Page 1: Manufacturability Assessment & Process Plan

MManufacturability anufacturability AAssessment & ssessment &

PProcess rocess PPlanlan

Supplier MAPP Overview Training

Page 2: Manufacturability Assessment & Process Plan

2

Training Goals

� Communicate Nexteer’s new approach to launch

� Understand what Nexteer is doing differently to improve launch performance

� Understand Nexteer’s new Manufacturability

Assessment & Process Plan (MAPP) process

Page 3: Manufacturability Assessment & Process Plan

3

GSM Launch Objectives

� Proactive Risk Assessment throughout Launch Process− Cross Functional BOM Risk Assessment (Nexteer)

− Internal Print Reviews (Nexteer)

− Internal Key Stakeholder Meeting (Nexteer)

− Manufacturability Assessment & Process Plan (Nexteer-Supplier)

− PFD, PFMEA & Control Plan Submission prior to PPAP (Supplier)

� Identify Target Supplier prior to Design Validation− Supplier input for Design Validation

− Production intent process for Design Validation to mitigate risk

− Production intent supplier for High Priority Parts to mitigate risk

� Emphasis on Collaborative relationships− Buyer-AQE-PE-Supplier are responsible for flawless launch of product

− Nexteer-Supplier teamwork approach to achieve quality & cost targets

Page 4: Manufacturability Assessment & Process Plan

4

Nexteer GSM Launch Goals

� Foster a Nexteer-Supplier Collaborative Culture

− Goal: Name a Target Supplier 6 weeks after issuing RFQ

− Engage the supplier earlier to allow for supplier input into thedesign

� Improve Launch Performance

− PPAP On-time

− Run at Rate On-time

− Delivery On-time

− Zero problem cases during launch

− Achieve cost targets

Page 5: Manufacturability Assessment & Process Plan

5

What is Nexteer Doing Differently?

Question: What is Nexteer Going to do Differently?

Answer: Collaborative Sourcing & Concurrent Engineering

� Traditionally, Nexteer Product Engineering worked independently to develop the product design

Develop Business Case

Source Supplier

Implement Mfg System

Validate Mfg System

Supplier Quotes

Team Feasibility

Final

Negotiations

Sourcing

Approval

PPAP Approval

Run at Rate

Approval

APQP Review

Engineering Development

Technical

Reviews

Page 6: Manufacturability Assessment & Process Plan

6

What is Nexteer Doing Differently?

� The Collaborative Sourcing Process & Concurrent Engineering Philosophy brings the Target Supplier into the

development phase to obtain supplier input into the design

Develop Business

Case

Develop Business

Case

Develop Sourcing

Strategy

Indentify Target

Supplier

CollaborateSource SupplierSource Supplier

Implement Mfg

System

Implement Mfg

System

Validate Mfg

System

Validate Mfg

System

Strategic

PartnershipsSupplier Quotes

Team Feasibility

Characteristic

Summary

Process Flow

Diagram

Technical

Review

PE-AQE Target

Supplier Input

Final

Negotiations

Sourcing

Approval

PPAP Approval

Run at Rate

Approval

Line Side

Reviews

Category

Strategies

Internal Tech

Review

PE&AQE Bid

List Approval

Pre-Bid

Approval

Technical

Reviews

Agreed Upon

Design/Process

FMEAReviews

Initial PFMEA

Initial

Gaging Plan

Pre-PPAP

PFMEA

Pre-PPAP

Control Plan

Pre-PPAP

Process Flow

APQP Review

Supplier MCA

Risk

Assessment

Page 7: Manufacturability Assessment & Process Plan

7

What We are Doing Differently?

Question: What is Nexteer Going to do Differently?

Answer: Identify & Mitigate Risk

� Rigorous Internal Risk Reviews

� Identify Target Supplier Early

� Implement the Manufacturability Assessment & Process Plan (MAPP)

Page 8: Manufacturability Assessment & Process Plan

8

What is the “MAPP”?

MAPP = Manufacturability Assessment & Process Plan

� Global Supply Management’s “MAPP to a Flawless Launch”

� Based on the “Compliance Matrix”that is required by our customers to

be submitted with our new business

pursuit quotes

� The MAPP template is located in the Nexteer Supplier Portal: Home > Frequently Used Documents >

Supplier Standards > Direct Material Sourcing Requirements

or copy & paste the link:

https://sss.portal.covisint.com/c/document_library/get_file?uuid=06330c8b-

461b-47e2-9fb1-93167e2a67f8&groupId=107759

Microsoft Excel

Worksheet

Click on excel

icon for an

example MAPP

Template

Page 9: Manufacturability Assessment & Process Plan

9

Why do we need the MAPP?

Take Action for Quality: It’s everyone’s job

� We must eliminate any Customer perception that

Nexteer is a risky supplier

during the Launch Phase.

� If we don’t win new business,

our suppliers won’t win new

business

� Encourages a collaborative relationship between the supplier and the Nexteer

Buyer, Supplier Quality and PECollaboration is the act of working

with others on a joint project

Page 10: Manufacturability Assessment & Process Plan

10

How is the MAPP Used?

MAPP: Risk Identification & Mitigation Tool

� Communicate expectations to the supplier

� Guides the Supplier, AQE, PE & Buyer to identify risk as early as possible

� Allows the team to assess risk to use their

experience & judgment whether a supplier is capable to make the part

� Documents risk mitigation plans

� The MAPP requires the supplier to consider each dimension, feature or requirement on the drawing, or in

the product spec, and document how the it will be

manufactured, measured and controlled in production.

Page 11: Manufacturability Assessment & Process Plan

11

MAPP & Supplier Selection

Mechanism to Identify the Target Supplier

� MAPP Template is sent out with RFQ

� Supplier is encouraged to use the

MAPP as a tool to generate their Quote

� Supplier MAPP must be provided to Nexteer prior to the Supplier Capability & Selection Review (first tech review)

� Open issues should be expected and welcomed

� Goal is to identify a Target Supplier 6 weeks from RFQ issue

date; in some cases, multiple suppliers may be selected.

� Identifies issues so that Nexteer can select a Target Supplier

to allow collaboration to begin earlier in the process

Page 12: Manufacturability Assessment & Process Plan

12

MAPP Process Timeline

2 3

Issu

e R

FQ

Rec

eive

Sup

plie

r Q

uote

Cap

abili

ty &

Sel

ectio

n R

evie

w(s

)

Nam

e Tar

get S

uppl

ier

Des

ign

& S

uppl

ier Pro

cess

Col

labo

ratio

n Act

ivity

Sup

plie

r Kic

koff

1

Rec

eive

Sup

plie

r M

APP

4

Fin

al S

ourc

ing

App

rova

l

1. Supplier eSigns MAPP with MAPP Submission

2. PC&L, PE & AQE/SQE Sign MAPP after Capability & Selection

Review(s)

3. Buyer identifies a Target Supplier

4. Supplier signs MAPP. PC&L, PE and/or SQE/AQE sign if there

are exceptions. Required for Final Sourcing Approval & Supplier

Kickoff.

Initi

al P

FM

EA

& M

APP

Rev

iew

Nexteer Sourcing Activity

Page 13: Manufacturability Assessment & Process Plan

13

MAPP Contents

1. Team Feasibility **

2. Supplier Assessment **3. Manufacturability Assessment ▼

4. Process Flow Diagram **

5. APQP Contact List **

6. Supplier Kickoff Information **

7. Approval Sheet **8. APQP Open Issues List (at AQE discretion)

9. Supplemental Technical Review Questions (at AQE discretion)

** Required for Supplier Capability & Selection Review

▼ Pilot Only: Required for Supplier Capability & Selection Review

** Completed by Nexteer

Page 14: Manufacturability Assessment & Process Plan

14

MAPP Process Timeline

Issu

e R

FQ

Rec

eive

Sup

plie

r Q

uote

Cap

abili

ty &

Sel

ectio

n R

evie

w(s

)

Nam

e Tar

get S

uppl

ier

Des

ign

& S

uppl

ier Pro

cess

Col

labo

ratio

n Act

ivity

Sup

plie

r Kic

koff

Rec

eive

Sup

plie

r M

APP

Fin

al S

ourc

ing

App

rova

l

Initi

al P

FM

EA

& M

APP

Rev

iew

Nexteer Sourcing Activity

� Supplier submits Sections 1, 2, 4 & 5 of the MAPP

NOTE: Section 3 will be required on pilot programs as directed by the Nexteer Buyer/AQE

� Supplier eSigns the MAPP and emails Excel file to the Buyer prior to the Supplier Capability & Selection Review (1st Tech Review)

Page 15: Manufacturability Assessment & Process Plan

15

MAPP Instructions

� Instructions with document links are included in the MAPP Template

Page 16: Manufacturability Assessment & Process Plan

16

MAPP Directions & Information

� Detailed comments are

included in the

MAPP Template for additional

information and support for the

supplier

Page 17: Manufacturability Assessment & Process Plan

17

� SUPPLIER: Answer each Team Feasibility question in Section 1. Add comments are as required.

� NEXTEER: The Buyer assigns a status for each item. Each item should be marked “Closed & Approved” before kicking off supplier tooling. “Open” items must have a mitigation plan completed before closing out the item.

1. Team Feasibility Requirements

Page 18: Manufacturability Assessment & Process Plan

18

� SUPPLIER: Answer 44 questions pertaining to your Manufacturing Site, Outside Processing, Quality, Program Management, Timing, etc.

� NEXTEER: The Buyer/AQE assigns a status for each item. Each item shouldbe marked “Closed & Approved” before kicking off supplier tooling. “Open”items must have a mitigation plan completed before closing out the item.

2. Supplier Assessment

Page 19: Manufacturability Assessment & Process Plan

19

� SUPPLIER: Attach a high level process flow diagram in the SECTION 4 -SUPPLIER PFD workbook tab.

� The Process Flow Diagram should be a sketch that adequately defines the process quoted. This may be a handwritten PDF file pasted into the workbook tab.

4. Supplier Process Flow

Page 20: Manufacturability Assessment & Process Plan

20

� SUPPLIER: Complete the highlighted fields in the APQP Project Contact List in the SECTION 5- CONTACT LIST worksheet tab.

5. APQP Contact List

Page 21: Manufacturability Assessment & Process Plan

21

� SUPPLIER: Fill out the Process Operation Number & Process Concept/Method

� SUPPLIER: Road Map the print and enter the Road Map #, the Requirement, Dimension, Note or Spec and the Class & Characteristic Number of each

� SUPPLIER: Complete a Manufacturing Process Feasibility Assessment for each dimension/process step.

3. Manufacturability Assessment

Page 22: Manufacturability Assessment & Process Plan

22

� SUPPLIER: Select whether the process will be completed In-House or at a Sub-Supplier

� SUPPLIER: The required Process Indices automatically populates based on the class of the dimension. Select whether or not there is a commitment to meet the required indices.

� SUPPLIER: Enter the control method for each item and the verification method

3. Manufacturability Assessment

See comments in the column headers for further instruction

Page 23: Manufacturability Assessment & Process Plan

23

Example

� Example provided for

the supplier

within the MAPP

Template

Page 24: Manufacturability Assessment & Process Plan

24

� Supplier eSigns the MAPP by entering the date and Name of their team responsible to address open issues and strive to achieve Nexteer business (cost and quality) targets

� Excel file emailed to the Buyer prior to the Supplier Capability & Selection Review

Supplier MAPP eSign

Page 25: Manufacturability Assessment & Process Plan

25

MAPP Process Timeline

Issu

e R

FQ

Rec

eive

Sup

plie

r Q

uote

Cap

abili

ty &

Sel

ectio

n R

evie

w(s

)

Nam

e Tar

get S

uppl

ier

Des

ign

& S

uppl

ier Pro

cess

Col

labo

ratio

n Act

ivity

Sup

plie

r Kic

koff

Rec

eive

Sup

plie

r M

APP

Fin

al S

ourc

ing

App

rova

l

Initi

al P

FM

EA

& M

APP

Rev

iew

Nexteer Sourcing Activity

� Internal Nexteer Signoff & Approval

� Nexteer Buyer names Target Supplier

� Nexteer AQE, PE & Supplier begin the Design & Supplier Process Collaboration Activity

� Buyer completes the Supplier Kickoff and APQP Contact List; Supplier completes the APQP Contact List

Page 26: Manufacturability Assessment & Process Plan

26

� NEXTEER: Buyer completes the APQP Project Contact List during the Design and Supplier Process Collaboration Activity

5. APQP Contact List

Page 27: Manufacturability Assessment & Process Plan

27

� SUPPLIER: Complete the APQP Project Contact List during the Design and Supplier Process Collaboration Activity.

5. APQP Contact List

Page 28: Manufacturability Assessment & Process Plan

28

� NEXTEER: Buyer, with PLPL support, fills out the QTC and Timing information during the Design & Supplier Process Collaboration Activity

6. Supplier Kickoff Information

Page 29: Manufacturability Assessment & Process Plan

29

� The AQE will document APQP Open issues within the MAPP Document

8. APQP Open Issues

Page 30: Manufacturability Assessment & Process Plan

30

� Commodity Technical Supplement questions are included in the MAPP and used at the AQE/SQE’s discretion

9. Supplemental Questions

Page 31: Manufacturability Assessment & Process Plan

31

MAPP Process Timeline

Issu

e R

FQ

Rec

eive

Sup

plie

r Q

uote

Cap

abili

ty &

Sel

ectio

n R

evie

w(s

)

Nam

e Tar

get S

uppl

ier

Des

ign

& S

uppl

ier Pro

cess

Col

labo

ratio

n Act

ivity

Sup

plie

r Kic

koff

Rec

eive

Sup

plie

r M

APP

Fin

al S

ourc

ing

App

rova

l

Initi

al P

FM

EA

& M

APP

Rev

iew

Nexteer Sourcing Activity

� Initial PFMEA & MAPP Review in preparation for Supplier Kickoff of production tooling

� Upon completion of the MAPP review, the Supplier prints the “Sections 1, 2, 3, 6 & 7 – MAPP” excel tab and the Supplier’s Key Stakeholders date & sign the MAPP.

� PDF scan of signed document is emailed to the Nexteer Buyer & AQE.

Page 32: Manufacturability Assessment & Process Plan

32

� SUPPLIER: Prior to Supplier Kickoff, the Supplier prints the “Sections 1, 2, 3, 6 & 7 – MAPP” excel tab and the Supplier’s Key Stakeholders date & sign the MAPP.

� SUPPLIER: A signed PDF copy is emailed to the Buyer and AQE.

Supplier MAPP Signoff for Kickoff

Page 33: Manufacturability Assessment & Process Plan

33

MAPP Process Timeline

Issu

e R

FQ

Rec

eive

Sup

plie

r Q

uote

Cap

abili

ty &

Sel

ectio

n R

evie

w(s

)

Nam

e Tar

get S

uppl

ier

Des

ign

& S

uppl

ier Pro

cess

Col

labo

ratio

n Act

ivity

Sup

plie

r Kic

koff

Rec

eive

Sup

plie

r M

APP

Fin

al S

ourc

ing

App

rova

l

Initi

al P

FM

EA

& M

APP

Rev

iew

Nexteer Sourcing Activity

� The Nexteer Buyer obtains Final Sourcing Approval and issues POs to kickoff the supplier to tool for production

Page 34: Manufacturability Assessment & Process Plan

34

Supplier Frequently Asked

Questions

Page 35: Manufacturability Assessment & Process Plan

35

Supplier FAQs

Question: Why is Nexteer burdening my company with this additional work?

Answer: This may appear to be a burden but this is all work that is completed during the launch process. This appears to be a burden because we are shifting from a reactive organization to a proactive organization. This also prepares the supplier for their PFD & Control Plan.

Page 36: Manufacturability Assessment & Process Plan

36

Supplier FAQs

Question: What if my company refuses to fill out the MAPP?

Answer: If your company wants our business, then you will need to comply with our request and use the MAPP. Keep in mind the intent of this document will help both of our organizations to flawlessly execute the program and minimize launch costs.

Page 37: Manufacturability Assessment & Process Plan

37

Supplier FAQs

Question: What if my company won’t provide this information without a PO?

Answer: Our policy is that we do not issue suppliers with a Purchase Order until our Design Validation is complete.

Nexteer will communicate the planned Supplier Kickoff Date to the supplier.

Page 38: Manufacturability Assessment & Process Plan

38

Supplier FAQs

Question: What if I am being pressured to provide a quote? Won’t this delay my RFQ response?

Answer: No. You can provide a quote without completing the MAPP.

The MAPP and SPI must be submitted to Nexteer prior to any tech reviews.

Page 39: Manufacturability Assessment & Process Plan

39

Supplier FAQs

Question: What if I am asked to support a Tech Review as soon as possible?

Answer: Nexteer should give you adequate time to prepare the MAPP for the Supplier Capability and Selection Review (1st Tech Review). However, there may be special circumstances. If you have concerns, please contact your Buyer or AQE/SQE.

Page 40: Manufacturability Assessment & Process Plan

40

Supplier FAQs

Question: What about a print with hundreds of dimensions?

Answer: In cases where there are many dimensions, you may group a large quantity into one line item. Example: If there are 50 non-critical cast dimensions, give them all the same road map number and document control method. Please contact your AQE if you have any questions regarding the MAPP.

Page 41: Manufacturability Assessment & Process Plan

41

Supplier FAQs

Question: Does my company have to have Covisint access to obtain a copy of the MAPP?

Answer: No. The MAPP is stored on the Supplier Portal and anyone can access this via the web. The link to Supplier Portal is included in the RFQ template. Please remember that Covisint Registration is required for all Nexteer Suppliers.