08/31/07 Shutdown’07 Week 4 F.G. Garcia 1
MTA beam line installation Weekly ReportAugust 31, 2007
Period covered: August 24th to August 31st (Week 4)
MTA – Week2
08/31/07 Shutdown’07 Week 4 F.G. Garcia 2
MTA Weekly Report – Week 4
Shielding underneath hatch area 08/27 Floor underneath the hatch area has been leveled to
aid the shielding wall installation. 08/30 Crane/Iron Workers returned to the job site
Lifted left over material and no more necessary equipment
Started restacking shielding wall yesterday!Linac side MTA side Next week:
- Finish the wall
- ETC: 09/05
08/31/07 Shutdown’07 Week 4 F.G. Garcia 3
MTA Weekly Report – Week 4
Electrical Work Cable tray installation 100% complete Cable pull started and is progressing well
Start with load cables – 30% complete.Next week: Continue with cable pulling and termination
Magnets Installation 4 magnets remain to be full stationed
Installation on hold until shielding wall is complete
Next week: Resume installation after completion of the wall
Alignment Crew was available this week to finish the network Crew assisted on checking stationing of some questionable
magnets
Next week: If schedule permits start roughing alignment late in the week (or maybe early week 6).
08/31/07 Shutdown’07 Week 4 F.G. Garcia 4
MTA Weekly Report – Week 4
LCW work LCW header connected up to Booster 95 LCW from the Linac
Lower level complete. Good progress with the long straight sections in the tunnel
Both supply/return 2” copper piping installed along the wall Contractors are approaching the cross over the beam lines
Next week: Continue with the 2” copper piping installation