Upload
delila
View
26
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Columbia-Snake River System Extended Navigation Lock Outage December 2010 – March 2011. Portland & Walla Walla Districts . - PowerPoint PPT Presentation
Citation preview
BUILDING STRONG®
US Army Corps of EngineersBUILDING STRONG®
Portland & Walla Walla Districts
Columbia-Snake River System Extended Navigation Lock OutageDecember 2010 – March 2011
Matt Cutts, P.E., CFMCritical Infrastructure Program ManagerPortland District , U.S. Army Corps of Engineers
Pacific Northwest Waterways Association2011 Mid-Year Meeting June 27, 2011
1
BUILDING STRONG®2
BUILDING STRONG®
Overview Coordination started 18 months before the outage. Estimated 12-16 week outage, took 15 weeks. Timing arranged to minimize impacts as much as possible. Locks had to be open by 1 April to allow Fish Barging per BiOp. Main Commodities affected:
► Wheat► Fuel/gas transport up river► Garbage► Commercial - recreation cruise liners
3
BUILDING STRONG®
Outage Work Plan Bonneville: Routine maintenance & emergency repair The Dalles: Downstream gate replacement John Day: Downstream gate & sheave replacement McNary: 5 Year Lock inspection and maintenance Ice Harbor: Downstream Gate picking eye repair Lower Monumental: Downstream gate replacement,
Phase 2 concrete repairs Little Goose: Routine maintenance Lower Granite: Upstream & downstream gate repairs
4
BUILDING STRONG®
Damaged Top Girder (both leaves)
Damaged Diagonals (both leaves)
Bonneville Dam Navigation Lock Upstream Gate Emergency Repair
5
BUILDING STRONG®
The Dalles Navigation Lock Outage
The downstream gate and both pintle bearings were replaced
Dix Corporation of Spokane, WA was the prime contractor
Subcontractor Thompson Metal Fab was the steel fabricator, along with Oregon Iron Works
Fabrication started in April 2010, completed by Feb 2011
6
BUILDING STRONG®
The Dalles old gate removal
7
BUILDING STRONG®
The Dalles gate hardware
8
BUILDING STRONG®
John Day Navigation Lock Downstream gate & sheave replacement
Replaced downstream gate & friction sheaves Prime: Advanced American Construction Subcontractor: Oregon Iron Works of Clackamas Fabrication: Dec 2009 - Oct 2010
9
BUILDING STRONG®
McNary Navigation LockOutage Duration 6-Weeks Routine work 5 Year Major Inspection Detailed maintenance and
lubrication Repair work
Non Routine work Rehab stop logs Replace Tainter Valve Trash
Racks Repair Navlock Armor steel
Completed Rehab of Navlock Cranes
10
BUILDING STRONG®
McNary: 5 Year Inspection
11
BUILDING STRONG®
Ice Harbor Navigation Lock
Outage Duration 9-Weeks Routine Work:
5 Year Major Inspection Detailed maintenance and
lubrication Repair work
Non-Routine work D/S Gate Cable/
Connectors - included cable replacement. Scheduled but not completed.
12
BUILDING STRONG® Longitudinal cracks in top slab of culvert Large crack in joint between top slab &
sides.
Collapse of concrete into culvert
Ice Harbor: Emptying Lateral Damage Damage found after unwatering lock Repairs critical to prevent concrete from entering fill/drain culvert Fast tracked contract to repair
13
BUILDING STRONG®1414 BUILDING STRONG®
Ice Harbor: Downstream cable connection/upstream trunnion hubs
Trunnion pin backed out, keeper plate failed
Plan to complete cable connections in FY12.
Monitoring gate for cracks, made interim repairs, requested add’l FY13 funding
BUILDING STRONG®
Lower Monumental Navigation Lock
Outage Duration 15-Weeks Routine
Upstream gate and ancillary equipment inspections
Detailed maintenance and lubrication
Repair work Non-Routine
Replace downstream gate, cables and gear boxes
Navlock Concrete Repairs Phase 2
Replace U/S gate seal15
BUILDING STRONG®
Lower Monumental downstream gate replacement
16
BUILDING STRONG®
Extremely complex heavy-liftingCoordinated between project & contractors to minimize disruption to operationsCoordinated with State and County road departments for mob and de-mob
Lower Monumental: Downstream Gate Replacement
17
BUILDING STRONG®
Next Steps - Hoist Machinery Upgrades
LOMO Existing Equipment John Day New Equipment
Lower Monumental: Downstream Gate Replacement
18
BUILDING STRONG®
Lower Monumental: Concrete Repair
Phase 1
Phase 2
Phase 2
Phase 3
19
BUILDING STRONG®
Little Goose Navigation Lock
Outage Duration 5-Weeks
Routine work Lock/gate and ancillary
equipment inspections Detailed maintenance and
lubrication Repair work
20
BUILDING STRONG®
Lower Granite Navigation Lock
Outage Duration 8-Weeks Routine Work
Lock/gate and ancillary equipment inspections
Detailed maintenance and lubrication
Repair work Non Routine Work
U/S gate detailed inspection and skin plate repairs/painting
Tainter drain valve #1 skin plate repair
21
BUILDING STRONG®
Outcomes from 2010 - 2011 Extended Navigation Lock Outage
Took major steps to restore the reliability of the Columbia – Snake River Navigation System
Completed backlog of Navigation Lock maintenance work Updated Navigation Operational Condition Assessments. Established a coordinated and collaborative process for
current and future work on the System.
22
BUILDING STRONG®
Planning and communication with stakeholders before and during outage
Coordination between NWP and NWW before and during outage
Aggressive schedule and ARRA funding Market research and contractor selection Design and contract development Team building and partnerships
Challenges & Keys To Success
23
BUILDING STRONG®
Future Outages Potential work:
Replacement of The Dalles & Ice Harbor upstream gates
Little Goose & McNary miter gate repairs Lower Monumental electrical/mechanical systems
repairs Interim repairs at other navigation locks
24
BUILDING STRONG®
Installation of New Gate Sections 15 Jan – 24 Feb 2011
John Day Navigation Lock D/S Gate and Sheave Replacement
25
BUILDING STRONG®
Questions?Portland District Public Affairs Office
(503) [email protected]
http://www.nwp.usace.army.mil/
Portland District Critical Infrastructure Program Manager
Matt Cutts (503) 808-4697
Walla Walla District Public Affairs Office(509) 527-7020
[email protected]://www.nww.usace.army.mil/
Navigation System Questions:Ann Glassley (509) 527-7115
26