Upload
jack-halpern
View
63
Download
3
Embed Size (px)
Citation preview
Paralleling Existing Rights-of-Way for Congested Areas
Jack Halpern Power Sector Leader-Environmental Services
19th Annual Transmission Summit 2016 March 31, 2016
Preference Approach for Siting in Congested Areas 1. Upgrade or double
circuit an existing line 2. Parallel an existing
line 3. Parallel roads,
railroads and pipelines 4. Green field solutions
Paralleling Situations • Entirely on existing ROW • Existing ROW /
overhanging adjacent land
• Adjacent existing ROW / overhang existing ROW
• Entirely adjacent land abutting existing ROW
Parallel Existing Transmission- Issues • Voltages • Crossing Restrictions • Substations • Adjacent Lands
Development • Accessibility Issues • ROW Acquisition Issues
Parallel Transmission Lines- Negatives • Induced voltage in a transmission line due to its
proximity to another transmission line can occur • Reduced reliability - Tornados, aircraft, fires,
sabotage, wind gust, and wet snow • Possible increase in impacts to agricultural
operations. • New double-circuited structures may be taller • Transmission lines in close proximity and parallel
to a distribution line can contribute to stray voltage issues.
Parallel Transmission Lines- Positives • Reduced right of way costs • Reduced environmental impacts • Simplified permitting • Reduced opposition by adjacent landowners • Existing access roads
Parallel Existing Roads- Issues • Interstate highways, primary roads & local roads • Overhead and underground • Bridges, tunnels and cut/fills • Adjacent Lands Development o Bill boards o Cell Towers
• Accessibility Issues • ROW Acquisition Issues • Construction issues
Some State Actions • Minnesota. Stat. §216E.03, subdivision 7: The commission
must make specific findings that it has considered locating a route for a high-voltage transmission line on an existing high-voltage transmission route and the use of parallel existing highway right-of-way and, to the extent those are not used for the route, the commission must state the reasons
• Maine’s Energy Infrastructure Interagency Review Panel (IRP) is accepting letters of intent for the possible use of state-owned I-95 and I-295 as corridors for electric transmission, according to an Oct. 9 2012 statement from Gov. Paul LePage
Fargo-St. Cloud 345 kV project
• Pennsylvania, Virginia, and Illinois: o Longitudinal occupation of limited access
highways not permitted o Perpendicular crossings and some very limited
conditions for longitudinal occupancy are sanctioned under very specific criteria
Some State Actions
Utilities have right by law to occupy highway ROW. Public utilities considered for permission to longitudinally occupy limited access highway ROW when demonstrated extreme cases need exist, shown best public interest and safety criteria can be met:
Accommodation not adversely affect the design, construction, operation, maintenance, or stability of the limited access highways A utility demonstrate alternate locations not available or cannot be implemented at reasonable cost Not interfere with or impair the present use or future expansion of limited access highways The public utility facility shall be placed underground; The public utility facility shall present no hazard to life, health or property, if it fails to function properly, is severed, or otherwise damaged; and After the public utility facility is installed, it will be virtually maintenance free.
Some State Actions – New Jersey
Parallel Railroads - Issues • Mainlines, secondary lines • Unused or recently abandoned right-of-way • Signaling and train control facilities • Sidings, branches and yards • Fiber optic lines • Bridges, tunnels, cuts/fills • Adjacent Lands Development • Accessibility Issues • ROW Acquisition Issues • Construction issues
Parallel Railroads – Negatives • Some RR ROWs have long distances between road
crossings and additional access roads would be needed • Railroad corridors that pass through wetlands are
generally berms that too narrow to support transmission structures, resulting in additional impacts to wetlands.
• Communication signals used by railroads can be affected by electromagnetic fields
• Electrical induction in rails can interfere with proper operation grade crossing control equipment/track-connected signal equipment.
• Foundation vibrations
Parallel Pipelines - Issues • Mainlines, secondary lines • Valves, cleanouts and compressor stations • Ownership issues • Adjacent Lands Development • Accessibility Issues • Electric cathodic protection • ROW Size/Acquisition Issues • Construction issues
Parallel Pipelines - Negatives • Pipeline ROWs often run cross-country with little
or no visual or agricultural effects • Transmission lines constructed cross-country can
interfere with farm operations and produce a negative visual impact
• For reasons of safety gas pipelines often require transmission line ROW to parallel the pipeline ROW with no or very minimal overlap-minimizes any potential benefits of corridor sharing
• Separation Distance-Severity Ranking of HVAC Interference o Distance less than 100 feet- High o 100 to 500 feet- Medium o 500 to 1,000 feet- Low o 1,000 to 2,500 feet- Very Low
• Collocation Length- Relative Severity o Length greater than 5,000 feet- High o 1,000 to 5,000 feet- Medium o Less than 1,000 feet- Low
INGAA – Criteria for Pipelines Co-Existing with Electric Power Lines *
*October 2015
CONCLUSIONS ON PARALLELING LINEAR FEATURES • THERE IS NO STANDARD CONCLUSION • INDEPENDENT OF SITING MODEL USED • EACH PARALLEL CASE MUST BE REVIEWED
SEPARATELY AS TO ITS OVER- ALL IMPACT ON: o Human Environment o Natural Environment o Reliability of the Grid o Engineering Variances o Project Costs
Jack Halpern Power Sector Leader-Environmental Services Stantec Consulting Services [email protected] 561.212.2282
Any Questions?
Contact Information