Page 1: Marina Bay Sands Integrated Resort - VSL | Heavy · PDF fileTower 1-2 and 2-3 Link Bridges Lifting Lifting of Link Bridge Girders between towers was carried out together by lifting

VSL Singapore with support from TCAA and VSL Switzerland-Heavy

IR Skypark Overall View During Lifting of IR Skypark Last North Cantilever Segment

The heavy lifting component consists of

Marina Bay Sands Integrated ResortHeavy Lifting of Skypark Steel Structure

INSERT SCANNED PHOTOHERE

TCAA and VSL Switzerland-Heavy Lifting, has successfully completed the heavy lifting works of 7,000-tonnes steel superstructure of Marina Bay Sands Skypark that sits on top of Marina Bay Sands hotel towers. The 340m long Skypark is 200m above the ground level linking the three hotel towers with a 64m long cantilever at Hotel Tower 3 end.

The construction of Marina Bay Sands Skypark steel structure was divided into 14 heavy lifts of the major components over a period of 3 months.

VSL scope of work included design of approximate 2,100-tonnes temporary steel structure for the lifting works, methodology, supply for temporary VSL CT stress bars and heavy lifting operation.

The heavy lifting component consists of lifting and sliding of a pair of Box Girder on top of Hotel Tower 3, lifting of 6 nos. of Link Bridges between Hotel Tower 1-2 and Hotel Tower 2-3, and lifting of 6 nos. of Hotel Tower 3North Cantilever segments.

Tower 3 Box Girders LiftingLifting of T3 Box Girders were carried out together by two sets of lifting frame supported on top of the hotel tower shear walls. The main girder of the lifting frames was made up of built up plate girders and spliced into different segment length considering its installation and assembly by tower crane. VSL CT stress bars were used to connect splice blocks between girder segments. Each lifting frame required 4 units of SLUs for this lifting operation.

T3 Box Girder Lifting InformationBox Girder length/height: 76m/5~10.5mLifting Weight: 2 x 760-tonnesMain Lifting Devices: 4 x SLU-330/550

4 x SLU-120/5508 x SC31-200(Hydraulic Coiler)

Lifting Height 200mSliding Distance 12m~16.7mLifting Speed 16m/hrLifting Duration 1 day (13 hours)

A pair of total 1,550-tonnes Tower 3 -Box Girders being lifted.

OWNER :Marina Bay Sands

ENGINEER :Ove Arup

MAIN CONTRACTOR :JFE/Yong Nam JV

Heavy Lifting Sub Con:VSL Singapore Pte Ltd

Page 2: Marina Bay Sands Integrated Resort - VSL | Heavy · PDF fileTower 1-2 and 2-3 Link Bridges Lifting Lifting of Link Bridge Girders between towers was carried out together by lifting

Tower 1-2 and 2-3 Link Bridges Lifting

Lifting of Link Bridge Girders between towers was carried out together by lifting frames on each tower. The lifting frame is stationary for the lifting operation and is supported on the permanent structure of the towers at Level 55. One unit of SLU lifting equipment Jack was installed on top each Cantilever Beam, which slid the Link Bridge Girder along Lifting Frame Main Beam. Due to tower crane obstruction, the Link Bridge Girders are required to be temporary load transfered onto sliding beam at Level 55M and slid for approx. 10m before it picked up again by 2nd set of SLU lifting equipment and continue to sliding to its final position along Lifting Frame Main Girder.

Tower 1-2 and 2-3 Link Bridge Girder Lifting InformationGirder length: 53mLifting Weight: 301~391-tonnesMain Lifting Devices: 2 x SLU-220/550

1 x SLU-220/550(2nd unit of Cantilever Beam)2 x SC31-200 (Hydraulic Coiler)

Lifting Height 200mSliding Distance maximum 54mLifting Speed 18m/hrLifting Duration 1 day (12 hours) for each

Girder

1st Link Bridge Between Tower 1 and Tower 2 – 372-tonnes Girder A3 being lifted.

Tower 3 North Cantilever Segment Lifting

A pair of Self-launching Lifting Frames were used to carry out the lifting of 6 North Cantilever segments. 4 units of SLU lifting equipment were installed on top of the lifting frame with ability to be adjusted independently in both transverse and longitudinal direction to suit each segment lifting position. Due to its critical completion schedule, work was carried out for 24 hours a day until completion of the cantilever was achieved.

Tower 3 North Cantilever Lifting InformationCantilever length: 64mNOS of Segment 6Segment Length 5.7~8.5mSegment Weight: 94.7~202-tonnesMain Lifting Devices: 4 x SLU-120/550

4 x SC31-200 (Hydraulic Coiler)

Lifting Height 200mLifting Speed 20m/hrLifting Duration 1 day (10 hours) for each

Segment

Tower 3 North Cantilever last segment being lifted.