Ugm Presentation

  • Upload
    shah241

  • View
    237

  • Download
    0

Embed Size (px)

Citation preview

  • 8/12/2019 Ugm Presentation

    1/20

    16asd

    1

    The Development of an AutomationProject

    Team:

    K. Ha2

    A. Kroetsch1

    J. Mora2

    A. Puri1

    E. Rubin3J. Valente2

    V. Vydra3

    W. Ying1

    1: DPST, 2: ABD, 3: LPCD

    Jaquan K. Levons

  • 8/12/2019 Ugm Presentation

    2/20

    26asd

    2

    Outline

    Statement of Purpose

    Peer Benchmark, Lessons Learned

    Process Followed for Automation Project

    Mapping

    Scope Value Calc.

    Ability To Execute

    Testing

    Hardware and Workflow Summary Timeline

  • 8/12/2019 Ugm Presentation

    3/20

    36asd

    3

    Peer Benchmarkingof Aseptic Formulation Automation

    Better implementation and testing to prevent 12 month + deployment

    Ensure dedicated FTE with management support

    Simpler workflows w/ less emphasis on integrated analytics

    Integrated analytics problematic in deployment

    Critical to develop appropriate testing plans (FAT & SAT) to ensureworkflow w ill operate as anticipated.

    Feedback from industry peers regarding recent deployments ofsimilar automated workflows provided some guidance on lessons

    learned.

  • 8/12/2019 Ugm Presentation

    4/20

    46asd

    4

    Ability to Execute Criteria

    Money for CapEx andrecurring OpEx (hrdwr &sftwr maint,consumables,contractors, annualqualification)

    Funding

    Laboratory facilities tosupport the newworkflow and proximityto users, collaboratorsand virtually integratedequipment

    Facilities

    ROI that meetsorganizational needs andwhich can be measured

    Value measures =Productivity, Throughput,Quality, Safety,Compliance

    ValueMeasures

    Impl. team in place todeliver the project

    Operational execution

    and support model toensure sustainablebenefits realization

    Teams

    Complete requirementsand testing criteria thatalign to functional area

    workflows and valuemeasures

    Requirements

    Availability & quality oftechnology to fulfillrequirements

    Technology

    4

  • 8/12/2019 Ugm Presentation

    5/20

    56asd

    5

    Value Measures

    Aseptic Technology Automation Value

    Productivity

    Support screening of the current

    portfolio and new Projects without

    the addition of FTE

    Throughput 3X more samples per project with noadditional material requirement

    Reduced Cycle

    Time

    Conduct 4 mo Of IND tox formulation

    development screening in 3 mo

    Quality

    Variability in execution

    Variability in designConsistency of experimental data

    interpretations and conclusions

    SafetyContainment (sample sterility)

    Exposure

    Definitions:

    Productivity - Number of studies/ projects/

    compounds executed per FTE

    Throughput Number of samples/conditionsprocessed per unit time/study

    Cycle Time Duration of a study or activity

    from initiation to completion

    (Data) Quality Accuracy, consistency of data

    and data interpretation

    Safety Risk of interaction with scientist due to

    pharmacological activity or lab process.

  • 8/12/2019 Ugm Presentation

    6/20

    66asd

    6

    Process

    1.Scoping Activities1. Define business objectives

    2. Generate Current State workflow process maps to identifyopportunities/gaps

    3. Draft Future State Process Maps

    4. Develop Value Proposition (ROI Calculations/Business

    Justification)5. Define requirements for budgetary estimate and Obtain

    budgetary estimate

    6. Deliver Workf low Proposal w/ROI & cost estimate forManagerial Approval

    2. Procurement Activities1. Obtain spend approval

    2. Engage Global Procurement to obtain vendor proposals

    3. Obtain approvals to spend, CAR, PO

    Project-Prosecution-TimelineActivities-24Sept2012.vsd

  • 8/12/2019 Ugm Presentation

    7/20

    76asd

    7

    Process Execution Activities

    3. Execution Activit ies

    1. Develop User Requirement Specifications (URS)

    2. Develop/Build Automated Workflow

    3. Factory Acceptance Testing (FAT)

    4. Shipment/Delivery/Installation

    5. Site Acceptance Testing (SAT)

    6. End-User Training

    7. Metrics Collection (monitor ROI)8. Establish workflow maintenance & support

    9. Engage asset management &/or PDI

    Project-Prosecution-TimelineActivities-24Sept2012.vsd

  • 8/12/2019 Ugm Presentation

    8/208

    6asd8

    Statement of Purpose

    Aseptic Technologies established objectives to:

    1. Meet the demand of an increasing number of biologics projects requiring formulationdevelopment in BMS

    2. Increase drug product robustness by enabling QbD in formulation development

    3. Expedite formulation development of incoming Pearls

    4. Facilitate down stream processing with supportive data packages

    5. Enable Fast to Phase I for biologics

    The Aseptic Technologies group needs to manage constraints from:

    1. Limited drug substance availability in early stage screening

    2. Limited quality outsourcing opportunities

    3. Limited headcount additions

    An automated biologics formulation workflow is targeted at enabling:

    1. Productivity increases in screening workflows2. Increased throughput in formulation stability screening to enable QbD

    3. Develop a workflow facilitating initial process robustness data package generation

    4. Reduced cycle time and miniaturized experiments during phase I formulationexploration

  • 8/12/2019 Ugm Presentation

    9/2096asd

    9

    Formulation Development: High-Level Overview

  • 8/12/2019 Ugm Presentation

    10/20106asd

    10

    Formulation Development: Future State Workflow

  • 8/12/2019 Ugm Presentation

    11/20116asd

    11

    Scope

    Automation WorkflowsTargeted:

    Asept ic TechnologyWorkflows Supported:

    Early Stage: Formulationscreening Pre-FIH, platformenabling, analytics on-deck inline

    Late Stage: Compounding highconcentration API, multi-excipientliquid preparations

    Initial Process Robustness DataPackage: (viscosity,

    concentration as a function oftemperature)

    Formulation stability samplepreparation

    Sample processing for analysis

    Formulation physical propertycharacterization (viscosity, pH,concentration as a function of

    temperature)

    Enables

  • 8/12/2019 Ugm Presentation

    12/20126asd

    12

    Value Estimations: Productivity Calculations

    Use process map to identify key activit ies and estimate time required for execution in the current state (collectingdata from peers) and future state.

    Productivi ty savings measured in the amount of scientist time saved, and is the product of:

    Number of scientists typically working on an activit y

    Number of hours of scientist time required

    Probability that thi s action will need to be executed as part of this w orkflow .

    Perform macroscopic calculation to ensure numbers are consistent with actual expenditures.

    Early Formulation Screening Scenario w/o

    Platform

    Current State Future State

    # of Scientists

    Activity Time

    (hours)

    Workflow

    Percentage

    Total Scientist Time

    (FTE-hrs)

    Total Scientist Time

    (FTE-hrs)

    [FTE*TIME*PERCENT]

    1

    Receive drug substance in native

    buffer 0 0 100 0 0

    2 Preparation for Buffer Exchange 1 6 100 6 2

    3 Buffer Exchange 2 10 100 20 2

    4 Concentration 1 4 25 1 4

    5 Add/Spike Excipients 2 8 100 16 4

    6 Prepare sterile area for filling 1 4 100 4 2

    7 Sterile Filtration 2 2 100 4 2

    8 Packaging 1 6 100 6 4

    9Move samples to stresstemperature incubators 2 1 100 2 1

    10 Pull samples and analytical prep 1 20 100 20 10

    11

    Analysis, Documentation, Study

    Planning 2 20 100 40 30

    Total 1 Tier of Formulation Screening 119 61

    49%

    Percent Savings**All Values Are Examples to Illustrate Calculations Only,

    and are not Representative of the Actual Scenario**

  • 8/12/2019 Ugm Presentation

    13/20136asd

    13

    Value Estimations: Throughput & Cycle Time

    Use process map to identify key activiti es and estimate time required for execution in the current state (collectingdata from peers) and fut ure state.

    Number of condit ions tested based on material constraints (e.g. 100 mg of drug substance), instrument cons traints

    (e.g. > 100 L sample si ze), and st udy design in the future state. Number of tiers of screening impacts the cycle time.

    Multiple tiers can be due to either a lack of throughput or need for information (e.g., optimal pH region).

    Excess tiers due to lack of throughput can be minimized by a higher throughput futu re state.

    Due to higher throughput, may be able to incorporate additional info rmational studies earlier and eliminatesequential tiers as well.

    Perform macroscop ic calculation to ensure numbers are consistent with actual expenditures.

  • 8/12/2019 Ugm Presentation

    14/20146asd

    14

    Projected Return on Investment Key Metrics

    FTE Savings: New workflow conducts the same work with fewer number of people

    required.

    Enables redeployment of FTEs to higher value added work

    FTE Avoidance New workflow conducts additional work which would have required hiring

    additional people instead.

    Enables generation of data previously unavailable.

    Financial Return Can be presented as financial value of FTEs saved/avoided minus

    depreciated value of investment and recurring costs of workflow.

    Often does not incorporate hard to quantify value propositions such asincreasing the value of a formulation. These can be identified separately.

  • 8/12/2019 Ugm Presentation

    15/20156asd

    15

    Projected Return on InvestmentVariables Future State Assumptions

    Screening Projects 10 *Estimation for demonstration purposes only

    Productivity w/Automation 200%

    *Workflow analysis suggests ca. 50% productivity savings for screening

    activities for projects where automation is applied.

    FTE required to conduct manually 15

    *1.5 FTE required during screening activities of each project. 1.5 FTE * 10

    projects = 15 FTE.

    FTE required to conduct

    w/automation 10.5

    *Amount of FTEs required to execute 8 projects with automation and 2

    project(s) manually considering 200% productivity when automation is

    leveraged with 1.5 dedicated FTE.

    FTE Savings 4.5 *15-10.5=4.5

    Experimental Space w/Automation 200

    *8-12 compositions in each of 10 tiers screened in the current state,

    compared to 32 compositions in each of 6 tiers where automation is applied

    in the future state. Initial analysis done primarily on early stage screens, butis applicable broadly across screening activities.

    FTE Avoidance 6.0

    *Amount of FTEs required to execute the additional experimental space

    (for 8 projects) manually instead of with automation. Incorporates an

    engineering factor of 0.5 acknowledging that it may not take twice as

    many people to conduct twice the work.

    Recurring Costs $0.7 MM/yr

    *Instrument cost depreciated (typically over 7 or 10 years) + maintenance

    costs and consumables

    FTE Savings & Avoidance $1.8 MM/yr *$175k/yr times (FTE savings + FTE avoidance)

    Return/yr$1.1 MM/yr

    *FTE Savings + Avoidance - Recurring Costs

    **All Values Are Examples to Illustrate Calculations Only,

    and are not Representative of the Actual Scenario**

  • 8/12/2019 Ugm Presentation

    16/20166asd

    16

    Key Aspects of Requirements

    Flow of samples/materials in automated workflow

    Accuracy of key quality attributes of final material (e.g., potencyaccuracy and precision, buffer pH, etc.)

    Functional specifications of key unit operations

    Volume transfer accuracy and precision

    Dilution accuracy and precision

    Manipulation of materials up to at least = 100 cp

    Consider expected environmental conditions

    Temperature not to exceed 25 C during processing

    Enclosure capable of class 100 conditions

    Consider sterility management

    Stoppering/Destoppering needed

    Minimize human interaction with samples

    Consider expected data management

  • 8/12/2019 Ugm Presentation

    17/20176asd

    17

    Key Aspects of Testing (FAT/SAT)

    Test an entire run of the workflow with materials that span the

    properties of actual materials you w ill use. Note: one successful execution may not be indicative of

    robustness

    Throughput should be similar to expected production throughput.

    develop test p lan that will test crit ical parameters to your workflow

    liquid transfer accuracy and precision, abili ty to deliver & measure viscosi ty of concentrated protein

    solutions

    Throughput how will the workflow handle source reagents andconsumables during execution

    Include a test of the full workflow execution. Mimic a real-life orproduction run to fully understand how the system will operate andgain understanding of constraints

    Consider developing tests to gain understanding of system robustnessin an time constrained environment like FAT or SAT

  • 8/12/2019 Ugm Presentation

    18/20186asd

    18

    Ability To Execute

    18

    Status

    Ability To Execute

    Funding Funding allocated from Strategic Initiatives Budgetover 2 years.

    FacilitiesAT Automation Lab Renovation underway, available

    ca. 3Q/2013. Available facilities aligned with

    proposed acquisition.

    Value Measures$ca. MM/yr net savings projected.

    Teams

    Cross-functional team evaluated solutions,

    developed ROI, refined requirements, and will

    support implementation.

    1 dedicated FTE required for operation/execution.

    Requirements

    Rigorous requirements developed by cross functional

    team and agreed upon with vendor. Custom

    acceptance tests developed to ensure delivery of

    requirements.

    Availability of Technology

    Solutions

    Vendors biologics formulation technology deployed

    at other competitors. Substantial internal experience

    with vendor technology. New BMS-based workflows

    to be added to the technology.

    *Projected PO Approval June 30th, 2013

    *2 Phase delivery, first acquisition Jan 2014

  • 8/12/2019 Ugm Presentation

    19/20196asd

    19

    Acknowledgements

    Core Team

    Andrew Kroetsch - DPST

    Aastha Puri DPST

    Joe Valente - ABD

    Vicky Vydra LPCD

    William Ying DPST

    Acknowledgements

    Chris Sinko

    Nancy Barbour

    Rajesh Gandhi

    Farah Kahn

    John Brunei

    Ed Hensler

    Krishnaswamy Raghavan

    Andy Stewart

    Freeslate Organizers

    Dave Yamane

    Carole Garner

    Paul Digregorio

    MVLA Strategic Initiative

    Erik Rubin - LPCD

    Johanna Mora ABD

    Khanh Ha ABD

  • 8/12/2019 Ugm Presentation

    20/20

    6asd

    Happily Ever After

    *Representative image of instruments after phase 1 and 2 deployment