GETTING READY TO TEST YOUR WEB APPLICATION A Guide for the Business Team in preparation for User Acceptance Testing.

Getting Ready for UAT

Embed Size (px)

DESCRIPTION

This guideline is to help you setup UAT as the business and project manager

Citation preview

Page 1: Getting Ready for UAT

GETTING READY TO TEST YOUR WEB APPLICATIONA Guide for the Business Team in preparation for User Acceptance Testing.

Page 2: Getting Ready for UAT

UAT for the Business Team

OVERVIEW

User Acceptance Testing is the point in the project life cycle where the business team will now focus on the product that is to be launched based on the initial project mandate and business case that was agreed between yourself and the developers.

Test• Test Product• User Testing

Fix Defects• User Feedback

• Defect fix implemented

Deliver• Finalise for Release

• Launch product

Page 3: Getting Ready for UAT

UAT for the Business Team

OVERVIEW

Testing your web application is vital to ensuring that you will launch a business product that meets all of the technical and quality requirements you agreed to at the beginning of the project

User Acceptance Testing (UAT) acts as a final

verification of the required business functionality

and proper functioning of the system, emulating

real-world usage conditions. This allows the

product to be moved to a live environment with

the knowledge that your product will perform in

line with the business objectives and vision.

Purpose

Please note

Page 4: Getting Ready for UAT

UAT for the Business Team

TECHNICAL TESTING

The Technical Team under the leadership of the Technical Project Manager

will conduct testing during the development cycle to ensure that all of the

requirements agreed to during the planning phase have been developed

according to the agreed specifications. These tests could include the

following:

Each defined test is agreed in a test scenario which could be defined as a test case and will control the development testing cycle.

Please note

Page 5: Getting Ready for UAT

UAT for the Business Team

TECHNICAL TESTING

During the development phase and specifically where an Agile or Scrum process has been used the business team would have been involved in the testing process in some form however it is now important to move ahead with a complete testing of the product.

User Acceptance Testing

Page 6: Getting Ready for UAT

UAT for the Business Team

PLANNING UAT

It is important that the technical project manager ensures

that the technical tests have been concluded successfully.

The business team should verify that each test conducted by

the technical team has been approved and released for UAT

testing.

Keep in mind that the web application should not be released

for User Testing if there are still fundamental errors during the

development cycle as this will impact on the agreed

timeframe for UAT and could have a cost impact.

Please note

Page 7: Getting Ready for UAT

UAT for the Business Team

Project Manager

Business Owner Test Team

Business team

Focus Groups

Technical Lead UX Designer Production

Manager

PLANNING UAT

The UAT

Please note

The UAT team could change depending on the availability of resources and skill levels

Page 8: Getting Ready for UAT

UAT for the Business Team

The full steps and process for UAT should be outlined in the UAT test plan. The test plan is defined and agreed during the planning phase of the project. This should include the test scenarios to be performed during UAT. The UAT test plan and test scenarios is the control document for the UAT process and the technical project manager should manage these documents.

Key steps• Confirm that the UAT test environment has been setup and communicated • Ensure that the test case process/methodology is agreed• Confirm that the test plan is agreed and approved• Confirm all required hardware is in place for the testing to commence.• Confirm what meetings and communication channels will be used during

the testing• Agree how defects will be logged – what ticket system is to be used.• Agree to how the defects will be categorised (e.g. High Medium Low – Low

defects could be fixed once the website has been moved to a live environment)

• Agree that how changes will be managed to prevent scope creep

PLANNING UAT

Please note

Page 9: Getting Ready for UAT

UAT for the Business Team

Role Key Function

Business Owner

• The business owner must approve that all of the UAT testing has passed and allow the product to be released to live production

Project Manager

• The project manager must control the agreed timetable for testing and ensure that this is maintained

• Must have regular update meetings with the business owner

Test Team • To perform the tests as agreed with the project manager • To update the defect log in the agreed way• To retest all defects before releasing the defect

Technical Lead

• Must coordinate and control the defect log • Must manage the technical team to resolve the defects as noted in the

raised log• Is responsible for the quality of the defects being resolved

UX Designer

• Must ensure that where the defects have an impact on the user journey that these are resolved immediately

• Must monitor the overall testing and communicate directly with the Technical lead where applicable

Production Manager

• Must control and monitor the tickets being raised for the testing cycle within the agreed timeframes

The roles and responsibilities can be adjusted where relevant.

UAT ROLES

Page 10: Getting Ready for UAT

UAT for the Business Team

GUIDELINES FOR THE UAT TEST TEAM

A clear indication of what they are going to be testing An explanation of the test cases that each tester has been assigned A laptop for the testing in good working order Mobile devices for the testing in good working order The correct testing software loaded Who to contact when there are issues How to log the defects

The following points noted below are just a high level indication of the guidelines needed to assist the UAT test team perform the testing. However it is recommended that these guidelines are clearly outlined in the UAT test plan

Please note

Page 11: Getting Ready for UAT

UAT for the Business Team

THE UAT PROCESS

Page 12: Getting Ready for UAT

UAT for the Business Team

MANAGING DEFECTS

Defect is identified

Tester logs defect in

agreed testing tool

Once resolved test log is updated

Defect is retested

Once approved by

test lead defect is closed

Test plan is updated with

results

Page 13: Getting Ready for UAT

UAT for the Business Team

FINAL UAT CHECKPOINT

Step Action

Test Log All test scenarios completed

Defects resolved Test log indicates outcomes

Defects not resolved Decision if defects are to be moved to live production and resolved under the support SLA

Production Handover Formal handover to the production team

Live Release The live release is sent by the project manager to business

Test Project The test project is closed in the ticket system

Test Team The test team is released and can return to their normal day to day activities

Page 14: Getting Ready for UAT

UAT for the Business Team

MOVING TO LIVE PRODUCTION

Once the testing has been signed off by the business team the project manager will prepare the release notification to handover the project to the support team. This will be managed by your supplier who is hosting your system.

The supplier is also responsible to ensure that all of the migration of data as agreed in the data mapping plan is moved over to the new website.

The business team will have to ensure that the relevant Service Level Agreements are in place which include the required Software Licenses.

Please note

Page 15: Getting Ready for UAT

UAT for the Business Team

THE LIVE WEBSITE

Congratulations you have now reached the stage where you are ready to launch your website.

Communication of the live release should be sent to the marketing and business teams

All of the information, logs and documentation should be stored in your project folder and used for lessons learnt for future developments

Please note