What is PPAP?

• Production Part Approval Process

• Standard used to formally reduce risks prior to product or service release, in a team oriented manner using well established tools and techniques

• Initially developed by AIAG (Auto Industry Action Group) in 1993 with input from the Big 3 - Ford, Chrysler, and GM

• AIAG’s 4th edition effective June 1, 2006 is the most recent version

• PPAP is part of the Donaldson Supplier Business Operating Standard (S.B.O.S.S.)

Page 3: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Purpose of PPAP

• Provide evidence that all customer engineering design record and specification requirements are properly understood by the organization

• To demonstrate that the manufacturing process has the potential to produce product that consistently meets all requirements during an actual production run at the quoted production rate

PPAP manages change and ensures product conformance!

Page 4: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

When is PPAP Required?New partEngineering change(s)Tooling: transfer, replacement, refurbishment, or additionalCorrection of discrepancyTooling inactive > one year (needs Cpk study)Change to optional construction or materialSub-supplier or material source changeChange in part processingParts produced at a new or additional location

PPAP is required with any significant change to product or

process!

Page 5: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Benefits of PPAP Submissions

• Helps to maintain design integrity• Identifies issues early for resolution• Reduces warranty charges and prevents cost of poor quality• Assists with managing supplier changes• Prevents use of unapproved and nonconforming parts• Identifies suppliers that need more development• Improves the overall quality of the product & customer

satisfaction

Page 6: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

DBV = online supplier monitoring● After a successful submitted and approved PPAP, part can be

supplied to the Donaldson organization● Each supply get’s monitored and deliveries are measured in ppm

and in % on-time● When defect parts are found, an NCR and 8D is executed● Monthly the DBV committee communicates supplier ranking● Yearly SQA management at headquarter organizes an supplier

PPM improvement event, based on a 6 months supplier base performance.

● Our purchase department has an active role encouraging our suppliers to be the best in class

Page 7: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Production Run

• PPAP data must be submitted from a production run using:

Production equipment and toolingProduction employeesProduction rateProduction process

All data reflects the actual production process to be used at

start-up!

Page 8: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Readiness Review (R-R)• The purpose of a R-R is to verify the supplier’s manufacturing

process is capable of producing components that meet Donaldson’s quality requirements, at quoted tooling capacity, for a specified period of time

• Verification of the R-R will be at the Supplier Quality Engineer’s (SQE) discretion. The supplier will be notified of the need to perform a R-R as early in the process as possible.

• The number of components to be produced during the R-R should be sufficient to demonstrate process capability and will be predetermined by the SQE and the supplier.

Factors such as product complexity, shelf life, storage, cost and single shift vs. multiple shift operations will be taken into consideration

Page 9: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

The start of using the PPAP workbook

● Safe the “Workbook template” as an Excel Workbook.File name = Donaldson Part number followed by Donaldson Part rev number.E.g. P566611-rev8-……(+ free suffix)

● Fill out the sheet: “PPAP Submission Info”To do so, headers of other sheets are filled out automatically.

● Most of the fields are filled out by the Donaldson PPAP team

Submit

Submit

SubmitSubmitSubmit

RequiredSubmitSubmitSubmitSubmit

Submit

SubmitSubmit

Appearance approval Report

Design recordsAuthorized change documentsPart Dimensional approvalList of checking aidsPart Material approvalProcess Flow MapDesign and or Process FMEA

PPAP Level 5 Checklist

Sample partsMaster Sample (If applicable)Customer Engineering Approval Form

Control Plan

Process Capability Study, Cpk Calculation

Measuring System Study, Gage R&R

Please execute and show evidense of capabillity

Supplier PPAP

Remarks

If designated appearance part, appearance compliance will be identified via a special purchase order notification.

Country

LEVEL 3

RequirementsPart Submission Warrant

PPAP Assigned Quality EngineerSupplier NameSupplier Number

Postcode / Zip code

Phone Number

Street Address City

PPAP Submission

Part Name (DonaldsonPart Number (Donaldson)

Due Date

Revision (Donaldson)Revision date (Donaldson)Supplier Part Number (optional)

Supplier Contact

van den Enden, Ed:SCROLL to find the right level

Page 10: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Official PPAP Requirements1. Design Records2. Authorized Engineering Change Documents3. Customer Engineering Approval, if required4. Design Failure Modes and Effects Analysis (DFMEA) applied in special situations5. Process Flow Diagram6. Process Failure Modes and Effects Analysis (PFMEA)7. Control Plan8. Measurement Systems Analysis (MSA)9. Dimensional Results10. Records of Material / Performance Test Results11. Initial Process Studies12. Qualified Laboratory Documentation13. Appearance Approval Report (AAR)14. Sample Production Parts15. Master Sample16. Checking Aids17. Customer-Specific Requirements18. Part Submission Warrant (PSW)

Have a closer look

Page 11: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Donaldson’s PPAP Requirements

Supplier shall submit 12 items and retain a

copy of 12 + 2 (R) records at

appropriate locations

For PPAP Level 5, SQA will witness at supplier location and will fill out PPAP level 5 work sheet.

Page 12: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

PPAP Submission Levels

Level 1Production Warrant and Appearance Approval Report (if applicable) submitted to Donaldson

Level 2Production Warrant, product samples, and dimensional results submitted to Donaldson

Level 3Production Warrant, product samples, and complete supporting data submitted to Donaldson

Level 4Production Warrant and other requirements as defined by Donaldson

Level 5

Production Warrant, product samples and complete supporting data (a review will be conducted at the supplier's manufacturing location)

Page 13: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

PPAP Submission Level Table

S = Supplier shall submit to Donaldson & retain a copy of records or documentation items at appropriate locations

R = Supplier shall retain at appropriate locations

and make readily available to Donaldson

upon request

* = Supplier shall retain at appropriate

locations, and submit to Donaldson upon

request. Donaldson will identify what is needed

for submission.

Page 14: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Definition of Risk and PPAP level• High Risk

• Parts associated with multiple critical features, complex design, or high end technology that is not yet established in the general manufacturing environment

• Supplier’s quality system and/or quality performance is not to Donaldson satisfaction

• Medium Risk

• Parts that have at least one critical feature

• Low Risk

• Parts that have no critical features and can be manufactured by any manufacturer in the commodity category

• Supplier’s quality system and quality performance are acceptable

Page 15: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Submission Level Requirements• New Parts

• Level 2 is required for Low Risk Parts

• Level 3 is required for Medium and High Risk Parts

• Part Changes

• Level 3 is required for Parts produced at a new or additional location

• Supplier Quality Excellence will define the level required for all other changes

Donaldson reserves the right to redefine the submission level required

Page 16: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

PPAP StatusApproved- The part meets all Donaldson requirements- Supplier is authorized to ship production quantities of the part

Interim Approval- Donaldson permits shipment of part on a limited time and quantity clearly in

writing defined.

On Hold- SQA needs more info

Rejected- The part does not meet Donaldson requirements, based on the production

lot from which it was taken and/or accompanying documentation

Production quantities may not be shipped before Donaldson Approval

Page 17: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Electronic Submission Requirements• Donaldson requires that all PPAPs be submitted electronically

[email protected]

• Use of paper submission must have prior approval by the SQA

• Submission must be received on or prior to the PPAP due date

• Review and Approval Process:Donaldson will attempt to review and provide feedback within

3 business days

Donaldson requires all submissions to be electronic

Page 18: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Donaldson PPAP book• What is the Donaldson PPAP book?

An Excel spreadsheet containing templates of the documents

suppliers are required to submit to Donaldson.Organization formats are allowed as long these documents are

providing the same. (Preferred language is English)

• Why use the PPAP book?

Simplifies the process for suppliers by serving as a “checklist”

of what needs to be submitted to DonaldsonReduces the number of files to manageEnables the SQA / PPAP team to quickly see if anything is

missing

Show PPAP book “CORP SQADOC 004”

Page 19: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Part Submission Part Submission Warrant Warrant

Page 20: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Part Submission WarrantWhat is It?• Document required for all newly

tooled or revised products in which the supplier confirms that inspections and tests on production parts show conformance to Donaldson requirements

Objective or PurposeUsed to :

• document part approval• provide key information• declare that the parts meet

specification

When to Use It• Prior to shipping production parts

Have a closer look

Page 21: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Part Submission Warrant

Donaldson Part NumberEngineering released finished end item part number

Safety and/or Government Regulation“Yes” if so indicated by the Design Record,otherwise “No”

Engineering Change Level & DateShow the change level and date of the Design Record

Additional Engineering ChangesList all authorized Engineering changes not yet incorporated in the design record but which are incorporated in the part

Shown on Drawing NumberThe design record that specifies the customer part number being submitted

Checking Aid Number, Change Level, & DateEnter if requested by the customer

Purchase Order NumberEnter this number as found on the contract / purchase order

Product weightEnter the product weight

Page 22: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Part Submission Warrant

Donaldson LocationShow the location where parts will be shipped toBuyer / Buyer Code

Enter the buyer’s name and code

Restricted SubstancesEnter “Yes” or “No”

Model Name / NumberEnter the model nameand number

Parts Identified with Appropriate Marking CodesULUL = Underwriters Laboratories safety standardsCECE = Conformite Europeenne (European Conformity) –Certifies that a product has met European consumerSafety, health, or environmental requirementsISO = International Organization for StandardizationEnter “Yes” or “No”

Supplier Manufacturing InformationShow the name and code assigned tothe manufacturing site on the purchase order / contract

Page 23: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Part Submission WarrantReason For SubmissionCheck the appropriate box(es)

Requested Submission LevelIdentify the submission levelrequested by Donaldson

Submission ResultsCheck the appropriate boxes

Mold / Cavity / Production ProcessIf production parts will be produced from more than one mold, cavity, tool, die, pattern, or production process, the supplier shall complete a dimensional evaluation onone part from each. The specific molds,lines, etc. shall then be identified here.

Page 24: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Part Submission Warrant

The approved Production Warrant officially warrants the parts ready for production

DeclarationEnter the number of pieces manufactured during the significant production run and the time (in hours) takenfor the significant production run

Explanation / CommentsProvide any explanatory comments on thesubmission results or any deviationsfrom the Declaration. Attach additionalinformation as appropriate.

Supplier Authorized SignatureA responsible supplier official, after verifying that the results show conformance to all Donaldsonrequirements and that all required documentationis available, shall approve the declaration

For Donaldson Use OnlyTo be completed by appropriateDonaldson Supplier Quality Engineer

DeclarationAffirmation that the samples represented by the warrant are representative and were made by a process that meets Donaldson’s PPAP requirements

PPAP Warrant DispositionApproved, Rejected, OtherDonaldson Signature

Signed by Donaldson Supplier Quality Engineer

Page 25: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Part Submission Warrant

●Reviewers ChecklistMust be completely filled outMust be signed by the supplierPart Number must match the POSubmitted at the correct revision levelSubmitted at the correct submission levelSpecify the reason for submissionReport the approval / Reject to the PPAP team and the

APD team

Page 26: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

AUTHORIZED ENGINEERING AUTHORIZED ENGINEERING CHANGE DOCUMENTS CHANGE DOCUMENTS

Page 27: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Authorized Engineering Change Documents

● The supplier shall provide authorized change documents for those changes not yet recorded in the design record, but incorporated in the product, part or tooling, such as:

ECNs (must be approved, not pending)Specifications (ECO)Feasibility studiesSupplier change requestsSub-assembly drawingsLife or reliability testing requirements

Page 28: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

PROCESS FLOW DIAGRAM PROCESS FLOW DIAGRAM

Page 29: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Process Flow DiagramWhat is It?• A visual diagram of the entire

process from receiving through shipping, including outside processes and services

• To help people “see” the real process. Process maps can be used to understand the following characteristics of a process:

• Set-by-step process linkage• Offline activities (measurement,

inspection, handling)• Rework, scrap

Objective or Purpose

When to Use It• To understand how a process is

done• Prior to completing the PFMEA

OperatorGet Traveler andNest from Holding

Shelf(26)

OperatorPrints Cut Tags

(27)

OperatorLoad Machine with

Blanket(28)

OperatorDownload Cutting

Infomation(2s to 2m)

(29)

OperatorProgram

Command"Ready to Cut"

(30)

OperatorObserve Cutting

Operation forErrors(32)

Cutting Error?(33)

OperatorSeparate Cutting

Tags(31)

OperatorCutting Operation

Complete(34)

Large or Small Pliesor Test Coupons?

(35)

OperatorTag while Laying

on the CuttingTable(39)

OperatorRemove SmallPlies from theCutting Table

(36)

OperatorMove to Kitting

Table(37)

Small Plies

LargePiies

AndCoupons

OperatorRemove Plies

from the CuttingTable(40)

OperatorTag Small Plies

(38)

OperatorMove Plies toKitting Table

(41)

Yes

Evaluate forCorrective Action

OperatorStamp Traveler

(43)

TravelerComplete?

(42)

Yes

No

No

Project Idea

Fill Out MasterForm

with InitialInformation

Is HardSavings > $???

Does theProject Involve

Only YourGroup?

Does theProject Involve

>3 Depts.outside Eng?

Does theProject Involve>2 Groups in

Eng?

Do youhave BB/GB toAssist/Work the

project?

Prefer to workthis projectwithin your

area?

6 SigmaProject

Departmentor GroupProject

Yes

No

Yes

No

Yes

No

No

No

Yes

Yes

Yes No

Enter RemainingInformation onMaster Form

Master Form WillGenerateContract

Finance Approvaland Signature

Other RequiredSignatures:

Segment CEOChampion

Process OwnerBB or GB

6 Sigma AssignsProject Number

Get WO Assigned

Begin/WorkProject

Follow DMAIC orDFSS process

Monitor Progressthrough PowerSteering and

MonthlyFinancialReviews

Complete Project(Has to be fully

Documented

Finance Approvaland Signature

Other RequiredSignatures:

Champion: Dir T&EProcess OwnerProject Owner

Dept BB or MBB

Enter RemainingInformation onMaster Form

Master Form WillGenerateContract

Finance Approvaland Signature

Other RequiredSignatures:Champion:

Process OwnerProject Owner

Dept GB/BB/MBB

Group AssignsProject Number

Get DLNAssigned

Monitor Progressthrough Bi-

Weekly Updatesand Monthly

Reviews

Begin/WorkProject

Follow DMAIC orDFSS process

Complete Project(Has to be fullyDocumented)

Finance Approvaland Signature

Other RequiredSignatures:

Champion: Dir T&EProcess OwnerProject Owner

Dept BB or MBB

Complete allDocumentation

including a(1) Page Close-

out Sheet

CloseProject

Complete allDocumentation

including a(1) Page Close-

out Sheet

Final ProjectReview

CloseProject

Final ProjectReview

6 Sigma ProjectHigh Level Process Map

Department/Group ProjectHigh Level Process Map

Page 30: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Process Flow Diagrams

Page 31: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Process Flow Diagrams

●Reviewers ChecklistProcess Flow must identify each step in the processShould include abnormal handling processes

ScrapRework

Process Flow must include all phases of the processReceiving of raw materialPart manufacturingOffline inspections and checksAssemblyShipping

Page 32: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

PROCESS FMEA PROCESS FMEA

Page 33: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Process FMEA (PFMEA) CORP QEHSDOC 014

When to Use It• After completion of the process

flow diagram.• Prior to tooling for production

Failure Mode and Effects Analysis(Design FMEA) FMEA Number:

Page ofSystem/Component: Prepared by:

FMEA Date (Orig.) (Rev.)Core Team:

ActionsTakenSev

Occur

Detec

R.P.N.

Design Responsibility:

Action ResultsOccur

Current Design Controls

Prevention

Current Design Controls Detection

Detec

R.P.N.

Recommended Action(s)

Responsibility & Target Completion

Date

Potential Cause(s)/Mechanism(s) of

Failure

Item / Process

Function

Potential Failure Mode

Potential Effect(s) of Failure

Sev

What is It?• A tool used to identify and prioritize

risk areas and their mitigation plans.

The PFMEA should be completed

using a cross-functional team!

IMPORTANT!

Objective or Purpose

• Identifies potential failure modes, causes, and effects. Inputs come from the process flow diagram.

• Identifies key inputs which positively or negatively affect quality, reliability and safety of a product or process.

Page 34: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

FMEA Origin

• Created by NASA following Apollo 1 mission failure

• Allows us to take a proactive approach to what can go wrong in a process and manage our risks better

Page 35: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Process FMEA (PFMEA)

This is included in the PPAP book!

Page 36: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Spray head clogged: - Viscosity too high- Temp too low- Pressure too low

5 Variables check for film thickness; Visual check for coverage; Test spray at start-up and after idle periods and preventative maintenance program to clean heads

5 175

Detec

R.P

.N.

Class

Potential Cause(s)/

Mechanism(s) of Failure

Occur

Current Process Controls

Process StepPotential Failure

Mode

Potential Effect(s) of

Failure

Sev

280Allows integrity breach of inner

door panel

Corroded interior lower door

panels

Deteriorated life of door leading

to: - Unsatisfactory appearance due to rust through paint over time

- Impaired function of

interior door hardware

Insufficient wax coverage over

specified surface

Op 70: Manual application of

wax inside door panel

7 Manually inserted spray

head not inserter far

enough

Variables check for film

thickness; Visual check for coverage

58

PFMEA - Step 1

TIPS• There should be at least one failure mode for each input.

Using the completed Process Flow Diagram, enter the process step.

Failure ModesFor each Process Input, determine the ways in which the input can gowrong.

Page 37: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Spray head clogged: - Viscosity too high- Temp too low- Pressure too low

5 Variables check for film thickness; Visual check for coverage; Test spray at start-up and after idle periods and preventative maintenance program to clean heads

5 175

Detec

R.P

.N.

Class

Potential Cause(s)/

Mechanism(s) of Failure

Occur

Current Process Controls

Process StepPotential Failure

Mode

Potential Effect(s) of

Failure

Sev

280Allows integrity breach of inner

door panel

Corroded interior lower door

panels

Deteriorated life of door leading

to: - Unsatisfactory appearance due to rust through paint over time

- Impaired function of

interior door hardware

Insufficient wax coverage over

specified surface

Op 70: Manual application of

wax inside door panel

7 Manually inserted spray

head not inserter far

enough

Variables check for film

thickness; Visual check for coverage

58

PFMEA - Step 2

TIPS

• There should be at least one failure effect for each failure mode.

• Effects should be specific, clear, and leave no doubt to the uninformed reviewer.

Potential Failure EffectsFor each Failure Mode, determine what effectthe specific failure could have on the process output.

Page 38: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Spray head clogged: - Viscosity too high- Temp too low- Pressure too low

5 Variables check for film thickness; Visual check for coverage; Test spray at start-up and after idle periods and preventative maintenance program to clean heads

5 175

280Allows integrity breach of inner

door panel

Corroded interior lower door

panels

Deteriorated life of door leading

to: - Unsatisfactory appearance due to rust through paint over time

- Impaired function of

interior door hardware

Insufficient wax coverage over

specified surface

Op 70: Manual application of

wax inside door panel

7 Manually inserted spray

head not inserted far

enough

Variables check for film

thickness; Visual check for coverage

58

Occur

Current Process Controls

Process StepPotential Failure

Mode

Potential Effect(s) of

Failure

Sev

Detec

R.P

.N.

Class

Potential Cause(s)/

Mechanism(s) of Failure

PFMEA - Step 3

TIPS• There should be at least one potential cause for each failure mode.

Potential CausesFor each Failure Mode, determine the possible cause of the failure.

Page 39: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Spray head clogged: - Viscosity too high- Temp too low- Pressure too low

5 Variables check for film thickness; Visual check for coverage; Test spray at start-up and after idle periods and preventative maintenance program to clean heads

5 175

Detec

R.P

.N.

Class

Potential Cause(s)/

Mechanism(s) of Failure

Occur

Current Process Controls

Process StepPotential Failure

Mode

Potential Effect(s) of

Failure

Sev

280Allows integrity breach of inner

door panel

Corroded interior lower door

panels

Deteriorated life of door leading

to: - Unsatisfactory appearance due to rust through paint over time

- Impaired function of

interior door hardware

Insufficient wax coverage over

specified surface

Op 70: Manual application of

wax inside door panel

7 Manually inserted spray

head not inserter far

enough

Variables check for film

thickness; Visual check for coverage

58

TIPS

• This step in the FMEA begins to identify initial shortcomings or gaps in the current control plan.

• If a procedure exists, enter the document number.

• If no current control exists, list as “none.”

Current ControlsFor each potentialcause, list the currentmethod used for preventing or detectingfailure.

PFMEA - Step 4

Page 40: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Spray head clogged: - Viscosity too high- Temp too low- Pressure too low

5 Variables check for film thickness; Visual check for coverage; Test spray at start-up and after idle periods and preventative maintenance program to clean heads

5 175

Detec

R.P

.N.

Class

Potential Cause(s)/

Mechanism(s) of Failure

Occur

Current Process Controls

Process StepPotential Failure

Mode

Potential Effect(s) of

Failure

Sev

280Allows integrity breach of inner

door panel

Corroded interior lower door

panels

Deteriorated life of door leading

to: - Unsatisfactory appearance due to rust through paint over time

- Impaired function of

interior door hardware

Insufficient wax coverage over

specified surface

Op 70: Manual application of

wax inside door panel

7 Manually inserted spray

head not inserter far

enough

Variables check for film

thickness; Visual check for coverage

58

PFMEA - Step 5● Assign Severity, Occurrence, and Detection ratings

Assign Severity(How serious is the effect if it fails?)

Assign Occurrence(How likely is the cause to occur?)

Assign Detection(How easily can the cause or failure mode be detected?)

Severity, Occurrence and Detection rating details on next slide

Page 41: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

PFMEA - Definition of Terms

● SeveritySeverity (of Effect)SSeverity of the effect on the Customer and other stakeholders (Higher Value = Higher Severity)

● Occurrence Occurrence (of Cause)Frequency with which a given Cause occurs and creates Failure Mode. ((Higher Value = Higher Probability of Occurrence))

● DetectionDetection (Capability of Current Controls) - ability of current Control scheme to detect the cause before creating the failure mode and/or the failure mode before suffering the effect ((Higher Value = Lower Ability to Detect))

Caution: Notice the scale difference for DetectionDetection!

Page 42: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

High 10

Low 1

RatingSeverity Occurrence Detection*

Hazardous without warning

Very high and almost

inevitable

Cannot detect or detection with very low

probability

Loss of primary function

High repeated failures

Remote or low chance of detection

Loss of secondary function

Moderate failures

Low detection probability

Minor defect Occasional failures

Moderate detection

probability

No effect Failure unlikely Almost certain detection

*If No Controls Exist, Detection = 10

Referring too 4th Edition FMEA Manualand the scales in Donaldson PPAP workbook.

An Example of Rating Definitions

Page 43: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Spray head clogged: - Viscosity too high- Temp too low- Pressure too low

5 Variables check for film thickness; Visual check for coverage; Test spray at start-up and after idle periods and preventative maintenance program to clean heads

5 175

Detec

R.P

.N.

Class

Potential Cause(s)/

Mechanism(s) of Failure

Occur

Current Process Controls

Process StepPotential Failure

Mode

Potential Effect(s) of

Failure

Sev

280Allows integrity breach of inner

door panel

Corroded interior lower door

panels

Deteriorated life of door leading

to: - Unsatisfactory appearance due to rust through paint over time

- Impaired function of

interior door hardware

Insufficient wax coverage over

specified surface

Op 70: Manual application of

wax inside door panel

7 Manually inserted spray

head not inserter far

enough

Variables check for film

thickness; Visual check for coverage

58

TIPS

• The RPN is used to prioritize the most critical risks identified in the first half of the FMEA.

• High RPNs (150 or above) are flags to take effort to reduce the calculated risk.

• Regardless of RPN, high Severity scores (9 or 10) should be given special attention.

Calculate the Risk Priority Number

RPNRPN = Severity x Occurrence x Detection

PFMEA - Step 6

Page 44: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

• Once the RPN Numbers are determined, they can be used to prioritize the most significant failure modes.

• Sort the FMEA by the RPN numbers. Graphical and statistical tools can help the team select a “cut-off” RPN for the next steps.

RPN Thresholds• When using an RPN threshold, DO

NOT forget to address high Severity scoresOthers

490150 75 9350 70 50 25 30

250300 15

3 2 2 2 2 4 4 4 4 6 8 910

5 3 3 3 3 7 7 7 710131517

100 95 92 88 85 82 75 68 62 55 45 32 17

60

50

40

30

20

10

0

100

80

60

40

20

0

Defect

CountPercentCum %

Per

cent

Co

unt

Pareto Chart for RPN

Pareto Chart

?How many items should be the focus of the next steps?

Sort by RPN to determinethe most significant failure modes

Analyzing the PFMEA

Page 45: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

PFMEA – Remediation Guidelines

● SeveritySeverityCan only be improved by a design change to the product or process

● OccurrenceOccurrenceCan only be reduced by a change which removes or controls a cause. Examples are redundancy, substituting a more reliable component or function or mistake-proofing.

● DetectionDetectionCan be reduced by improving detection. Examples are mistake-proofing, simplification and statistically sound monitoring.

In general, reducing the Occurrence is preferable to improving the Detection

In general, reducing the Occurrence is preferable to improving the Detection

Page 46: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Actions Taken

Sev

Occ

Det

R.P

.N.

Add positive depth stop to sprayer

Mfg. Eng. By 5/10/10

Stop added, sprayer checked on-line

Automate spraying

Mfg. Eng. By 5/25/10

Rejected due to complexity of different doors on the same line

175 Use DOE on viscosity vs. temp vs. pressure

Mfg. Eng. By 5/31/10

Temp and press limits were determined and limit controls have been installed - Control charts show process is in control Cpk = 1.85

7 1 5 35

Action Results

R.P

.N.

Recommended Actions

Responsibility & Target Date

Process StepPotential Failure

Mode

Potential Effect(s) of

Failure

280Allows integrity breach of inner

door panel

Corroded interior lower door

panels

Deteriorated life of door leading

to: - Unsatisfactory appearance due to rust through paint over time

- Impaired function of

interior door hardware

Insufficient wax coverage over

specified surface

Op 70: Manual application of

wax inside door panel

7 2 5 70

FMEA – Step 7• Determine Actions Recommended to reduce High RPNs

For the high RPN numbers, determine the recommended actions.

Page 47: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Actions TakenS

ev

Occ

Det

R.P

.N.

Add positive depth stop to sprayer

Mfg. Eng. By 5/10/10

Stop added, sprayer checked on-line

Automate spraying

Mfg. Eng. By 5/25/10

Rejected due to complexity of different doors on the same line

175 Use DOE on viscosity vs. temp vs. pressure

Mfg. Eng. By 5/31/10

Temp and press limits were determined and limit controls have been installed - Control charts show process is in control Cpk = 1.85

7 1 5 35

Action Results

R.P

.N.

Recommended Actions

Responsibility & Target Date

Process StepPotential Failure

Mode

Potential Effect(s) of

Failure

280Allows integrity breach of inner

door panel

Corroded interior lower door

panels

Deteriorated life of door leading

to: - Unsatisfactory appearance due to rust through paint over time

- Impaired function of

interior door hardware

Insufficient wax coverage over

specified surface

Op 70: Manual application of

wax inside door panel

7 2 5 70

FMEA – Steps 8 and 9

• Now recalculate your RPNs based on mitigation plans.TIPS:

  Continue updating the actions taken and resulting RPNs until all risks are at an acceptable level (below 100).

Resp (responsibility)Assign a specific person who will be responsible for recommended actions.

Actions TakenAs actions are identified and completed, document in the “Actions Taken” column.

SEV, OCC, DET, RPNAs actions are complete reassess Severity, Occurrence, and Detection and recalculate RPN.

Page 48: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Summary Steps To Complete a FMEA1. For each Process Input, determine the ways in which the Process Step

can go wrong (these are Failure Modes).

2. For each Failure Mode associated with the inputs, determine Effects on the outputs.

3. Identify potential Causes of each Failure Mode.

4. List the Current Controls for each Cause.

5. Assign Severity, Occurrence and Detection ratings after creating a ratings key appropriate for your project.

6. Calculate RPN.

7. Determine Recommended Actions to reduce High RPNs.

8. Take appropriate Actions and Document.

9. Recalculate RPNs.

10. Revisit steps 7 and 8 until all the significant RPNs have been addressed.

Page 49: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Tips and Lessons Learned

• Collaborative Effort: Do not try alone, use a group

• Very comprehensive: Time consuming process. Take necessary breaks.

• Action items are required for completion

• Train team ahead of time by explaining scoring criteria

• Proper preparation is needed for meetings

• Summarize often: FMEA is a living document

Process FMEA (PFMEA)

Page 50: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Process FMEA (PFMEA)

●Reviewers ChecklistVerify there is a system for prioritizing risk of failure such as RPN

numbers of 150 or aboveMake sure that high RPN process concerns are carried over into the

control planMake sure that all critical failure modes are addressed

SafetyForm, fit, functionMaterial concerns

Page 51: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

CONTROL PLAN CONTROL PLAN

Page 52: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Control Plan

A document that describes how to control the critical inputs to continue to meet customer expectations of the output.

What is It?

Objective or Purpose• Primary reference source for

minimizing process and product variation.

• Description of how teams should react to out-of-control situations.

Since processes are expected to be continuously

updated and improved, the control plan

is a living document!

NOTEWhen to Use It

• Implementation of new process• Following a process change

Page 53: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Process StepsProcess Steps

New/Revised Process Steps

New/Revised Process Steps

Project Idea

Fill Out MasterForm

with InitialInformation

Is HardSavings > $???

Does theProject Involve

Only YourGroup?

Does theProject Involve

>3 Depts.outside Eng?

Does theProject Involve>2 Groups in

Eng?

Do youhave BB/GB toAssist/Work the

project?

Prefer to workthis projectwithin your

area?

6 SigmaProject

Departmentor GroupProject

Yes

No

Yes

No

Yes

No

No

No

Yes

Yes

Yes No

Enter RemainingInformation onMaster Form

Master Form WillGenerateContract

Finance Approvaland Signature

Other RequiredSignatures:

Segment CEOChampion

Process OwnerBB or GB

6 Sigma AssignsProject Number

Get WO Assigned

Begin/WorkProject

Follow DMAIC orDFSS process

Monitor Progressthrough PowerSteering and

MonthlyFinancialReviews

Complete Project(Has to be fully

Documented

Finance Approvaland Signature

Other RequiredSignatures:

Champion: Dir T&EProcess OwnerProject Owner

Dept BB or MBB

Enter RemainingInformation onMaster Form

Master Form WillGenerateContract

Finance Approvaland Signature

Other RequiredSignatures:Champion:

Process OwnerProject Owner

Dept GB/BB/MBB

Group AssignsProject Number

Get DLNAssigned

Monitor Progressthrough Bi-

Weekly Updatesand Monthly

Reviews

Begin/WorkProject

Follow DMAIC orDFSS process

Complete Project(Has to be fullyDocumented)

Finance Approvaland Signature

Other RequiredSignatures:

Champion: Dir T&EProcess OwnerProject Owner

Dept BB or MBB

Complete allDocumentation

including a(1) Page Close-

out Sheet

CloseProject

Complete allDocumentation

including a(1) Page Close-

out Sheet

Final ProjectReview

CloseProject

Final ProjectReview

6 Sigma ProjectHigh Level Process Map

Department/Group ProjectHigh Level Process Map

Project Idea

Fill Out MasterForm

with InitialInformation

Is HardSavings > $???

Does theProject Involve

Only YourGroup?

Does theProject Involve

>3 Depts.outside Eng?

Does theProject Involve>2 Groups in

Eng?

Do youhave BB/GB toAssist/Work the

project?

Prefer to workthis projectwithin your

area?

6 SigmaProject

Departmentor GroupProject

Yes

No

Yes

No

Yes

No

No

No

Yes

Yes

Yes No

Enter RemainingInformation onMaster Form

Master Form WillGenerateContract

Finance Approvaland Signature

Other RequiredSignatures:

Segment CEOChampion

Process OwnerBB or GB

6 Sigma AssignsProject Number

Get WO Assigned

Begin/WorkProject

Follow DMAIC orDFSS process

Monitor Progressthrough PowerSteering and

MonthlyFinancialReviews

Complete Project(Has to be fully

Documented

Finance Approvaland Signature

Other RequiredSignatures:

Champion: Dir T&EProcess OwnerProject Owner

Dept BB or MBB

Enter RemainingInformation onMaster Form

Master Form WillGenerateContract

Finance Approvaland Signature

Other RequiredSignatures:Champion:

Process OwnerProject Owner

Dept GB/BB/MBB

Group AssignsProject Number

Get DLNAssigned

Monitor Progressthrough Bi-

Weekly Updatesand Monthly

Reviews

Begin/WorkProject

Follow DMAIC orDFSS process

Complete Project(Has to be fullyDocumented)

Finance Approvaland Signature

Other RequiredSignatures:

Champion: Dir T&EProcess OwnerProject Owner

Dept BB or MBB

Complete allDocumentation

including a(1) Page Close-

out Sheet

CloseProject

Complete allDocumentation

including a(1) Page Close-

out Sheet

Final ProjectReview

CloseProject

Final ProjectReview

6 Sigma ProjectHigh Level Process Map

Department/Group ProjectHigh Level Process Map

Process FlowchartProcess Flowchart

New/Revised

Process Steps

New/Revised

Process Steps

Process Steps

Process Steps

Process StepKey

Process Input

Potential Failure Mode

Potential Failure Effects

SEV

Potential CausesOCC

Current ControlsDET

RPN

EOC

Actions Recommended

Resp. Actions Taken

Receive Payment

Checks Delay internal mail

AR balance does not go down

7

Inadequate staffing in mail room 7

None

10 490

Investigate mail room staffing and associated processes

G. Lee

7 1 10 70

Identify Customer

Wire Transfer reference line

Information not supplied

AR balance is past due

10

Customer or bank did not include name and/or account info on wire transfer

5

Acct identifies problem when trying to apply payment

5 250

Poka-Yoke wire transer process

N. Peart

10 1 3 30

Identify Invoice Checks Incorrect invoice supplied

Invoice shows outstanding (AR balance does go down)

5

Customer error

5

Customer might catch it when reviewing the next statement 10 250

Provide payment stub with statement for each invoice

A. Lifeson

5 1 5 25

Identify Invoice Checks Invoice number not supplied

Invoice shows outstanding (AR balance does go down)

5

Customer error

10

Acct identifies problem when trying to apply payment 5 250

Provide payment stub with statement for each invoice

S. Hagar

5 1 5 25

Process StepKey

Process Input

Potential Failure Mode

Potential Failure Effects

SEV

Potential CausesOCC

Current ControlsDET

RPN

EOC

Actions Recommended

Resp. Actions Taken

Receive Payment

Checks Delay internal mail

AR balance does not go down

7

Inadequate staffing in mail room 7

None

10 490

Investigate mail room staffing and associated processes

G. Lee

7 1 10 70

Identify Customer

Wire Transfer reference line

Information not supplied

AR balance is past due

10

Customer or bank did not include name and/or account info on wire transfer

5

Acct identifies problem when trying to apply payment

5 250

Poka-Yoke wire transer process

N. Peart

10 1 3 30

Identify Invoice Checks Incorrect invoice supplied

Invoice shows outstanding (AR balance does go down)

5

Customer error

5

Customer might catch it when reviewing the next statement 10 250

Provide payment stub with statement for each invoice

A. Lifeson

5 1 5 25

Identify Invoice Checks Invoice number not supplied

Invoice shows outstanding (AR balance does go down)

5

Customer error

10

Acct identifies problem when trying to apply payment 5 250

Provide payment stub with statement for each invoice

S. Hagar

5 1 5 25

Process FMEAProcess FMEA

Risk P

riorit

ized

Proce

ss S

teps

Risk P

riorit

ized

Proce

ss S

teps

Impro

ved

Contr

ols

Impro

ved

Contr

ols

Control PlanControl Plan

Tool Interaction

Control Plan

Page 54: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Control Plan

This is included in the PPAP book!

Page 55: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Control Plan

3 Distinct Phases1. Prototype – a description of the

dimensional measurements and material and performance tests that will occur during Prototype build.

3 Distinct Phases

3 Distinct Phases2. Pre-Launch – a description of the

dimensional measurements and material and performance tests that will occur after Prototype and before full Production.

3 Distinct Phases3. Production – a comprehensive

documentation of product/process characteristics, process controls, tests, and measurement systems that will occur during mass production

Page 56: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Control Plan

Administrative SectionIdentifies part number and description, supplier, required approval signatures,

and dates.

Administrative Section

Page 57: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Control Plan

Part/ProcessUse this area to define

part/process number and description.

Machine/ToolsList the machine, device, jig, or tools

that will be used in the manufacturing process

CharacteristicsDefine the characteristics of the product or process

Process, Machine/Tools, Characteristics

Page 58: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Control Plan

Specifications/ToleranceUse this area to define upper/lower

spec limits for each control element.

Measurement TechniqueFor each line in the control plan, list the measurement procedure that will be used (may list R&R Gage Plan or Poka-Yoke).

Sample SizeWhat is the size of the

sample you should gather data from?

FrequencyDefine the frequency for which the measurement

will be taken.

Specifications, Measurement, Sample Size & Frequency

Page 59: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Control Plan

Control MethodMethod that will be used

to control the process

Reaction PlanActions to be taken if

controls fail

Control Method, Reaction Plan

Page 60: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Control Plan

• Audit plans should be included in the control plan as a separate line.• Auditing is an important tool for control.• Process auditing should be a key element of the quality system of a

business.• Audits generally cover:

Effectiveness of controlsControl plan (say) vs. what is actually done (do)

• Audits should be objective (done by internal or external third parties if possible).

• Audit frequencies should be based on balancing level of risk (FMEA) and cost.

Audit Plans

Page 61: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Control Plan

Use process flow diagram and PFMEA to build the control plan; keep them aligned

Controls must be used to be effective. Keep it simple.Ensure that the control plan is in the document control system of the

business.Good control plans address:

All testing requirements - dimensional, material, and performanceAll product and process characteristics at every step throughout the processAn periodical Audit. (Audit Frequency indicated and data stamp for next Audit given!)

The control method should be based on an effective analysis of the processSuch as SPC, Error Proofing, Inspection, Sampling Plan

Control plans should reference other documentationSpecifications, tooling, etc.

Reviewer’s Checklist

Page 62: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

MEASUREMENT SYSTEM MEASUREMENT SYSTEM ANALYSIS (MSA) ANALYSIS (MSA)

Page 63: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Measurement System Analysis (MSA) Gage R&R

An G R&R is a statistical tool used to determine if a measurement system is capable of precise measurement.

What is It?

Objective or Purpose• To determine how much error is in

the measurement due to the measurement process itself.

• Quantifies the variability added by the measurement system.

• Applicable to attribute data and variable data.

When to Use It• On the critical inputs and outputs

prior to collecting data for analysis.• For any new or modified process in

order to ensure the quality of the data.

Measurement System Analysis is an analysis of the measurement process, not an analysis of the people!!

IMPORTANT!Who Should be Involved

Everyone that measures and makes decisions about these measurements should be involved in the MSA.

Page 64: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

– AttributeAttribute Data Examples:

Count, Pass/fail, yes/no, red/green/yellow, timekeeping buckets

– VariableVariable Data Examples:

Physical measurement (length, width, area, …)

Physical conditions (temperature, pressure…)

Physical properties (strength, load, strain…)

Continuous or non-ending

Attribute and Variable MSA

Unless approved by an Donaldson SQA, attribute data is not acceptable for PPAP submission

Unless approved by an Donaldson SQA, attribute data is not acceptable for PPAP submission

Page 65: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Measurement System Analysis (MSA)

Process VariationProcess Variation

Measurement System Variation

Measurement System Variation

Observed Variation

Observed Variation

The observed variation in process output measurements is not simply the variation in the process itself; it is the variation in the process plus the variation in measurement that results from an inadequate measurement system.     

Conducting an MSA reduces the likelihood of passing a bad part or rejecting a good part

Page 66: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Measurement System Analysis (MSA)

Process VariationProcess Variation

Measurement System Variation

Measurement System Variation

Observed Variation

Observed Variation

The output of the process measured by:

• Cycle time• Dimensional data• Number of defects and others

Observed Variation

Page 67: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Observed Variation

Observed Variation

Process Variatio

n

Process Variatio

n

Measurement System Variation

Measurement System Variation

ReproducibilityReproducibility

Precision(Variability)

Precision(Variability)

LinearityLinearity

BiasBias

StabilityStability

ResolutionResolution

RepeatabilityRepeatability

Accuracy(Central Location)

Accuracy(Central Location)

Observed Variation

Calibration addresses accuracy

Measurement System Analysis (MSA)

Page 68: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Observed Variation

Observed Variation

Observed Variation

Process Variatio

n

Process Variatio

n

Measurement System Variation

Measurement System Variation

Precision(Variability)

Precision(Variability)

LinearityLinearity

BiasBias

StabilityStability

ResolutionResolution

RepeatabilityRepeatability

ReproducibilityReproducibility

Accuracy

(Central Location)

Accuracy

(Central Location)

Calibration Addresses AccuracyLet’s take a closer look

at Precision

Measurement System Analysis (MSA)

Page 69: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Measurement System Analysis (MSA)

Error in ResolutionThe inability to detect small changes.

Possible Cause Wrong measurement device selected - divisions on scale not fine enough to detect changes.

Resolution

Page 70: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Measurement System Analysis (MSA)

Error in RepeatabilityThe inability to get the same answer from repeated measurements made of the same item under absolutely identical conditions.

Possible Cause Lack of standard operating procedures (SOP), lack of training, measuring system variability.

Repeatability

Equipment Equipment VariationVariation

Page 71: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Measurement System Analysis (MSA)

Error in ReproducibilityThe inability to get the same answer from repeated measurements made under various conditions from different inspectors.

Possible Cause Lack of SOP, lack of training.

Reproducibility

Appraiser Appraiser VariationVariation

Page 72: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Variable MSA – Gage R&R Study

• Gage R&R is the combined estimate of measurement system RepeatabilityRepeatability and ReproducibilityReproducibility

• Typically, a 3-person study is performedEach person randomly measures 10 marked parts per

trialEach person can perform up to 3 trials

• There are 3 key indicatorsEVEV or Equipment VariationAVAV or Appraiser VariationOverall % GRR% GRR

Page 73: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Donaldson’s Gage R&R Form

Included in PPAP Playbook!

Automatically calculates EV, AV, and % GRR!

Page 74: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Variable MSA – Gage R&R Steps

1. Select 10 items that represent the full range of long-term process variation.

2. Identify the appraisers.

3. If appropriate, calibrate the gage or verify that the last calibration date is valid.

4. Open the Gage R&R worksheet in the PPAP book to record data.

5. Have each appraiser assess each part 3 times (trials – first in order, second in reverse order, third random).

6. Input data into the Gage R&R worksheet.

7. Enter the number of operators, trials, samples and specification limits

8. Analyze data in the Gage R&R worksheet.

9. Assess MSA trust level.

10. Take actions for improvement if necessary.

Step 1 Step 3 Step 4 Step 5 Step 6 Step 7 Step 8 Step 9 Step 10Step 2

Page 75: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Steps 1 and 2: Variable MSA - Gage R&R

Select 10 items that represent

the full range of long-term process

variation.Step 1

Identify the appraisers.

– Should use individuals that actually do the process being tested.

– Can also include other appraisers (supervisors, etc.).

– Should have a minimum of 3 appraisers.

Step 2

Page 76: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Steps 3 and 4: Variable MSA – Gage R&R

If appropriate, calibrate the gage

or verify that the last calibration

date is valid.Step 3

Open the Gage R&R worksheet in the

PPAP book to record the data

Step 4

Page 77: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Step 5: Variable MSA – Gage R&R

Have each appraiser assess each item 3 times.• Each appraiser has to work independently.• Items should be evaluated in random

order.• After each appraiser completes the first

evaluation of all items – repeat the process at least 2 more times.

• Do not let the appraisers see any of the data during the test !!

Step 5

Page 78: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Steps 6 and 7: Variable MSA – Gage R&R

Input data into the Gage R&R worksheet

Enter the number of operators, trials, samples and specification limits

Step 6

Step 7

Page 79: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Steps 8 and 9: Variable MSA – Gage R&R

Analyze data in the Gage R&R worksheet

Assess MSA Trust Level.

– Red:Red: > 30% (fail)

– Yellow:Yellow: 10-30% (marginal)

– Green:Green: < 10% (pass)

Step 9

Step 8

% Tolerance*

10%

30%

Page 80: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Step 10: Variable MSA – Gage R&R

If the Measurement System needs improvement:

• Brainstorm with the team for improvement solutions.• Determine best “practical solution” (may require some experimentation).• Pilot the best solution (PDSA)• Implement best solution – train employees.• Re-run the study to verify the improvement.

Step 10

Page 81: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

MSA Parameters

» (3) Operators

» (3) Trials

» (10) Samples

Problem Statement• The sulfuric acid concentration in process tank 8 is measured at least

once per day

• Additions/deletions of chemicals and decisions to shut down the process are dependent on these results.

• Based on current data, we need to do an MSA.

A Gage R&R was conducted in order to validate the process.

MSA Process

Variable MSA – Gage R&R Example

Page 82: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Selected 10 samples to be measured

Chose 3 operators to be appraisers

Had each appraiser measure each

sample 3 times

Results calculated automatically

Entered the number of operators, trials,

and samples

Entered upper and lower process

specification limits

Variable MSA – Gage R&R Example

Page 83: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Variable MSA – Gage R&R Example

Repeatability = (EV) Equipment Variation

Repeatability = (EV) Equipment VariationReproducibility = (AV) Appraiser Variation

Reproducibility = (AV) Appraiser VariationRepeatability & Reproducibility = R&R

Repeatability & Reproducibility = R&R

% Tolerance*

10%

30%% Tolerance is > 30%

MSA fails!

Page 84: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Important: An MSA is an analysis of the process, not an analysis of the people. If an MSA fails, the process failed.

A Variable MSA provides more analysis capability than an Attribute MSA. For this and other reasons, always use variable data if possible.

The involvement of people is the key to success.Involve the people that actually work the processInvolve the supervisionInvolve the suppliers and customers of the process

An MSA primarily addresses precision with limited accuracy information.

Tips and Lessons Learned

Page 85: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

MSA – Gage R&R

If the gage/inspection affects quality, then conduct a Gage R&RMake sure the study is recent - less than 1 yearCompare the control plan gages against the Gage R&RsIf you question that gage, then

−Question the technique and part sampling

−Ask for additional studies

Reviewer’s Checklist

Page 86: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

DIMENSIONAL RESULTS DIMENSIONAL RESULTS

Page 87: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Dimensional Results

Evidence that dimensional verifications have been completed and results indicate compliance with specified requirements.

What is It?

Objective or Purpose• To show conformance to the

customer part print on dimensions and all other noted requirements.

When to Use It• For each unique manufacturing

process (e.g., cells or production lines and all molds, patters, or dies

Page 88: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Donaldson Dimensional Report (Critical)

Requires 35 data pointsRequires 35 data points

CpkCpk must be greater than or equal to 1.671.67

This is included in the PPAP book!

Automatically

Calculates Cpk!

Page 89: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Acceptance Criteria

Critical Non-Critical Decision

Red (Bad) <1.33 <1.00

Yellow (OK) 1.33-1.67 1.00-1.33

Green (Good) >1.67 >1.33

Acceptance criteria for critical vs. non-critical characteristics

CpkCpk must be greater than or equal to 1.67 for 1.67 for criticalcritical

processesprocesses

CpkCpk must be greater than or equal to 1.33 for 1.33 for non-criticalnon-critical

processesprocesses

Page 90: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Donaldson Dimensional Report Example

Nominal ValueTolerance Sample DataCp & Cpk

CalculationsPass / Fail

CpkCpk > 1.33 for all 1.33 for all non-criticalnon-critical dimensions = Pass!dimensions = Pass!

Page 91: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Dimensional Results

Thirty-five critical data points & 5 non-critical data points are required for part qualification

Critical and non-critical data points must be taken from the same 35-piece sampleFive parts from a production run must be shipped to Donaldson for verification of

form, fit, and functionThe same 5 parts will be used to verify both critical and non-critical dimensionsSupplier must clearly identify which of the 35 parts are being shippedSupplier should make every effort to ship 3 parts that represent both the low and

high ends of the specifications for non-critical dimensionsCapability must be greater than 1.67 for critical dimensions and greater than 1.33

for non-critical dimensions

Reviewer’s Checklist

Page 92: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

RECORDS OF MATERIAL / RECORDS OF MATERIAL / PERFORMANCE TEST PERFORMANCE TEST

RESULTS RESULTS

Page 93: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Records of Material/Performance Test Results

Material Test ResultsMaterial Test ResultsThe supplier shall perform tests for all parts and product

materials when chemical, physical, or metallurgical requirements are specified by the design record or Control Plan

For products with Donaldson-developed material specifications and/or an Donaldson-approved supplier list, the supplier shall procure materials and/or services from suppliers on that list

Performance Test ResultsPerformance Test ResultsThe supplier shall perform tests for all parts or product

materials when performance or functional requirements are specified by the design record or Control Plan

Page 94: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Material Results

Page 95: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Module Test Results

Page 96: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

QUALIFIED LABORATORY QUALIFIED LABORATORY DOCUMENTATIONDOCUMENTATION

Page 97: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Qualified Laboratory Documentation

• Inspection and testing for PPAP shall be performed by a qualified laboratory as defined by Donaldson requirements (e.g., an accredited laboratory).

• The qualified laboratory (internal or external to the supplier) shall have a laboratory scope and documentation showing that the laboratory is qualified for the type of measurements or tests conducted

When an external laboratory is used, the supplier shall submit the test results on the laboratory letterhead or the normal laboratory report format

The name of the laboratory that performed the tests, the date(s) of the tests, and the standards used to run the tests shall be identified.

Page 98: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

APPEARANCE APPROVALAPPEARANCE APPROVALREPORTREPORT

Page 99: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Appearance Approval Report

When to Use It• Prior to tooling for production

What is It?• A report completed by the supplier

containing appearance and color criteria

Typically only applies for parts with color, grain,

or surface appearance requirements

IMPORTANT!

Objective or Purpose

• To demonstrate that the part has met the appearance requirements on the design record

Page 100: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Appearance Approval ReportAdministrative Section

Supplier Sourcing & Texture InformationList all first surface tools, grainingSource(s), grain type(s), and grain and Gloss masters used to check part

Pre-Texture EvaluationTo be completed by SQE

Page 101: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Appearance Approval Report

Color Suffix

Master Number

Master Date

Material Type

Material Source

Color Shipping

Suffix

Part Disposition

DL* Da* Db* DE CMC Red Yel Grn Blu Light Dark Gray CleanHigh Low High Low

Color Evaluation

Comments:

Supplier Signature Phone No. Date Customer Representative Signature Date

ChromaMetallic

BrillianceGlossTristimulus Data Hue Value

Color SuffixAlphanumeric or numeric color identification

Tristimulus DataList numerical (colorimeter) data of submission part as compared to the customer-authorized master

Master NumberEnter alphanumeric master identification

Master DateEnter the date on which the master was approved

Material TypeIdentify first surface finish and substrate (e.g. paint / ABS)

Material SourceIdentify first surface and substrate suppliers

Hue, Value, Chroma, Gloss, and Metallic BrillianceVisual assessment by Donaldson

Color Shipping SuffixColor part number suffix or color number

Part DispositionTo be determined by Donaldson (approved or rejected)

Tristimulus data

Page 102: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

SAMPLE PRODUCTION SAMPLE PRODUCTION PARTSPARTS

Page 103: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Sample Production Parts

Actual samples that reflect the parts documented in the PPAP.

What is It?

Objective or Purpose

• Confirm cosmetic or functional part approval.

When to Use It

• Sample parts should be delivered WITH the PPAP submission

Page 104: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Sample Production Parts

• The sample parts provided should be the same parts measured for the dimensional results

• Default quantity for all submissions is 3 parts unless otherwise requested

Page 105: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Sample Production Parts

● Sample production parts MUST be properly identified • Include the following information on the part label:

- Shipping date-Donaldson part number-Quantity submitted- Supplier part number (optional)-Donaldson Part name-Carrier name-Country of origin- Tracking number-Approval markings (UL, CE, etc.) where applicable

See Donaldson part label examples on the next

slide

Page 106: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

Part Label Example

0Yes NoYes No

NameNumber

Shipping quantityCountry of origin

PPAP sample submission To:Donaldson Italia S.r.l., Via Dell’Industria 17, I-46035 Ostiglia (Mantova), Italy

Sample with PPAP?Sample Parts separate submittedShipping CarrierTracking Number

00

0

Supplier NamePart NamePart NumberPart revision level

Shipping date

PPAP Workbook includes these PPAP samples submission labels.Where applicable, fields get filled out automatically by filling out the PPAP submission sheet.

Page 107: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

PPAP Summary• The Production Part Approval Process is an

extensive approval process for new or changed designs or processes

• It is very formalized, so it inevitably causes some administrative work

• Later changes to the product or process can be expensive and time-consuming!

Page 108: Donaldson EMEA Supplier Quality Assurance PPAP TRAINING January 2013 CORP MAN 006 PPAP WORKBOOK TRAINING – Rev 5– dd 03/04/2013

PPAP to prevent loosing an opportunity for saving costs


Recommended