  • XXX Development Facility Feasibility Studies

    Doc #: YYY-DRL-PM-PEP-0001-C03 Jan 2015

    XXX Development

    Facility Feasibility & Option Selection Plan

    C For Information Jan 3 2015 MR JM / SC DL

    Rev Status Date Author Checker Lead EM PM

    Document Title:

    XXX Facility Feasibility & Option Selection Plan DRL Document No. Page

    MOL-DRL-PM-PEP-0001-C1 of 16

    Client Document No.

  • XXX Development Facility Feasibility Studies

    Doc #: YYY-DRL-PM-PEP-0001-C03 Jan 2015

    DW FEASIBILITY & OPTION SELECTION Rev C Jan 2 2015

    Table of Contents 1 INTRODUCTION .............................................................................................................. 3

    1.1 FACILITY WORK PLAN SUMMARY .................................................................... 4

    2 WORKPLAN ..................................................................................................................... 52.1 STUDY ACTIVITIES ............................................................................................. 52.2 FEASIBILITY STUDIES ........................................................................................ 7

    3 OPTION SCREENING (QUALITATIVE SELECTION PHASE 1) .................................. 83.1 SCREENING SUMMATION ................................................................................ 103.2 OPTION SELECTION PHASE 2 (QUANTITATIVE) ........................................... 113.3 PHASE 2 OPTION SELECTION ......................................................................... 113.4 HULL SELECTION .............................................................................................. 133.5 RISK ASSESSMENT .......................................................................................... 143.6 PHASE 2 OPTION SELECTION RESULTS SUMMARY .................................... 15

    4 VE STUDY ...................................................................................................................... 165 FEASIBILITY & OPTION SELECTION GATE CRITERIA ............................................. 166 CONTRACTING AND PROCUREMENT STRATEGIES................................................ 177 FEED INPUT & ITT DATA .............................................................................................. 188 STUDY TEAM ORGANISATION .................................................................................... 19

    8.1 STUDY TOOLS AND PROCEDURES ................................................................ 19

    9 DEVELOPMENT SCHEDULE ........................................................................................ 259.1 SCHEDULING ..................................................................................................... 25

  • XXX Development Facility Feasibility Studies

    Doc #: YYY-DRL-PM-PEP-0001-C03 Jan 2015

    DW FEASIBILITY & OPTION SELECTION Rev C Jan 2 2015

    1 INTRODUCTION This document presents a Study Plan to undertake the field development facility studies (Surface Facilities and Subsea) for YYY Development. The principles of the facility FE work will follow the following route map:

    However, the field development requires the integration of subsurface, drilling, operations, commercial and facilities in an overall development plan e.g. as typical below:

    JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

    Preliminary Cost, Schedule & FEED

    Budget & Cost EstimatesO&M Philosophy & Operability

    Preliminary Functional Basis (SOR)Contracting Strategy PlanContractor Tendering & EvaluationRegulatory BasisDeveloment plan (POD)

    SUBSURFACEAppraisal Development

    DRILLING

    FEED

    Contractor & Market Assessments

    Multi Beam & AUV Surveys

    Hull Selection StudiesUpdate Functional Basis Option Selection Evaluation studiesFEED Definition

    SUBSEA

    Riser Feasibility Studies

    Metocean StudyFlow Assurance studiesField Architecture StudiesFlowlines & Export Lines Engineering

    EXAMPLE PRE-SANCTION WORKPLAN

    SURFACE PRODUCTION FACILITIESProcess and Facility Feasibility

    Risk Assessment

    2015

    DEVELOPMENT MILESTONESExecutive Charter Brief

    DEFINE ACTIVITIES SELECTFEASIBILITY

    2014

    Appraisal Well 1Appraisal Well 2

    Preliminary PEPReviews

    CHARTERSOR

    STRATEGY

    REGULATOR

    RISK

    DRILL TESTDRILL TEST

    STUDIES - OFF/S

    HULL SELECTION

    SANCTION

  • XXX Development Facility Feasibility Studies

    Doc #: YYY-DRL-PM-PEP-0001-C03 Jan 2015

    DW FEASIBILITY & OPTION SELECTION Rev C Jan 2 2015

    1.1 FACILITY WORK PLAN SUMMARY This document presents an example front end plan to mature a prospect through Option Selection, through to the FEASIBILITY gate and readiness to commence FEED and Tendering. The document describes the following main steps:

    1. Development Team Set-up & mobilization 2. Project Charter or Statement of Requirements (SOR) 3. Preliminary Functional Requirements 4. Feasibility Studies & Brainstorms (Demonstrate Technical & Economic Feasible

    Schemes (Including riser performance vs hull form, flow assurance, field architecture, reservoir depletion requirements, oil and gas disposition options, etc.) 5. Development Option Screening 6. Final Option Selection 7. Feasibility Deliverables (FEASIBILITY) Facilities (Surface and Subsea), G&G and

    Subsurface, Operations and Drilling 8. Value Engineering (VE) 9. Contracting Strategy 10. FEED Tender ITT Data 11. FE Study and Team Administration and Planning

    Graphic representation of study stages:

    Concept Selection

    Field Planning

    Feasibility studies

    Concept Definition

    Execution

    Total field development level System / discipline level

    40%

    30%

    20%

    10%

    Cos

    t est

    imat

    es

    Major building block level

    Most likely to succeed technology

    Most cost efficient concepts

    Improved subsystems Improved

    execution

    Work Processes: - Front End Gate Process

  • XXX Development Facility Feasibility Studies

    Doc #: YYY-DRL-PM-PEP-0001-C03 Jan 2015

    DW FEASIBILITY & OPTION SELECTION Rev C Jan 2 2015

    2 WORKPLAN

    2.1 STUDY ACTIVITIES Initial study work activities focus on technical requirements and feasibility of the key building blocks reservoir and well depletion requirements, field architecture, flow assurance, riser performance vs hull selection options, oil and gas export options etc.

    STUDY TEAM SET-UP

    Establish framework for Study Team to work efficiently and effectively: Non-disclosure agreement Preliminary Study Plan and approach Document Control procedure and file structure Team Roles and Organization Reporting Charter (SOR) & Preliminary Functional Basis Brainstorm alignment sessions Preliminary Schedule Milestones Equipment Tagging procedure Team Office Facilities, Communications

    A provisional suggested FE team would be organized as follows:

  • XXX Development Facility Feasibility Studies

    Doc #: YYY-DRL-PM-PEP-0001-C03 Jan 2015

    DW FEASIBILITY & OPTION SELECTION Rev C Jan 2 2015

    A Preliminary Functional Basis for commencement of studies would include the following items. This functional basis will be developed thru several working sessions and data compilation.

  • XXX Development Facility Feasibility Studies

    Doc #: YYY-DRL-PM-PEP-0001-C03 Jan 2015

    DW FEASIBILITY & OPTION SELECTION Rev C Jan 2 2015

    2.2 FEASIBILITY STUDIES This stage needs to determine technically feasible schemes, and an understanding of the limitations and definition of key building blocks.

  • XXX Development Facility Feasibility Studies

    Doc #: YYY-DRL-PM-PEP-0001-C03 Jan 2015

    DW FEASIBILITY & OPTION SELECTION Rev C Jan 2 2015

    3 OPTION SCREENING (QUALITATIVE SELECTION PHASE 1) Once an understanding is established of feasible building blocks and credible schemes, then the option selection process can be commenced. Key elements are summarized as follows, and further defined in DRL Option Screening Methodology (Phase 1 - Qualitative & Phase 2 - Quantitative).Procedures see attached.

    Establish all the building blocks and brainstorm all credible options for base development, futures and potential 3rd parties. Requires involvement of all leading disciplines and management:

    Agree screening selection parameters Prepare preliminary Field Schematics and descriptions of main options and

    associated preliminary benchmark cost and schedules

  • XXX Development Facility Feasibility Studies

    Doc #: YYY-DRL-PM-PEP-0001-C03 Jan 2015

    DW FEASIBILITY & OPTION SELECTION Rev C Jan 2 2015

    Screening Workshop to select leading options based on :

    i. Relative Costing, ii. Schedule iii. Recoverable Reserves efficiency iv. Technical Risk, v. Integration and Installation Risk vi. Operability & Reliability, vii. Flexibility for futures

    Typical screening parameters/characteristics tabulation:

    Typical extract from Option Generator sheet including score tabulation of a rated option

    STAND ALONE Reservoir System

    CASE Name Reservoir Drive

    Relative Cost

    Project Schedule

    HC Reservoir Recovery and Yield

    Technical Risk

    Installation & HUC

    Operability &

    Reliability

    SUM

Recommended