Project Quality Management Based on PMBOK 5th Edition

Waleed El-Naggar, MBA, PMP

https://www.facebook.com/waleed.naggar

Agenda

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 2

Quality Theories

Evolution of Quality Management

8.1 Plan Quality Management

8.2 Perform Quality Assurance

8.3 Control Quality

Quality is the degree to which the project fulfills

requirements.

Quality Management includes creating and

following policies and procedures in order to

ensure that a project meets the defined needs it

was intended to meet.

Quality Management

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 3

Joseph Juran: 80/20 principle, top management

involvement. Quality is fitness for use.

W. Edwards Deming: 14 steps of total Quality

Management, Plan-Do-Check-Act cycle.

Philip Crosby: Cost of poor quality, prevention

over inspection and zero defects. Quality is

“conformance to requirements”

Quality Theorists

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 4

1950 1960 1970 1980 1990 2000 2007

Evolution of Quality Management

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 5

Quality Control

Quality is separating good

from bad parts without

feedback to the production

process ; Final Inspection

1950 1960 1970 1980 1990 2000 2007

Evolution of Quality Management

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 6

Quality Control

Quality Assurance

Quality develops during the

production process; Inspection

shifted into to the production

process, prevention, process

orientation

1950 1960 1970 1980 1990 2000 2007

Evolution of Quality Management

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 7

Quality Control

Quality Assurance

ISO 9000

Quality is defined, planned and

supervised company-wide;

commitment of management,

participation of employees, step

by step improvement.

Six Sigma

Evolution of Quality Management

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 8

1950 1960 1970 1980 1990 2000 2007

Quality Control

Quality Assurance

ISO 9000

Total quality Management

Total Quality management: Customer, employees,

process, society & stakeholder orientated. A

philosophy that encourages companies and their

employees to focus on finding ways to continuously

improve the quality of their business practices and

products.

1950 1960 1970 1980 1990 2000 2007

Six Sigma

Evolution of Quality Management

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 9

Quality Control

Quality is separating good

from bad parts without

feedback to the production

process ; Final Inspection

Quality Assurance

Quality develops during the

production process; Inspection

shifted into to the production

process, prevention, process

orientation

ISO 9000

Total quality Management

Six Sigma,

Is an overall methodology that drives

business improvement.

DMAIC process : Define, Measure, Analyze, Improve &

Control

Customer Satisfaction

Prevention over inspection

Continuous improvement

Management Responsibility

Cost of Quality (COQ)

ISO Compatibility

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 10

Quality is:

A. Meeting & exceeding customer needs.

B. Adding extra to make customer happy.

C. Conformance of requirements and fitness of use

D. Conformance to management’s requirements

Quiz:

PMP - Project Quality Plan 11 https://www.facebook.com/waleed.naggar

Identifying quality requirement and/or

standards for the project and its deliverables,

and documenting how the project will

demonstrate compliance with the relevant

quality requirements.

8.1 Plan Quality Management

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 12

1. Project Management Plan, includes but

not limited to

Scope baseline

Work Breakdown Structure

WBS Dictionary

Schedule baseline

Cost baseline

Other management Plans

Plan Quality: Inputs (1)

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 13

2. Stakeholder Register

3. Risk register

4. Requirements Documentation

5. Enterprise environmental factors

6. Organizational process assets

Plan Quality: Inputs (2)

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 14

1. Cost-benefit Analysis

2. Cost of Quality (COQ)

3. Seven Basic Quality Tools

Cause-and-Effect Diagram

Flowcharts

Check-sheet

Pareto Diagram

Histograms

Control Charts

Scatter Diagram

Plan Quality: T & T

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 15

4. Benchmarking

5. Design of Experiments

6. Statistical Sampling

7. Additional Quality Tools

Brainstorming

Force field analysis

Nominal Group Technique

Quality Management and control tools

8. Meetings

Plan Quality: T & T

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 16

The primary benefit of meeting quality

requirements is less rework, i.e., higher

productivity, lower costs and increased

stakeholder satisfaction.

The primary cost of meeting quality

requirements is the expenses associated

with quality management activities.

Cost-benefit Analysis

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 17

Cost of Quality

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 18

Cost of Quality

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 19

Cause and Effect Diagram

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 20

Trace the problem’s source back to its “actionable

root cause”

A graphical representation of a process showing the

relationships among process steps.

Flowcharting

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 21

Tally Sheets

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 22

Pareto Diagram

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 23

Histogram

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 24

Graphic displays of the results, over time, of a

process; used to assess whether the process is

“in control”

Rule of Seven – Run of seven points toward

upper or lower control limit may indicate that

process is out of control

Assignable causes – Variations may be caused

by differences in machines, workers overtime,

etc. Identify the root cause.

Control Charts

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 25

Control Chart – contd.

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 26

Scatter Diagram

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 27

Benchmarking involves comparing actual or

planned project practices to those of other

projects in order to generate ideas for

improvement and to provide a standard by which

to measure performance.

These other projects may be within the

performing organization or outside of it, and may

be within the same or in another application area.

Benchmarking

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 28

Design of experiments is a statistical method

that helps identify which factors might influence

specific variables. It also plays a role in the

optimization of products or processes.

Design of Experiment

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 29

Statistical sampling involves choosing part of a

population of interest for inspection (e.g., selecting

10 samples of 75 electronic components).

Appropriate sampling can often reduce the cost of

quality control.

There is a substantial body of knowledge on

statistical sampling; in some application areas, it is

necessary for the project management team to be

familiar with a variety of sampling techniques.

Statistical Sampling

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 30

1. Quality Management Plan

2. Process Improvement Plan

Process Boundaries

Process Configuration

Process Metrics

Targets for Improved Performance

3. Quality Metrics

4. Quality Checklist

5. Project Documents Updates

Plan Quality Management: Outputs

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 31

Training costs are part of:

A. Prevention costs

B. Appraisal costs.

C. Internal failure costs.

D. External failure costs.

Quiz:

PMP - Project Quality Plan 32 https://www.facebook.com/waleed.naggar

1. Auditing the quality requirements and the results

from quality control measurement to ensure that

appropriate quality standards and operational

definitions are used.

2. The key benefit of this process is that it facilitates

the improvement of quality processes

8.2 Perform Quality Assurance

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 33

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 34

1. Quality Management Plan

2. Process Improvement Plan

3. Quality Metrics

4. Quality Control Measurements

5. Project Documents

Perform Quality Assurance: Input

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 35

1. Quality Management and Control Tools

Affinity Diagrams

Process Decision Program Charts

Interrelationship Digraphs

Tree Diagrams

Prioritization Matrices

Activity Network Diagram

Matrix Diagrams

2. Quality Audits

3. Process Analysis

Perform Quality Assurance: T & T

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 36

Affinity Diagrams

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 37

Process Decision Program Charts (PDPC)

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 38

Interrelationship Digraph

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 39

Tree Diagrams

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 40

1. Change Requests

2. Project Management Plan Updates

3. Project Documents Updates

4. Organizational Process Assets

Perform Quality Assurance: Output

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 41

Who is responsible of the quality management in

the project:

A. Project Quality Manager.

B. Project Manager

C. Project Team members.

D. Quality Assurance Department.

Quiz:

PMP - Project Quality Plan 42 https://www.facebook.com/waleed.naggar

Perform Quality Control is the process of

monitoring and recording results of executing

the quality activities to assess performance and

recommend necessary changes

The key benefits of this process include

Identifying the causes of poor quality

Validating that project deliverables and work meet

the requirements

8.3 Control Quality (1)

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 43

Important Quality terms

Prevention (Keeping errors out of the process) vs.

Inspection (Keeping errors out of the hands of the

customer).

Attribute sampling (either conform or doesn't) vs.

Variables sampling (degree of conformity)

Tolerance (range of acceptable results) and control

limits (thresholds which may indicate out of control)

8.3 Control Quality (2)

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 44

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 45

1. Project Management Plan

2. Quality Metrics

3. Quality checklists

4. Work Performance Data

5. Approved Change Requests

6. Deliverables

7. Project Documents

8. Organizational Process Assets

Control Quality: Input

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 46

1. Seven Basic Quality Tools

2. Statistical Sampling

3. Inspection

4. Approved Change Request Reviews

Control Quality: T & T

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 47

1. Quality Control Measurements

2. Validated Changes

3. Verified Deliverables

4. Work Performance Information

5. Change Requests

6. Project Management Plan Updates

7. Project Document Updates

8. Organizational Process Assets Updates (Completed

checklists, lessons learned documentation, etc.)

Control Quality: Output

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 48

When a process considered to be in control, it:

A. Should not be adjusted

B. May not be changed to provide improvements.

C. Shows differences caused by expected causes.

D. Should not be inspected or reworked for any

reason.

Quiz:

PMP - Project Quality Plan 49 https://www.facebook.com/waleed.naggar

Thank you

PMP - Project Quality Plan https://www.facebook.com/waleed.naggar 50