Validation

Supplementary Training Modules on Good Manufacturing Practice

WHO Technical Report Series, No. 937, 2006. Annex 4.

Page 2: Validation Part6

Validation | Slide 2 of 27 August 2006

ValidationValidation

Part 1. General overview on qualification and validation

Part 2. Qualification of HVAC and water systems

Part 3. Cleaning validation

Part 4. Analytical method validation

Part 5. Computerized system validation

Part 6. Qualification of systems and equipment

Part 7. Non sterile product process validation

Page 3: Validation Part6

Validation | Slide 3 of 27 August 2006

Qualification of systems and equipment

Part 6

Supplementary Training Modules on Good Manufacturing Practice

WHO Technical Report Series, No. 937, 2006. Annex 4. Appendix 6.

Page 4: Validation Part6

Validation | Slide 4 of 27 August 2006

ValidationValidation

Objectives

To discuss the principles of qualification of systems and equipment, with specific focus on:

The different stages of qualification

Requalification and

Qualification of “in use” systems and equipment

Page 5: Validation Part6

Validation | Slide 5 of 27 August 2006

ValidationValidation

Principle

Systems and equipment: Appropriately designed, located, installed, operated and maintained

Critical systems and equipment – should be qualified

May include, where appropriate:– Water purification systems, air-handling systems,

autoclaves, coating machines

Continued suitable performance needed – Why? To ensure batch-to-batch consistency

1.1 – 1.3

Page 6: Validation Part6

Validation | Slide 6 of 27 August 2006

ValidationValidation

Scope

Guidelines describe the general aspects of qualification for systems and equipment

Normally qualification would be applicable to critical systems and equipment whose performance may have an impact on the quality of the product

2.1 – 2.2

Page 7: Validation Part6

Validation | Slide 7 of 27 August 2006

ValidationValidation

General

Qualification policy for systems and equipment

To include instruments used in production and quality control

New systems and equipment: All stages of qualification applicable (DQ, IQ, OQ and PQ)

In some cases: Not all stages of qualification may be required– e.g. electrical supply systems

3.1 – 3.4

Page 8: Validation Part6

Validation | Slide 8 of 27 August 2006

ValidationValidation

General (continued)

Systems: Qualified before equipment

Equipment: Qualified before routine use

Systems and equipment: Periodic requalification, as well as requalification after change

Certain stages done by the supplier or a third party

Maintain the relevant documentation, e.g.– standard operating procedures (SOPs), specifications and

acceptance criteria, certificates and manuals 3.5 – 3.9

Page 9: Validation Part6

Validation | Slide 9 of 27 August 2006

ValidationValidation

General (continued)

Qualification should be done in accordance with predetermined and approved qualification protocols

The results of the qualification should be recorded and reflected in qualification reports

The extent of the qualification should be based on the criticality of a system or equipment, e.g.

– Blenders, autoclaves or computerized systems

3.10 – 3.11

Page 10: Validation Part6

Validation | Slide 10 of 27 August 2006

ValidationValidation

Blender

Discuss the approach of qualification of a newly installed blender

Page 11: Validation Part6

Validation | Slide 11 of 27 August 2006

ValidationValidation

Stages of qualification

3.11

Design qualification

Installation qualification

Operational qualification

Performance qualification

Page 12: Validation Part6

Validation | Slide 12 of 27 August 2006

ValidationValidation

Stages of qualification

3.11.

Design qualification

Installation qualification

Operational qualification

Performance qualification Change control

Page 13: Validation Part6

Validation | Slide 13 of 27 August 2006

ValidationValidation

Design qualification

User requirements should be considered when deciding on the specific design of a system or equipment

A suitable supplier should be selected for the appropriate system or equipment (approved vendor)

4.1 – 4.2

Page 14: Validation Part6

Validation | Slide 14 of 27 August 2006

ValidationValidation

Installation qualification

Correct installation as per plan and protocol

Normally advised to prepare requirements for calibration, maintenance and cleaning at this stage

Identification and verification of all system elements, parts, services, controls, gauges and other components

Calibrate the measuring, control and indicating devices– against appropriate, traceable national or international

standards5.1 – 5.4

Page 15: Validation Part6

Validation | Slide 15 of 27 August 2006

ValidationValidation

Installation qualification (2)

Documented records for the installation– installation qualification report

Indicate satisfactory installation

Include details, e.g.– The supplier and manufacturer– System or equipment name, model and serial number– Date of installation– Spare parts, relevant procedures and certificates

5.5

Page 16: Validation Part6

Validation | Slide 16 of 27 August 2006

ValidationValidation

The handout shows a typical format for

"An installation qualification protocol / report"

It reflects the minimum information that should be included

This is an example – and should be used as such

Specific formats need to be designed for a specific system or piece of equipment

5.5

Page 17: Validation Part6

Validation | Slide 17 of 27 August 2006

ValidationValidation

Operational qualification

Systems and equipment should operate correctly – operation verified as in the qualification protocol

Studies on critical variable to include conditions encompassing upper and lower operating limits and circumstances (i.e. “worst case conditions”)

To include verification of operation of all system elements, parts, services, controls, gauges and other components

6.1 – 6.3

Page 18: Validation Part6

Validation | Slide 18 of 27 August 2006

ValidationValidation

Operational qualification (2)

Documented records (Operational qualification report)

Finalize and approve SOP (operation)

Training of operators provided – training records

Systems and equipment released for routine use after completion of operational qualification, provided that:

– All calibration, cleaning, maintenance, training and related tests and results were found to be acceptable

6.4 – 6.7

Page 19: Validation Part6

Validation | Slide 19 of 27 August 2006

ValidationValidation

The handout shows a typical format for:

"An operational qualification protocol / report"

It reflects the minimum information that should be included

This is an example – and should be used as such

Specific formats need to be designed for a specific system or piece of equipment

6.7

Page 20: Validation Part6

Validation | Slide 20 of 27 August 2006

ValidationValidation

Performance qualification

Systems and equipment should consistently perform in accordance with design specifications – verified in accordance with a performance qualification protocol

Documented records – performance qualification report

Show satisfactory performance over a period of time

Manufacturers to justify the selected period

7.1 – 7.2

Page 21: Validation Part6

Validation | Slide 21 of 27 August 2006

ValidationValidation

The handout shows a typical format for:

"A performance qualification protocol / report"

It reflects the minimum information that should be included

This is an example – and should be used as such

Specific formats need to be designed for a specific system or piece of equipment

7.2

Page 22: Validation Part6

Validation | Slide 22 of 27 August 2006

ValidationValidation

8.1 – 8.3

Requalification

Defined schedule

Periodic

After change

Page 23: Validation Part6

Validation | Slide 23 of 27 August 2006

ValidationValidation

Requalification

Defined schedule

Frequency based onFactors

Results of calibrationmaintenance ,verification

Periodic

After change

Part ofChange control procedure

Extent based onRisk assessment

8.1 – 8.3

Page 24: Validation Part6

Validation | Slide 24 of 27 August 2006

ValidationValidation

What about "old manufacturers" who have not performed DQ, or IQ for existing, in-use systems and/or equipment?

Page 25: Validation Part6

Validation | Slide 25 of 27 August 2006

ValidationValidation

Qualification of “in-use” systems and equipment

Data to support and verify the suitable operation and performance of systems and equipment

Should include operating parameters and limits for critical variables, calibration, maintenance and preventive maintenance, standard operating procedures (SOPs) and records

9.1 – 9.2

Page 26: Validation Part6

Validation | Slide 26 of 27 August 2006

ValidationValidation

Page 27: Validation Part6

Validation | Slide 27 of 27 August 2006

ValidationValidation

Group session