Transcript
Page 1: electrical service line standards - Doyon Utilities

             

DESIGNANDCONSTRUCTIONSTANDARDS  

ELECTRICAL SERVICE LINE   

 

2015  

     

714 FOURTH AVENUE, SUITE 100 FAIRBANKS, ALASKA 

    

PO BOX 74040 FAIRBANKS, AK  99707 

(907) 455‐1500       

WWW.DOYONUTILITIES.COM

Page 2: electrical service line standards - Doyon Utilities

 

ii 

 

Distribution And Construction Standards Electrical Service Line 

Revisions between 2014 Standard and 2015 Standard 

Item or Location  Description of Revision  

SPECIFICATIONS 

Cover Sheet  Date “2014” changed to “2015” 

All pages after Cover Sheet 

Date in footer:  “2014” changed to “2015” 

TABLE OF CONTENTS 

First Line  Removed “2013”  

Page 1 ‐ INTRODUCTION 

Last paragraph added “To ensure equipment quality and to decrease the likelihood that the facility contractor will be required to replace newly installed equipment (at contractor expense) prior to electric hookup, all service equipment must be approved by DU via the submittal review process before installation.   When service equipment is provided by DU,” 

 

Page 3: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

TABLEOFCONTENTS 

2015  iii  Doyon, Utilities, LLC  

 

LIST OF REVISIONS……………………………………………………………………………………………………………………………….….ii 

TABLE OF CONTENTS……………….………………………………………………………………………………………………………….….iii 

INTRODUCTION ............................................................................................................................................. 1 

SECTION 1 ‐ ELECTRICAL SERVICE STANDARDS ............................................................................................. 3 

1.1  SERVICENAMINGCONVENTION ............................................................................................... 3 

1.2  TYPICALPERMANENTOVERHEADSERVICE,TYPEA(NOTTOEXCEED200AMPS) .......... 5 

1.3  TYPICALPERMANENTOVERHEADSERVICE,TYPEB(NOTTOEXCEED200AMPS) ......... 9 

1.4  TYPICALPERMANENTUNDERGROUNDSERVICE(NOTTOEXCEED200AMPS) ............. 16 

1.5  TYPICALMULTIPLEMETERSERVICEENTRANCE(SIXUNITSORLESS) ............................ 19 

1.6  TYPICALMULTIPLEMETERSERVICEENTRANCE(MORETHANSIXUNITS) ................ 24 

1.7  TYPICALCTMETEREDSERVICE(1000AMPSORBELOW) .................................................. 28 

1.8  TYPICALCTMETEREDSERVICE(GREATERTHAN1000A) .................................................. 35 

1.8.1  NEWCONSTRUCTION: ...................................................................................................... 35 

1.8.2  RENOVATION/UPGRADES: .............................................................................................. 36 

1.9  SHUNTTRIPREQUIREMENTS ................................................................................................. 36 

1.10  PRIMARYMETERING ................................................................................................................ 36 

SECTION 2 ‐ METERING AND SERVICE RELATED STANDARDS AND DETAILS .............................................. 39 

2.1  SELF‐CONTAINEDMETERSOCKETS(100AND200AMPS) ................................................. 39 

2.2.  CURRENTTRANSFORMERMETERSOCKET ........................................................................... 39 

2.3  GROUNDING ............................................................................................................................... 43 

2.4  METERING/SERVICEEQUIPMENTLOCATIONREQUIREMENTS ......................................... 46 

2.5  GUYINGDETAILS ....................................................................................................................... 46 

2.5  ALUMINUMCONDUCTORSUBSTITUTIONTABLE ................................................................. 48 

2.6  TRANSFORMERIMPEDANCEVALUES .................................................................................... 49 

SECTION 3 – SERVICE APPLICATION CHECKLIST AND FORMS ..................................................................... 51 

3.1  LOADANDPRINTINFORMATIONREQUIREDBYDU ............................................................ 53 

 

Page 4: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    1   Doyon Utilities, LCC 

 

INTRODUCTION Doyon Utilities  (DU) standards of construction shall be utilized  for all  facilities  to be owned, operated and maintained by the utility, to include hookups from the utility facility to the demarcation point.  Generally, utility mains/distribution lines will be constructed by DU or by DU's contractor at DU expense. Thus, these standards will be followed by DU contractors.   DU will  be  responsible  for  planning,  designing  and  constructing  utility water, wastewater,  gas,  heat mains and electrical distribution system  improvements  for new government  facilities. This will require close  cooperation  and  utility  involvement  in  the  government  facility  planning  process. Without  this coordination, facilities constructed will have no utility service.  The  government,  Army,  or  Corps  of  Engineers  will  not  be  responsible  for  design,  construction,  or oversight of any utility owned facilities, whether main/distribution, lines, or hookups.  Doyon Utilities will be responsible for construction of the hookup for the utility from the building to the utility main/electrical distribution system facility as described below: 

 Electric: The electric hookup will be  from  the  transformer  to  the  load  side of  the disconnect.  The  utility will  provide  and  install  the meter.    At  a minimum  for  overhead  services,  Doyon Utilities will install the overhead service drop from the transformer to the service entrance mast.  At a minimum for underground services, Doyon Utilities will  install the service  lateral from the transformer to the service side of the first (main) disconnect. 

 In most installations, Doyon will provide and install the service equipment up to and including the first (main)  disconnect.  However,  in  rare  circumstances  (with  prior written  approval  of  the  utility),    the facility  contractor may be  tasked with  installation of  the  service entrance equipment at DU expense, including but not  limited  to meter base, CT enclosure,   main disconnect,  service entrance grounding, shunt trip devices, and mast/service entrance conduits.     Regardless of  installation, Doyon Utilities will own, operate and maintain  the service hook‐up  from  the service  transformer up  to and  including  the first disconnect downstream of the transformer, which is the service point of demarcation.  Regardless of  the  installer,  the  service entrance equipment  shall be  installed  in accordance with  these Electrical Service Line Standards as well as applicable local, military, and national codes.    To ensure equipment quality and to decrease the likelihood that the facility contractor will be required to  replace  newly  installed  equipment  (at  contractor  expense)  prior  to  electric  hookup,  all  service equipment must be approved by DU via the submittal review process before installation.   When service equipment  is  provided  by  DU,  coordination  will  be  necessary  so  that  the  appropriate  meters  and equipment are on hand for the facilities to be constructed.        

Page 5: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    2   Doyon Utilities, LCC 

 

For new  services or  service upgrades, a completed Service Application  including a  request  for  service coversheet, all DU required  load and print  information and the appropriate Electric Service Checklist  is required  before work will  begin  by  DU  to  provide  service.  See  Pages  51‐58  of  these  Standards  for samples of  these  forms.    The  conductor  size  and material  that  the  customer  intends  to  land on  the Doyon’s  disconnect  is  imperative  to  include  on  the  Coversheet,  this  allows  DU  to  provide  the appropriate provisions  for  the customer  to  terminate  their conductors.   Without  this  information,  the customer may be responsible to pay for the additional costs  incurred to change out the  loadside  lugs.  After receipt of paperwork and a site inspection has been completed, if DU determines that any of the customer’s  electrical  installation  doesn’t meet  all  pertinent  current  electrical  codes,  they  have  the option to refuse service until such time code violations are rectified.      Although Doyon will be responsible for  installation of service equipment up to and  including the main disconnect, Doyon Utilities  is not  responsible  for  correctly  sizing  the  service entrance equipment and conductors  in  accordance  with  the  NEC,  including  the  grounding  electrode  conductor.    The  facility designer will be  responsible  for  correctly designing  those  items  and  submitting  the  required  sizes  to Doyon  with  the  Service  Application.    Doyon  will  size  the  service  equipment,  conductors  and main breakers in accordance with the information provided on the Service Application.  Doyon can supply customers with the following secondary voltages for both overhead and underground:  

1. Single Phase, 120/240V, 3 wire 2. Single Phase, 240/480V, 3 wire 3. Three Phase, 120/208V, 4 wire* 4. Three Phase, 277/480V, 4 wire* 

 If a secondary voltage other than the above  is required, contact DU.   Three Phase service may not be available  to all  locations, DU will advise of  the additional costs associated with providing  three phase service where there is currently only single phase available.     

Page 6: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    3   Doyon Utilities, LCC 

 

SECTION1‐ELECTRICALSERVICESTANDARDS 1.1 SERVICENAMINGCONVENTION

 In general,  the service designation and detail will adhere  to  the  following naming convention, SS‐AA‐B‐C D, explained as follows: 

 

SS refers to Service Standard and is the first two letters of all service types. 

AA  refers  to  the  service  amperage  rating  and  indicates  hundreds  of  amperes  of  the 

service  rating,  i.e  SS‐01 would be  for a 100 Amp  Service, and  SS‐12 would  indicate a 

1200 Amp Service. 

B refers to the voltage of the service based on a numbering code, where 1=240/120V, 

2=208/120V, 3=480/240V, and 4=480/277V 

C  refers  to  type of  service entrance  feed  type, T=Top Feed  (Overhead) and B=Bottom 

Feed (Underground) 

D  is  only  applicable  for  Top  Feed  Services  and  refers  to  the  style  of  deadending  the 

overhead service drop, where H=House Knob and M=Mast type deadending. 

 So, for example, a 200 Amp, overhead, 1‐phase 240/120V service on the gable end of building where the mast does not penetrate the roof would be  indicated by SS‐02‐1‐T‐H.   A 600 Amp, underground, 3‐phase 480/277V service would be indicated by SS‐06‐4‐B  Additional suffixes may be added to the service name to  indicate additional  features,  like –G indicates  group metering  service  entrance  and    ‐GM  indicates  a  group metering  installation with an overall main disconnect.                 

Page 7: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    4   Doyon Utilities, LCC 

 

1.2 TYPICALPERMANENTOVERHEADSERVICE,TYPEA(NOTTOEXCEED200AMPS)1. Refer to detail SS‐AA‐B‐T‐M schematic and material lists (pages 5‐9) 

2. Service Entrance Conductor shall extend out of the weather head a minimum of 18”. 

3. Conductors  shall  be  phased  taped  using  the  following  convention:  120/240:Black/Red, 

240/480:Brown/Orange, 120/208:Black/Red/Blue, and 277/480: Brown/Orange/Yellow 

4. All  service  entrance masts  that  extend  above  the  roof  line  shall  be  a minimum  2"  rigid 

metal  conduit  (RMC)  or  intermediate  metal  conduit  (IMC)  and  shall  be  guyed  using 

minimum 1/8" aircraft cable and approved clamp. See Roof Guy Detail on page 47. 

5. If  roof  overhang  is  less  than  2  feet,  provide  suitable  protection  for meter  from  ice  and 

snow. Protection by overhanging roof is preferred. An acceptable alternative is a protective 

hood made of 18 gauge (minimum) galvanized steel, fastened at the roof edge or wall, and 

extending out a minimum of 6" beyond  face of meter and 6" on each side of the service 

equipment. 

6. The use of split‐bolts is not allowed. 

7. Couplings in the conduit shall be below roof line. 

8. Telephone drop may not be attached to mast. See NEC 230.28. 

9. Meter base  shall be able  to handle a  ring‐type meter, with  test bypass. Ringless are not 

acceptable.     

10. Meter base shall be per the material call out or approved equal.   

11. Locking provisions shall be factory installed, no field installed or modified locking provisions 

are acceptable.      

12. Contractors  shall  provide  and maintain  a minimum  4  ft. wide  clearing  between  service 

entrance and the Doyon Utilities pole. 

13. Utility service drop is limited to a maximum 150' span.   

14. See NEC 230.24  for  required  clearances over  roof.  If Army  requirements  call  for  vertical 

clearance of service drop conductors to be greater than 3 ft. or a flat roof  is classified as 

accessible,  then  the mast assembly and guying will be designed by a qualified engineer. 

Mast designs shall be submitted to the Doyon Utilities Engineering Services Department for 

review prior to installation. 

15. Conductor insulation shall be type XHHW‐2. 

16. Maintain all NEC required clearance at all times.  See NEC 230.9 and 230.24.   

17. lf  the  grounding  electrode  conductor  is  exposed  to  physical  damage  it  shall  be  run  in 

conduit securely fastened to the structure. See NEC 250.64(B). 

18. Install sealing lock nuts or hubs on all conduit penetrations of outdoor enclosures. 

19. Install  intersystem bonding  termination per NEC 250.94.   Doyon doesn’t allow  the use of 

the NEC exceptions under this rule in any circumstance. 

20. AIC Ratings of Specified Equipment are 10K AIC, except for 200 Amp, 480V Service, which 

are 22K AIC. If Engineer determines higher ratings are required, adjust equipment callouts 

accordingly. 

Page 8: electrical service line standards - Doyon Utilities
Page 9: electrical service line standards - Doyon Utilities
Page 10: electrical service line standards - Doyon Utilities
Page 11: electrical service line standards - Doyon Utilities
Page 12: electrical service line standards - Doyon Utilities
Page 13: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    10   Doyon Utilities, LCC 

 

 

1.3 TYPICALPERMANENTOVERHEADSERVICE,TYPEB(NOTTOEXCEED 200AMPS)

 1. Refer to detail SS‐AA‐B‐T‐H schematic and material lists (pages 11‐15) 

2. Service  drop  conductors  shall  be  above  or  at  least  36"  from  any  door,  opening window, 

building vent, or other building opening. 

3. Service Entrance Conductor shall extend out of the weather head a minimum of 18”. 

4. Conductors  shall  be  phased  taped  using  the  following  convention:  120/240:Black/Red, 

240/480:  Brown/Orange, 120/208: Black/Red/Blue, and 277/480: Brown/Orange/Yellow 

5. The use of split‐bolts is not allowed. 

6. Telephone drop shall be more than 12" (vertical clearance) below power cable at all points. 

See NESC 235C1, Exception 3. 

7. Conductor insulation shall be type XHHW‐2. 

8. If the grounding electrode conductor is exposed to physical damage it shall be run in conduit 

securely fastened to the structure. See NEC 250.64(B). 

9. Install sealing lock nuts or hubs on all conduit penetrations of outdoor enclosures. 

10. Meter  base  shall  be  able  to  handle  a  ring‐type meter, with  test  bypass.  Ring  less  aren’t 

acceptable. 

11. Meter base shall be per the material call out or approved equal. 

12. Locking provisions shall be factory installed, no field installed or modified locking provisions 

are acceptable. 

13. Contractors  shall  provide  and maintain  a minimum  4  ft.  wide  clearing  between  Service 

entrance and the Doyon Utilities pole. 

14. Utility service drop is limited to a maximum 150' span. 

15. Maintain all NEC required clearance at all times.  See NEC 230.9 and 230.24.   

16. Install intersystem bonding termination per NEC 250.94.  Doyon doesn’t allow the use of the 

NEC exceptions under this rule in any circumstance. 

17. AIC Ratings of Specified Equipment are 10K AIC, except  for 200 Amp, 480V Service, which 

are 22K AIC.  If Engineer determines higher ratings are required, adjust equipment callouts 

accordingly. 

   

 

Page 14: electrical service line standards - Doyon Utilities
Page 15: electrical service line standards - Doyon Utilities
Page 16: electrical service line standards - Doyon Utilities
Page 17: electrical service line standards - Doyon Utilities
Page 18: electrical service line standards - Doyon Utilities
Page 19: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    16   Doyon Utilities, LCC 

 

1.4 TYPICAL PERMANENT UNDERGROUND SERVICE (NOT TO EXCEED

200AMPS)

1. Refer to detail SS‐AA‐B‐B schematic and material lists (pages 17‐19)  

2. Service entrance location shall be approved by DU and shall be located as close as possible 

to existing DU facilities. 

3. Conduit for service cable shall be sized per NEC but shall not be less than 2 inches. 

4. The Army Facilities' service equipment shall conform to the NEC and State of Alaska Codes 

and shall be inspected and approved prior to connection of service by DU. 

5. Any deviation from this standard shall be approved in writing by DU's Engineers. 

6. If grounding electrode conductor  is exposed  to physical damage  it  shall be  run  in conduit 

securely fastened to the structure. See NEC 250.64(B). 

7. Equipment shall be mounted so that center of meter is located at height of 5’‐0” minimum 

and 6’‐0” maximum above grade. 

8. Install sealing lock nuts or hubs on all conduit penetrations of outdoor enclosures. 

9. Service  Lateral  Conductors  shall  be  phased  taped  using  the  following  convention: 

120/240:Black/Red,  240/480:Brown/Orange,  120/208:  Black/Red/Blue,  and  277/480: 

Brown/Orange/Yellow 

10. Install intersystem bonding termination per NEC 250.94.  Doyon doesn’t allow the use of the 

NEC exceptions under this rule in any circumstance.  

11. AIC Ratings of Specified Equipment are 10K AIC, except  for 200 Amp, 480V Service, which 

are 22K AIC.  If Engineer determines higher ratings are required, adjust equipment callouts 

accordingly. 

 

  

   

Page 20: electrical service line standards - Doyon Utilities
Page 21: electrical service line standards - Doyon Utilities
Page 22: electrical service line standards - Doyon Utilities
Page 23: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    20   Doyon Utilities, LCC 

 

 

1.5 TYPICALMULTIPLEMETERSERVICEENTRANCE(SIXUNITSORLESS) 

1. Refer to detail SS‐04‐B‐B‐G schematic and material lists (pages 21‐23)  

2. Service entrance location shall be approved by DU and shall be located as close as possible 

to existing DU facilities. 

3. Conduit for service cable shall be sized per NEC but shall not be less than 2 inches. 

4. The Army Facilities' service equipment shall conform to the NEC and State of Alaska Codes 

and shall be inspected and approved prior to connection of service by DU. 

5. Any deviation from this standard shall be approved in writing by DU's Engineers. 

6. If grounding electrode conductor  is exposed  to physical damage  it  shall be  run  in conduit 

securely fastened to the structure. See NEC 250.64(B). 

7. The bottom of  the  service entrance equipment  shall not be  less  than 36"  above  finished 

grade  or  finished  floor.  Choose  equipment  size  to maintain  this minimum  distance  and 

maximum height of 6'‐7" to the horizontal centerline of the highest breaker or handle of the 

disconnecting means. 

8. Install sealing lock nuts or hubs on all conduit penetrations of outdoor enclosures. 

9. Service  Lateral  Conductors  shall  be  phased  taped  using  the  following  convention: 

120/240:Black/Red,  240/480:Brown/Orange,  120/208:  Black/Red/Blue,  and  277/480: 

Brown/Orange/Yellow 

10. Install intersystem bonding termination per NEC 250.94.  Doyon doesn’t allow the use of the 

NEC exceptions under this rule in any circumstance.   

11. Coordinate additional requirements with DU  if overhead service  is desired  for  this  type of 

installation. 

12. AIC Ratings of Specified Equipment are 10K AIC.  If Engineer determines higher  ratings are 

required, adjust equipment circuit breaker callouts accordingly. 

 

   

   

Page 24: electrical service line standards - Doyon Utilities
Page 25: electrical service line standards - Doyon Utilities

22

Page 26: electrical service line standards - Doyon Utilities

23

Page 27: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    24   Doyon Utilities, LCC 

 

1.6 TYPICALMULTIPLEMETERSERVICEENTRANCE(MORETHANSIXUNITS)

 1. Refer to detail SS‐AA‐B‐B‐GM schematic and material lists (pages 25‐27)  

2. Service entrance location shall be approved by DU and shall be located as close as possible 

to existing DU facilities. 

3. Conduit for service cable shall be sized per NEC but shall not be less than 2 inches. 

4. The Army facilities' equipment shall conform to the NEC and State of Alaska Codes and shall 

be inspected and approved prior to connection of service by DU. 

5. Any deviation from this standard shall be approved in writing by DU's Engineers. 

6. The bottom of  the  service entrance equipment  shall not be  less  than 36"  above  finished 

grad  or  finished  floor.  Choose  equipment  size  to  maintain  this  minimum  distance  and 

maximum height of 6'‐7' to the horizontal centerline of the highest breaker or handle of the 

disconnecting means. 

7. Install sealing lock nuts or hubs on all conduit penetrations of outdoor enclosures. 

8. Service  Lateral  Conductors  shall  be  phased  taped  using  the  following  convention: 

120/240:Black/Red,  240/480:Brown/Orange,  120/208:  Black/Red/Blue,  and  277/480: 

Brown/Orange/Yellow. 

9. Install intersystem bonding termination per NEC 250.94.  Doyon doesn’t allow the use of the 

NEC exceptions under this rule in any circumstance. 

10. AIC Ratings of Specified Equipment are 10K AIC.  If Engineer determines higher  ratings are 

required, adjust equipment circuit breaker callouts accordingly. 

   

    

Page 28: electrical service line standards - Doyon Utilities
Page 29: electrical service line standards - Doyon Utilities
Page 30: electrical service line standards - Doyon Utilities
Page 31: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    28   Doyon Utilities, LCC 

 

1.7 TYPICALCTMETEREDSERVICE(1000AMPSORBELOW) 

1. Refer to detail SS‐AA‐B‐B schematic and material lists (pages 29‐34) 

2. The maximum ampacity of a new overhead  service  shall be  limited  to 200 Amps without 

special permission from Doyon Utilities.  If a service greater than 200 Amps is required than 

it will be served by an underground connection. 

3. Service entrance location shall be approved by DU and shall be located as close as possible 

to existing DU facilities. 

4. The Army Facilities' service equipment shall conform to the NEC and State of Alaska Codes 

and shall be inspected and approved prior to connection of service by DU. 

5. Any deviation from this standard shall be approved in writing by DU's Engineers. 

6. CT  cabinet, meter  enclosure,  and main  disconnect(s)  shall  be  grouped  together  on  the 

outside  of  building. All  enclosures  shall  be  raintight  (NEMA  3R).  Inside  locations  are  not 

permitted without written Doyon approval prior to installation. 

7. Conduit  for conductors between CT’s and Meter  shall be at  least 1  inch diameter and no 

longer  than  30  feet.  Conduit  shall  be  GRS.  Conduit  used  for  CT  circuits  shall  be  of  the 

threaded type.   

8. CT's shall be mounted at right angles to enclosure panels with polarity marks facing source 

side. 

9. DU shall install CT secondary wiring and test switch. 

10. Install sealing lock nuts or hubs on all conduit penetrations of outdoor enclosures. 

11. If grounding electrode conductor  is exposed  to physical damage  it  shall be  run  in conduit 

securely fastened to the structure. See NEC 250.64(B). 

12. Conductor insulation shall be type XHHW‐2 for conduit installations. 

13. Service  Lateral  Conductors  shall  be  phased  taped  using  the  following  convention: 

120/240:Black/Red,  240/480:Brown/Orange,  120/208:  Black/Red/Blue,  and  277/480: 

Brown/Orange/Yellow 

14. Install intersystem bonding termination per NEC 250.94.  Doyon doesn’t allow the use of the 

NEC exceptions under this rule in any circumstance.   

15. AIC  Ratings  of  Specified  Equipment  are  65K  AIC  for  120/208V  services,  35K  AIC  for  400 

Ampere and 600 Ampere 277/480V services, and 50K AIC for 800 Ampere and 1200 Ampere 

277/480V  services.  If  Engineer  determines  higher  ratings  are  required,  adjust  equipment 

callouts accordingly. 

 

   

Page 32: electrical service line standards - Doyon Utilities
Page 33: electrical service line standards - Doyon Utilities
Page 34: electrical service line standards - Doyon Utilities
Page 35: electrical service line standards - Doyon Utilities
Page 36: electrical service line standards - Doyon Utilities
Page 37: electrical service line standards - Doyon Utilities
Page 38: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    35   Doyon Utilities, LCC 

 

1.8 TYPICALCTMETEREDSERVICE(GREATERTHAN1000A)

1.8.1 NEWCONSTRUCTION: 

Ft. Wainwright and Ft. Greely:  At the time of design of a new service greater than 1000A, Doyon shall be notified.  It is the  intent of Doyon to append a metering and main breaker section or sections to the Building MDP and have it integrated into the MDP from the MDP manufacturer.  Doyon will provide  the contractor procuring  the MDP with  their requirements and reimburse the facility contractor for the cost adder of the additional Doyon sections.  Coordination with Doyon Utilities during  the  facility design process will be  required.   The  following minimum requirements shall be met for these installations:   

1. Adequate  interior working space shall be provided  for  the  interior  installation. 

Refer  to  the  interior Doyon  service equipment working  space detail  (page 37) 

for minimum requirements. 

2. The metering and CT section of the MDP shall be built to EUSERC standards for 

the  ampacity  and  voltage  of  the  service  size.    The  CT  section  shall  include 

removable bus sections to accommodate window type CT’s appropriate for the 

ampacity of the switchgear.   

3. The main breaker shall  include a shunt  trip module  for connection  to exterior 

located shunt trip knife switch.  The MDP shall also include a 15A, 1 pole breaker 

to power  the  shunt  trip  circuit. At Doyon’s discretion  and expense,  they may 

request  the  facility electrical contractor  install  the shunt  trip circuit and shunt 

trip disconnect on  the  exterior of  the  building.    See pages  36,  38  and  39  for 

shunt trip requirements and details.  

4. CT meterbases  for  these  installations  shall be  installed on exterior of building 

and accessible to DU employees.  The conduit for conductors between CT’s and 

Meter shall be installed by the facility electrical contractor, and shall be at least 

1 inch diameter and no longer than 30 feet.  Conduit shall be RMC.  

5. In locations where an exterior CT meterbase is not feasible or cannot meet the 

requirements of  item 4, written acceptance of an  interior meter  location  from 

DU  is required.   In such  instances, the  installation shall  include  installation of a 

1” RMC  from  the meter  location  to a DU accepted  location on exterior of  the 

building to accommodate installation of a remote meter reading antenna on the 

exterior of the building. 

6. The service equipment shall conform to the NEC and State of Alaska Codes and 

shall be inspected and approved prior to connection of service by DU. 

7. DU  employees  shall  have  access  to  service  equipment  installed  indoors  in 

facilities at all times. 

  

Page 39: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    36   Doyon Utilities, LCC 

 

JBER Richardson:  At the time of design of a new service greater than 1000A, Doyon shall be notified.  It is the  intent of Doyon to supply a metering and main breaker/disconnect section on the exterior  of  the  building.    Only  with  Doyon’s  written  approval  shall  any  of  their equipment be  located  inside.     Such  interior  installations shall meet  the  requirements noted above.    

1.8.2 RENOVATION/UPGRADES: 

Ft. Wainwright and Ft. Greely:  At these above posts, the first choice is to modify existing installation to add a metering and main  breaker  section.    It  is  imperative  to  contact Doyon Utilities  at  the  time  of planning to determine the feasibility of this retrofit.  If an interior retrofit isn’t possible, DU will install their equipment on the exterior.   In the case where exterior mounting is chosen, DU will reimburse the Army for the work required to reconnect the new service equipment to the existing equipment within the building.    JBER Richardson:  At Richardson any electrical service renovation work will  include relocating the service equipment outside  if applicable.   DU will reimburse the Army for the work required to reconnect the new service equipment to the existing equipment within the building.   

1.9 SHUNTTRIPREQUIREMENTSA minimum 8” x 8” Red Placard with White Letters shall be installed at each Shunt Trip location.  The Placard  shall  read “Service Shunt Trip Utility”.    In  the case of multiple  shunt  trips  for  the same building, the placard shall also indicate specifically which room the main breaker is located in and the panel voltage it controls.  The shunt trip switch shall be of the safety switch style and disconnect  the main breaker  in  the off position.   Handle  shall be  lockable  in  the ON and OFF position. See Shunt Trip details on page 38.  

1.10 PRIMARYMETERINGWhere  primary  voltage  metering  is  desired,  coordinate  with  Doyon  Utilities  for  primary metering availability and requirements.   

 

Page 40: electrical service line standards - Doyon Utilities

37

Page 41: electrical service line standards - Doyon Utilities

38

Page 42: electrical service line standards - Doyon Utilities

39

Page 43: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    40   Doyon Utilities, LCC 

 

SECTION2‐METERINGANDSERVICERELATEDSTANDARDSANDDETAILS 

2.1 SELF‐CONTAINEDMETERSOCKETS(100AND200AMPS) 

1. Manual  bypass  sockets  are  not  allowed  unless  specifically  approved  by  DU  prior  to 

installation; all meter bases shall be of the Test Block Bypass style. 

2. As required by NEC 110.15  the phase conductor  in  the service entrance having  the higher 

voltage to ground shall be identified by the color ORANGE, and be located on the right hand 

lug of the meter base (4‐wire delta only). 

 

2.2.  CURRENTTRANSFORMERMETERSOCKET  

1. Meter base enclosure for any of the above metering configurations shall include provisions 

for a DU provided  test  switch.   The maximum distance between  the meterbase and CT’s 

shall be 30’ assuming the use of #10 CU XHHW‐2.  In applications where this distance will be 

exceeded, contact DU to determine if the actual distance is acceptable, given the exact CT’s 

and conductor that will be used on the project.       

2. Unless specific variance  is granted by DU, DU shall provide and  install  the meterbase, CTs 

and test switch, including wiring.   

3. As required by NEC 110.15, the phase conductor  in the service entrance having the higher 

voltage to ground shall be identified by the color ORANGE, and be located on the right hand 

lug of the meter base. (4‐wire delta only). 

4. If  the  test switch doesn’t have built  in capabilities of shunting  the neutral wires  together, 

this shall be done.   

5. Individual wires between the X2 on each CT and each test switch phase neutral is required.  

One wire between the test switch and CT cabinet isn’t allowed. 

6. Depending on the manufacture of the test switch, the X1 and X2 locations may be swapped 

from detail.   The X1 position(hot)  identified by determining which switch has  the shorting 

fingers.   At the  time of this writing,  the wiring diagram shows a Millbank style  test switch 

with X1 on the  left.   Cooper B‐Line’s normal standard  is the exact opposite; however, they 

are  intending  to provide Doyon with  test  switches  that  conform  to  the  same  standard as 

Milibank (X1 on the left). Contact Doyon if there is a question on the identification of X1. 

7. For single phase CT services, see Meter Connection Diagram 4S on page 41. 

8. For three phase CT services, see Meter Connection Diagram 9S on page 42. 

    

   

Page 44: electrical service line standards - Doyon Utilities

41

Page 45: electrical service line standards - Doyon Utilities

42

Page 46: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    43   Doyon Utilities, LCC 

 

2.3 GROUNDING 

1. Bond  grounding  electrode  conductor  to metal water  pipe  and  other  available  grounding 

electrodes as required by NEC 250.50 “Grounding Electrode System”. 

2. If grounding requirements of NEC 250.50 cannot be met, and made electrodes are utilized 

as  the sole  type of grounding electrodes,  then  the  resistance requirements of NEC 250.56 

shall  be  met.    Electrodes  may  be  directly  bonded  together  with  grounding  electrode 

conductor, individually routed to the neutral bus, or connected to an optional terminal bus 

as stated  in  item 12.   A ground rod  is required by DU even  if a metal water pipe or other 

electrodes listed in NEC 250.50 are used. 

3. For new construction,  it  is  the  responsibility of  the  facility electrical contractor  to provide 

and  install  the  grounding  electrode  conductors  and  bonding,  sized  and  installed  in 

accordance with the requirements of NEC article 250, for each of the available electrodes of 

the building  listed  in NEC 250.52.   Sufficient additional conductor shall be  left coiled at the 

service entrance to allow connection to the service entrance ground bus without splicing the 

conductor.   Auxiliary  grounding electrodes  (ground  rods)  at  the  service entrance  shall be 

installed by DU or DU’s contractor. 

4. Supply side equipment bonding jumper shall be sized in accordance to NEC 250.102(C) with 

minimum  size  to  be  #4  CU  as  required  by  DU.    Equipment  bonding  jumper  shall  be 

continuous throughout service equipment. 

5. Grounding electrode conductors sized in accordance to NEC 250.66 with minimum size to be 

#4 CU in accordance with DU requirements.  For specific service entrance, see approved DU 

load data  for minimum permissible  grounding electrode  conductor  size.    See  item 12  for 

another  grounding  electrode  bonding  jumper  connection  option.    Grounding  conductors 

shall be continuous as per NEC 250.64(C) and protection from physical damage as per NEC 

250.64(B). 

6. Use #4 CU conductors to bond CT meter enclosure.   CT meter bonding conductor shall be 

continuous between bonding points. 

7. All neutral buses  shall be  either directly or  indirectly  effectively bonded  to  enclosures  in 

accordance with NEC 250.92.  Install separate grounding lug in enclosure if neutral bus is not 

directly bonded  to enclosure.   Factory supplied neutral bus bonding means are subject  to 

approval. 

8. Per NEC 250.12 and 250.96, paint shall be removed from surfaces in contact with grounding 

fittings.    Exposed metal  at  ground  points  shall  be  protected  with  conductive  corrosion 

inhibitor. 

9. Equipment bonding  jumpers and CT meter bonding conductor shall be routed through the 

conduit.  Each end of the conduit shall be bonded as required by DU. 

10. Threadless  couplings and  connectors are not allowed  for bonding  service equipment.   OZ 

Gedney  Type  CHM‐T  or  similar  UL  listed  with  piercing  screw  approved  for  bonding  are 

Page 47: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    44   Doyon Utilities, LCC 

 

acceptable for bonding bushings.   Standard  locknuts or sealing  locknuts are not acceptable 

for bonding at service equipment. 

11. Compression or screw‐type connectors are acceptable means of splicing conductors.   Split 

bolt type are not allowed. 

12. Optional  terminal bus can be added  to connect bonding  jumpers  form multiple grounding 

electrodes.   Optional  terminal bus  shall be effectively bonded  to enclosure.   A grounding 

electrode conductor shall connect the optional bus with the neutral bus and it shall be sized 

as per NEC 250.66. 

13. Install intersystem bonding termination per NEC 250.94.  Doyon doesn’t allow the use of the 

NEC exceptions under this rule in any circumstance.   

14. At  all newly  constructed  facilities with  concrete  foundations,  it  is  the  facility  contractor’s 

responsibility  to  install  an  appropriate  concrete  encased  grounding  electrode  per  NEC 

250.52‐A(3). The facility contractor shall also install a copper grounding electrode conductor 

from  the  concrete  encased  electrode  to  the  service  entrance  equipment  location  for 

connection to the service grounding electrode system. That grounding electrode conductor 

shall be sized in accordance with NEC 250.66.   

15. See Grounding Detail on page 45 for typical service entrance grounding detail. 

 

Page 48: electrical service line standards - Doyon Utilities

45

Page 49: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    46   Doyon Utilities, LCC 

 

 

2.4 METERING/SERVICEEQUIPMENTLOCATIONREQUIREMENTS 

1. Whenever  possible, metering  and  service  equipment  shall  be  installed  nearest  Doyon’s 

primary  facilities  to minimize  the  extension  of  the  required  primary  system.    Coordinate 

with Doyon Utilities during  facility design  to determine optimal  location  for metering and 

service equipment. 

2. For  services  less  than  1200A  at  Ft.  Wainwright  and  Ft.  Greely,  metering  and  service 

equipment  shall be  located on  the exterior of  the building unless Doyon provides written 

consent  that  the  location may be on  the  interior.   At  JBER Richardson, any variance  from 

locating the metering and service equipment on the exterior requires written consent. 

3. At  locations  that  require  multiple  metered  services,  all  equipment  shall  be  grouped 

together.   

4. Metering and service equipment shall be readily accessible to Doyon at all times and not in a 

locked location, unless Doyon has granted permission to the contrary.   

5. Metering and  service equipment  shall be  located  in a  safe, non hazardous, above ground 

location that is free from mechanical damage including falling snow and ice.  

6. Metering and service equipment shall be mounted on a  rigid surface, with an attachment 

system capable of securing the full weight of the equipment  in accordance with applicable 

codes and standards. 

7. Metering and service equipment shall be located so to allow a minimum of 5’ working space 

around the equipment without any obstacles. 

8. Metering equipment shall be mounted such that the meter  is at a height between 60” and 

72” above  final grade, with a desired height of 66”.        In  the case of multiple meters,  the 

equipment shall be centered at 66” whenever possible, while still maintaining a maximum 

height of 72”.  The preferred location of the center of the disconnect(s) is 66”, where there 

are multiple  disconnects,  the middle of  the uppermost disconnect(s) handle  shall  not  be 

greater than 79”.    

9. Meter base shall maintain a minimum of 3’ away from gas facilities.   

10. Doyon shall have access to the meter at all times without prior notification.    

 

2.5 GUYINGDETAILS 

1. See page 47 for service mast guying details. 

2. No other attachments are permitted on the mast. 

3. For mast heights  greater  than 60”  contact DU.   Mast designs  shall be  submitted  to DU’s 

Engineers for review and approval prior to installation. 

 

Page 50: electrical service line standards - Doyon Utilities

47

Page 51: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    48   Doyon Utilities, LCC 

 

2.5 ALUMINUMCONDUCTORSUBSTITUTIONTABLE1. See page 49. 

 

 

   

Page 52: electrical service line standards - Doyon Utilities

49

Page 53: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    50   Doyon Utilities, LCC 

 

2.6 TRANSFORMERIMPEDANCEVALUES The table below shows the assumed % impedance and phase angle for distribution transformers on the transformer base. Where fault current involves on one‐half of the low voltage winding, the % impedance values, based on full rated kVA, are 1.5 and 1.2 times the full winding %R and %X respectively. An infinite bus is assumed on high side of the transformer.  If a overhead transformer bank is feeding the service, the %Z that shall be used in fault calculations  is  the %Z  for one of  the OH  transformers.   EX: 112.5kVA(3‐37.5kVA) bank  is  feeding service, use %Z of 1.6.        

Distribution Transformer Size [kVA/Phase]  

% Impedance [% Z]   

Phase Angle [degrees]   

% R +jX [% Z] 

5  2.1  30  1.819 + j1.050 

10  1.6  30  1.386 + j0.800 

15  1.6  40  1.226 + j1.028 

25  1.6  45  1.131 + j1.131 

37.5  1.6  45  1.131 + j1.131 

50  1.6  52.5  0.974 + j1.269 

75  1.6  52.5  0.974 + j1.269 

100  1.6  60  0.800+ j1.386 

150  1.7  60  0.850 + j1.472 

167  1.7  60  0.850 + j1.472 

225  1.7  60  0.850 + j1.472 

300  1.7  60  0.850 + j1.472 

500  1.7  60  0.850 + j1.472 

750‐2000  5.75  60  2.875 + j4.980 

       

Page 54: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    51   Doyon Utilities, LCC 

 

SECTION3–SERVICEAPPLICATIONCHECKLISTANDFORMS      

Page 55: electrical service line standards - Doyon Utilities

Doyon Utilities, LLCWO# (for Doyon’s Use)

COVER SHEETELECTRICAL LOAD DATA AND ELECTRICAL PRINT

Application Name Telephone

Business Name Telephone

Mailing Address

New Service Location

Architect/Engineer Telephone

Electrical Contractor Telephone

Mailing Address

AK Specialty Contractor License#

Service Requested Amps Configuration: Volts

DU has adopted the National Electrical Code (NEC) as the minimum standard acceptable for electrical installations it serves. The Contractor should be aware that in addition to NEC requirements there may be more stringent requirements imposed by the Utility.

DU requires a detailed electrical print and detailed listing of the electrical load by a registered electrical engineer or licensed electrical contractor on all multi-residential, commercial and industrial services. Please ensure all applicable information required on the list below is attached to this cover sheet.

Checklist of Required Information

Site PlanConnected Load

Motors and StartersDiversified DemandElectrical Print

Typical Electrical Service ChecklistConductors and ConduitsOver-current Device(s)Meter(s) Equipment Bonding and GroundingSealing ProvisionsReduced Neutral Calculations

When you have submitted the required information, DU will prepare a “ Service Entrance Equipment Requirement” sheet. A copy of this sheet will be sent to the applicant. DO NOT ORDER equipment prior to receiving this “Service Entrance Equipment Requirement” sheet.

Load and Print Data Submitted by Date

Load and Print Data Received by Date

Phase

52

Page 56: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    53   Doyon Utilities, LCC 

 

3.1 LOADANDPRINTINFORMATIONREQUIREDBYDU Site Plan   Site plan shall include property lines or adjacent roadways; location of structure to be served by utility with respect to the property  lines or roadways;  location of service entrance equipment; location  of  DU  transformer  pole  that  is  to  serve  your  structure;  distance  between  DU transformer pole and your service entrance equipment.  Site plan shall be provided in AutoCAD format.   Connected Load and NEC Load Calculation   Provide the total connected  load  in kilovolt‐amps (kVA) as well as the NEC service  load  in kVA, computed in accordance with the current edition of the National Electric Code.  This calculation shall be performed by or under the supervision of a registered professional electrical engineer. Motors and Starters:  DU  conducts  a motor  starting  study  for motors  10  horsepower  and larger.  If  the  load contains motor(s) rated 10 horsepower or  larger,  then  the  following data  is required for each motor:  

o Rated horsepower  

o NEC locked‐rotor indicating code letter  

o Voltage  

o Indicate whether single phase or three phase  

o Indicate  motor  starting  method  (full  voltage,  reduced  voltage  [auto 

transformer], or drive)  

o Indicate motor starting and running sequence for multiple motors  

 Diversified Demand:   If the load is a dwelling type load, then the demand (in kilowatts) shall be the load computed per the current edition of the National Electric Code. It shall include a calculation for the individual dwelling units as well as the total load on the service equipment.   Electrical Print   Include  a  one‐line  diagram  AND  riser  diagram  of  service  equipment  from  service  entrance conductors  through  the  main  disconnect  and  describing  all  physical  details  of  installation.  Although not  required at  initial application,  these prints  should be  stamped by a professional electrical engineer  registered  in  the State of Alaska, and Doyon Utilities may  request a  set of stamped drawings prior  to  service hook‐up. Refer  to  the  typical electric  service  checklists on pages 55 and 56.   

o Conductors and conduits ‐ type, insulation, size, and number  

o Over‐current Device(s) and Equipment AIC rating  

Page 57: electrical service line standards - Doyon Utilities

DESIGNANDCONSTRUCTIONSTANDARDSELECTRICALSERVICELINE

2015    54   Doyon Utilities, LCC 

 

o Meter(s) ‐ including numbering system  

o Equipment Bonding and Grounding ‐ per NEC and DU Electrical Service Entrance 

Requirements  

o Sealing Provisions  ‐ All access  to unmetered  conductors or bussing  shall have 

provisions  for  installing split/lock seals  in accordance with DU Service Security 

Equipment Sealing program. All meter  retaining  rings  shall be  the  screw  type. 

More detailed information is available on request. 

   

Page 58: electrical service line standards - Doyon Utilities

55

Page 59: electrical service line standards - Doyon Utilities

56


Recommended