1 Solar Update July 11, 2013 Michael E. Finn, CFO
Preview:
Citation preview
- Slide 1
- 1 Solar Update July 11, 2013 Michael E. Finn, CFO
- Slide 2
- Coyote Hills, Zuni Hills and Peoria High School to begin
construction April 1 Elementary schools completed August 2 High
School completed August 30 Cheyenne, Desert Harbor, and Santa Fe to
begin construction May 27 All completed September 27 2 Construction
Schedule- Original Schedule
- Slide 3
- Zuni Hills Plans submitted to city March 15th Permits issued
May 23 rd Broke ground May 31 st New projected completion date of
September 20 th Coyote Hills Plans submitted to city March 17th
Permits issued May 23 rd Broke ground June 3 rd New projected
completion date of September 20th 3 Updated Schedules and
Progress
- Slide 4
- Peoria High School Plans submitted to city March 18th Permits
issued June 13 th Broke ground June 17 th New projected completion
date of September 20 th Cheyenne Elementary School Plans submitted
to city April 29th Permits issued July 1 st New projected
completion date of November 15th 4 Updated Schedules and
Progress
- Slide 5
- Santa Fe Elementary School Plans submitted to city April 29th
Permits still under review Projected permits on July 17th New
projected completion date of November 15 th Desert Harbor
Elementary School Plans submitted to city April 29 th Projected
permits on July 17th Permits still under review New projected
completion date of November 15th 5 Updated Schedules and
Progress
- Slide 6
- AERIAL VIEWS OF WORK IN PROGRESS 6
- Slide 7
- 7
- Slide 8
- 8
- Slide 9
- 9
- Slide 10
- QUESTIONS 10