Upload
iaeainformation
View
249
Download
0
Embed Size (px)
DESCRIPTION
Plenary Session, Tuesday 20.03.2012
Citation preview
U.S. NRC Fukushima Lessons-Learned Actions
Bill Borchardt
Executive Director for Operations
International Atomic Energy Agency International Experts Meeting
March 19-22, 2012
Ongoing Oversight of U.S. Nuclear Power Plants
• Reactor Oversight Process • Comprehensive inspection program • Continuous licensing
2
NRC Actions Through Summer 2011
• Activated operations center • Site team in Japan • Inspections at U.S. plants • Near-Term Task Force convened
– Evaluated safety of U.S. plants – Made recommendations to further
enhance safety of U.S. plants
3
Task Force Recommendations
• Seismic and flooding protection
• Prolonged loss of AC power
• Containment venting • Spent fuel pool cooling • Severe accident
procedures • Emergency preparedness
(EP) • Regulatory framework for
low probability, high consequence events
• Greater attention to defense-in-depth for low probability events
• Seismically induced fires and floods
• Hydrogen control mitigation inside buildings
• EP topics for multiunit events and prolonged SBO
• EP topics on decision making, radiation monitoring, and public education
4
Tier 1 Recommendations
• Seismic and flooding reevaluations
• Seismic and flooding walkdowns
• Station blackout (SBO) rulemaking
• Mitigating strategies for beyond design basis events • Reliable hardened vents for Mark I and II
containments
• Spent fuel pool (SFP) instrumentation
• Integration of emergency procedures rulemaking
• Enhanced EP staffing and communications 5
Tier 2 Recommendations
• Spent fuel pool makeup capability • Order licensees to provide safety-related AC electrical power for SFP makeup • Order licensees to revise their technical specifications to address requirements to
have one train of onsite emergency electrical power operable for SFP makeup and SFP instrumentation when there is irradiated fuel in the SFP, regardless of the operational mode of the reactor
• Order licensees to have an installed seismically qualified means to spray water into the SFPs, including an easily accessible connection to supply the water
• Emergency preparedness regulatory actions • Require licensees to have guidance for multiunit dose assessment capability • Require licensees to hold training and exercises for multi unit and prolonged SBO
scenarios • Require that licensees practice the identification and acquisition of offsite resources • Require that licensees ensure that EP equipment and facilities are sufficient for
dealing with multiunit and prolonged SBO scenarios
• Reevaluation of other external hazards • Request that licensees reevaluate external hazards other than seismic and flooding
6
Tier 3 Recommendations
• Ten-year confirmation of seismic and flooding hazards • Potential enhancements to the capability to prevent or mitigate seismically
induced fires and floods • Reliable hardened vents for other containment designs • Hydrogen control and mitigation inside containment or in other buildings • EP enhancements for prolonged SBO and multiunit events • Emergency Response Data System (ERDS) capability • Additional EP topics for prolonged SBO and multiunit events • EP topics for decision-making, radiation monitoring, and public education • Reactor Oversight Process modifications to reflect the recommended defense-in-
depth framework • Staff training on severe accidents and resident inspector training on severe
accident management guidelines (SAMGs) • Basis of Emergency Planning Zone size • Prestaging of potassium iodide beyond 10 miles • Transfer of spent fuel to dry cask storage
7
NRC Actions on Lessons Learned
• The Commission directed the staff to move forward on Tier 1 activities
• Orders and Request for Information
were issued in March 2012
8
Mitigating Strategies for Beyond Design Basis External Events
• Requires a three-phase approach for maintaining or restoring core cooling, containment, and spent fuel cooling
9
Phase Licensee may use
Initial Installed equipment
Transition Portable, onsite equipment
Final Resources obtained from offsite
Reliable Hardened BWR Vents
• Applicable to BWR Mark I and Mark II containments
• Controls containment pressure by removing decay heat if active containment heat removal capability is lost
• Must work under station blackout conditions
10
Reliable Spent Fuel Pool Instrumentation
• Requires licensees to install instrumentation to be able to identify when water reaches the following levels: – Level adequate for normal fuel pool cooling
system – Level adequate to provide radiation shielding
for a person standing on the operating deck – Level where fuel remains covered and actions
to add make-up water should no longer be deferred
11
Schedule Overview – Orders
Milestone Operating Reactors
Combined License Holders
Construction Permit
Holders Guidance
Issued August 31, 2012 August 31, 2012
August 31, 2012
1st Update October 31,
2012 October 31, 2012
October 31, 2012
Plan
Submitted February 28,
2013 August 31, 2013 August 31, 2013
Periodic Updates
Every six months
Every six months
Every six months
Latest Completion
December 31, 2016
Prior to initial fuel load
Prior to receipt of operating license
12
Seismic and Flooding Reevaluations
• Licensees were asked to perform and provide
the results of a reevaluation of hazards, including actions planned to address vulnerabilities
• Results will be used to determine whether additional regulatory actions are necessary
13
Schedule Overview – 50.54(f) Letter Seismic/Flooding Reevaluations Milestone Operating Reactors and Construction Permit
Holders
Guidance Issued November 30, 2012
Initial Response
January 30, 2013
Licensee Seismic Hazard Evaluations Due
September 9, 2013 (CEUS) / March 9, 2015 (WUS)
Licensee Flooding Hazard Evaluations Due
March 9, 2013 – March 9, 2015 (based on prioritization)
Future Steps
Pending NRC evaluation and prioritization, with completion of evaluations for all facilities between
October 2016 and April 2019
14
Seismic and Flooding Walkdowns
• Licensees were asked to perform walkdowns to verify that the plant is in conformance with its design basis
• Any performance deficiencies are expected to be addressed by the site’s corrective action program
• The scope includes the integrated effects of severe storms within the licensing basis
15
Schedule Overview – 50.54(f) Letter Seismic/Flooding Walkdowns
Milestone Operating Reactors
Guidance Issued or
Endorsed
~ May 2012
Licensees Identify
Walkdown Procedures To Be
Used
June 9, 2012 (flooding) / July 9, 2012 (seismic)
Licensees Provide
Results of Walkdowns
180 days after NRC endorsement of the walkdown procedure (~November 2012)
16
Enhanced Emergency Planning Staffing and Communications
• Licensees were requested to assess: – current communications systems and equipment
used during an emergency to ensure that power is maintained during a large scale event natural event
– the staffing needed to respond to a large scale natural event and to implement strategies contained in the licensee’s emergency plan
17
Schedule Overview – 50.54(f) Letter Emergency Preparedness
Milestone Operating Reactors, Combined License Holders, and Construction Permit Holders
4.2 Guidance Issued or Endorsed
Licensee Responses
August 31, 2012
June 9, 2012 (communications)
June 9, 2012 (staffing items 3 through 6)
October 31, 2012 (staffing items 1 and 2)*
* 60 days after issuance of guidance associated with Recommendation 4.2 order
18
NRC Follow-Up
• Review and assess licensee responses • Establish necessary regulatory
framework • Inspect to ensure licensee compliance
with all new regulatory requirements • Consider implications for other types of
nuclear facilities
Regulatory Development Activities
• Station Blackout (SBO) Rulemaking
– Modify the SBO rule to require enhanced capability to mitigate a prolonged SBO
– Advanced Notice of Proposed Rulemaking to be issued soon – The Commission directed that SBO rulemaking be completed
within 24-30 months
• Emergency Procedures Integration Rulemaking
– Create a new rule requiring the integration of the emergency procedures
– Advanced Notice of Proposed Rulemaking under development – The rulemaking is expected to be completed in 2016
20
Short-Term Next Steps
• Developing implementation guidance for the orders and request for information
• Developing the advanced notices of proposed rulemaking
• Providing the Commission with Tier 3 recommendation implementation plans in July 2012
21
Conclusion
• NRC is moving forward with identified enhancements for U.S. plants
• NRC is following the development of lessons learned by the international community
• NRC will evaluate additional lessons learned for applicability to U.S. plants
22