18
Update on the Superfund Program: U.S. Tour de Table NATO SPS Pilot Study Prevention and Remediation in Selected Industrial Sectors June 17-23, 2006 Ljubljana, Slovenia Walter W. Kovalick, Jr. Ph.D. [email protected]

Update on the Superfund Program: U.S. Tour de Table

  • Upload
    clove

  • View
    40

  • Download
    1

Embed Size (px)

DESCRIPTION

Update on the Superfund Program: U.S. Tour de Table. NATO SPS Pilot Study Prevention and Remediation in Selected Industrial Sectors June 17-23, 2006 Ljubljana, Slovenia Walter W. Kovalick, Jr. Ph.D. [email protected]. Progress Cleaning up Superfund Sites. - PowerPoint PPT Presentation

Citation preview

Page 1: Update on the Superfund Program: U.S. Tour de Table

Update on the Superfund Program: U.S. Tour de Table

NATO SPS Pilot StudyPrevention and Remediation in Selected

Industrial SectorsJune 17-23, 2006

Ljubljana, Slovenia

Walter W. Kovalick, Jr. [email protected]

Page 2: Update on the Superfund Program: U.S. Tour de Table

Progress Cleaning up Superfund Sites

Page 3: Update on the Superfund Program: U.S. Tour de Table

Remaining Sites Are More ComplexSites That Have Not Completed Remedy Construction

Have More Operable UnitsAverage Number of Operable Units per

Site

1.8

4.3

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

5

CC not CC

ave.

# o

f Ope

rabl

e Un

its

Page 4: Update on the Superfund Program: U.S. Tour de Table

Remaining Sites Are More Complex Sites completed after 2001 required greater EPA resources per

site.

Cost Distribution 1981-2000

More than $5m

15%

$1m - $5m32%

$0 - $1m53%

Cost Distribution 2001-2006

$1m - $5m26%

$0 - $1m35%

More than $5m

39%

* EPA Costs Only

Page 5: Update on the Superfund Program: U.S. Tour de Table

14 Sites Used 45% of Construction Resources in FY 2006

What is the Nature of these“Megasites”?

*

* Note that several manufacturing sites have impacted fluvial systems resulting in major river sediment cleanup projects (Hudson, Fox, etc).

Page 6: Update on the Superfund Program: U.S. Tour de Table

Cleaning Up Sediment Sites under Superfund

• Selected a remedy at over 150 sediment sites – as of September 2005– 11 considered mega sites (cost for sediment remedy exceeded

$50 million) • Approximately 50 other sites with ongoing sediment

investigations – Expect some to become mega sites

• Tracking cleanup progress on roughly 60 “Tier I” sites – Remedy has been selected, and – Includes dredging or excavation of at least 10,000 yd3, or

capping or monitored natural recovery of at least 5 acres

http://www.epa.gov/superfund/resources/sediment/

Page 7: Update on the Superfund Program: U.S. Tour de Table

Nature of the “Tier I” Superfund Sediment Sites*

• Over 1/2 are rivers/streams and about 1/3 are wetlands • PCBs drive risk at 1/2 the areas, while metals at 1/3, and

PAHs at 1/5 of the areas • Dredging or excavation is sole remedy at 30 sites, while

1/3 included capping and/or MNR in addition to dredging or excavation. Capping or MNR alone were selected at

< 10% of the sites, but MNR is frequent component • The volume of sediment removed < 50,000 yd3 at 1/2 of

the areas, while > 1 million yd3 at 10% • The number of areas dredged vs. excavated were about

the same; at almost 1/2 of these areas, a thin layer of sand was used to backfill

• Caps range in size from less than 1 acre to 430 acres, but most are between 10 and 70 acres.

*Data is further broken down for 98 areas within the 60 Tier I sites

Page 8: Update on the Superfund Program: U.S. Tour de Table

EPA Continues to Enforce “Polluter Pays” Principle

General revenues and cost recoveries are currently the Trust Fund’s largest revenue sources, in addition to fines and penalties and interest. The Trust Fund (Superfund) stands at about $3 B.

Just from 2006 enforcement efforts, parties held responsible for pollution will invest $391 million for cleanups of contamination from up to 15 million cy of soil and 1.3 billion cy of groundwater at waste sites.

In addition to penalties paid in 2006, regulated entities will also be required to invest $4.9 billion to reduce pollution and achieve compliance with environmental laws.

Page 9: Update on the Superfund Program: U.S. Tour de Table

Superfund Site Reuse: Beyond CleanupRedevelopment at Superfund sites has resulted in nearly 80,000 on-

site jobs, $2.7 billion in annual income and more than 244,000 acres of land in reuse or made ready for reuse

Approximately 550 Superfund sites are ready for reuse, or have already been returned to productive uses

• 56 sites in ecological use• 50 sites in residential use• 68 sites in recreational use• 21 sites in agricultural use• 40 sites in public service use• 117 sites in commercial use• 108 sites in industrial use.

Wide Beach Development in Brant,

New York

Page 10: Update on the Superfund Program: U.S. Tour de Table

T r eatment of a Sour ce Only (182)12%

T r eatment of Gr oundwater Only (358)23%

Containment or Off -Site Disposal of a Sour ce (189)12%

Other Sour ce Contr ol (47)3%

No Remedy Decision (215)14%

T r eatment of Both a Sour ce and Gr oundwater (428)

27%

No Action or No Fur ther Action (91)6%

Non-T r eatment Gr oundwater Remedy (47)3%

Remedy Types at NPL Sites 1982-2005, 1557 Sites

Treatment 62%

No Decision 11%

Containment and Other 27%

Page 11: Update on the Superfund Program: U.S. Tour de Table

Solidification/Stabilization (21)

17%

Thermal Desorption (9)7%

Bioremediation (8)6%

Physical Separation (5)4%

Other Ex Situ (8)6%

Soil Vapor Extraction (27)21%

Multi-Phase Extraction (13)

10%

Chemical Treatment (12)10%

Other In Situ (6)5%

Solidification/Stabilization (7)

6%Bioremediation (5)4%

In Situ Thermal Treament (5)

4%

Ex Situ Technologies (51) 40%

In Situ Technologies (75) 60%

Recent Source Control Treatment Projects 2002-2005 RODS - Total of 126 ( Prelim. Data)

Other Ex Situ (8)Incineration (off-site) - 3Open Burn/Open Detonation - 3Chemical Treatment - 1Neutralization - 1

Other In Situ (6)Mechanical Soil Aeration - 2Phytoremediation - 2Flushing - 1Neutralization - 1

Page 12: Update on the Superfund Program: U.S. Tour de Table

In Situ Technologies for Source Control

31% 31%

17%

28%

47%

36%

48%

38%

43%45%

37%

60%

56%

47%

57%

49%

63%

52%

79%

44%

78%

10%

20%

30%

40%

50%

60%

70%

80%

90%

1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005

Fiscal Year

Perc

enta

ge o

f Sou

rce

Trea

tmen

t Pro

ject

s

Percentage of Source Treatment Technologiesthat are In Situ

Linear Trendline (In Situ Source TreatmentProjects)

Page 13: Update on the Superfund Program: U.S. Tour de Table

Progress in GW Treatment TechnologiesThen: Groundwater Remedies Through ‘97

(ASR 9th Edition) Total Sites = 663

Sites with In Situ Treatment Only (39) 6%

Sites with Pump-and-Treat Remedies Only (588) 89%

Sites with Pump-and-Treat and In Situ

Treatment (36) 5%

Sites with Pump-and-Treat only (588) 89%

Page 14: Update on the Superfund Program: U.S. Tour de Table

Now: Sites with P&T, In Situ Treatment, or MNA as Part of a Groundwater Remedy

(ASR 12th Edition) Total Sites = 881

P&T Only (488)55%

P&T and MNA (71)8%

P&T and In Situ (114)13%

In Situ Only (37)4%

P&T, In Situ, and MNA (58)

7%

In Situ and MNA (18)2%

MNA Only (95)11%

Page 15: Update on the Superfund Program: U.S. Tour de Table

In situ Groundwater Remedies in Superfund

0%

5%

2%

6%

11%

9%

16%

22%

18%

28%

24%

9% 9%

5%3%

28%

17%16%

26%

31%

0%

5%

10%

15%

20%

25%

30%

35%

86 87 88 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05*

Fiscal Year

Perc

enta

ge o

f All

Gro

undw

ater

RO

Ds

RODs Selecting In Situ Treatment for GroundwaterLinear (RODs Selecting In Situ Treatment for Groundwater)

*RODs and Amendments are included in this figure. As of October 2006, 74% of FY 2005 RODs and Amendments were available.

Page 16: Update on the Superfund Program: U.S. Tour de Table

Advancing Knowledge of the State of the Practice

Page 17: Update on the Superfund Program: U.S. Tour de Table

• Cluin.org – 130,000 visits a month• Free Internet Seminars – 60,000

participants• TechDirect – 30,000 subscribers • Publications, hard copy or download• Technology databases

http://cluin.org

Page 18: Update on the Superfund Program: U.S. Tour de Table