Click here to load reader
Upload
steve-williams
View
591
Download
0
Tags:
Embed Size (px)
Citation preview
Former NAS Moffett Field
Site 26 Eastside Aquifer Treatment SystemSite 26 Eastside Aquifer Treatment System
Neil Hey, PGShaw Environmental, Inc.
Valerie Harris PEValerie Harris, PENavy BRAC PMO West
S t b 8 2011September 8, 2011RAB Meeting
1
Presentation Overview
• Treatability Study Update
• Focused Feasibility StudyFocused Feasibility Study
• Schedule
• Questions
2
Site 26 Treatability Study - Location
3Note – inset location not to scale
Treatability Study Purpose
Evaluate the applicability and effectiveness ofEvaluate the applicability and effectiveness of EHC®, an in situ abiotic/biotic treatment technology to reduce the chemicals of concerntechnology, to reduce the chemicals of concern (COC; PCE, TCE, DCE, & VC) concentrations in groundwater to levels below the ROD cleanup g pstandards at IR Site 26
4
EHC® Treatment Technology
• A product of Adventus Americas, Inc.
• Patented combination of zero valent iron (ZVI)• Patented combination of zero-valent iron (ZVI) particles & plant-based carbon
• Combination of chemical (abiotic) and biological (biotic) reductive dechlorination processes
5
Project Description
• Installed 5 observation wells
• Injected EHC® at 16 locations
• Performed 10 post-injectionpost-injection groundwater monitoring events
6
g
Site LocationEHC® Injection
Total CEs ~80 µg/L
50 ft x 50 ft area
40 to 8 feet bgs
~6,600 gallons6,600 gallons hydrant water
~23 000 poundsGroundwater Flow
~23,000 pounds EHC®
7
Treatment Area Results
82 µg/L total82 µg/L total
2 µg/L total4 µg/L total
8
Treatment Area Results
9
TS Conclusions
• EHC® easy to prepare but difficult to injectEHC® t di t ib t d if l d t h t• EHC® not distributed uniformly due to heterogeneous nature of subsurface
• Complete reductive dechlorination observed in all treatment area wells
• 98% reduction in total COCs concentration in treatment areaarea
• PCE, TCE, & DCE concentrations in treatment area reduced below ROD cleanup standards in < 1 yearVi l hl id i i i• Vinyl chloride concentration in treatment area remains slightly above ROD cleanup standard but decreasing
• EHC® continues to treat on-flow of COCs 2 years after
10
ytreatment
Focused Feasibility Study
11
Site 26 Background
• Chlorinated solvents identified in groundwater near Hangar 3 in 1983
• Record of decision (ROD) signed in 1996. Selected remedy was groundwater extraction and treatmentremedy was groundwater extraction and treatment to restore groundwater to cleanup standards.
• Cleanup standards – drinking water– Tetrachloroethene (PCE) = 5 g/L– Trichloroethene (TCE) = 5 g/L
C 2 d hl h 6 /– Cis-1,2-dichloroethene = 6 g/L– Vinyl chloride = 0.5 g/L
12
Site 26 Background (continued)
• Eastside Aquifer Treatment System (EATS) began q y ( ) goperating in 1999. – extracted 67 million gallons of water– removed 23.7 pounds of chlorinated volatile organic
compounds (VOCs)• Shut down in 2003 to evaluate:• Shut down in 2003 to evaluate:
– Evaluate plume stability– Chemical rebound– Natural attenuation– HRC in plume hot spots
13
– Treatability study (almost completed)
2010 Groundwater Plume
Combined CVOC concentrations• 85.9 g/L (maximum) located near current treatability studystudy• Max combined CVOC concentration in other areas b t 25 /about 25 g/L
TREATABILITY STUDY AREA
14
Groundwater Flow
Focused Feasibility Study
Purpose – to evaluate several technologies along with the selected remedythe selected remedy
• Identify remedial action objectives and applicable regulations
• Identify and screen treatment technologies– Monitored Natural Attenuation– Abiotic/Biotic Treatment (EHC®)– In Situ Biostimulation/Bioaugmentation
• Develop and evaluate remedial alternatives against• Develop and evaluate remedial alternatives against seven of the nine NCP criteria
• Compare the remedial alternatives against each other
15
• Compare the remedial alternatives against each other
Preliminary Remedial Alternatives
• Alternative 1 – No Action
• Alternative 2 – Monitored Natural Attenuation (MNA)(MNA)
• Alternative 3 – Optimized Pump and Treat
16
Preliminary Remedial AlternativesPreliminary Remedial Alternatives
• Alternative 4 – Abiotic/biotic Treatment and MNA
• Alternative 5 – In Situ Biostimulation /Bi t ti d MNA/Bioaugmentation and MNA
Biotic PCE
TCE
VC
Cis 1,2‐DCE Trans 1,2‐DCE
VC
Ethene
17
Ethane
β‐eliminationα‐elimination
Conceptual Treatment Areas
•Trend analysis performed forperformed for each well
•Identify areas th t ld b fitthat could benefit from treatment
Natural
Natural processes = 60 years
processes > 60 years (increasing trend/no
18
trend/no trend)
Sustainability
• An evaluation of sustainability will be included in the feasibility study (FS)in the feasibility study (FS)
• FS will use SiteWiseTM
Streamlined life cycle analysis tool– Streamlined life-cycle analysis tool – Developed by Navy, Army Corps and Battelle– Available at http://www.ert2.org/t2gsrportalAvailable at http://www.ert2.org/t2gsrportal
• Sustainability metrics considered are:– Energy and resource consumptiongy p– Greenhouse gas and criteria pollutant emissions– Water and ecological impacts
19
– Worker and community safety
ScheduleSchedule
• November 30, 2011- Draft FS Report p
• December 1, 2011 to January 29, 2011 – Agency/RAB Review of draft g y/
• April 30, 2012 - Final FS Report
Next Steps
– Proposed planProposed plan
– ROD amendment
20
Questions?
21