27
SARAWAK OPERATIONS WORKPACK ACTIVITY : SWITCHGEAR & MCC MAINTENANCE PLATFORM : TEMANA PLATFORM EQUIPMENT : GS100, MCC-100, MCC-101 WO NUMBER : PERSONNEL NAME POSITION SIGNATURE DATE PREPARED BY: Mohammad Yusmin ACSB ENGINEER REVIEWED BY: Azmi Ahmad ACSB MANAGER ENDORSED BY: M Syakiq Mat Sihat PCSB ENGINEER BME Manager PCSB MANAGER APPROVED BY: SECTION HEAD SUMANDAK OIM Ref Number:

Workpack TEMANA Shutdown

Embed Size (px)

Citation preview

Page 1: Workpack TEMANA Shutdown

SARAWAK OPERATIONS

WORKPACK

ACTIVITY : SWITCHGEAR & MCC MAINTENANCE PLATFORM : TEMANA PLATFORM EQUIPMENT : GS100, MCC-100, MCC-101WO NUMBER :

PERSONNEL NAME POSITION SIGNATURE DATE

PREPARED BY:Mohammad Yusmin

ACSBENGINEER

REVIEWED BY: Azmi AhmadACSBMANAGER

ENDORSED BY:

M Syakiq Mat Sihat

PCSB ENGINEER

BME Manager PCSB MANAGER

APPROVED BY:SECTION HEAD

SUMANDAK OIM

Ref Number: ACSB/SKO/W/SUM/1

Page 2: Workpack TEMANA Shutdown

TABLE OF CONTENTS

1 INTRODUCTION 21.1 Field Background 21.2 Project Background 21.3 Equipment Details & Specifications 3

2 DETAILED WORK SCOPE 42.1 Work Procedure 42.2 Work Planning 11

3 MANPOWER LOADING 143.1 Manpower List 143.2 Organization Chart 143.3 PCSB Focal Person 153.4 HSE Requirement 15

3.4.1 Toolbox Meeting 153.4.2 PTW 153.4.3 JHA 15

4 TOOLS & MATERIALS LIST 174.1 Tools & Parts Require 174.2 Lifting Plan 18

5 PROJECT DETAILS 215.1 Project Schedule 21

6 APPENDICES 21

2

Page 3: Workpack TEMANA Shutdown

1 INTRODUCTION

1.1 Field Background

Temana Platform

1.2 Project Background

This shutdown maintenance and services of the switchgear and MCC at Temana platform is to maintain the equipment as per routine activity as per below:

a) Shall perform visual inspection for damage, overheating, corrosion, cracked insulation and loose terminals.

b) Shall perform general cleaning on switchgear (ACB, MCC, busbar, compartment, etc).

c) Shall perform insulation resistance for contactor and circuit breaker.d) Shall perform continuity check by measuring closed contact resistance of

contactor.e) Shall verify conductivity, continuity and integrity of the busbar assembly,

switchgear earthing and bonding. f) Shall perform functional check on switchgears and MCC inclusive of control

systems and electrical/mechanical interlocks. g) Shall verify the ACB and MCC panels operation and interlocks.h) Shall verify the control wiring system against the schematic diagram. i) Shall inspect and service MCC contactors and circuit breakers for condition,

alignment and correct setting.j) Shall troubleshoot and rectify any switchgear and MCC having abnormalities.k) Shall perform testing and recording data.l) Shall perform tightening for any losing part.m) Shall perform cleaning

3

Page 4: Workpack TEMANA Shutdown

1.3 Equipment Details & Specifications

Lists below show the switchgears and MCC involved during shutdown maintenance:

4

Page 5: Workpack TEMANA Shutdown

2 DETAILED WORK SCOPE

2.1 Work Procedure

2.1.1ACB Panel Servicing & Testing

i. PTW and IEC Cert shall be approved by PCSB before work commences.

ii. Switching (De-energize) to be done by PCSB Chargeman.iii. Contractor to confirm no supply from ACB using HV Test Pen.iv. Switchgear Panel to be placed at the Earth Position. Before inspecting

or performing any maintenance on either the breaker or its mechanism, be sure the breaker is in the open position. Both the closing and opening, springs should be discharged or blocked mechanically before any maintenance is done.

v. Compare nameplate data with drawings and specifications.vi. Inspect circuit breaker for correct mounting.

vii. Operate circuit breaker to insure smooth operation.viii. Inspect case for cracks or other defects.

ix. Inspect all bolted electrical connections for high resistance.x. Inspect mechanism contacts and arc chutes in unsealed units.

xi. Inspect anchorage, alignment, and grounding. Inspect moving and stationary contacts for condition, wear, and alignment.

xii. Perform a contact-resistance test. Microhm drop values shall not exceed the high levels of the normal range as indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

xiii. Perform an insulation-resistance test at 1000 volts dc from pole-to-pole and from each pole-to-ground with breaker closed and across open contacts of each phase. Circuit breaker insulation resistance should be in accordance with attached appendices table for minimum IR value.

xiv. Clean the area of arc chutes until thoroughly clean and ensure the arc chutes are clear of contamination and have no significant damage on grids or ceramics.

xv. Perform cleaning and lubricate the ACB contacts (aux, finger) and linkages

xvi. Determine IR and contact resistant measurement after servicing.xvii. Check on earthing system, alignment and rack condition.

xviii. Report on abnormal findings immediately to PIC.xix. Check for leftover tools and consumables.xx. Rack in the breaker to service position.

5

Page 6: Workpack TEMANA Shutdown

2.1.3 MCC Servicing and Testing

i. PTW and IEC Cert shall be approved by PCSB before work commences.

ii. Compare equipment nameplate data with drawings and specifications.

iii. Inspect physical and mechanical condition.iv. Inspect all bolted electrical connections for high resistancev. Test all interlocking systems for correct operation and sequencing.

vi. Inspect all indicating and control devices for correct operation.vii. Perform cleaning and servicing on contact, surface, internal

component and structural of MCC & proper lubrication.viii. Perform insulation-resistance tests on each pole, phase-to-phase and

phase-to-ground with switch closed and across each open pole for one minute. Test voltage and minimum insulation resistance shall be in accordance with manufacturer’s published data or attached table on appendices

ix. Report on abnormal findings immediately to PIC.x. Check for leftover tools and consumables.

2.1.4 Busbar Servicing and Testing

i. PTW and IEC Cert shall be approved by PCSB before work commences.

ii. Switching (De-energize) to be done by PCSB Chargeman.iii. Contractor to confirm no supply from busbar using HV Test Pen.iv. Before perform electrical test, ensure the entire load (breaker, MCC,

CT, VT and fuses) to busbar is disconnected.v. Compare equipment nameplate data with drawings and

specifications.vi. Inspect busbar for physical damage and correct connection in

accordance with single-line diagram.vii. Inspect all bolted electrical connections for high resistance.

viii. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method

ix. Measure insulation resistance of each busbar, phase-to-phase and phase-to-ground for one minute. Insulation-resistance test voltages and resistance values shall be in accordance with manufacturer’s published data or attached table on appendices. Minimum resistance values are for a nominal 1000 foot busbar run.

x. Perform contact-resistance test on each connection point of non-insulated busbar. Compare bolted connection resistances and bus joint resistances to values of similar connections. Microhm drop values shall not exceed the high levels of the normal range as

6

Page 7: Workpack TEMANA Shutdown

indicated in the manufacturer’s published data. If manufacturer’s data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value.

xi. Perform general cleaning on busbarxii. Apply all new silicon sealant to all busduct joint and gasket.

xiii. Measure IR and contact resistance after service.xiv. Report on abnormal findings immediately to PIC.xv. Check for leftover tools and consumables.

xvi. Closed the busbar compartment.

2.1.5 Testing Procedure

A. Insulation Resistance Test

Procedure before Performing Insulation Resistance Test

i. The system or equipment is taken out of service and disconnected from all other circuits, switches, capacitors, brushes, lightning arrestors and circuit breakers. (Make sure the measurements are not affected by leakage current through switches and over current protective devices.

ii. The temperature of the conductor is above the dew point of the ambient air. When this is not the case, a moisture coating will form on the insulation surface and in some cases will be absorbed by the material.

iii. The surface of the conductor is free from carbon and other foreign matter that can become conductive on humid conditions.

iv. Applied voltage is not too high when testing low voltage system. Too much voltage will damage the insulation.

v. The system under test needs completely discharged to the ground. The grounding discharge time should be about five times the testing charge time.

Safety Procedure on Insulation Resistance Test

i. Never connect the insulation tester to energized conductors or energize equipment and always follow manufacturer’s recommendation.

ii. Shut down the equipment to be tested by opening fuses, switches and circuit breakers.

iii. Disconnect the branch circuit conductor, grounding conductor and all other equipment from the unit under test.

iv. Discharge conductor capacitance, both before and after the test. Some instrument may have automatic discharge functions.

7

Page 8: Workpack TEMANA Shutdown

v. Check for any leakage current through fuses, switches and breakers on de- energized circuits. Leakage current can cause inconsistent and incorrect reading.

vi. Do not use an insulation tester in dangerous or explosive atmosphere since the instrument can generate arching in damaged insulation.

vii. Use insulated rubber glove when connecting the test lead.

Procedure of Insulation Resistance Test

i. Use multimeter or voltmeter to make sure there is no power applied to the tested circuit.

ii. Set the voltage level to as per table attached on appendices depend on equipment. E.g. 1000V for LV switchboard (ACB, MCC) and 2500V for MV switchboard (VCB).

iii. Plug one end of the black test lead to the common terminal on the meter end and touch the test probe to the ground or another conductor. Sometimes it is helpful to ground all conductors that are not part of the test.

iv. Plug one end of the red test lead to the volt/ohm terminal on the meter and connect the test probe to the conductor to be tested.

v. Press the test button to apply the desired voltage and read the resistance display on the meter. It could take a few seconds for the reading to be settled. The higher the resistance the better.

vi. Test the insulation between phase to phase and phase to neutral as per checklist.

vii. Keep a dated record of the measured value.viii. If some of the conductors fail the test, identify the problems and take

necessary actions. Moisture, water and dirt can create low resistance readings.

8

Page 9: Workpack TEMANA Shutdown

Figure 1: Connection Diagram of CB Insulation Resistance Test

Figure 2: Connection Diagram of Busbar Insulation Resistance Test

9

Page 10: Workpack TEMANA Shutdown

B. Micro-ohm Measurement/Contact Resistance/Ductor Test

Procedure Performing Contact Resistance Test

i. Make certain that the circuit breaker is de-energised on both sides, closed and safety grounded and that local safety regulations are followed.

ii. Ground the test instrument.iii. Make sure that the test instrument is switched off.iv. Connect current and sensing cables according to the drawing.v. Switch the test instrument on.

vi. Set the test current to minimum 100A (according to ANSI C 37.09)vii. Perform the measurement.

viii. Repeat the test on the different phase.

Figure 3: Connection Diagram of Ductor/Contact Resistance Test

10

Page 11: Workpack TEMANA Shutdown

2.2 Work Planning

2.2.1 Shutdown activity

Day Work Description Plan Man Hours

1 - Arrival at Temana Platform- Apply for PTW, ensure isolation certificate in place, and prepare

the worksite. ET : 2 hrs

- Do a toolbox meeting prior to the job.- Barricade the work area to prevent unauthorized personnel enter

the area.- Ensure system is disconnected from all electrical sources and do a

proof test to ensure system is totally dead.ET : 1 hr

- Shutdown activities: To perform servicing on busbar and dropper on switchgear GS-100 as per work scope and listed as per table below:

BusbarET : 4 hrs

GS-100 busbar

ACBET : 3 hrs

1. ACB G700 Gas Generator2. ACB G710 Diesel Generator3. ACB Bustie

- Housekeeping and apply PTW for next day activities and submit report to PIC. ET : 1 hr

12 hrs

2 - Arrival at Temana Platform- Apply for PTW, ensure isolation certificate in place, and prepare

the worksite. ET : 2 hrs

- Do a toolbox meeting prior to the job.- Barricade the work area to prevent unauthorized personnel enter

12 hrs

11

Page 12: Workpack TEMANA Shutdown

the area.- Ensure system is disconnected from all electrical sources and do a

proof test to ensure system is totally dead.ET : 1 hr

- Shutdown activities: To perform servicing on busbar and MCC at switchgear MCC100 as per work scope and listed as per table below:

BusbarET : 4 hrs

Busbar MCC100

MCCET : 4 hrs

15 units MCC2 units Isolator Switch

- Housekeeping and apply PTW for next day activities and submit report to PIC.ET : 1 hr

3 - Arrival at Temana Platform- Apply for PTW, ensure isolation certificate in place, and prepare

the worksite. ET : 2 hrs

- Do a toolbox meeting prior to the job.- Barricade the work area to prevent unauthorized personnel enter

the area.- Ensure system is disconnected from all electrical sources and do a

proof test to ensure system is totally dead.ET : 1 hr

Shutdown activities: To perform servicing on busbar and MCC at switchgear MCC101 as per work scope and listed as per table below:

BusbarET : 4 hrs

Busbar MCC100

MCCET : 4 hrs

15 units MCC2 units Isolator Switch

- Housekeeping and apply PTW for next day activities and submit report to PIC.ET : 1hr

12 hrs

4 - Ensure PTW and isolation certificate in place, and prepare the worksite.

12

Page 13: Workpack TEMANA Shutdown

ET : 1 hr

- Do a toolbox meeting prior to the job.- Barricade the work area to prevent unauthorized personnel enter

the area.ET : 1 hr

- Post-Shutdown activities: To perform servicing on remaining VCB, VCU, ACB and MCC and also perform thermography on switchgear SG-7510. SB7710 and SB-7720.ET : 8 hr

- Housekeeping and apply PTW for next day activities and submit report to PIC.ET : 1hr

3 MANPOWER LOADING

3.1 Manpower List

Below is the list of manpower for site work activities:

No.

Name Designation

IC No. HUET Expiry Date

Medical Expiry Date

1Mohammad Yusmin

Engineer 811006035183

09/03/2014

01/01/2012

23

Dianto RasaliTechnician 85123149561

726/01/2014

17/01/2012

4Muhd Daud Abd Wahab

Technician 860804295327

17/08/2013

05/09/2011

13

Page 14: Workpack TEMANA Shutdown

5Roslan Abu Bakar

Technician 801123115271

28/06/2012

29/06/2012

6Mohd Sabri Abdul Ghani

Technician 811218115441

16/05/2012

21/05/2012

3.2 Organization Chart

3.3 PCSB Focal Person

Muhammad Syaqiq Bin Mat Sihat,Maintenance Department (BME-5),PCSB-Sarawak OperationTel : 085-475874Mobile : [email protected]

3.4 HSE Requirement

3.4.1 Toolbox Meeting

Work leader will briefly discuss the work plan.

14

Page 15: Workpack TEMANA Shutdown

Possible injuries from Electricity such as Dangers from electricity:

Voltage can cause ventricular fibrillation (stop heart function).

Current flow can cause severe burns. Reaction to Electric Shock (varies and can depend on)

Voltage level and duration Physical condition of victim Contact area with voltage Victim skin condition Ambient conditions

Before carrying out the switching work, several safety precautions has to be observed such as,

Isolation / switching must be performed by competent / authorized person.

Ensure the breaker/MCC is dead before carrying out any maintenance.

Care should be taken when withdrawing and removing breaker/MCC carriage.

Breaker/MCC servicing should be performed by a team of at least 2 persons.

3.4.2 Permit to Work

The objective of electrical work permits is to establish safe working practices by

Defines responsibilities Specifies the work & time period the permit is valid Precautions to be taken for the work Defines safe working limits to avoid DANGER Defines procedures to be followed Identifies any special equipment, tools or clothing

A few people of ASAGA personnel who involved with this turnaround maintenance attend PETRONAS Carigali PTW Applicant course.

3.4.3 Job Hazards AnalysisSee Attachment on appendices for JHA

15

Page 16: Workpack TEMANA Shutdown

4 TOOLS & MATERIAL LIST

4.1 Tools & Parts RequiredNo Description Quantity1 IR Tester 1kV 32 Contact Resistance Tester 13 Digital Multimeter 24 Test plug 15 Digital clamp meter 26 Discharge Rod 17 Blower 18 Vacuum Cleaner 19 Common Tools (Tools bag) 210 Long nose pliers 8 inch 211 Locking pliers 8 inch 212 Adjustable spanner 8 inch 413 Adjustable spanner 12 inch 214 Iron saw with blade 215 Iron saw with blade small 216 Flat file (Kikir) 217 Round file (Kikir) 218 Steal brush 219 Cable snapper 220 Common Spanners set 221 Power Extension Cords 222 Torchlight (explosion proof) 123 Torque Wrench (8-60 Nm) 124 Cordless Drill (12 Volt) 125 Paint brush 126 Digital camera 127 WD-40 428 Contact Cleaner 429 3M Tape 430 Cotton Rag 1 pack31 Sand Paper 432 Teflon Tape 1 pack33 Cotton Hand Glove 1 pack34 Masking Tape 435 Plastic Bag 1 pack36 PVC Tape (Red, yellow, blue, black & green) 6 each37 Cable/busbar cleaner 438 Barricade tape 2

16

Page 17: Workpack TEMANA Shutdown

4.2 Lifting Plan

During the turnaround activity, ASAGA team will bring a numbers of boxes and need a crane service to carry the loads to the platform. The dimension and estimated weight of the boxes as illustrated below.

ITEM 1BOX 1: Tools and Test Equipments

Dimension : 24” x 54” x 22”Estimated weight : 50kg

ITEM 2BOX 2: Tools and Test Equipments

Dimension : 27” x 55.5” x 18”Estimated weight : 50kg

17

Page 18: Workpack TEMANA Shutdown

ITEM 3BOX 3: Tools and Test Equipments

Dimension : 17” x 21” x 15”Estimated weight : 25kg

ITEM 4BOX 4: Contact Resistance Tester

Dimension : 19” x 22” x 10”Estimated weight : 20kg

18

Page 19: Workpack TEMANA Shutdown

ITEM 5BOX 5: Plastic Container

Dimension : 19” x 22” x 10” Estimated weight : 20kg

ITEM 6

2x Fiber Ladder

19

Page 20: Workpack TEMANA Shutdown

5 PROJECT DETAILS

5.1 Project Schedule

20

Page 21: Workpack TEMANA Shutdown

6 APPENDICES

6.1 Job Hazard Analysis6.2 Single Line Drawing6.3 QA/QC Plan - Checklist

21