25
1 Leaside Open House East Tunnel Construction March 2014

Eglinton Crosstown Leaside Open House Presentation

Embed Size (px)

DESCRIPTION

Councillor John Parker's Eglinton Crosstown Open House Presentation, March 18, 2014

Citation preview

Page 1: Eglinton Crosstown Leaside Open House Presentation

1

Leaside Open House

East Tunnel Construction

March 2014

Page 2: Eglinton Crosstown Leaside Open House Presentation

2

Page 3: Eglinton Crosstown Leaside Open House Presentation

3

Eglinton Crosstown LRT

Project

$4.9 B (2010$), funded by the Province of Ontario

19 kilometres east-west LRT from Kennedy to Jane/Black Creek,

including 10 kilometres of tunnel

Connections to Yonge-University-Spadina Subway, Scarborough RT

and GO Stouffville

Up to 26 stations

Page 4: Eglinton Crosstown Leaside Open House Presentation

4

East Tunnel Construction Timeline

At future station locations underground structures (emergency exits,

cross passages) utility relocation and headwall installation is

expected to last approximately six to eight months on average

Emergency Exits at Donlea/Hanna and at Petman Avenue are

expected to take up to 24 months to construct

The deep excavation at Brentcliffe is expected to take up to 12

months to construct

Tunnelling activities to Yonge are expected to be completed by

summer 2016

Following the completion of tunnelling works, the site will be turned

over to the Metrolinx station contractor

Page 5: Eglinton Crosstown Leaside Open House Presentation

5

Tunnel Boring Machine

The construction of new tunnels under Eglinton Avenue is done by

tunnel boring machines (TBMs).

Each TBM moves forward by pushing off against concrete segments.

The operator advances the machine as soil is removed from the TBM

face through a conveyor system.

The launch pit remains active for removal of muck/spoils.

Expected to arrive on site mid-2014 and be constructed on site

alongside the completion of the launch shaft.

Page 6: Eglinton Crosstown Leaside Open House Presentation

6

Assembly of Tunnel Boring Machines

Page 7: Eglinton Crosstown Leaside Open House Presentation

7

East Tunnels Launch Shaft

To Brentcliffe To Leslie

Page 8: Eglinton Crosstown Leaside Open House Presentation

8

Launch Shaft

Page 9: Eglinton Crosstown Leaside Open House Presentation

9

Sequence of Tunnel Drive

Page 10: Eglinton Crosstown Leaside Open House Presentation

10

Tunnel Drive Works 2014

Headwalls are temporary support walls for future excavation of

the LRT stations.

Made of concrete and installed to the depth of the future track

level

Two methods of installation used: Secant Pile Walls, Jet Grout

Machinery including drill rigs, grout tanks, diggers and other

equipment

Page 11: Eglinton Crosstown Leaside Open House Presentation

11

Tunnel Drive Works 2014

Secant pile wall : formed by intersecting

concrete piles Jet grout wall : uses engineered

grout to form wall on site

Page 12: Eglinton Crosstown Leaside Open House Presentation

12

TBM Launch- Vicinity of Brentcliffe Road and

Eglinton

Launch Shaft: a deep excavation located just east of

Brentcliffe where two tunnel boring machines will be launched

toward Yonge

Utility relocation will occur before excavation begins

Concrete temporary support walls will form the foundation of

the shaft

Work will start on the north side of Eglinton Avenue. Traffic will

be shifted according to phases of the work.

Page 13: Eglinton Crosstown Leaside Open House Presentation

13

Utility Relocations Construction of the headwalls and shafts requires that some

utilities be moved safely out of the way

Depending on site conditions: gas, hydro, water mains, sewers,

lighting and telephone and cable lines may be relocated to allow

for construction

In the vicinity of the launch and extraction shafts Metrolinx is co-

ordinating with Bell, Enbridge, Toronto Water and Toronto Hydro,

Cogeco regarding required relocations

In most cases utility relocations will be undertaken by Metrolinx

contractor

Enbridge will coordinate works with Metrolinx

Page 14: Eglinton Crosstown Leaside Open House Presentation

14

Emergency Exit Buildings

Required where station

platforms are more than 762

metres apart

Required between the

following stations:

Mount Pleasant/ Bayview

Bayview/ Laird

Constructed by Tunnels

contractors

Page 15: Eglinton Crosstown Leaside Open House Presentation

15

Emergency Exit Buildings and Cross Passages

Hannah Road

Petman

Avenue

Page 16: Eglinton Crosstown Leaside Open House Presentation

16

Approach to Traffic Management

Maintain a minimum of one lane eastbound and westbound on

Eglinton in construction work zones

Buses and general traffic will share this lane

Additional lanes will be provided if space allows

Metrolinx will work with City of Toronto Transportation, local

elected officials and neighbours to monitor local traffic

Signal timing may be modified and turning restrictions may be

added or relaxed

Page 17: Eglinton Crosstown Leaside Open House Presentation

17

Traffic Lane Reductions

Page 18: Eglinton Crosstown Leaside Open House Presentation

18

Transit Services during Tunnel Construction

Both eastbound and westbound TTC stops in the affected area

may be shifted and relocated for the safety of transit riders

Watch for TTC posted signs indicating the adjusted stop

locations

Page 19: Eglinton Crosstown Leaside Open House Presentation

19

Pedestrians

In the construction zone for temporary sidewalks or existing

sidewalks the goal is to maintain 1.5 metre sidewalk widths

wherever possible

Access to properties from sidewalks should be maintained

Some sections of sidewalk may be closed and crossings will be

available at traffic signals

Please take care when travelling near construction. Watch for

additional signage directing pedestrians

Page 20: Eglinton Crosstown Leaside Open House Presentation

20

Pedestrian Detours

Page 21: Eglinton Crosstown Leaside Open House Presentation

21

Brentcliffe Portal

Page 22: Eglinton Crosstown Leaside Open House Presentation

22

Brentcliffe Portal

Page 23: Eglinton Crosstown Leaside Open House Presentation

23

Laird Station – Longitudinal Section

Page 24: Eglinton Crosstown Leaside Open House Presentation

24

Bayview Station

Longitudinal Section

Page 25: Eglinton Crosstown Leaside Open House Presentation

25 25

E-mail:

[email protected]

Online: www.thecrosstown.ca

Tel: 416-782-8118

Community Office:

Current Community Office

1848 Eglinton Avenue West

Pending Community Office

Bayview and Eglinton

Crosstown Community Relations Team