XFEL Technical Reviews. Introduction Riko Wichmann, XFEL Project Office (XPO). XFEL Organization: Work Package Groups and Work Packages. Work Package Groups - WPGs. Work Packages - WPs. joint project management for XFEL project XFEL project leader and his team - PowerPoint PPT Presentation
Citation preview
Introduction
Riko Wichmann, XFEL Project Office (XPO)
XFEL Technical Reviews
XFEL Technical Reviews: Introduction
XFEL Organization: Work Package Groups and Work Packages 2
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
WPG-3:Photon Beam
Systems
WPG-4:Control & Operation
WPG-2Accelerator Sub-
Systems
WPG-5:Infrastructure
WPG-1:LINAC
WPG-6:Site & Buildings
WP-01RF System
WP-02:Low Level RF
WP-03:Accelerator
Module
WP-04:SC Cavities
WP-05:Power Coupler
WP-06HOM Coupler
WP-07:Frequency Tuner
WP-08:Cold Vacuum
WP-09:String Assembly
WP-11:Cold Magnets
WP-46:3.9 GHz System
WP-16:Lattice
WP-17:Standard Beam
Diagnostic
WP-15:Bunch
Compressor
WP-18:Special Beam
Diagnostic
WP-14:Injector
WP-19:Warm Vacuum
WP-12:Warm Magnet
WP-20:Beam Dumps
WP-75:Detector
Development
WP-76:DAQ & Control
WP-74:X-ray Photon
Diagnostic
WP-77:Scientific
Instruments
WP-73:X-ray Optics &
Beam Transport
WP-78:Optical Lasers
WP-21FEL Concepts
WP-79:Sample
Environment
WP-71:Undulators
WP-35:Radiation Safety
WP-36:General Safety
WP-29:Operability &
Reliability
WP-38:Personnel Interlock
WP-28:Control System
WP-39:EMC
WP-13:Cryogenic
WP-32:Survey &
Alignement
WP-10:AMTF
WP-33:Tunnel
Installation
WP-34:Utilities
WP-42:Site Lot 2
WP-43:Site Lot 3
WP-41:Site Lot 1
WP-44:Site
Engineering
WP-31:Site & Civil
Construction
WP-45:AMTF Hall
WP-40:Information &
Process Support
XFEL Project Board
Work Packages - WPs
Work Package Groups - WPGs
XFEL Technical Reviews: Introduction
XFEL Project Board
joint project management for XFEL project XFEL project leader and his team Accelerator Consortium Coordinator and his team
steers the construction of the XFEL facility board receives status information from the WPs and
follows them up each WP is represented in the board by one of its
members
3
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
XFEL Technical Reviews: Introduction
Representation of WP in the Project Board 4
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
WP-73
X-Ray Optics &
Beam Transport
WP-81
Scient.Instr. FDE
WP-82
Scient.Instr. HED
WP-84
Scient.Instr. SPB
WP-83
Scient Instr. MID
WP-78
Optical Lasers
WP-31
Site & Civil Constr.
WP-44
Site Engineering
WP-41/42/43
Site Lot 1-3
WP-45
AMTF Hall
WP-71
Undulators
WP-75
Detector Development
WP-76
DAQ & Control
WP-74
X-Ray Diagnostics
WP-85
Scient.Instr. SQS
WP-86
Scient.Instr. SCS
WP-79
Sample Environment
WP-10*
AMTF
WP-13*
Cryogenics
WP-32*
Survey & Alignment
WP-34*
Utilities
WP-33*
Tunnel Installation
WP-40*
IPS
WP-03*
Acc. Modules
WP-04*
S.C. Cavities
WP-05*
Power Couplers
WP-06*
HOM Couplers
WP-07*
Frequency Tuners
WP-08*
Cold Vacuum
WP-09*
Cavity String Assem.
WP-11*
Cold Magnets
WP-46*
3.9 GHz System
WP-01*
RF System
WP-02*
Low Level RF
WP-21
FEL Concepts
WP-14*
Injector
WP-20*
Beam Dumps
WP-12*
Warm Magnets
WP-16*
Lattice
WP-18*
Special Diagnostics
WP-15*
Bunch Compression
WP-17*
Stand. Diagnostics
WP-19*
Warm Vacuum
WP-12*
Warm Magnets
WP-36
General Safety
WP-35
Radiation Safety
WP-38
Personnel Interlock
WP-39*
EMC
WP-28*
Accelerator
Control SystemWP-29*
Operability & Reliability
WP-28*
Acc. Controls
* Work Packages, which are covered by the Accelerator Construction Consortium
Monitored by PB-member: H. Weise
Monitored by PB-member: W. Decking /T . Limberg
Monitored by PB-member: T. Hott
Monitored by PB-member: S. Molodtsov
Monitored by PB-member: A. Schwarz
Monitored by PB-member: T. Tschentscher
Cold Linac Coord.
Machine Layout Coord.
Technical Coord. IK-Contribution Office
Project Office
WPG3-Coord.Project Board (PB)
Project Management
WP-Group 1 WP-Group 2 WP-Group 4 WP-Group 3 WP-Group 3 WP-Group 6WP-Group 5
XFEL Technical Reviews: Introduction
XFEL Project Board
joint project management for XFEL project XFEL project leader and his team Accelerator Consortium Coordinator and his team
steers the construction of the XFEL facility board receives status information from the WPs and
follows them up each WP is represented in the board by one of its
members relevant decisions of the board are communicated to the
project in the weekly project meeting
5
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
XFEL Technical Reviews: Introduction
XFEL Project Planning Challenges
distributed planning approach with in-kind contributions bottom-up project planning by work package leaders XFEL Project Office (XPO) to maintain overall schedule
maintain overall consistent project plan over ~6 years maintain dependencies between WPs
in a transparent & traceable way provide trend analysis as early warning system provide reporting platform (PM, WPL, funding agencies etc)
6
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
Challenges:
XFEL Technical Reviews: Introduction
Planning Process:XFEL Project Plan = Hierarchical System of Plans
XFEL milestone plan: maintained by XPO project relevant milestones linked to WP milestones dependencies between different WPs via milestones
WP plans: maintained by the WPLs activities with schedule and resources, milestones progress reporting by “% complete” and remaining work
7
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
XFEL milestone plan
WP-01 WP-02
XFEL Technical Reviews: Introduction
Planning Process: Approach – Execution WPL
activity length for this & next quarter: 6 – 18 weeks in later quarters activities that can be longer investment and resource planning determine dependencies from/of other WPs request milestone from XPO
8
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
last quarter next quarter later quarters milestone other WP
via master plan
XFEL Technical Reviews: Introduction
Controlling Process: Update Approach – Execution WPL
progress reporting quarterly mark tasks as finished update unfinished tasks: no unfinished work in the past refine planning for up-coming quarters
file a status report (generated out of project plan) to PM PM follows-up on the status
9
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
status date
XFEL Technical Reviews: Introduction
Planning & Controlling Process: Tool Support 10
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
XFEL MS Project 2007 Enterprise
Project Web Access as PMS Portal and Project Analysis Center
Reporting Platform
Status Report available via EDM Explorer
XFEL Technical Reviews: Introduction
XFEL Structural Aspect
elementary unit of project: WP responsible for planning & execution of its tasks does all technical work
WP are very independent units with lots of responsibility all run in parallel and contribute to building the same facility⇨interfaces to other WP⇨interfaces to the XFEL PM
11
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
Milestone (time)XFEL milestone plan
WP-01 WP-02
XFEL Technical Reviews: Introduction
Side Note: Milestones
milestones used to establish a logical dependence between WPs via Milestone Plan
general: milestones are important tracking and monitoring instrument mark important events with in the project / WP formal: duration = 0, cost =0 often decision points
12
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
XFEL Technical Reviews: Introduction
Output
Output
Output
Output
13
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
Component Development Phase Model
development and production of components in phases independent on whether series or small number
each phase produces certain outputs/deliverables e.g. functional model, technical drawing, fabrication tools,
product, etc end of phase: milestone and decision point
output is reviewed go-ahead for next phase is given (or not)
Detailed
DesignProduction
decision point decision point decision point decision pointdecision point
Conceptual
Design
Fabrication Planning ……
XFEL Technical Reviews: Introduction
Output
Output
Output
Output
14
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
Phase Model: Technical Reviews
Conceptual Detailed Design: Conceptual Design Review Detailed Design Fabrication Planning: Detailed Design
Review Fabrication Planning Production: Production Readiness
Review
Detailed
DesignProduction
DDR PRRCDR
Conceptual
Design
Fabrication Planning ……
Complexity of review directly related to complexity of system Mandatory for all large/important systems
XFEL Technical Reviews: Introduction
Main Review Goals
prepare all necessary documentation and finalize all required deliverables at the end of a phase confirmation of the accomplished work within the WP by the
PM enter review with the “certainty” to pass not an open point assessment
provide valid and up-to-date information for all interfacing parties/WP to enhance planning certainty essential to build 1 facility in this distributed fashion
get the go-ahead from the PM to proceed with the work (next phase) e.g. approval place call for tender after PRR
15
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
XFEL Technical Reviews: Introduction
Benefits for Reviewing WP
Assurance that all required tasks are accomplished checklist of required deliverables per phase approval of phase results by PM maybe: confirmation by “external” expert
Certainty that open points are dealt with quickly acknowledgement of “my good work” by PM and others “forced” to finalize all deliverables until a fixed date
review is prepared with documentation and other deliverables
availability of approved and released documentation for others
16
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
XFEL Technical Reviews: Introduction
Benefits for Interfacing Parties / PM
ensures that my requirements are incorporated
availability of a released, reliable and valid set of docs describing the reviewed system enhances planning certainties for my tasks
certainty that open points are dealt with quickly
PM: assurance that a defined “quality standard” is reached
17
2nd CDE Workshop, 12. / 13. May 2009Riko Wichmann, XFEL Project Office, Desy
XFEL Technical Reviews: Introduction
Goals of this CDE Workshop
come to a common understanding of the reviews goals, procedures
define mandatory deliverables for the 3 technical reviews (CDR, DDR, PRR) checklist what should be available at the end of a certain
phase
define criteria for passing the 3 technical reviews
18