19
1 © 2010 Electric Power Research Institute, Inc. All rights reserved. Virtual Power Plant Modeling & Simulation Gale Horst Project Manager, Smart Grid Demonstrations Electric Power Research Institute (EPRI) Roger Dugan Sr. Technical Executive Electric Power Research Institute (EPRI) 2 © 2010 Electric Power Research Institute, Inc. All rights reserved. American Electric Power (AEP) Virtual Power Plant Simulator (VPPS)

Virtual Power Plant Modeling Simulation Gale Horst …smartgrid.epri.com/doc/07_AEP Smart Grid Project Modeling and... · Virtual Power Plant Modeling & Simulation Gale Horst

  • Upload
    buihanh

  • View
    216

  • Download
    1

Embed Size (px)

Citation preview

1© 2010 Electric Power Research Institute, Inc. All rights reserved.

Virtual Power PlantModeling & Simulation

Gale HorstProject Manager, Smart Grid Demonstrations

Electric Power Research Institute (EPRI) 

Roger DuganSr. Technical Executive

Electric Power Research Institute (EPRI)

2© 2010 Electric Power Research Institute, Inc. All rights reserved.

American Electric Power (AEP) Virtual Power Plant Simulator (VPPS)

3© 2010 Electric Power Research Institute, Inc. All rights reserved.

The Evolution of the Electric Utility SystemThe Evolution of the Electric Utility System

Before Smart Grid:One-way power flow, simple interactions

After Smart Grid:Two-way power flow, multi-stakeholder interactions

Adapted from EPRI Presentation by Joe HughesNIST Standards Workshop

April 28, 2008

4© 2010 Electric Power Research Institute, Inc. All rights reserved.

Smart Grid Enables Energy StorageSmart Grid Enables Energy Storage

Adapted from EPRI Presentation by Joe HughesNIST Standards Workshop

April 28, 2008

But where is the best location/size for the storage ?

5© 2010 Electric Power Research Institute, Inc. All rights reserved.

Migratory Path of Energy Storage Migratory Path of Energy Storage –– AEPAEP

Large Central Units

Storage at Grid Edge

Substation Batteries

Graphics adapted from an EPRI Presentation by Joe Hughes

6© 2010 Electric Power Research Institute, Inc. All rights reserved.

CES(Community)

Devaluators:• Aesthetics

Locational Value of Electricity StorageLocational Value of Electricity Storage

120 V240 V69 kV 4 to 34 kV 480 V138 kV345 kV765 kV

Storage Value

Central Units Distributed Units

Devaluators:• No Backup• High Security Risk• Less effect on losses

Pumped Hydro(Central)

Devaluators:• Safety Concerns• No Load Diversity• No Cost Sharing• Little Grid Benefits •No Standardization

ResidentialNaS

(Substation)

Devaluators:• Complex Islanding• Storage Size & Location•Medium Security Risk

7© 2010 Electric Power Research Institute, Inc. All rights reserved.

To Optimize StorageTo Optimize Storage

1.Very Close to Customers• Backup Power, • Buffer Customer Renewables

2.Grid-Connected• Load Leveling, • Volt / VAR support

3.Utility-Operated• Load Diversity (multiple customers on one storage)• Improved Safety• Optimizing Grid Performance

4.Utility-Owned• Standardization & Commodity Pricing• Socializing the Cost

Need an energy storage system with the following FOUR key features:

8© 2010 Electric Power Research Institute, Inc. All rights reserved.

CES CES –– A Virtual Substation BatteryA Virtual Substation Battery

Local Benefits:1) Backup power2) Voltage correction3) Renewable Integration

Substation

Power LinesCommunication and Control Links

CES

CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

9© 2010 Electric Power Research Institute, Inc. All rights reserved.

CES CES –– A Virtual Substation BatteryA Virtual Substation Battery

Communication & Control Layout for

CES

Utility Dispatch Center /SCADACES Control Hub

Substation

Power LinesCommunication and Control Links

Integration Platform

CES CESCESCES

CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:4) Load Leveling at substation5) Power Factor Correction6) Ancillary services

Local Benefits:1) Backup power2) Voltage correction3) Renewable Integration

10© 2010 Electric Power Research Institute, Inc. All rights reserved.

Benefits of Local Energy Benefits of Local Energy StoraeStorae

• More reliable Backup Power to customers (closer)

• More scalable, flexible implementation (many small units)

• More efficient in buffering customer renewable sources

• More synergy with Electric Vehicle batteries

• Easier installation and maintenance (240 V)

• A Unit outage is less critical to the grid (smaller)

While Local Storage can function as a Multi-MW, Multi-hour Substation Battery, It has Inherent Advantages over Larger Batteries located in Substations:

11© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Following Peak Shaving

Circuit Demand

12© 2010 Electric Power Research Institute, Inc. All rights reserved.

Community Energy Storage Simulations

In the

AEP Smart Grid Demonstration

Roger DuganSr. Technical Executive

Electric Power Research Institute (EPRI)

13© 2010 Electric Power Research Institute, Inc. All rights reserved.

Circuit Diagram

84 Storage Elements25 kW each

14© 2010 Electric Power Research Institute, Inc. All rights reserved.

Voltage Profile

Voltage Profile Plot

0.97

0.98

0.99

1

1.01

1.02

1.03

1.04

1.05

0 0.5 1 1.5 2 2.5 3 3.5 4

Distance from Substation

Per

Uni

t Vol

tage

V1V2V3

15© 2010 Electric Power Research Institute, Inc. All rights reserved.

Storage Element Model in OpenDSS

% Eff. Charge/DischargeIdle | Discharge | Charge

Idling Losses

kW, kvar

kWh STORED

Other Key Properties

% ReservekWhRatedkWhStored%StoredkWRated

etc.

16© 2010 Electric Power Research Institute, Inc. All rights reserved.

StorageController Element in OpenDSS

Discharge ModeCharge Mode

kW TargetDischarge Time

Total Fleet kW CapacityTotal Fleet kWh

et. al.

Storage “Fleet”Substation

V, IComm Link

Time + Discharge ratePeak ShavingLoad FollowingLoadshape

17© 2010 Electric Power Research Institute, Inc. All rights reserved.

Example Simulations

Investigating 25, 50, and 75 kWh storage options with various 

discharging schemes

18© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Peak Shave, Target=8000 kW, Storage=75 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

10

20

30

40

50

60

70

80

Base kWNet kW kWh Stored

19© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Peak Shave, Target=8000 kW, Storage=25 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

5

10

15

20

25

30

Base kWNet kW kWh Stored

20© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Peak Shave, Target=8000 kW, Storage=25 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

5

10

15

20

25

30

Base kWNet kW kWh Stored

“Ran Out of Gas”

21© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Load Follow, Time=12:00, Storage=75 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

10

20

30

40

50

60

70

80

Base kWNet kW kWh Stored

22© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Load Follow, Time=12:00, Storage=75 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

10

20

30

40

50

60

70

80

Base kWNet kW kWh Stored

12:00 is too early Load declines after 12:00

23© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Load Follow, Time=12:00, Storage=50 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

10

20

30

40

50

60

Base kWNet kW kWh Stored

24© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Load Follow, Time=12:00, Storage=25 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

5

10

15

20

25

30

Base kWNet kW kWh Stored

25© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Load Follow, Time=13:00, Storage=25 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

5

10

15

20

25

30

Base kWNet kW kWh Stored

26© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Load Follow, Time=14:00, Storage=25 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

5

10

15

20

25

30

Base kWNet kW kWh Stored

27© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Time + fixed rate, Time=12:00 @ 30%, Storage=25 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

5

10

15

20

25

30

Base kWNet kW kWh Stored

28© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Time + fixed rate, Time=12:00 @ 30%, Storage=25 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

5

10

15

20

25

30

Base kWNet kW kWh Stored

Quickly discharges to reserve kWh

29© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Time + fixed rate, Time=14:00 @ 25% Storage=25 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0 50 100 150 200 250 300

Hours

kW

0

5

10

15

20

25

30

Base kWNet kW kWh Stored

30© 2010 Electric Power Research Institute, Inc. All rights reserved.

Load Shapes With and Without StorageMode=Time + fixed rate, Time=14:00 @ 25% Storage=25 kWh

Charge=2:00 @ 30%

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

200 210 220 230 240 250

Hours

kW

0

5

10

15

20

25

30

Base kWNet kW kWh Stored

(Expanded Scale)

31© 2010 Electric Power Research Institute, Inc. All rights reserved.

Conclusions

• 25 kWh storage is quickly depleted when used for day‐to‐day peak shaving– Have to be very careful with discharge strategy

• Load following with a later time trigger is likely more useful than a fixed discharge rate or an early time trigger

• 75 kWh would be “nice to have”– Costs are a factor

32© 2010 Electric Power Research Institute, Inc. All rights reserved.

Discharge Algorithm Development

Scheduled Discharge

0

1000

2000

3000

4000

5000

6000

7000

8000

Load

(kW

)

Load without Battery

Load with Battery

Aug 3rd Aug 4th Aug 5th Aug 6th Aug 7th

Is it time to trigger ?

33© 2010 Electric Power Research Institute, Inc. All rights reserved.

Discharge Algorithm Development

Scheduled Discharge

0

1000

2000

3000

4000

5000

6000

7000

8000

Load

(kW

)

Load without Battery

Load with Battery

Aug 3rd Aug 4th Aug 5th Aug 6th Aug 7th

Is it time to trigger ?

34© 2010 Electric Power Research Institute, Inc. All rights reserved.

Discharge Algorithm Development

Scheduled Discharge

0

1000

2000

3000

4000

5000

6000

7000

8000

Load

(kW

)

Load without Battery

Load with Battery

Aug 3rd Aug 4th Aug 5th Aug 6th Aug 7th

Is it time to trigger ?

35© 2010 Electric Power Research Institute, Inc. All rights reserved.

Discharge Algorithm Development

Scheduled Discharge

0

1000

2000

3000

4000

5000

6000

7000

8000

Load

(kW

)

Load without Battery

Load with Battery

Aug 3rd Aug 4th Aug 5th Aug 6th Aug 7th

Is it time to trigger ?

36© 2010 Electric Power Research Institute, Inc. All rights reserved.

Discharge Algorithm Development

Scheduled Discharge

0

1000

2000

3000

4000

5000

6000

7000

8000

Load

(kW

)

Load without Battery

Load with Battery

Aug 3rd Aug 4th Aug 5th Aug 6th Aug 7th

37© 2010 Electric Power Research Institute, Inc. All rights reserved.

AEP Approach to Smart Grid Technology Simulations

38© 2010 Electric Power Research Institute, Inc. All rights reserved.

Together…Shaping the Future of Electricity