP and HP heaters are of surface type i.e. condensate or feed

water is inside the heater tubes in the heater shells. L.P. heaters are of single

flow whereas HP heaters are of double flow type. Deaereator is contact type

heater in which steam and condensate come in direct contact.

(IV, V) CHIMNEY STEAM AND GLAND STEAM CODENSER: - There

are additional two heating stages provided in the regeneration system of the

turbine for heating the condense flowing through it steam leaks off from the

turbine glands is used for heating the condensate in these heaters.

(VI, VII, VIII, IX, X) VARIOUS OIL PUMPS

Centrifuge is an oil purifier used to remove moisture and other impurities

from the turbine oil. Maximum allowable moisture content in the turbine oil

is 0.2%. In case the oil level of the main oil tank is to be made up then either

oil can transferred from clean oil tank to main oil tank with centrifuge or

from dirty oil tank to main oil tank with centrifuge.

Page 50: Thermal Power Plant Mechanical

(XI) STARTING OIL PUMPS AND EMERGENCY OIL PUMPS

Starting oil pumps supply the necessary turbine oil during starting of the

turbine and upto turbine speed of 2930 rpm till the main oil pump mounted

on the turbine rotor at the HP extension takes manually in order to provide

lubrication oil for the turbo set. Emergency oil pumps are meant to start on

auto, when turbine trips and lubrication oil pressure falls in order to provide

lubrication to the turbine and generator bearings.

MAIN TECHNICAL DATA ABOUT TURBINE

a) The Basic Parameters

Rated output measured at terminal of the generator.

110,000KW

Economical output. 95,000KW

Rated speed 3,000 RPM

Rated temp. Of steam just before the stop valve. 535C

Max temp. Of steam before the stop valve 545C

Rated pressure of steam before the MP casing 31.63 ata

Max. Pressure of steam before the MP casing 35 ata

Rated temp. Of steam before the MP casing 535C

Max. Temp. of steam before the MP casing 545C

(a) System of turbine:

Governing valves 2 interceptor valves

Page 51: Thermal Power Plant Mechanical

HP cylinder 2 Row Curtis wheel +8 moving

wheels.

Wt. of HP rotor is approx. 5,5000kg.

MP cylinder 12 moving wheels.

Wt. Of MP rotor is approx. 11,000kg

LP cylinder 4 Moving wheels of double flow

design.

Wt. of MP rotor is approx. 24,000.

Direction of the turbine rotation is to the right when looking at the turbine

from the front bearing pedestal.

RELAY SECTION

Protective relay is a device that detects the fault and initiates the operation of

the circuit breaker to isolate the defective section from the rest of the system.

We have seen that whenever fault occurs on the power system, the relay

detects the fault and closes the trip coil circuit. This results in the opening of

circuit breaker, which disconnects the faulty section. Thus a relay ensures

the safety of the circuit equipments from damage which may be causes by

the faulty current.

ESSENTIAL ELEMENTS OF A RELAY

All the relays have the following three essential fundamental elements as

shown in block diagram see fig.

(a) Sensing element: - Sensing or measuring element is the element which

responds to the change in magnitude or phase of the actuating quantity e.g.

current in the over current relay.

Page 52: Thermal Power Plant Mechanical

(b) Comparing element: - It is the element which compares the action of

the actuation quantity of the relay with pre-designed relay setting. The relays

only pick up if the actuating quantity is more than the relay setting.

(c) Control Element: - When a relay picks up it accomplishes a sudden

change in the controlled quantity such as closing of trip coil circuit.

1. TYPES OF RELAYS

There are many kinds of relays applied in the power system. The relays can

be designed and constructed. To, operate in response to one or more

electrical quantities such as voltage, current, phase angle etc. The relays are

classified in different ways.

According to construction and principle of operation

(i) Thermal relays: - The heating effect of electric current is used for the

operation of these relays.

(ii) Electromagnetic attraction relays: - The operation of these relays

depends upon the movement of an armature under the influence of attractive

forces due to the magnetic field set up by current flowing through the relay

coil.

(iii) Induction Relays: - Electromagnetic induction phenomenon is used

for the operation of these relays by induction, eddy currents are induced in

the aluminum disc, free to rotate, which exerts torque on it.

2. ACCORDING TO APPLICATION

(i) Over current, over voltage or over power relays:-These relays operate

when the current, voltage or power rises beyond a specific value.

Page 53: Thermal Power Plant Mechanical

(ii) Directional or reverse current relays: - These relays operate when the

applied current assumes a specified phase displacement with respect to the

applied voltage and the relay is compensated for fall in voltage.

(iii) Under current, under voltage or under power relays: - These relays

operated when the current, voltage or power falls below a specific value.

(IV) Directional or reverse power relays: - These relays operate when the

applied voltage and current assumes a specified phase. Displacement and no

compensation is allowed for fall in voltage.

(V) Distance relays: - The operation of these relays depends upon the ratio

of the voltage to the current.

(Vi) Differential relays: - The operation of these relays takes place at some

specific phase difference or magnitude difference between two or more

electrical quantities.

3. According to the time of operation:-

(i) Instantaneous relays:-In these relays, complete operation takes place

instantaneously i.e., the operation is complete in a negligibly small interval

of time from the incidence of the actuating quantity.

(ii) Definite time lag Relays: - In these relays operation takes place after

definite time lag which is independent of the magnitude of actuating

quantity.

(iii) Inverse time lag Relays:–In these relays the time of operation is

inversely proportional to the magnitude of actuating quantity.

Page 54: Thermal Power Plant Mechanical

Inverse Definite Minimum Time Lag Relays: - In these relays, the time of

operation is approximately inversely proportional to the actuating quantity,

but is never less than a definite minimum time for which relay is set.

THERMAL RELAYS

A relay in which heating effect of electric current is used for its operation is

known as thermal relays. These relays may be actuated by a.c. or d.c.

CONSTRUCTION

The schematic diagram of an indirectly heated general purpose thermal relay

is shown in fig. It has a bimetallic strip which is heated by heating element

which gets supply from a current transformer. An insulated contact arm

carrying a moving contact is pivoted and is held by a spring. The other

contact of trip circuit is a fixed contact. The spring tension can be varied by

changing the position of contact arm with the help of sector plate.

Page 55: Thermal Power Plant Mechanical

WORKING

Under normal conditions, the current flowing through the heating element is

proportional to the normal full load current of the circuit. The heat produced

by the heating element, under this condition is not sufficient to bend the

bimetallic strip. However, when fault occurs current flowing through the

heating element increases which produces heat sufficient to bend the

bimetallic strip. This releases the contact arm and because of the spring

tension the relays contacts are closed which closes the trip coil circuit or the

alarm circuit once the alarm circuit or the trip coil circuit is closed; it

operates the alarm circuit or the circuit breaker to open the circuit

respectively.

These over current tripping relays are use mostly for motor controls. The

heating elements of such relays are designed to with stand short time

overload up to 7 times the normal full load.

ELECTROMAGNETIC ATTRACTION RELAYS

Electromagnetic attraction type relays are operated by virtue of an armature

being attracted towards the poles of an electromagnet. These relays may be

actuated by D.C. or A.C. quantities.

Construction

The schematic diagram of an electromagnetic attraction type relay is shown

in fig. It consists of a magnet which carries a relay coil having number of

tapings. The armature is held by the spring attached it. The armature has

spring loaded moving contact which bridges the trip coil circuit.

Page 56: Thermal Power Plant Mechanical

Working

Under normal conditions, the current flowing through the relay coil is such

that spring tension is more than the attractive force of the electromagnet.

Therefore armature is held in the open position. However when fault occurs,

current flowing through the relay coil increases. This increases the attractive

force of the electromagnet. At the instant when attractive force of

electromagnet is more than the spring tension, the armature is tilted down

wards and moving contact bridges the fixed contacts. This closes the trip

coil circuit.

The current setting can be adjusted by changing the number of turn of relay

coil. The larger numbers of turns are introduced in the operating coil, the

smaller is the value of actuating current. The time setting can adjust by

changing the tension of spring by a screw. Terminal AC act as normally can

also be used for the operation of another circuit.

Page 57: Thermal Power Plant Mechanical

INDUCTION RELAYS

The basic principle of operation of these relays is electromagnetic induction.

These relays are only actuated by a.c. An induction relay essentially consists

of a pivoted aluminum disc place in between two alternating fields of the

same frequency but displaced from each other by some angle. A torque is

produced in the disc by the interaction of two fields. Such relays may be

over current reverse power or directional over current relays as discussed in

the coming articles.

INDUCTION TYPE OVER CURENT RELAY

Construction

An induction type over current relay is shown in fig. 5 (a) it consists of an

aluminum disc which is free to rotate to be placed in between the two

electromagnets. The upper magnet has three limbs whereas lower magnet

has two. The tapped winding is wound on the central limbs of the upper

magnet. This winding is connected to the CT of the line to be protected. The

tapings one connected to a plug setting bridge as shown in fig.5 (a) by

changing the position of plug by which the number of active turns of the

primary winding can be varried, thereby the desired current setting is

obtained. The secondary is a closed winding and wound on the central limb

of the upper magnet and both the limbs of the lower magnet. The winding is

energized by the primary winding.

The controlling torque is provided by connected a spiral spring on the

spindle of the disc. The spindle of the disc also carries a moving contact,

when the disc rotated through a preset angle, the moving contact bridges the

two fixed contact of the trip coil circuit as shown in fig.5 (b). The preset

Page 58: Thermal Power Plant Mechanical

angle can be adjusted to any value between O and 360, by adjusting the

angle, the travel of the moving contact can be adjusted and the relay can be

set for any desired time setting.

Working

When current flows through the primary winding, an e.m.f. is induced in the

secondary winding by induction. Since secondary is closed, a current flows

through it. The fluxes are produced by the currents flows through primary

and secondary winding. These fluxes are separated in phase and space and

produces a driving torque on the disc. This torque is opposed by the

restraining torque provided by the spring. Under normal conditions, the

restraining torque is more than the driving torque, therefore, the disc

remains stationary.

However when a fault occurs, the current flowing through the primary

exceeds the preset value. The driving torque becomes more than the

restraining torque consequently the disc rotates and moving contact bridges

the fixed contacts when the disc rotates through a pre-set angle.

Specification of over current relay

S.No. M292523

Model NO. CDG 31EG 1212 A5

Type Auxiliary voltage 220V d.c.

Manufacturer Jyoti Ltd. Baroda.

Page 59: Thermal Power Plant Mechanical

Spending Our six months of training in Guru Nanak Dev Thermal Plant, Bathinda, We

concluded that this is a very excellent industry of its own type. They have achieved

milestones in the field of power generation. They guide well to every person in the

industry i.e. trainees or any worker. We had an opportunity to work in various sections

namely switch gear, Boiler section, Turbine section, EM-2 CELL etc. while attending

various equipments and machines. We had got an endeverous knowledge about the

handling of coal, various processes involved like unloading, belting, crushing and firing

of coal. The other machines related to my field that We got familiar with boiler, turbine,

compressors, condenser etc. We found that there existed a big gap between the working

in an institute workshop and that in the industry. Above all the knowledge about the

production of electricity from steam helped me a lot to discover and sort out my problems

in my mind related to the steam turbine, their manufacture, their capacity, their angle of

blades and their manufacturing. The training that We had undergone in this industry will

definitely help me to apply theoretical knowledge to the practical situation with

confidence.

CONCLUSION

CONCLUSION

Page 60: Thermal Power Plant Mechanical

1. A Textbook of electrical technology (A.C & D.C Machines) – B.L.THERAJA, A.K.THERAJA

2. A course in electrical power: - J.B.GUPTA

3. A course in electrical & electronic measurement and instrumentation: - A.K.SAWHNEY

4. A course in electrical power: - M.L.SONI, P.V.GUPTA

5. A textbook of power plant engineering: - Er. R.K.RAJPUT

6. www.wikipedia.com

7. www.sensorland.com

8. Manual of GURU NANAK DEV THERMAL PLANT, BATHINDA.

BIBLIOGRAPHY

BIBLIOGRAPHY

Page 61: Thermal Power Plant Mechanical

ACKNOWLEDGEMENT

I am really grateful and convey my deep sense of gratitude and

appreciation to the officers/officials at G.N.D.T.P. BATHINDA for their

valuable guidance and unstinted co-operation throughout this summer

training. We would like to thank Er. T.N BANSAL ADD. S.E at

G.N.D.T.P BATHINDA for providing us an opportunity to work under his

thorough guidance and critical intervention during our training . Most of all

we wish to thank Er. Ravinder Pal Singh (T.T. Cell) for their valuable

help in providing relevant data and all the logistic facilities which have

contributed immensely towards the smooth progress and preparation of this

report.

Sukhjinder Singh 008545335630

Mechanical Engineering

Page 62: Thermal Power Plant Mechanical

TRAINING REPORT OF

45 DAYS INDUSTRIAL TRAINING REPORT

AT

THERMAL POWER PLANTBATHINDA

SUBMITTED BYSUKHJINDER SINGH

008545335630

Mechanical Engineering

G.G.S.C.E.T. TALWANDI SABO

SUBMITTED TO

TRAINING CELL

G.N.D.T.P, BATHINDA