Transcript
Page 1: Supplementary Environmental Project – Yellowstone sACP

Yellowstone River sub-Area Contingency Plan Overview

Page 2: Supplementary Environmental Project – Yellowstone sACP

Supplementary Environmental Project – Yellowstone sACP

Page 3: Supplementary Environmental Project – Yellowstone sACP

Supplemental Environmental Project• Yellowstone River Basin Sub-Area Contingency Plan (sACP)• Tactical Response Plan (TRP)• Additional spill response equipment and equipment

staging • Training and exercises for local emergency responders

including:• Training on the content and use of the sACP and TRP• Boom deployment and hands-on use of response equipment; • Additionally, targeted grant funding may be provided to

assist LEPC’s or other appropriate party in the region provide training (e.g., HAZWOPER) to local individuals

• sACP and TRP annual maintenance for three years

Page 4: Supplementary Environmental Project – Yellowstone sACP

Tactical Response PlansPurpose: To provide responders with a pre-developed plan of action in

the event of an incident.

1.) Reduces critical initial response time by identifying the following:- Staging Areas- Protection areas- Recovery areas

2.) Pre-identified response sites take the guess work out of resource deployment.

- Booming strategies on maps with optional driving directions

- Pre-populated ICS 204 forms (Work Assignment)

3.) It aims to protection the public’s Health and Safety and Environment.

- Environmentally Sensitive Areas- Water Intakes/Irrigation Intakes- Local, State, and Federal Parks/Schools/Public

Facilities

Administrator
I moved this up to better represent the continuity of how a plan will be used.
Page 5: Supplementary Environmental Project – Yellowstone sACP

Tactical Response PlansFunction:Tactical Response Plans may be used for actual emergencies or

training purposes.

1.) Actual emergencies:- Pages from the document may be copied and sent into the field for rapid deployment.

2.)Training purposes:- Familiarizes responders with the surrounding terrain, response techniques, and procedures.

Tactical Response Plans are created to be NIMS compliant, to adhere to the “universal language” of the ICS process.- ICS 204 forms- Response techniques- Equipment types and deployment methods

Page 6: Supplementary Environmental Project – Yellowstone sACP

Tactical Response PlansBenefits:

1.) All parties (RP, local, state, federal, contractor) involved are able to work off the same plan with the same set of instructions.

2.) Ensures allocation of resources to the highest priority protection sites.- If no plan is in place to begin with, OSRO’s and field responders have to develop impromptu strategies, potentially proving costly to the response.

Page 7: Supplementary Environmental Project – Yellowstone sACP
Page 8: Supplementary Environmental Project – Yellowstone sACP
Page 9: Supplementary Environmental Project – Yellowstone sACP
Page 10: Supplementary Environmental Project – Yellowstone sACP
Page 11: Supplementary Environmental Project – Yellowstone sACP
Page 12: Supplementary Environmental Project – Yellowstone sACP

Proposed Montana OSR Equipment

Specification of larger equipment

Page 13: Supplementary Environmental Project – Yellowstone sACP

Trailers

Page 14: Supplementary Environmental Project – Yellowstone sACP

Containment Boom

Page 15: Supplementary Environmental Project – Yellowstone sACP

Boom Deflectors

Page 16: Supplementary Environmental Project – Yellowstone sACP

Skimmer Option

Unit Cost: $1,800.00

Page 17: Supplementary Environmental Project – Yellowstone sACP

Proposed Equipment Locations

Total Estimate: $138,400.00

Glendive Boom (pre-existing Trailer)

Page 18: Supplementary Environmental Project – Yellowstone sACP

Recommended