INTRODUCTION TO CONSTRUCTION INDUSTRY Final Project: Development proposal Persiaran Forest Height 2 , Taman Forest Height (Commercial & Recreation area) Individual Proposal Name : Teoh Zi Wei Student ID : 0323372 Tutor : Pn. Hasmanira Course : Foundation in Natural and Built Environment (FNBE) Module : Introduction to the Constructed Industry Intake : March 2015

Teoh zi wei indivudual ici

Embed Size (px)

Citation preview

Page 1: Teoh  zi wei indivudual ici

INTRODUCTION TO

CONSTRUCTION INDUSTRY

Final Project:

Development proposal

Persiaran Forest Height 2 , Taman Forest Height(Commercial & Recreation area)

Individual Proposal

Name : Teoh Zi Wei

Student ID : 0323372Tutor : Pn. Hasmanira

Course : Foundation in Natural and Built Environment(FNBE)

Module : Introduction to the Constructed Industry

Intake : March 2015

Page 2: Teoh  zi wei indivudual ici

Index

No Topic Pages

1 Advantages /disadvantages of site&Analysis what tot develop

1

2 Benefits & objective 2

3 Project concept 3

4 Plan explanation 4

5 Plan of building 5-7

6 Public facilities 8

7 Sport facilities 9

8 Relaxation facilities service and inner

design

10-12

9 Profession Involved and task 13-18

10 Costing 18-20

11 Conclusion 21

Page 3: Teoh  zi wei indivudual ici

Identify Advantages and Disadvantages of our site

Advantages

Our site located right beside the main road, hence it is easily accessible

to the residential areas, commercial supermarkets and shop lots around

that area. It also located at the focus point of the whole area as it has

various roads leading to every residential areas. There are many facilities

nearby such as fast food restaurants, supermarkets and school hence,

people are most likely to spend more time at this area. The traffic

condition near our site is always great although it is linked to few

residential areas.

DisadvantagesAlthough our site has bring various benefits to the residents, but

nothing is perfect. Firstly, there is no recreation area, relaxation service

area or any sport central nearby. This caused the residents have no place

for sports and relaxation. Secondly, this area have insufficient of parking

spaces in this area as most of the car driver are forced to park their car

beside the road ,especially in front of the supermarkets and Mc Donald

fast food restaurant.

ConclusionAfter I have considering all the potential and disadvantages of the site I

have come out with an idea to develop this site into a combination of

recreation area, commercial area and parking area.

Page 4: Teoh  zi wei indivudual ici

Benefits:A place for people to relax: Our site will become a place for public to

relax and do their sports activity

Solve the problem of insufficient of parking spaces: Our site will

provide parking services for public who wish to go for a walk nearby.

A place for people to communicate: Our site act as a place for the

residents to communicate which each another and meet new friends

Objective:-To build a sport area for the residents in Forest Height area

-To enclose the relation between neighborhood

-To promote and encourage residents awareness about importance of

exercise

-Act as a place to held community activities-Provide a relax and high standard sports environments-Act as a place for residents to get close to the nature-a place for all family members to gather (girls go for shopping, boy go

for sports!)

-a place to release stress and chill la~-provide more parking spaces to the visitors and residents nearby

Page 5: Teoh  zi wei indivudual ici

Project concept

Modern lifestyle, country livingProject name:ecospace

In “ecospace” we focus on the term of eco that means green technology

and nature. In this ecospace, residents will be really relax just like they

are so close to the nature. The building will be surrounded by green plants

and solar energy will be the main force to generate electricity. In our

building most of the design is in wood and plants as we all know

greenery colour make the atmosphere and surrounding to become cooler.

This place will become a heaven for sport lover as ecospace is well equip

with many types of sport facilities. The third floor of the ecospace will be

specially design as a peaceful space for public to release stress , special

service such as spa , sauna and “smash room” will be open to public for

them to have a peace of mind.

In the first floor (commercial floor): there will have some shop lots,

restaurants, spa and special services for visitors to take a rest .

In second floor of ecospace: there will be badminton courts, tennis courts,

squash court and gym and yoga room

In the basement: a huge parking area which is free to public

Page 6: Teoh  zi wei indivudual ici

PLAN EXPLANATIONEcospace is a special design commercial sport complex which is

equipped with complete facilities to fulfill the need of residents and

enable them to have a high quality environment to exercise.

. The main entrance is facing the west to prevent direct sunlight. There

are 2 main lift to access to the upper floor (the green zone in plan).In

front of the lift there is also a staircase to access to the ground floor (the

red zone)

In the ground floor, there is a spa, sauna, smash room and restaurants

and mini markets. This floor has 2 entrances 1 is from the south and 1 is

from the east. The lifts also access to this floor. There are toilet at the end

of the floor and a emergency exit right opposite the toilet. There is only 1

staircase to access to the third floor which is the staircase near the south

entrance.

In the second floor, which is the sport facilities floor, there is a gym and

yoga room (yellow zone) at the left of the staircase. The is a counter at

the entrance to ensure every visitors is registered before they enter. There

is a tennis court (grass green zone), 2 badminton courts (white zone) and

2 squash courts in this floor. There is only 1 staircase to access to this

floor to ensure everyone come to the counter before enter to the facilities

room.

Page 7: Teoh  zi wei indivudual ici

FLOOR PLAN

Basement(car park)

This basement is specially design to supply more parking space to

public.It have 2 emergency exit door and a emergency gathering point

which will allow the upper floor customer to escape when accident

happen.

Lift accessto upperfloor

Emergencyexit

Lift accessto upperfloor

Emergencygatheringpoint

Entrance

Road

Page 8: Teoh  zi wei indivudual ici

Group floor

Commercial and relaxation area

Sauna

Cloths and shoes shop

Toilet

Sport shop

restaurant

Smash Room

Stationary shop

Mini market

Spa

Sideentrance

Lift

MainentranceStaircase

to upperfloor

Page 9: Teoh  zi wei indivudual ici

Second floor

Sport Facilities floor

Tenniscourt

Sittingarea

SquashRooms

Badmintoncourts

benches

Counter

Gym & yogaroom

Toilet Changingroom

Page 10: Teoh  zi wei indivudual ici

PUBLIC FACILITIES

Public computer areaNowadays computer really help us alot in our life ,hence this publiccomputer area is to provide computerusage to public. This is a free serviceand no time limit for those who areusing the computers

Benches and coffee tableBenches is set in every part of theecospace. Elder can sit and take arest after a whole day of shopping.

Water dispenserWe care about customerhealth!Water dispenser will beplace every part of ecospaceespecially at sport facilities floorfor public to take a cup of water toprevent them from dehydrated

Locker ServiceHow can u go on sport with yourheavy backpack?Locker servicewill be provide to public for themto keep their things before they gofor sport or shopping

Page 11: Teoh  zi wei indivudual ici

Sport Facilities

SQUASH COURTS

BADMINTON COURTS

TENNIS COURT

GYM AND YOGA ROOM

Page 12: Teoh  zi wei indivudual ici

RELAXATION FACILITIES AND SERVICES

SMASH ROOM

The smash room facility is a place where you can let your hair down,

gear up and destroy real-life mocked rooms that simulate an actual

workplace, living area or kitchen. These rooms is complete with daily use

item such as: TVs, table sets sofa and more breakable item.

Everyone have different ways to express their anger, and most of them

prefer to damage or destroy something, in this room visitors are free to

smash and damage anything around them and this help them to calm

down after they are tired. We all get angry, we are human, so why not do

everything you have dreamed of doing when you are mad without paying

the insane cost and severe consequences of your actions.

Once visitor enter the room they are force to wear a hard suit and helmet

to prevent themself from being hurt.

SMASH ROOM HELP INDECREASE CRIME RATE

SMASH ROOM IS A GOOD PLACETO EXPRESS YOUR ANGER ANDYOU ARE SAFE TO DAMAGE ANDSMASH ANYTHING

Page 13: Teoh  zi wei indivudual ici

SPA

Our spa service including massage and facial treatment.

Massage is a good way to improve the flow of blood in lymphatic system. It also

can release stress, pain and muscle tension. For those elder who are suffer for

headaches and muscle pain massage is a good way to reduce their pain and help them

to sleep well.

The essential massage oil, cool color background and soft music will also cooperate

well to give customer a comfortable and relaxing environment.

Facial treatment

Facial treatment is a service to cleanse, firm smooth and moisturize your skin.

Facial treatment bring multitude of other benefits that offer you and your skin

health and wellness.Facial treatment help in restore circulation of your skin layers and

increasing the flow of oxygen-enriched blood to skin cells.

Beside that, facial treatment help us to relax and offering soothing relaxation this

benefit us a lot though emotional. Lastly, facial massage is a anti-aging process that

means it help us to slow the skin-aging process and offer us more youthful and supply

skin

Inner lookof spamassageroom

Inner plan

design of my

facial

treatment

room

Page 14: Teoh  zi wei indivudual ici

SAUNA SERVICE

Sauna is a good relaxation after a long day of work. We can totally unwind and

“sweat bath” in the small warm room. The hear of sauna room will keep your skin at

about 104 degree F causing your blood vessel to dilate and speed up your heat

rate .This improve make your blood flowing system and help to to sweat and clean up

the toxins inside your body.

Inner design of my sauna room

Bath area

Toilet

Temperature control system

seat

Page 15: Teoh  zi wei indivudual ici

Professions involved and tasks

1. Architect

2. Contractor

3. Quantity Surveyor

4. Civil and Structural Engineer

5. Supplier

6. Mechanical and Electrical Engineering

Architect

An architect is a person who plans, designs, and oversees the

construction of buildings. Architect has to produce some of the detail

drawing and come out with the idea of the whole building follow the

requirement of client. During the design phase, architect need to discuss

with the client about the requirement, concept and budget of the project.

After that architect need to heading up the team of professionals to do

their work and discuss about his design. Architect need to prepare and

present reports and design proposal to client.

During the documentation phase, architect need to produce some detail

drawing specifically using computer-aided design software. Some

professional software such as CAD is used to test the feasibility of the

design. Architect must also specifying the nature and quality of material

required to construct the building. After everything is finish documented,

architect need to prepare application for planning and building control

departments.

After all these application is done, now is the time to transform a

design into a real building. Once the project reached the construction

Page 16: Teoh  zi wei indivudual ici

stage, architect need to visit the site regularly to ensure smooth progress.

If any problem happen, site meeting need to be held to change the design

or find out the solution to solve the problem. Architect also need to

ensure the project finished on time and within the budget to avoid over

budget and extensions of time limit.

Contractor

Contractor is someone who directly employs or engages construction

workers or manages construction. In this project, contractor need to

appoint a designer or a subcontractor to ensure the designer or contractor

has the skills, knowledge and experience and, where relevant,

organisational capability to carry out the work for which they are being

appointed.

A contractor also need to overseeing the whole project and make sure

everyone did their job well, and the work can be done before the due date.

Beside of employing the profession and worker, contractor need to

manage and organize all aspects of a building site.

The building contractor is also responsible for obtaining materials for the

project. As a contractor, they need to search for suppliers for different

materials that are needed in the project and compare the quality and price

of it, try to lower the budget and obtain good quality of materials.

Another responsibility of contractor is to acquire all necessary licenses

and permits from relevant entities so that the building project can begin.

These range anywhere from building licenses to zoning permits and there

are many regulations that relate to these documents which each building

contractor must follow in order to engage in construction.

Page 17: Teoh  zi wei indivudual ici

QUANTITY SURVEYOR

A quantity surveyor (QS) is a professional working within the

construction industry concerned with construction costs and contracts.A

QS need to prepare tender and contract documents, including bills of

quantities with the architect and/or the client.

A QS need to minimize the cost of material for a project and enhance

value for money. QS need to seek for materials that are low cost ,high

quality and high quantity. Beside of controlling the materials price, they

also need to come out with the costing of repair and maintenance for a

project.

A QS have to give their advice on procurement strategy and providing

advice on contractual claims and insurances. QS also need to valuing

completed work and arranging payment from the client to the workers.

If the architect design is in a unit structure that will cost a lot of money,

QS need to give him advise to change his design and maintaining

awareness of different building structure may result in different prices.

A QS can either work for the client or the contractor, and either in an

office or at site. When project started, they need to keep track on any

variations that can affect the costs and send report to the client regularly

Page 18: Teoh  zi wei indivudual ici

Civil and Structural Engineer

Civil and Structural Engineer (C&S) is a group of expect who are train to

ensure the safety of certain building in a project. C&S need to produce

with professional drawing, idea and reports and make calculation about

the safety of the building. The structural engineer need to calculate the

loads and stresses of a building to ensure it is strong enough to withstand

the weight in a building.

Before the construction work start C&S need to go to the site to

investigate about the hardness and quality of the land and ground and

identify either it is suitable for the upcoming project.

The C&S need to check and redesign or give advise to the architect

about his design to ensure the structural of the building is safe to build

and can withstand certain amount of load and humans inside the tall

building.

C&S also need to cooperate with some professional such as

environmental scientists , architect and landscape architect and

investigate the build site and the design that is suitable to be built on

certain land.

Civil engineer need to design the inner safety of a certain building such

as the fire control system and installing quick fire exit point that directly

access to an empty land. His job is to minimize the loss of life when

accidents happen. Civil engineer even have to check the safety of the lift

and design and arrange the pathway for the public to escape when the

building is on fire.

Page 19: Teoh  zi wei indivudual ici

SUPPLIER

Supplier is someone who provide goods and materials to a certain

project. Supplier need to modify, package and supply the material to the

site when it receive order.

Supplier can be a manufactured factory or someone who sell the

materials. Some of the big supplier become a subcontractor and help the

contractor to hire profession and install certain material into the building.

Supplier also need to provide with transportation of materials to the site

and ensure the quality of material is excellent when it arrived at the site.

A delivery timetable need to be fix to ensure the stores have enough stock.

Supplier need to come to a duel either will the architect, contractor or

the QS about the price and the quantity of the material. Some of the

supplier even provide services to modify the material such as curving the

flat glass into sharp and additional charges will be calculated.

Supplier need to arrange the payment of materials from the contractor

and make calculation about the bills of material that sent to the

construction site.

Page 20: Teoh  zi wei indivudual ici

Mechanical &Electrical Engineering

Mechanical engineering is the discipline that applies the principles

of engineering, physics, and materials science for the design, analysis,

manufacturing, and maintenance of mechanical systems. Mechanical

engineer need to obtain the skill to read and interpret blueprint and

technical drawings. A mechanical engineer do their research and design,

install and operate mechanical product in certain building if required by

client.

Some of the mechanical engineer help in designing of building machines

such as Bulldozer, excavators which is use to transport and do heavy

work that can be done by human man. Beside of operating and design this

machines they have to have the knowledge to repair and maintain the

machines.

The electrical engineer need to cooperate with other engineers and

architect to come out with the electrical plan which show how the

electrical generate and transport to every single shop lots. Besides that,

electrical engineer need to design the lighting, heating and ventilation

system of a building.

To ensure the electrical system is safe to use and meet electrical and

construction safety regulation, electrical engineer need to test the whole

system and solve the issue facing related to electricity.

Electrical engineer also need to design the transportation and transport

networks. This is very important for a building to receive good signal.

Page 21: Teoh  zi wei indivudual ici

Costing

No Item Unit Quantity Amount(RM)

1. Cement M2 500 12,500.00

2. Brick M2 570 14,250.00

3. Roof M2 2000 32,000.00

4. Lamp No. 450 7,200.00

5. Locker No. 30 3,600.00

6. Dustbin No. 30 1,500.00

7. Toilet bowl No. 14 1,400.00

8. Sliding door No. 5 600.00

9. Toiler door No 16 2,400.00

10. Fan No. 35 2,975.00

11. Bench No. 15 4,500.00

12. Spa beds No. 20 3,000.00

13. Spa facilities No. 5,000.00

14. Toilet Sink No. 15 3,000.00

15. Air conditioner No. 35 70,000.00

16. Smash room No. 15 7,500.00

17. Sport facilities No. 15,000.00

18. Gym facilities No. 15,000.00

19. Sauna Room No. 4 17,500.00

Page 22: Teoh  zi wei indivudual ici

20. Car park M2 12,500.00

21 Emergency Exit

door

No. 4 400.00

22. Water Tap No. 15 375.00

23. Fire extinguisher No. 8 150.00

24. Fire alarm No. 10 12,500.00

25. Fire Sprinkler No. 15 750.00

Subtotal:RM867600.00

Page 23: Teoh  zi wei indivudual ici

CONCULSION

At the end of the project , we have concluded that is important for every

construction professional to cooperate as there are deep working relations

among various industry player.We have learn to design and plan a certain

area for it to be develop into a more valuable land.We also learn the skill

to draw a floor plan ,design of inner arrangement of a building.The most

important part is we have learn to observe and record as well as do site

analysis of our site to understand the micro climate , traffic and facilities

around it.

This project allow us to improve our documentation and observation

skill as well as to plan the way to present our research on paper.We also

learn to separate works and cooperate with our teammates and work out

effectively.

This project trade Qs and architect students equally. I as a Qs student

have learn a lot on how to do the costing work and do research on the

number of materials needed to build this building including the costing of

build in facilities such as air-conditional and doors.