21

Click here to load reader

Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Embed Size (px)

Citation preview

Page 1: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Former NAS Moffett Field

Site 26 Eastside Aquifer Treatment SystemSite 26 Eastside Aquifer Treatment System

Neil Hey, PGShaw Environmental, Inc.

Valerie Harris PEValerie Harris, PENavy BRAC PMO West

S t b 8 2011September 8, 2011RAB Meeting

1

Page 2: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Presentation Overview

• Treatability Study Update

• Focused Feasibility StudyFocused Feasibility Study

• Schedule

• Questions

2

Page 3: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Site 26 Treatability Study - Location

3Note – inset location not to scale

Page 4: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Treatability Study Purpose

Evaluate the applicability and effectiveness ofEvaluate the applicability and effectiveness of EHC®, an in situ abiotic/biotic treatment technology to reduce the chemicals of concerntechnology, to reduce the chemicals of concern (COC; PCE, TCE, DCE, & VC) concentrations in groundwater to levels below the ROD cleanup g pstandards at IR Site 26

4

Page 5: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

EHC® Treatment Technology

• A product of Adventus Americas, Inc.

• Patented combination of zero valent iron (ZVI)• Patented combination of zero-valent iron (ZVI) particles & plant-based carbon

• Combination of chemical (abiotic) and biological (biotic) reductive dechlorination processes

5

Page 6: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Project Description

• Installed 5 observation wells

• Injected EHC® at 16 locations

• Performed 10 post-injectionpost-injection groundwater monitoring events

6

g

Page 7: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Site LocationEHC® Injection

Total CEs ~80 µg/L

50 ft x 50 ft area

40 to 8 feet bgs

~6,600 gallons6,600 gallons hydrant water

~23 000 poundsGroundwater Flow

~23,000 pounds EHC®

7

Page 8: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Treatment Area Results

82 µg/L total82 µg/L total

2 µg/L total4 µg/L total

8

Page 9: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Treatment Area Results

9

Page 10: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

TS Conclusions

• EHC® easy to prepare but difficult to injectEHC® t di t ib t d if l d t h t• EHC® not distributed uniformly due to heterogeneous nature of subsurface

• Complete reductive dechlorination observed in all treatment area wells

• 98% reduction in total COCs concentration in treatment areaarea

• PCE, TCE, & DCE concentrations in treatment area reduced below ROD cleanup standards in < 1 yearVi l hl id i i i• Vinyl chloride concentration in treatment area remains slightly above ROD cleanup standard but decreasing

• EHC® continues to treat on-flow of COCs 2 years after

10

ytreatment

Page 11: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Focused Feasibility Study

11

Page 12: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Site 26 Background

• Chlorinated solvents identified in groundwater near Hangar 3 in 1983

• Record of decision (ROD) signed in 1996. Selected remedy was groundwater extraction and treatmentremedy was groundwater extraction and treatment to restore groundwater to cleanup standards.

• Cleanup standards – drinking water– Tetrachloroethene (PCE) = 5 g/L– Trichloroethene (TCE) = 5 g/L

C 2 d hl h 6 /– Cis-1,2-dichloroethene = 6 g/L– Vinyl chloride = 0.5 g/L

12

Page 13: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Site 26 Background (continued)

• Eastside Aquifer Treatment System (EATS) began q y ( ) goperating in 1999. – extracted 67 million gallons of water– removed 23.7 pounds of chlorinated volatile organic

compounds (VOCs)• Shut down in 2003 to evaluate:• Shut down in 2003 to evaluate:

– Evaluate plume stability– Chemical rebound– Natural attenuation– HRC in plume hot spots

13

– Treatability study (almost completed)

Page 14: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

2010 Groundwater Plume

Combined CVOC concentrations• 85.9 g/L (maximum) located near current treatability studystudy• Max combined CVOC concentration in other areas b t 25 /about 25 g/L

TREATABILITY STUDY AREA

14

Groundwater Flow

Page 15: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Focused Feasibility Study

Purpose – to evaluate several technologies along with the selected remedythe selected remedy

• Identify remedial action objectives and applicable regulations

• Identify and screen treatment technologies– Monitored Natural Attenuation– Abiotic/Biotic Treatment (EHC®)– In Situ Biostimulation/Bioaugmentation

• Develop and evaluate remedial alternatives against• Develop and evaluate remedial alternatives against seven of the nine NCP criteria

• Compare the remedial alternatives against each other

15

• Compare the remedial alternatives against each other

Page 16: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Preliminary Remedial Alternatives

• Alternative 1 – No Action

• Alternative 2 – Monitored Natural Attenuation (MNA)(MNA)

• Alternative 3 – Optimized Pump and Treat

16

Page 17: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Preliminary Remedial AlternativesPreliminary Remedial Alternatives

• Alternative 4 – Abiotic/biotic Treatment and MNA

• Alternative 5 – In Situ Biostimulation /Bi t ti d MNA/Bioaugmentation and MNA

Biotic PCE

TCE

VC

Cis 1,2‐DCE       Trans 1,2‐DCE

VC

Ethene

17

Ethane

β‐eliminationα‐elimination

Page 18: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Conceptual Treatment Areas

•Trend analysis performed forperformed for each well

•Identify areas th t ld b fitthat could benefit from treatment

Natural

Natural processes = 60 years

processes > 60 years (increasing trend/no

18

trend/no trend)

Page 19: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Sustainability

• An evaluation of sustainability will be included in the feasibility study (FS)in the feasibility study (FS)

• FS will use SiteWiseTM

Streamlined life cycle analysis tool– Streamlined life-cycle analysis tool – Developed by Navy, Army Corps and Battelle– Available at http://www.ert2.org/t2gsrportalAvailable at http://www.ert2.org/t2gsrportal

• Sustainability metrics considered are:– Energy and resource consumptiongy p– Greenhouse gas and criteria pollutant emissions– Water and ecological impacts

19

– Worker and community safety

Page 20: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

ScheduleSchedule

• November 30, 2011- Draft FS Report p

• December 1, 2011 to January 29, 2011 – Agency/RAB Review of draft g y/

• April 30, 2012 - Final FS Report

Next Steps

– Proposed planProposed plan

– ROD amendment

20

Page 21: Moffett Superfund Site 26 Update to the Moffett Restoration Advisory Board

Questions?

21