TRAINING REPORT FOR JAL NIGAM

GOMTI ACTION PLAN & USAB TECH.

Presented by-

ARTI SINGH

BBDESGICE-

4th year

1050800013

Page 2: Gomti action plan

ACKNOWLEDGEMENT

• I WOULD LIKE TO THANK MR. ……………………….. OUR PROJECT MANAGER AT JAL NIGAM UNDER WHOSE ENRICHING GUIDANCE THIS PRESENTATION HAS PROVEN TO BE SUCH A SUCCESS.

• I WOULD ALSO LIKE TO THANK ALL MY FACULTY MEMBERS, FRIENDS AND MY FAMILY FOR THEIR CONSTANT SUPPORT .

Page 3: Gomti action plan

LUCKNOW’S USHER ~ GOMTI RIVER

• TRIBUTARY OF GANGA ORIGINATING FROM VILLAGE CHANDERPUR AND MERGES IN GHAZIPUR

• A COURSE OF 715KM THROUGH 15 DISTRICT

• THE ULTIMATE 12KM SOURCE OF WATER OF LUCKNOW.

• CARRIES 390MLD INDUSTRIAL AND HOUSEHOLD WASTE OUT FROM LUCKNOW.

• DAILY DRINKING WATER CONSUMPTION OF LKO 200MLD.

• BACTERIA COUNT 2.5X107 /100ML WATER, MAX. PRESCRIBED LIMIT 5000/100ML WATER.

• OXYGEN LEVEL 1.2MG/LITRE ,70% BELOW LOWEST SURVIVAL LIMIT FOR AQUATIC LIFE.

Dry flow-1500mld

High flow-55000mld

Lean summer flow-500mld

Page 4: Gomti action plan

OVERVIEW OF GOMTI ACTION PLAN

• IMPLEMENTED AFTER 600 ACRE SEWAGE FARM LAND USE WAS CHANGED AND TRANSFORMED TO GOMTINAGAR.

• HIGH LEVEL OF TOXICITY AND DECR. OXYGEN QUANTITY MOTIVATED THE IMPLEMENTATION OF PLAN.

• THE PROJECT WAS DIVIDED INTO TWO PHASE WHICH COVERED LUCKNOW,SULTANPUR AND JAUNPUR.

• IMPLEMENTATION OF UPFLOW ANAEROBIC SLUDGE BLANKET TECHNOLOGY (UASBT)

Page 5: Gomti action plan

PHASE 1

• 42 MLD SEWAGE TREATMENT PLANT AT DAULATGANJ , LKO.

• RS 61.01CRORE SANCTIONED BY CENTRE GOVT.

• LUCKNOW CITY BUDGET WAS RS 50.29 CRORE .

• INTERCEPTION AND DIVERSION OF KUKRAIL NALA , RS 8.06 + RS 5.58 CRORE.

• DIVERSION OF SEWAGE OF GAUGHAT,SARKATA,PATA,NAGARIA,WAZIGANJ,GHASIYAMANDIR AND CREATION OF STP.

• AMOUNTING TO RS 28.5 CRORE

• COMMISSIONED IN 12/2002

• 6.81 CRORE WAS USED FOR EMERGENCY WORK

• CLEANING OF MAJOR NALAS ,SEWER CCTV SURVEY ,DIVERSION OF GAUGHAT NALA

• RENOVATION OF CIS GOMTI SEWAGE PUMPING STATION (CGSPS)

• COMPLETED BY MARCH 1999

Page 6: Gomti action plan

PHASE 2

• 120 HECTARE 345 MLD STP AT BHARWARA.,LKO

• RS 263.04 CRORE SANCTIONED FOR PHASE 2 ON 70:30BASIS B/W CENTRE AND STATE.

• INCREASE IN CAPACITY OF DAULATGANJ STP BY 5MLD.(LATER CANCELLED)

• INTERCEPTION OF 19 DRAINS AND DIVERSION TO BHARWARA STP.NER UP/DN

STREAMCHINA BAZAR

LA-PLACE

JOPLING ROAD

LAMARTINIERE JIAMAU

Page 7: Gomti action plan

GOMTI ACTION PLAN DESIGN PARAMETERS

S.NO.

PARAMETER INFLUENT EFFLUENT

1 TOTAL SUSPENDED SOLIDS MG/L 300-600 <50

2 BOD5 MG/L 150-250 <30

3 PH 7-8 7-8

4 MPN PER 100ML 106-109 <104

5 SULPHIDE MG/L <2

• DESIGN AVERAGE FLOW 345 MILLION LITRE PER DAY

• PEAK FACTOR 1.50

Page 8: Gomti action plan

UASB TECHNOLOGY

• ANAEROBIC PROCESS

• INITIAL ADOPTION AT KANPUR FOR 5MLD STP UNDER GANGA ACTION PLAN PHASE-1 IN 1988

• EFFICIENCY 65% TO 70%

• ADDITIONAL TREATMENT REQUIRED e.g. POLISHING POND(BOD5), AERATED

LAGOONS(SULPHUR REMOVAL) etc TO MAINTAIN BOD AND TSS.

• EFFLUENCE AND SUSPENDED SOLIDS LESS THAN 30 MG/L & 50 MG/L

Page 9: Gomti action plan

RAW SEWAGE FROM MPS SCREEN

PARSHAL FLUME

PREPARATION TANK

CHLORINE CONTACT

TANK

BIO GAS FOR UTILIZATION

SLUDGE DRYING BED

Page 10: Gomti action plan

UNITS

1. SCREEN-PRE TREATMENT DONE IN SCREEN AND GRIT CHAMBER

2. GRIT CHAMBER-CONTAINS PARTICLES OF SAND,ASH,CLINKER,EGGSHELL ETC .SPECIFIC GRAVITY 2.4-2.65

3. UASB REACTOR

4. PRE AERATION TANK

5. POLISHING TANK

6. CHLORINE CONTACT TANK-5MG/L OF CHLORINE GAS KEPT FOR 30 MIN.

7. SLUDGE DRYING BED-25CM BED FOR 10 DAYS FOR DRYING PURPOSE

8. FILTATE SUMP

9. EFFLUENT DISPOSAL

Page 11: Gomti action plan

10. EFFLUENT REUSE

11. RESOURCE RECOVERY VIA BIOGAS AND SLUDGE CAKE

12. EXPECTED BIOGAS RECOVERY 400M3/HR

13. DRY SLUDGE 100TONNES/DAY

14. 1500KVA ELECTRICITY TO BE PRODUCED VIA BIOGAS

Page 12: Gomti action plan

SALIENT FEATURES OF 345 MLD UASB STP AT BHAISORA VILLAGE ,LKO

S.NO.

UNITS NO. SIZE

1 INLET CHAMBER 1 20X9X4M SWD

2 NO. OF STREAM PROPOSED 3 115 MLD EACH

3 DISTRIBUTION CHAMBER 3 8.8X7.5X2M SWD

4 SCREEN(MECHANICAL) 6+3 2 EACH STREAM+1 STANDBY 6X1.8X1M SWD

SCREEN(MANUAL) 3 6X2.8X085M SWD

5 GRIT CHAMBER(MECH.) 6 2 FOR EACH STREAM 9.5*9.5*1M SWD

(MANUAL STANDBY 50%) 3 1FOR EACH STREAM DIV.IN 2 CHANNEL9.5*4.6*.7

6 PARSHALL FLUME 3 10*1.5*1.5 SWD

7 DIVISION BOX 3 12.8*2.5*2.25 SWD

8 DIVISION BOX 2A 12 4/STREAM 6.85*2*2.25M SWD

DIVISION BOX 2B 60 20/STREAM 3.6*1.5*1M SWD

9 UASB REACTOR 11.5 MLD EACH

30 32*28*4.6M SWD(2SET OF 5 REACTOR/STREAM)

10 FEED PIPES(75MM DIA)HDPE 6720 224/REACTOR (4sqm./PIPE)

11 HRT AT AVG. FLOW 8.5 HRS.

Page 13: Gomti action plan

S.NO.

UNITS NO. SIZE

12 HRY AT PEAK FLOW 5.6HRS.

13 SRT 35 DAYS

14 GAS HOLDER 3 17.5M SWD & 3.5M SWD

15A PRE AERATION TANK 3 29.6*13.5*3M SWD

15B SURFACE AERATOR 6 2/30HP / STREAM

16A POLISHING POND COMP. 1 3 1/STREAM 140*140*3M SWD

16B COMP. 2 3 550*140*1.5M SWD

17 FLOATING AERATOR COMP. 1 18 6/SURFACE AERATOR OF 50HP/STREAM

18 CHLORINE CONTACT TANK 3 60*20*2M SWD

19 CHLORINATION 3 50Kg/hr. Booster pump 20m3/hr@6kg/cm2

20 SLUDGE CONC. 65KG/M3

21 TOTAL SLUDGE GENETATION(WET)

1812 M3/DAY

22 TOTAL SLUDGE GENERATION(DRY)

100 TONNES /DAY

23 SLUDGE SUMP 3 1/STREAM 9.85*6.8*1M SWD

24 SLUDGE PUMP 16(9W+9S)

6/STREAM OF 68m3/hr. at 35m head

25 Sludge drying bed 106 27*27m

26 Sludge cycle 10days

Page 14: Gomti action plan

S.NO. UNIT NO. SIZE

27 FILTRATE WATER SUMP 2 10*7.5*1M SWD

28 FILTRATE WATER PUMP 4 41m3/hr. 18m HEAD

29 Total power req. of stp 1500kva

30 Effluent pipe 1500m

2400mm dia RCC pipe

31 Dual fuel engine for bio gas utilization

2 850KVA each

32 Gas flaring system 2 Aspiration type pre mixing burner 6m above G.L.

Page 15: Gomti action plan

CONCLUSION OF TRAINING

• THIS TRAINING IS COMPREHENSIVE IN FILLING THE GAP BETWEEN THE THEORETICAL & PRACTICAL STUDIES

• AT THE SITE THERE WAS A GOOD MANAGEMENT SYSTEM BETWEEN THE CONTRACTOR, THE CONSULTANT, AND THE CLIENT.

• I FOUND THAT THERE WAS GOOD UNDERSTANDING BETWEEN THE SUPERVISOR AND THE WORKERS, THOUGH WORKS ARE INTERDEPENDENT BUT THERE WERE NO CONTRADICTION BETWEEN THEM.