POINT LOCKER - NEVER LOSE A THING 1

PointLocker Project Plan -Team #3

Prepared by Team

Surbhi Anurag Gupta Nishant Bochare

Oded Mossak

Prepared for Prof. Nitu Parimi

EMGT 345 Program Management

Date: 6/7/2016

Page 2: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 2

Contents 1. EXECUTIVE SUMMARY .......................................................................................................... 3

2. INTRODUCTION ........................................................................................................................ 4

3. What is PointLocker ..................................................................................................................... 4

4. Why PointLocker .......................................................................................................................... 4

5. PointLocker Objectives ................................................................................................................ 4

6. PointLocker Market ...................................................................................................................... 5

7. Scope and Requirements ............................................................................................................... 6

8. Cost ............................................................................................................................................... 7

9. PointLocker Functioning .............................................................................................................. 8

10. Program Road Map ..................................................................................................................... 10

11. Fig1: Program Roadmap ............................................................................................................. 10

12. Project Work Breakdown Structure ............................................................................................ 12

13. Fig 2: Work Breakdown Structure .............................................................................................. 12

14. Project Milestones and Critical Path ........................................................................................... 13

15. Project Organization ................................................................................................................... 15

16. PointLocker Project Organization .............................................................................................. 15

17. PointLocker Organizational Structure ........................................................................................ 16

18. Roles and Responsibilities .......................................................................................................... 16

19. PointLocker Salaries & Benefits ................................................................................................ 18

20. PointLocker Infrastructure - Expenses ....................................................................................... 19

21. PointLocker Total Expenses ....................................................................................................... 19

22. PointLocker ROI ......................................................................................................................... 20

23. Risks and Risk Management ...................................................................................................... 24

24. PointLocker Risk Management .................................................................................................. 24

25. PointLocker Market Viability ..................................................................................................... 25

26. PointLocker Technology ............................................................................................................ 26

27. PointLocker Cost ........................................................................................................................ 27

28. Change Management Plan .......................................................................................................... 28

29. PointLocker Change Management Plan ..................................................................................... 28

30. PointLocker Change Control Board (CCB) ................................................................................ 28

Page 3: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 3

EXECUTIVE SUMMARY

This proposal presents that Entrepreneurs invest in PointLocker, a smart tiny bluetooth

tracker that finds everything in seconds. This will help users save time in searching for their

belongings. According to the Newsweek, an Average Americans spends 55 minutes a day

(roughly 12 days a year) looking for their belongings. An average person loses over $95.78

worth of belongings every year, which accounts for billions being cost all over the world.

Across 5 countries surveyed, there’s a loss of more than $47 billion every year. But this number

doesn't take into account the emotional value attached to the lost items. US News and World

reports state that 1 out of 5 Americans want to be better organized. One common theme behind

all these facts is the misplacement of items and tracking them. There have been applications in

the market that let user track their items within a smaller range but none of them scale up to

an entire city or country. The PointLocker will be available for purchase via the online stores

while the application will be available to the users via Apple App Store and can be downloaded

onto a iPhone/iPod/Mac/Window/Android users. This application will be available on App

Stores for free of cost while the PointLocker can be purchased for $25 each. After 9 months, we

would breakeven.

Page 4: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 4

INTRODUCTION

What is PointLocker:

PointLocker is an smart bluetooth tracker that is in a square shape and can be placed

behind or along with any valuable items like phone, wallet, laptop. PointLocker requires the

download of an application via the AppStore in order to track items. This application would

be installed on phones and can be accessed via the web browser as well. This application will

interact with the PointLocker and track the location of the items. In case a user wants to track

the location of the item, the application can be opened and a sound would be played on the

PointLocker attached to the item for the user to easily track it down.

Why PointLocker:

To sell any product, there has to be financial value and the psychological value of

customer satisfaction associated with it. In a lifetime the average person spends about 153 days

looking for misplaced possessions and valuables. Our product will provide a way for a user to

cut down on the number of hours or days lost in finding for their valuables. There are about

60% of users that misplaced their belongings outside their homes. Tracking belongings

misplaced outside can get hard and impossible at times as the user is not sure about the

locations they must have dropped their belongings at. PointLocker will help users track items

lost outside their homes as well by giving them a dynamic feed of locations that the item is

currently at. Based on the psychological, scientific, and financial data, our solution of

combining PointLocker with an Application based tracking makes sense. We are confident that

our product PointLocker will be a sure success in the application and consumer market.

PointLocker Objectives:

Our motto is loosing less of everything including time. With that objective in mind, we

will be catering our product, PointLocker, to all users who loose track of their items and want

to cut down time in searching for their valuables. Another important objective of PointLocker

is that it will show you the exact position on map indicating its last known position and time.

An item can be tracked within a smaller range by its sound. PointLocker batteries last for an

extended 2 year lifetime, after which the PointLocker will be replaced by us at a fraction of the

cost. The PointLocker is water resistant to IP5 standard. PointLocker has no distance limitation

as when the items can be located by different users.

Page 5: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 5

PointLocker Market:

There are several applications on the market that are available for the user to track

his/her valuables but all these applications can track items in a limited range. Our primary

focus is to attract more customer base with the new and superior functionalities of being able

to track a lost item all over the world along with a longer battery life. Bar chart shows that

number of users downloading Applications from AppStore are increasing by the year:

Graph 1: PointLocker Market

From the above chart, it can be deducted that we have a vast market of users that use

iPhone/Android application stores. There were 100 billion downloads made as of June’15. Our

market research shows that there was an increase of 20% from 2015 to 2016 in the number of

users downloading applications to track user items. As a result of all the above market facts,

we recommend that we sell PointLocker to the above stated market for free and make money

by combining the PointLocker pricing at $25 and application for free.

Page 6: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 6

Scope and Requirements

The following characteristics define the scope and requirements of PointLocker:

❖ PointLocker items can be found within the app/software community for unlimited distance

❖ Lost items shall ring just like you’d call a lost phone (PointLocker has tiny speakers that are

easy to hear)

❖ For Low Power Mode (battery saving) there is an option to put the ring on silent for any

PointLocker item

❖ PointLocker app shows location and distance of the lost item

❖ PointLocker has a 100 ft bluetooth range from any bluetooth device

❖ PointLocker App can be installed on iOS, Android, OS X and Windows (mobiles, tablets and

laptops)

❖ PointLocker can be attached, stuck or placed on desired items

❖ Any of your PointLockers can be pressed to make your lost phone ring - even if it’s on silent

• Find it near - If your lost phone is within the 100 ft bluetooth range, it will loudly ring -

even on silent

• Find it far - Can be located at its last known location, to make it ring, or to send a lock-

screen message to the other users who might find it

• Find each other - Using the app to find each other (phones, tablets, etc…) - cross-platforms

between OS

❖ The app tracks the time and location dynamically for the items

❖ Ask others to help - In case the PointLocker item is out of range, the app shall let you expand

your search using all PointLocker apps in the community

❖ App/Software shall be easy to install (App Store, Google Play) - No heavy thinking is

required

❖ App is designed to be simple and setup shall take less than 2 minutes

❖ PointLockers shall have independent power supply (batteries) and shall be connected to

PointLocker app/software via bluetooth

❖ PointLockers shall be found without Wi-Fi connection (app/software shall not require any

Wi-Fi connection to work) - within the 100 ft bluetooth range

❖ App/Software shall consume minimum battery power (shall have an On/Off ability)

❖ App/Software shall not be interrupting with regular functioning of any device

❖ Zero Upkeep - PointLocker batteries shall last for 2 years

❖ PointLocker shall be water-resistant (for rainy days)

Page 7: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 7

Cost

❖ PointLocker mobile app or software is free to download.

❖ 1 PointLocker costs $25.

❖ Option to save money if buying different packs of PointLocker

• Save 30% for 4-pack = $17.50

• Save 35% for 8-pack= $ 16.25

• Save 40% for 12-pack = $ 15.00

❖ 1- year warranty

❖ 30 - days guarantee

❖ Free shipping

❖ After 1 year you need to get a new Battery lasts for 1 year, you can replace battery

with price of $7 from dealer and shops.

❖ At 10 and 11 months, we’ll send you a friendly reminder to replace your product

with new batch product with just $15 per product.

Page 8: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 8

PointLocker Functioning

PointLocker is a tiny bluetooth tracker that helps find your lost stuff in seconds. Attach,

stick, or place PointLockers inside everyday items (phone, keys, wallet, Remote, etc…) and

keep of them in our easy-to-use app.

Setting up your account:

1. Download the PointLocker app on your phone, tablet or laptop.

2. Open the app and “Sign Up”.

3. Allow PointLocker access to bluetooth and location finding so you can see your

PointLocker on map.

4. Start using PointLocker!

Adding your first PointLocker:

1. Add a PointLocker: Select the + button to add a PointLocker

2. Confirm your account for security reasons

3. Press the tiny button on your PointLocker and listen for the tune.

4. Place the PointLocker next to your phone.

5. Make sure the PointLocker is right next to your phone after you press the tiny button on

your PointLocker.

6. Give your PointLocker a name.

7. It will be fully activated after some time and will say "PointLocker Activated”.

8. Now PointLocker can be found!

Sharing a PointLocker:

You can share each of your PointLockers with one other user. A shared PointLocker allows

you and the other PointLocker to update location and find your PointLocker.

❖ In the app, simply tap the PointLocker you want to share.

Ask other to help:

❖ Every phone in the community can help you search a lost PointLocker. You just need to

choose the option of “Notify When Found”

❖ As soon as someone running the PointLocker app comes within range of your item, its

location will be sent to you

❖ Use your phone to guide you to the exact spot your item ended up

Page 9: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 9

Finding your PointLocker - Tap on your PointLocker from the list view at your app and

nearby PointLockers within Bluetooth range (100 SF) are easily identified with a green circle

around them on the app’s list view. Your PointLocker is easily found when it’s calling out for

you.

Get an extra set of eyes – Think Marco-Polo! When you begin searching for a lost item, your

phone tracks the signal strength to your PointLocker. As you get closer, the app’s tracking

circle fills in, giving you a clear indication of your progress. To see the tracking circle, tap on

the PointLocker icon.

Page 10: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 10

Program Road Map

Fig1: Program Roadmap

❖ Project Management Meeting: As a small project we will start the project execution

planning and meetings from 5/27/2016 with a goal to define a clear vision and mission of

the product and final planning for successful product launch of PointLocker 1.0 .

❖ Market Research: As per initial market research product seems to be profitable. According

to the management and executive members’ decision, it is necessary to research about

available current market for this product, competitor and associated risk. Market research

is targeted to be achieved before 7/11/2016.

❖ Product Requirement Documents: Product requirement document will be prepared by

7/22/2016 which will be used to decide the steps required for concept design.

❖ Concept design and research: Product requirement phase is followed by the concept

design and research. Aims to analyze the design of product according to PRD with risk

assessment and alternate concept. This process has to complete before 8/12/16.

Page 11: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 11

❖ Software application development: This process is very crucial and important for the

project. Project requires iOS and Android application to work with crowd GPS and

Bluetooth technology. It expected to complete first phase in 72 days from 8/18/2016 with

agile methodologies including 3 to 4 Iterative sprints. It also includes QA, bug fixing,

testing during prototyping and continuous support for application by providing cloud

computing technology.

❖ Hardware design: Hardware design is expected to be completed by 10/28/16. It consist of

PCB design, Bluetooth module design, try and error with different design including

battery, speaker and user interface module. It also focuses on the research about

manufacturing techniques as 3D printing and different shapes and sizes of PointLocker. It

will work in parallel with the software application development.

❖ Prototyping and testing: Prototyping phase will be started as soon as the hardware design

and software application is ready for beta testing. This process consist of multiple

iterations of testing and required 30 days, expected to complete before 1/7/2017 with final

document.

❖ Manufacturing and Shipping: Manufacturing will start after finalizing the product design

and manufacturing process. Company is expected to complete manufacturing and

packaging for the 1st batch in 44 days as well as release the software applications on

2/17/2017. Shipment will start in Feb 2017.

❖ Marketing and financial strategy: Company will start marketing as soon as hardware and

software designs are finalized until 12/30/2016. Financial strategy includes bill of material,

offers, deals and other marketing related finance. It also include customer feedback of first

batch and providing PRD for second batch.

❖ Support: Support phase will start from 12/09/2016 with hiring and team formation.

Page 12: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 12

Project Work Breakdown Structure

Fig 2: Work Breakdown Structure

Project work breakdown structure is as shown related to seven categories which are interrelated to each other. Such breakdown is easy to manage and track for the program and project manager. WBS helps manager to focus on all different aspect of works and task. WBS helps project manager to schedule according to tasks, milestones and related works. In this WBS we decided to breakdown each major activity into subtask and milestones which provides detail understanding of critical task and scheduling requirement. WBS is unique method to understand full project plan and it helps to manage it according to subproject task. We have developed PointLocker scheduling according to this WBS as in next topic.

Page 13: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 13

Project Milestones and Critical Path

Page 14: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 14

Fig 3: PointLocker Milestones and Critical Path

Page 15: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 15

Project Organization

PointLocker Project Organization

❖ Chief Executive Officer - Managing the organization

❖ Chief Technical Officer - Managing the technical department for the organization

❖ Software Manager - Responsibility for delivering the software package

❖ Software Engineer - Software design and development

❖ Test Engineer - Testing the software

❖ Hardware Manager - Responsibility for delivering the hardware package

❖ Hardware Engineer - hardware design and development

❖ Test Engineer - Testing the hardware

❖ Chief Marketing Officer - Managing the marketing and sales departments for the

organization

❖ Marketing Manager - Managing promoting, positioning, pricing, branding and

advertising the product

❖ Marketing Engineer - Branding, advertising, public relations, events coordinating and

product promotion

❖ Sales Representative - Pricing and selling the product

❖ Finance Manager - Managing financial activities for the organization

❖ Human Resources - Payroll, insurance, employees records

❖ Admin - Administrative work

❖ Recruiter - Managing the hiring process for new employees

Page 16: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 16

PointLocker Organizational Structure

Roles and Responsibilities

Fig 4: Roles and Responsibilities

❖ Chief Executive Officer

• Implements strategic goals and objectives for the organization

• Gives direction and leadership to achieve organization’s goals and objectives

• Manages strategic planning process

• Communicates high performance standards and shows confidence in followers

❖ Chief Technical Officer

• Implements R&D goals and objectives for the organization

• Provides technical direction and leadership for the company’s product

• Communicates technical high performance standards

❖ Chief Marketing Officer

• Implements marketing and sales goals and objectives for the organization

• Maintains and improves customers’ relations

Page 17: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 17

• Provides marketing direction and leadership for the organization

• Reviewing marketing activities with management

❖ Software Manager

• Subject Matter Expert

• Development Lead

• Quality Assurance

❖ Hardware Manager

• Subject Matter Expert

• Development Lead

• Quality Assurance

❖ Marketing Manager

• Promotes sales for the product

• Pricing, branding, positioning, advertising

• Customer engagement

❖ Finance Manager

• Managing accounting, audit and budget

• Payrolls

• Procurement

• Recruiting

• Personal policies

❖ Software Engineer

• Software design

• Software development

❖ Hardware Engineer

• Hardware design

• Hardware development

❖ Test Engineer

Page 18: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 18

• Testing the software/hardware

• Quality Assurance

❖ Marketing Engineer

• Advertising, branding

• Public relations, events coordinating

❖ Sales Representative

• Marketing, pricing and selling the product development

• Customer relations

❖ Human Resources

• Payroll

• Employees records, insurance

❖ Admin

• Administrative and clerical duties

• Schedule meeting

❖ Recruiter

• Conducting the hiring process for new employees

PointLocker Salaries & Benefits

❖ CEO - $300K annual (equity of 30%)

❖ CTO - $270k annual (equity of 30%)

❖ CMO - $250k annual (equity of 30%)

❖ HW Manager - $140k annual

❖ SW Manager - $150k annual

❖ Marketing manager -$130k annual

❖ Finance Manager - $110k annual

❖ SW Engineer - $110k annual

❖ HW Engineer - $100k annual

❖ Test Engineer - $75k annual

❖ Marketing Engineer - $90k annual

Page 19: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 19

❖ Sales Representative - $65k annual (not including bonus per sales)

❖ Human Resources - $70k annual

❖ Admin - $60k annual

❖ Recruiter -$65k annual (not including bonus per hiring)

Total - $1,985k annuals

*The rest of the 10% equity is split between the rest of the company’s employees

PointLocker Infrastructure - Expenses

❖ Product Building (HW & SW) - $200k annual

❖ Product marketing - $100k annual

❖ Offices - $70k annual

❖ Miscellaneous Expenses - $200k annual

Total - $570k annual

PointLocker Total Expenses

Total Expenses (Salaries & Benefits and Infrastructure Expenses) - $1985+$570 = $2555K

As per quarterly expense= $851.66K

As per monthly expense= $ 212.91K

Page 20: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 20

PointLocker ROI

As per the initial market research and by using linear forecasting methods PointLocker

project comes to the following observation.

Graph 3: Forecasted revenue and sales

Table1: Forecasted sales

Page 21: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 21

Table 2: Forecasted product sales and profit

Project management and marketing team initially decided to sell the product as per

current marketing strategy in pack of 4,8 and 12 with 30%,35% and 40% respectively. Above

observation is totally dependent upon current market survey and statistics analyzed from

similar type of product companies. We have considered many factors for forecasting such as

new in established market, technology adaptation, etc. PointLocker marketing strategy an also

makes a difference in the above result. In all from above observation company can make break

even in 9th month i.e. in November 2017.

Page 22: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 22

Graph 2: Break Even Point

Graph 3 : Profit Percent (%)

Page 23: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 23

Graph 4 : Accumulated Profit in Dollars

Page 24: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 24

Risks and Risk Management

PointLocker Risk Management

1. Identify all risks, internal (company development), competitors and external (customers)

2. Risk management is the iterative approach to identifying, assessing, and prioritizing of

risks followed by coordinated and economical application of resources to minimize and

monitor the probability or impact of unfortunate events.

3. Its main goal is to ensure that uncertainty doesn't deflect the endeavor from the business

goals.

Fig 5 : Risk

Risk Impact Analysis

It has 2 dimensions:

1. Probability of occurrence

2. Impact of the event

These two measures are used to plot the risk on

the chart below. This gives a quick, clear view of

the priority that we need to give to each.

Page 25: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 25

PointLocker Market Viability

Risk Identification

❖ Analyze the market

❖ Is there a market for PointLocker ? Yes, Having a competitive advantage over the

existing products in the market can help monetize the product in the market. Competitors

are PointLocker, TrackR Bravo, pebble honey, PROTAG Duet, Cube, Nut.

• Market space – identify the target customers

• Adoption Rate – Initial research shows that the market responds positively to the

introduction of PointLocker. Big Scale Consumers being marine researchers,

commercial robotics drone companies, Car rental companies.

• Applications – Multiple OS X and Window Softwares as well as Android/iOS

Handling Methods

❖ Do a thorough Market research of all the competitors present along with the pricing

and technology they present

❖ User Personas

❖ Accept Tolerable Risk

❖ Mitigate the main risk drivers

Page 26: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 26

PointLocker Technology

Risk Identification

❖ What is the value proposition (external risk)? PointLocker is able to locate items all over the world rather than just a short distance. The batteries last for 2 years and are replaceable for a fraction of the cost.

❖ Does it differentiate itself from PointLocker (external risk)? Identify the lifetime of an PointLocker with respect to a PointLocker. PointLocker can only be located within 200ft distance while an PointLocker can be located anywhere in the world.

❖ Accuracy of the location pointer (internal risk)? Show an accurate location on the map for the item.

Handling Methods

❖ Advertise features with respect to the improvements compared to competitors

❖ Provide tutorials for ease of use

❖ Partner with Google Maps to reduce the anxiety in people for inaccuracy of the map

❖ Mitigate accuracy concerns with thorough internal testing

Page 27: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 27

PointLocker Cost

Risk Identification

❖ Internal R&D and marketing costs - Developing and marketing costs breakdown (salaries

& benefits, infrastructure and budget)

❖ Consumer costs associated with downloading the application from App Store and

purchasing PointLockers

❖ Impact on Property Privacy

Handling Methods

❖ Transfer costs to consumers - purchasing new batteries

❖ Develop couple of versions and PointLocker Generations to prevent errors in R&D and

expanses - Developing in couple of steps

❖ Offer free first PointLockers to entice consumer demand

❖ Transfer liability to consumers

Page 28: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 28

Change Management Plan

PointLocker Change Management Plan

PointLocker Change Control Board (CCB)

In software development, a Change Control Board (CCB) or Software Change Control

Board (SCCB) is a committee that makes decisions.

In this project any change proposed by any team can cause major changes in other factors

such as change in software requirement can leads to more cost and risk. CCB works as a

decision authority for change management plan.

• Filtering changes

• Managing changes and the change process

• Reviewing and closing of Requests for Change

• Management reporting and providing management information

The PointLocker CCB team would be responsible for review and evaluation of change

request which is proposed by the software management team. Approving changes is

dependent on study and research by CCB over the change and its impact on the overall

project. Mostly CCB will focus on change impact for cost, quality, time and profit. If CCB

regards the changes in management and software to be beneficial to the project then the team

gets a green signal.

The PointLocker team will initially schedule development and testing as 90 days of work in

which software team can make changes according to requirement and pass a change request

to CCB.

CCB teams work in parallel with development, testing phase and review changes with

subject matter experts. CCB is responsible for scheduling meetings with the software team,

management team and marketing team in consideration of time limit. Also CCB has to

communicate with respective teams about approved changes in scheduling, management

and marketing. CCB should consider customer in the decision of approving changes.

Page 29: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 29

In this project following are the some areas where change in management plan is expected.

1. Software Development: Mainly in developing application

2. Marketing: Marketing teams can change management plan for particular target customer

and clients.

3. Manufacturing: Manufacturing planning teams may come up with new idea in 3D

printing technology.

Main activity of CCB:

• Reviewing changes

• Making decision with result document.

• Managing Changes and teams.

• Communicating respective management teams.

• Providing suitable suggestion in changes to make balance in whole project.

IP5 Resistant - Change control process PointLocker follows IP5 water resistant technology.

This will help to improve customer perception of our product quality.

Page 30: Point locker

POINTLOCKER PROJECT PLAN

POINT LOCKER - NEVER LOSE A THING 30

References:

1. Smartphone OS Market Share, 2015 Q2 “http://www.idc.com/prodserv/smartphone-os-market-share.jsp “.

2. Change in management and CCB.”http://www.pmhut.com/change-management-change-management-process”.