2295-10PR

• Capacity 95 tons

• Hydraulic Stroke 11 inches

• Screw Extension 5 inches

• Closed Height 10 inches

• Extended Height 26 inches

• Operating Pressure

– First Stage 4335 psi

– Second Stage 6795 psi

© Columbus JACK Corp. 2011

2295-10PR

Cylinder Support Caster

Air Pump

Accumulator

Cylinder Assembly

© Columbus JACK Corp. 2011

2295-10PR

Hand Pump

Towbar

Control Console

© Columbus JACK Corp. 2011

2295-10PR

© Columbus JACK Corp. 2011

2295-10PR

Air Control Valve

Release Valve

Dual Reading Load Gauge (Optional)

© Columbus JACK Corp. 2011

2295-10PR

Air Pressure Relief Valve

Air Inlet

System Relief Valve

Shown Without Optional Load Gauge

Release Valve

© Columbus JACK Corp. 2011

2295-10PR

Accumulator Charge Port

Test Port

Accumulator Relief Valve

© Columbus JACK Corp. 2011

2295-10PR

Cylinder Bushing

O-Ring

O-Ring

1st Stage Ram

2nd Stage Ram

O-Ring

© Columbus JACK Corp. 2011

Operation – To Raise

• Locate jack under aircraft lifting point.

• Raise towbar to lower cylinder to ground.

• Raise rain hat and unscrew screw extension as required.

• Close release valve.

• Operate pump until rams have raised aircraft to desired height.

© Columbus JACK Corp. 2011

Operation – To Lower

• Slowly open release valve.

– Opening release valve too quickly will cause restrictor fuse to actuate, resulting in the rams lowering very slowly.

– To reset the restrictor fuse, close release valve, operate hand pump 1-2 strokes. Open release valve slowly to lower rams.

• When load is removed from cylinder rams, accumulator will “power retract” rams to their fully collapsed position.

© Columbus JACK Corp. 2011

Operation – To Lower

• Lower screw extension completely.

• Place rain hat over cylinder.

© Columbus JACK Corp. 2011

• To verify/recharge the nitrogen pressure in the accumulator:

– Open release valve on console and insure rams are fully collapsed.

Special Maintenance Instructions

– Open accumulator isolation valve under frame.

– Attach 0-300 psi test gauge to top of accumulator.

– Verify accumulator charge is 225 + 5 psi. Re-charge as necessary with nitrogen.

– Close accumulator isolation valve.

© Columbus JACK Corp. 2011

• To recharge hydraulic fluid pressure in the accumulator:

– Open release valve on console.

– Attach 0-600 psi test gauge to test port at bottom of accumulator.

– Close release valve on console.

– Fully extend both cylinder rams.

– Open accumulator isolation valve under frame.

– Loosen hose fitting at top of cylinder assembly.

Special Maintenance Instructions

© Columbus JACK Corp. 2011

Special Maintenance Instructions

– Using hand pump, slowly pump hydraulic fluid until all entrapped air is removed.

– Tighten hose fitting at top of cylinder assembly.

– Loosen gauge fitting at test port at bottom of accumulator.

– Using hand pump, slowly pump hydraulic fluid until all entrapped air is removed.

– Tighten gauge fitting at test port.

– Using hand pump, pressurize system to 425 psi maximum.

– Close accumulator isolation valve under frame.

© Columbus JACK Corp. 2011

Special Maintenance Instructions

– As there may be some residual pressure in the system, slowly remove gauge from test port on bottom of accumulator and install cap.

– Cycle rams several times to verify smooth extension and retraction.

– Open release valve on console and verify rams retract fully.