Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
EM-1000 Public
Manual No. 015
Business Practices ManualGenerator Interconnection
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
2/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage i
Disclaimer
This document is prepared for informational purposes only to support the application of the
provisions of the Open Access Transmission, Energy and Operating Reserve Markets Tariff
(Tariff) of the Midwest ISO, Inc. (MISO) and the services provided under the Tariff. MISO may
revise or terminate this document at any time at its discretion without notice. However, every
effort will be made by MISO to update this document and inform its users of changes as soon as
practicable. Nevertheless, it is the users responsibility to ensure you are using the most recent
version posted on MISO website. In the event of a conflict between this document and the
Tariff, the Tariff will control, and nothing in this document shall be interpreted to contradict,
amend or supersede the Tariff.
This Business Practices Manual (BPM) contains information to augment the filed and accepted
Tariff of MISO. In all cases the Tariff is the governing document and not the BPM. Additionally, if
not otherwise defined herein, all capitalized terms in this BPM have the meaning as defined in
the Tariff.
Time Zone
In 2006, Central Indiana, where MISO offices are located, began observing Daylight Savings
Time. However, MISO, its systems, and the Midwest Markets, will continue to do business in
Eastern Standard Time year-round.
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
3/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage ii
Revision History
DocumentNumber
Reason for Issue Revised by: Effective Date
BPM-015-r6 Revised to reflect the November 1st,2011 filing of the modifications to theGenerator Interconnection Proceduresand Agreement.
E. Laverty
BPM-015-r5 MISO Rebranding Changes E. Nicholson MAR-21-2011
BP-015-r5 Revised to reflect the sixth M2 milestoneoption and separate deliverabilityanalysis into its own subsection.
E. Laverty MAR-21-2011
BPM-015-r4 Revised to reflect July 15th
filing forShared Network Upgrades
E. Laverty JUL-16-2010
BPM-015-r3 Revised to reflect numbering protocol E. Laverty JAN-01-2010
TP-BPM-004-r2 Revised to reflect the Open AccessTransmission, Energy and OperatingReserve Markets Tariff for the MidwestISO, Inc. (Tariff) relating toimplementation of the Day-Ahead andReal-Time Energy and AncillaryServices Markets and to integrateproposed changes to the Balancing
Authority Agreement.
E. Laverty JAN-06-2009
TP-BPM-004-r1 Revised to reflect the June 25th, 2008filing of the modifications to theGenerator Interconnection Proceduresand Agreement.
J. Doner AUG-25-2008
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
4/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage iii
TABLE OF CONTENTS
1. Introduction ...........................................................................Error! Bookmark not defined.11.1 Purpose of the MISO Business Practices Manuals ....Error! Bookmark not defined.11.2 Purpose of this Business Practices Manual ...............Error! Bookmark not defined.11.3 References ................................................................Error! Bookmark not defined.1
2. Generator Interconnection Process Overview .......... ..........Error! Bookmark not defined.33. Pre-Queue Phase ..................................................................Error! Bookmark not defined.4
3.1 Resources Available ..................................................Error! Bookmark not defined.43.1.1 Contour Map.....................................Error! Bookmark not defined.43.1.1.1 Ongoing Efforts ................................Error! Bookmark not defined.6
3.2 Regularly Scheduled Information Sessions .......... ......Error! Bookmark not defined.63.3 Ad Hoc Information Sessions ........... .......... ........... .....Error! Bookmark not defined.6
4. Application Review Phase ....................................................Error! Bookmark not defined.84.1 Scoping Meeting ........................................................Error! Bookmark not defined.84.2 Initial Screening .........................................................Error! Bookmark not defined.9
4.2.1 Application Milestones (M1) .......... ..Error! Bookmark not defined.104.2.2 Definitive Planning Phase Entry Milestones (M2)Error! Bookmark not defined.114.2.3 Letter of Credit Requirements .........Error! Bookmark not defined.134.2.4 Feasibility Study .............................Error! Bookmark not defined.134.2.5 Study Deposits and Refunds ..........Error! Bookmark not defined.15
4.3 Determination of Project Linkages and Potential GroupingError! Bookmark not defined.184.4 Queue Position ........................................................Error! Bookmark not defined.19
5. System Planning and Analysis Phase ...............................Error! Bookmark not defined.205.1 Regular Generator Interconnection System Impact StudyError! Bookmark not defined.235.2 Planning and Operating Horizon Studies .................Error! Bookmark not defined.235.2.1 Power Flow Analysis ................................................Error! Bookmark not defined.23
5.2.1.1 Determine available injection capabilityError! Bookmark not defined.235.2.1.2 Determine upgrades for requested serviceError! Bookmark not defined.245.2.1.3 Base Case Assumptions ................Error! Bookmark not defined.24
5.2.1.3.1 Load Levels and Generation DispatchError! Bookmark not defined.24
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
5/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage iv
5.2.1.3.2 Generation to Include ....Error! Bookmark not defined.255.2.2 Criteria Used to Determine Constraints .......... .......... Error! Bookmark not defined.255.3 Custom Scope .........................................................Error! Bookmark not defined.255.3.1 Timeframe ...............................................................Error! Bookmark not defined.255.3.2 Transmission Modeled .............................................Error! Bookmark not defined.265.3.3 Generation modeled ................................................Error! Bookmark not defined.265.3.4 Study Scenarios and Analyses ................................Error! Bookmark not defined.27
5.3.4.1 Injection (ERIS) evaluation ........... ..Error! Bookmark not defined.275.3.4.2 Deliverability (NRIS) evaluation ......Error! Bookmark not defined.275.3.4.3 Transmission Service Request (TSR) evaluationError! Bookmark not defined.275.3.4.4 Net Zero evaluation ........................Error! Bookmark not defined.28
5.3.5 Study Generator Dynamic Model .............................Error! Bookmark not defined.285.3.6 Outages ...................................................................Error! Bookmark not defined.28
5.3.6.1 System Intact ..................................Error! Bookmark not defined.285.3.6.2 Planned Outages (specify) .............Error! Bookmark not defined.28
5.3.7 Deliverables .............................................................Error! Bookmark not defined.295.3.7.1 Required System Improvements & CostError! Bookmark not defined.295.3.7.2 Amount of Service Available without Additional UpgradesError! Bookmark not defined.295.3.7.3 Interconnection Facilities for Reactive CompensationError! Bookmark not defined.305.3.7.4 Availability of Transmission ServiceError! Bookmark not defined.30
6. Definitive Planning Phase ..................................................Error! Bookmark not defined.326.1 Generator Interconnection System Impact Study .....Error! Bookmark not defined.326.1.1 Steady State Analysis ..............................................Error! Bookmark not defined.33
6.1.1.1 Thermal analysis ............................Error! Bookmark not defined.336.1.1.1.1 Base Case AssumptionsError! Bookmark not defined.346.1.1.1.1.1. Load Levels and Generation DispatchError! Bookmark not defined.346.1.1.1.1.2. Generation to Include Error! Bookmark not defined.356.1.1.1.2
Applicable Reliability CriteriaError! Bookmark not defined.35
6.1.1.1.3 Cascading Outage ConditionsError! Bookmark not defined.366.1.1.1.4 Prior Outage Conditions Error! Bookmark not defined.366.1.1.1.5 Permissible Software ToolsError! Bookmark not defined.36
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
6/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage v
6.1.1.1.6 Criteria Used to Determine ConstraintsError! Bookmark not defined.366.1.1.1.7 Deliverability Analysis....Error! Bookmark not defined.376.1.1.1.8 Network Upgrade Cost AllocationError! Bookmark not defined.386.1.1.1.9 Shared Network Upgrade Cost Allocation EligibilityError! Bookmark not defined.39
6.1.1.2 Steady State Voltage Analysis ........Error! Bookmark not defined.426.1.1.3 Power Factor Requirement Analysis for Wind Turbine GeneratorError! Bookmark not defined.42
6.1.2 Short Circuit and Stability Analysis .......... ........... ......Error! Bookmark not defined.426.1.2.1 Base Case Assumptions ................Error! Bookmark not defined.43
6.1.2.1.1 Load Levels .......... .........Error! Bookmark not defined.436.1.2.1.2 Generation to Include ....Error! Bookmark not defined.43
6.1.2.2 Applicable Reliability Criteria ......... .Error! Bookmark not defined.436.1.2.3 Permissible Software Tools .......... ..Error! Bookmark not defined.436.1.2.4 Criteria Used to Determine Stability and Short Circuit ConstraintsError! Bookmark not defined.436.1.2.5 Mitigation Used to Resolve Stability ConstraintsError! Bookmark not defined.44
6.1.3 Mitigation Verification ...............................................Error! Bookmark not defined.446.1.4 Backfilling ................................................................Error! Bookmark not defined.446.1.5 Customer Funded Network Upgrade Optional StudyError! Bookmark not defined.45
6.1.5.1 Background ....................................Error! Bookmark not defined.456.1.5.2 Network Upgrade Funding and Facilities Studies:Error! Bookmark not defined.466.1.5.3 MISO Sub Regional Planning MeetingsError! Bookmark not defined.466.1.5.4 Availability of ARRs ........... .......... ...Error! Bookmark not defined.466.1.5.5 Shared Network Upgrade Cost Allocation Treatment:Error! Bookmark not defined.46
6.2 Facility Study ...........................................................Error! Bookmark not defined.466.2.1 Study Objectives ......................................................Error! Bookmark not defined.476.2.2 Scope of Upgrades ..................................................Error! Bookmark not defined.486.2.3 Cost of Upgrades .....................................................Error! Bookmark not defined.496.2.4 Contingencies ..........................................................Error! Bookmark not defined.506.2.5
Facility Study Exhibits for the GIA ............................Error! Bookmark not defined.50
6.2.6 Interconnection and Operating Guidelines ......... ......Error! Bookmark not defined.516.2.6.1 Interconnection Agreement Appendices PopulatedError! Bookmark not defined.51
6.2.7 Submittal of IA for Appendix Review ........................Error! Bookmark not defined.52
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
7/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage vi
6.2.8 Submittal of GIA/FCA for Execution / Filing UnexecutedError! Bookmark not defined.526.2.9 Provisional Generator Interconnection Agreement ...Error! Bookmark not defined.536.2.10 Use of Multi Party Facility Construction Agreement (MPFCA)Error! Bookmark not defined.54
7. Post GIA Phase ...........................................................................................................8567.1 Providing Modeling Data .........................................................................................9577.2 Suspension .............................................................................................................9577.3 Construction ............................................................Error! Bookmark not defined.587.4 Testing .....................................................................Error! Bookmark not defined.587.5 Registration of Asset with MISO...............................Error! Bookmark not defined.587.6 Inclusion in Network Model ......................................Error! Bookmark not defined.597.7 Commercial Operation .............................................Error! Bookmark not defined.59
Appendix A .................................................................................Error! Bookmark not defined.60Sample Contour Map .................................................................Error! Bookmark not defined.60Appendix B .................................................................................Error! Bookmark not defined.61Generator Interconnection Ad hoc Information Session Request FormError! Bookmark not defined.61Appendix C .................................................................................Error! Bookmark not defined.64General Study Process Diagrams .............................................Error! Bookmark not defined.64Appendix D ..........................................................................................................................1166Modeling data to be submitted by Interconnection Customer to MISO .......................... 1166Appendix E .................................................................................Error! Bookmark not defined.69Pre-Commercial Generation Test Notification Form ...............Error! Bookmark not defined.69
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
8/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage 7
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
9/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage 8
7. Post GIA Phase
The following sections describe various activities in project development after the Generator
Interconnection Agreement is executed.
Initial Payment
The Interconnection Customer is required to pay the initial payment of either 1) 20% of the total
cost of Network Upgrades, Transmission Owner Interconnection Facilities, Transmission
Owners System Protection Facilities, Distribution Upgrades and/or Generator Upgrades
identified in the GIA within 30 days of executing its GIA if the Generator In-service date is within
5 years of executing the GIA; or 2) 10% if it is beyond 5 years; or 3) the total cost of Network
Upgrades, Transmission Owner Interconnection Facilities, Transmission Owners System
Protection Facilities, Distribution Upgrades and/or Generator Upgrades in the form of security.
Limited Operation
If any of the Transmission Owners Interconnection Facilities, Network Upgrades, or
Transmission Owners System Protection Facilities, Distribution Upgrades or Generator
Upgrades are not reasonably expected to be completed prior to the Commercial Operation Date
of the Generating Facility, Transmission Provider shall, upon the request and at the expense of
Interconnection Customer, perform operating studies on a timely basis to determine the extentto which the Generating Facility and the Interconnection Customers Interconnection Facilities
may operate prior to the completion of the Transmission Owners Interconnection Facilities,
Network Upgrades, Transmission Owners System Protection Facilities, Distribution Upgrades
or Generator Upgrades consistent with Applicable Laws and Regulations, Applicable Reliability
Standards, Good Utility Practice, and the GIA. The maximum permissible output of the
Generating Facility will be updated on a quarterly basis if the Network Upgrades necessary for
the interconnection of the Generating Facility pursuant to the GIA are not in service within six (6)
months following the Commercial Operation Date of the Generating Facility as specified in
Appendix B of the GIA. These quarterly studies will be performed using the same methodology
set forth Section 6.2.9 of this BPM for Provisional Generation Interconnection Agreements.
These quarterly updates will end when all Network Upgrades necessary for the interconnection
of the Generating Facility pursuant to this GIA are in service.
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
10/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage 9
7.1 Providing Modeling Data
Within thirty (30) Calendar Days after the Generation Interconnection Agreement has been
signed, the Interconnection Customer is required to provide a model for the Generating Facility
to MISO.
The Interconnection Customer shall provide power flow modeling data for the generator and
associated interconnection facilities as applicable by submitting a project into Model on Demand
(MOD). The Interconnection Customer shall provide a working stability model for the Generating
Facility that is compatible with MISO standard models (typically PSS/e models). Refer to
Appendix D for the specific requirements to be provided. These models are intended to be used
in MISO Planning Studies. The Interconnection Customer will be required to update the
submitted models throughout the development of the Generating Facility as needed.
Submittal of modeling data for corresponding Network Upgrades shall be coordinated between
the Interconnection Customer and the Transmission Owner.
7.2 Suspension
After the execution of the Interconnection Agreement, the Interconnection Customer is expected
to meet the milestones and construction schedule as established in the Interconnection
Agreement. In certain conditions, Interconnection Customer has the option to suspend the
construction of the Network Upgrades and Interconnection Facilities based on narrowly defined
criteria. The following rules and conditions will govern the suspension of a project in the post-IAphase.
Permitted only for Force Majeure reasons: Any act of God, labor disturbance, act of
the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or
accident to machinery or equipment, any order, regulation or restriction imposed by
governmental, military or lawfully established civilian authorities, or any other cause
beyond a Partys control. A Force Majeure event does not include an act of
negligence or intentional wrongdoing by the Party claiming Force Majeure.
When coming out of suspension with only partial construction resulting in reduced
project capacity, recovery eligibility is reduced on a pro-rata basis relative to the new
size of the project
Will require an up-front payment equivalent to greater of Network Upgrade costs or
$5 million
Formatted: Space After: 12 pt
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
11/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
OPS-12 PublicPage 10
Suspended IRs may be revisited periodically to ensure Interconnection Customer is
working toward coming out of suspension
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
12/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
Page 11OPS-12
Public
Appendix D
Modeling data to be submitted by Interconnection Customer to MISO
Powerflow Modeling data into Model on Demand (MOD)
Interconnection Customer to submit project in MOD to model their Generating Facility, as notedahead:
Submit MOD projects to model generators with a project type Generator in MOD. Set the
project status as per the following:o For generator with a signed Generation Interconnection Agreement (GIA) that is not in
service, set the status as Planned.
o For changes to existing generators as per representation in the MOD base case, submit
project with a status of In-Service
Choose an effective date of MOD project as per best available information of the expected
in-service date.
Include the following information in the project name as per the naming convention below:
o MISO generator interconnection project number
o Interconnecting Transmission Owner (ITO)
o State where project is interconnecting
o Fuel Type
o Example: G000-XEL-MN-Wind.prj
Include the following power-flow data in the MOD project:o Bus number(s) corresponding to POI approved by ITO
o For the Generator Step-up transformer, provide:
Voltage ratings (kV)
Normal and emergency rating (MVA)
Impedance
Load tap changer/phase shifter information
o As applicable, for Generating Facility with collector systems:
Pad-mount transformer data (voltage levels, ratings, impedance parameters)
Collector system equivalent (voltage level, MVA rating, impedance)
Interconnection radial line parameters (voltage level, MVA rating, impedance
parameters)
Additional equipment as needed
o Net maximum and minimum real power (MW) output (Pmax and Pmin)o Net maximum and minimum reactive (MVArs) output (Qmax and Qmin) ( if a wind
machine, please note below)
Formatted: Font: 14 pt, No underlin
Formatted: Heading 1
Formatted: Font: 14 pt, Not Bold, N
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
13/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
Page 12OPS-12
Public
o Remote bus number for which the voltage is to be regulated by the generator, as
applicable
o External Reactive Compensation, as applicable
o Power Factor and reactive power limits:
Type of wind machine WMOD1 WPF Notes
Not a wind machine 0 Do not populateReactive limits will be asspecified by Qmax and Qmin
Wind machine with arange of reactive poweroutput with unequal,leading and laggingpower factor limits
1 Do not populate
Reactive limits will be as
specified by Qmax and Qmin.This would be most applicablefor wind machines that have adifferent range for lagging andleading power factor.
Wind machine with theequal leading andlagging power factorcapability
2Specify rated powerfactor value
Reactive limits will change as afunction of active power outputand power factor specified here.This will replace the maximumand minimum reactive limitsspecified under Qmax andQmin.
Wind machine with afixed leading OR laggingreactive power capability
3
Specify rated power
factor value (specifypositive WPF forlagging power factoroperation and viceversa)
Reactive power output willchange to a fixed value as a
function of the active poweroutput and power factor. Thiswill replace the maximum andminimum reactive limitsspecified under Qmax andQmin.
1For more details, refer to the PSS/e Program Operation Manual for the specifics on generator data records.
Formatted: Left
Formatted Table
Formatted: Left, Indent: Left: 0", Abetween paragraphs of the same style
Formatted: Left, Indent: Left: 0", Abetween paragraphs of the same style
Formatted: Left, Indent: Left: 0", Abetween paragraphs of the same style
Formatted: Left, Indent: Left: 0", Abetween paragraphs of the same style
7/28/2019 20121127 IPTF Item 02 Modeling Update - BPM-015-r6_Section 7.1
14/14
Generator Interconnection
Business Practices ManualBPM-015-r6Effective date: TBD
Page 13OPS-12
Public
Dynamic Modeling
Interconnection Customer to submit working dynamic model for Generating Facilitycompatible with MISO standard models (typically PSS/E models) that include:
General parameters for various generator types:
o Time constants
o Sub-transient, transient, and synchronous impedances:
Saturated
Unsaturated
o Mechanical parameters:
Inertia Damping
For Steam or Hydro Units:
o Generator Data
o Exciter Data
o Governor Data
o Power System Stabilizer Data (if installed)
o Min/Max exciter limiter Data (optional)
o Turbine Load Controller Data (optional)
For Wind Units:
o Wind Turbine Generator Type (i.e. 1, 2, 3, or 4)
o Generator Data
o Control mode
o Mechanical (Turbine) Datao Electrical (Exciter/Converter) Data
o Pitch Control Data (optional)
o Aerodynamic Data (optional)
For PV Units:
o Electrical (Converter) Data
o Control Data
Dynamic models for reactive compensation devices used, if applicable
Maximum and minimum generator terminal voltage limits for normal and emergency
conditions (including LVRT capabilities)
Protection information including voltage and frequency protection as applicable
Single line diagram (including breaker configuration)
Formatted: ParaText, Line spacing:
Recommended