Etobicoke General Hospital Redevelopment Info Session November 17, 2016

Osler EGH Redevelopment update - Nov2016

Embed Size (px)

Citation preview

Etobicoke General Hospital

Redevelopment Info SessionN o v e m b e r 1 7 , 2 0 1 6

3

THE PRIZE

4

CAMPUS

GETTING CLOSER EVERY DAY

EARLY WORKS – WE’RE DONE!

• Comfortable interior temperatures

through one of the hottest summers on

record!

• Reliable heating heading into winter

• Reliable infrastructure to support the

new patient tower

PHASE 1 - NEW PATIENT TOWER

100% Detailed Design user group meetings

complete

50% Construction Documents user group

meetings start in December

Ongoing Committees:

o Works

o ICAT

o Facilities Management

o FF&E

o Transition (kick-off)

Safety:

o Regular site visits from MOL

o No lost time incidents to date

o Regular site review of temp surfaces

Help us and report any

issues!

7

NEW PATIENT TOWER – WHERE ARE WE?

Milestone Date

Commercial/Financial close May 2016

Mobilization/Construction May/June 2016

50% DD 100% DD May 2016 Nov 2016

50% CD 100% CD1st round user group meetings in Dec (further rounds as required)

Dec 2016 April 2017

Below Grade Structure Jan 2017

Substantial Completion June 2018

Occupancy Fall 2018

WE ARE

HERE

PHASE 2 – THE JOURNEY CONTINUES

• Storm Water Tank installation

• Additional parking on Hydro Lands

• Infrastructure work on Humber

College Blvd

• New Main Entrance/Intersection

(Humber College Blvd/Westmore)

• Roads on East and South of ASB

• Completion – May 2017

IN THE TRENCHES

ANCILLARY SERVICES BUILDING

ANCILLARY SERVICES BUILDING

April – Shell and Core underway

Fit-out activities starting Fall 2017:

• L1 underground parking linked to CKD

and Ambulatory care clinic

• Level 2 ground floor retail

• Level 3 CKD fit out at stage 4 MOHLTC

capital projects approvals process

• Level 4 Ambulatory care user group

sign off of block layouts complete

• Level 5 Ambulatory care space tbd

• Level 6 and 7 Physician offices layout

blocking complete / costing underway

12

ASB – WHERE ARE WE?

Milestone Date

Slab on grade and basement parking level complete

November 2016

Detailed Design (fit-out usermtgs ongoing)

May – Oct 2016

Level 2 columns poured for 3rd

floor slabDecember 2016

Substantial Performance (Core & Shell)

October 2017

Osler ASB Fit-outs June 2017 – March 2018

CKD Fit-out (pending MOH approvals)

Nov 2017 – July 2018

WE ARE

HERE

BUT WAIT, THERE’S MORE….

• Patient Tower Infrastructure Upgrades Project

– Nurse Call (65% complete)

– Level 7 Dialysis Capable Beds/Destructive Investigation (MOH 4.1)

• Phase 2 Hydro Lands Parking (doubles capacity)

• AHU Upgrades

– Steam coil replacements

– Improve temperature/humidity control

• Mental Health

– Washroom upgrades

– Patient safety

• Lock-down

– Enhance patient and staff safety and security

EGH PUBLIC ART PROGRAM

• Call to Artist (RFQ) – August 17th to Sept 10th

• Toronto Public Art Committee (TPAC) endorsement - October 7th

• Submission of Concepts – Dec, 2016

• Agreement in place – Early 2017

• Forming/pouring: concrete footings, mud-slabs, foundation walls,

columns, stairwells

• Completion of Storm Water management system, underground

services and partial reinstatement of Lot D

• Construction entrance opposite Westmore Dr. intersection and

new main entrance road adjacent to ASB

• Revised fire exiting and Fire Safety Plan

• Construction of new Morgue

• Adjustments to pedestrian and vehicle circulation

• Regular site safety inspections

WHAT TO EXPECT over the next few months

Parking

• Site work in lot D ongoing

• Completion - early December

• Golf cart shuttle service for patients &

visitors

• Additional Impark Health customer service

staff

• December - 130 spaces for patients &

visitors returned to service

• No site work for winter months

• Spring 2017 – site works on east side of

site

WHAT TO EXPECT over the next few months

Share your feedback!

[email protected]

17

EGH PHASE 2 LOT ALLOCATION: SEPT – DEC 2016

ASB

Physicians & Staff

Patient / Visitor

Patient / Visitor

NPT

MOBStaff Overflow

ASB

Patient / Visitor

Patient / Visitor Patient / Visitor

Physicians, Staff & MOB

On-Call Staff

NPT

NPT

Patient /Visitor

QUESTIONS?

Submit now online at

[email protected]

Q: Are any food vendors going to be in the new wing?

Q: What’s the plan for the main floor of the existing building once the ED and

ICU move over to the new wing?

19

THANK YOU!