87

Click here to load reader

CMAA Riverwalk Presentation

Embed Size (px)

Citation preview

PowerPoint Presentation

THE RIVERWALK DESIGN TEAM

THE RIVERWALK CONSTRUCTION MANAGEMENT TEAM

STAKEHOLDERSCity of ChicagoFHWAIDOTUSACEUSCGIDNR/ICMPIEPAMWRDGCCTAUSFWSIllinois Historic Preservation AgencyBuilding OwnersCommercial & Tour Boat OperatorsRecreational Users/BoatersRetailers/Business OwnersUtility CompaniesCommunity GroupsChicago Park DistrictLocal ResidentsAlderman

PROJECT GOALSMissionDevelop the underutilized Riverwalk as a premier public space and continuous system.

Project ThemesCulturalEnvironmentalEconomicRecreational

CULTURAL OBJECTIVES

Create diverse gathering spacesCelebrate the Rivers uniquenessEmbrace the sites historyEnhance community life

ENVIRONMENTAL OBJECTIVESRestore aquatic habitatCultivate terrestrial habitatImprove the water qualityUse sustainable building strategies

ECONOMIC OBJECTIVESMaximize leasable opportunitiesActivate the space along the RiverImprove the perception of safetySupport commercial boating activity

RECREATIONAL OBJECTIVESCreate a continuous public walkwayImprove vertical circulationIncrease recreational boatingProvide more public river uses

PROJECT STUDY HISTORY Chicago Riverwalk FeasibilityMain Branch GuidelinesChicago River Development PlanChicago Riverwalk Program and DevelopmentVolpe AnalysisChicago River Master PlanChicago Riverwalk AgendaChicago River MarketAction Plan for the RiverOWPP Riverwalk StudyCentral Area Action PlanChicago Riverwalk Framework Plan199219951999199920012002200520062007200820092009

PHASE 1Michigan Ave. State St.2008 2009Designers: RBA, CollinsContractors: Walsh & RauschConst. Manager: BeneschCost: $19M PHASE 2State St. LaSalle St.2014 - 2015Designers: Sasaki, RBA, BeneschContractor: WalshConst. Manager: BeneschCost: $43M PHASE 3LaSalle St. Lake St.2015 - 2016Designers: Sasaki, RBA, BeneschContractor: WalshConst. Manager: BeneschCost: $53M PROJECT PHASES

PROJECT FUNDINGPhase 1 Michigan Avenue to State StreetCentral Loop tax-increment financing district (TIF)Phases 2 & 3 State Street to Lake StreetTransportation Infrastructure Finance Innovation Act Program (TIFIA)Provides credit assistance for qualified infrastructure projectsIntended only for projects of regional or national significanceCDOT submitted letter of interest to the USDOT in 2012 for fundingLoan maturity date is 2048Loan repayment methods:

Rent / LeasesTour boatsPrivate boats

Charter boat dockingAdvertisingSponsorships

REGULATORY & PERMITTING PROCESSThe Chicago River is designated as Waters of the United States and is protected by federal law.

The City was required to obtain permission from Congress to construct the Riverwalk into the river.On September 24, 2003, the U.S. House of Representatives passed Water Resources Development Act H.R. 2557 allowing the City to build:

20 feet into the river beneath each bascule bridge (six total).25 feet between the bascule bridges.50 feet between Franklin and Lake Streets where the river widens at the confluence of the three branches of the Chicago River.

PERMITTINGFederal

USACESection 404 (Clean Water Act) Individual PermitUSCGUnderbridge and Overall Project Sign-OffInitial Risk Assessment for USACE PermitBridge Permit ApplicationBridge Lighting Permit ApplicationNavigation Lighting ReviewUSFWSThreatened and Endangered Species Sign-OffFHWANotification of Adverse Effect and Memorandum of Agreement (MOA)Final Plan Review Sign-OffState

IEPASection 401 (Clean Water Act) Water Quality Certification with Anti-Degradation ReportStormwater Pollution Prevention Plan (SWPPP)IDNR/ICMPICMP Federal Consistency Determination & Certification + Part 3704 IDNR PermitMWRDGCHydraulic Analysis & Operations Report Sign-OffSewer Permit for Sewer Connections/Structure Modifications

Illinois Historical Preservation Agency State Historic Preservation Office (SHPO)National Historic Preservation Act Section 106 Sign-Off from Advisory Council on Historic PreservationCity of Chicago

CDOTCity of Harbor PermitIrrigation & LandscapingDWMProposed Sewer Design Sign-OffWater Supply Design Sign-OffOUCStructures/Deep Foundations/Sheet Piling (Depth > 12 feet) Sign-OffNew Sewers or Drainage Structures (Depth > 12 feet) Sign-OffDEOElectrical & Lighting Internal DEO plan review and approvalMOPDInternal plan review and approvalHEDLandmarks Commission Internal plan review and approvalOther

Wacker Drive Building Owners/ManagersVerification of existing pipes and coordination/approval of proposed pipe extensions and related workCTAUnderbridge Structure over CTA Red Line Tunnel at State StreetUnderbridge Structure under Wells Street Brown & Purple Line TracksMarine Structure near CTA Blue Line Tunnel at Lake Street

PHASE 1 (COMPLETED 2009)

PHASE 1 (VIETNAM VETERANS MEMORIAL)

PHASE 1 (MICHIGAN AVENUE)

PHASE 1 (MICHIGAN AVENUE)

PHASES 2 & 3 (EXISTING CONDITIONS)

PHASES 2 & 3 (EXISTING CONDITIONS)

Dearborn to ClarkState to Dearborn

Clark to LaSalleLaSalle to Wells

Wells to FranklinFranklin to Lake

PHASES 2 & 3 (EXISTING CONDITIONS)River depth = 20 FT.Existing walkway width = 10 FT.Upper Wacker elevation = +22.0Existing dock elevation = +5.0 CCDNormal water elevation = -2.0 CCDMax. recorded water elevation = +4.1 CCDModeled 100yr storm elevation = +6.4 CCD

EXISTING SUBSURFACE FACILITIES

EXISTING SUBSURFACE FACILITIES

THE RIVERWALK PLAN PHASES 2 & 3

6 distinct blocks (rooms)Length of each room is approximately 300 feet except far west roomLength of far west room is approximately 600 feet

THE RIVERWALK PLAN PHASE 2

THE MARINA PLAZA

Dining terrace / restaurant spaceCustom public seatingTransition to Vietnam Veterans Memorial Plaza

THE MARINA PLAZA

THE MARINA PLAZA

THE MARINA PLAZA

THE COVE

Kayak and rental spaceFacilitate human-powered watercraft dockingShallow edge allows easy access to river

THE COVE

THE COVE

THE COVE

THE RIVER THEATER

Vertical access locationSculptured staircase/ramp (stramp)Boat/Water Taxi access

THE RIVER THEATER

THE RIVER THEATER

THE RIVER THEATER

THE RIVER THEATER

THE RIVERWALK PLAN PHASE 3

THE WATER PLAZA

Recreational spaceInteractive water featuresZero-depth fountain and water jetsHigh exposure to sunlight

THE WATER PLAZA

THE WATER PLAZA

Ecological learning environmentPromotes aquatic and celestial habitatsFloating gardensFishing piers and overlooksTHE JETTY

THE JETTY

THE JETTY

Vertical access locationLargest room50 build-out limitLargest green space/parkTHE BOARDWALK

THE BOARDWALK

Creates continuity between roomsClose to waterCustom canopy structuresTHE UNDERBRIDGES

THE UNDERBRIDGES

CLARK STREET UNDERBRIDGE

Structural DesignChallenges

PRIMARY STRUCTURAL DESIGN CHALLENGESExpand the RiverfrontIncorporate the existing dock wall and provide redundancyPoor soil conditionsMaintain constructability in submerged conditions

Crossing Beneath the Bascule BridgesCoast Guard design criteria for vessel collisionAvoid existing tunnels and submarine cablesMaintain constructability beneath/adjacent to the bridges

Typical Room Design ChallengesExpand the RiverfrontVarious systems from floating docks to pile-supported piers were consideredTieback system selected for cost and proven performanceReuse the existing dock wall to minimize cost and construction impactsSystem must have redundancy in the event of an existing tie rod failureRiverwalk platform designed as structural slab on grade to alleviate settlement concernsAddress utilities that must extend and pass through new dock wallConsider the constructability of various elements that will ultimately be underwater

Typical Room Plan View

Expand the Riverfront

Typical Room Cross SectionExpand the Riverfront

Assess the Existing Dock WallExpand the Riverfront

Connect New and Existing SystemsExpand the Riverfront

EXPAND THE RIVERFRONT

EXPAND THE RIVERFRONT

EXPAND THE RIVERFRONT

EXPAND THE RIVERFRONT

EXPAND THE RIVERFRONT

EXPAND THE RIVERFRONT

EXPAND THE RIVERFRONT

Jetty Plan ViewExpand the Riverfront

Jetty Design ChallengesExpand the RiverfrontPier layout limited the choice of structural systemNeeded to avoid the existing tunnels beneath the riverSame vessel collision criteria as the underbridgesMust retain existing fill if existing timber piles and sheeting fail

Jetty Cross SectionExpand the Riverfront

Underbridge Design ChallengesCrossing Beneath the Bascule BridgesMiss submarine cables and existing tunnelsAccommodate Coast Guard vessel collision criteriaMaintain constructability

Typical Underbridge Plan ViewCrossing Beneath the Bascule Bridges

Typical Underbridge Cross SectionCrossing Beneath the Bascule Bridges

Vessel CollisionCrossing Beneath the Bascule Bridges1,622 kip force parallel to channel811 kip force perpendicular to channel

Vessel CollisionCrossing Beneath the Bascule BridgesMarine Angel Largest vessel to traverse both the Mississippi and Chicago Rivers500 ft long and 70 ft wide

Vessel CollisionCrossing Beneath the Bascule Bridges

Vessel CollisionCrossing Beneath the Bascule BridgesEnvelope behavior with two separate analysesLUSAS finite element softwareL-Pile for nonlinear soil structure interactionDeflection was not deemed to be a critical limit stateUnderbridges will create a substantial improvement to the protection of the existing bridge houses in the event of an impact

Vessel Collision at State StreetCrossing Beneath the Bascule Bridges

Vessel Collision at State StreetCrossing Beneath the Bascule Bridges

Vessel Collision at Jetty PierExpand the Riverfront

Constructibility Crossing Beneath the Bascule BridgesDrilled shafts had to be drilled adjacent to and beneath the bascule bridgesConstructing the interior shafts requires bridges to be open and remain open for extended periods of timeUnderbridge drilled shaft cap is halfway underwater and must be placed in the dry

Drilled ShaftsCrossing Beneath the Bascule Bridges

Drilled ShaftsCrossing Beneath the Bascule Bridges

Drilled ShaftsCrossing Beneath the Bascule Bridges

Drilled Shaft CapCrossing Beneath the Bascule BridgesBathtub construction method chosen by Contractor

Drilled Shaft CapCrossing Beneath the Bascule Bridges

Contractor proposed to place the bottom and side primary reinforcement within the precast bathtubNeed to achieve adequate bond and horizontal shear transfer to ensure section behaves monolithically rather than as two separate membersBar splicers and grooves

Drilled Shaft CapCrossing Beneath the Bascule Bridges

Jacking PostsCrossing Beneath the Bascule Bridges

CHICAGO RIVERWALK UNDER CONSTRUCTION

THE RIVER THEATER