Agenda
Chatfield Watershed Authority Technical Advisory Committee (TAC) Meeting March 6th, 2018
2:00 p. m. – 4:00 p. m.
Castle Rock Water
175 Kellogg Court, Castle Rock, CO 80109 Entrance at Gate C
For Teleconference call-in capabilities, please contact Valerie Mozena at least 24 hours in advance by email (valerie.mozena@lrewater.com)
TAC meeting packets will be available at www.chatfieldwatershedauthority.org
2:00 p.m. Authority TAC Call to Order
• Introductions – please sign in • TAC Member disclosures
Action Items/Recommendation to Board
Patrick O’Connell & Mary Kay Provaznik A. Approval of February 6th, 2018 TAC Meeting Minutes (Attachment 1)
B. Review of April 3rd, 2018 TAC Meeting Date
C. Review/Approval of Invoices for Payment - The table summarizes the invoices included in the TAC
packet. Board post-payment ratification is required at quarterly Board meetings (Attachments 2 - 4)
D. Review/Approval of Policies (Emailed Separately, Katie Fendel & Kate Moran) a) Manure Management b) Reserve Pool c) Site Location Approval Review Requirements
Discussion and Presentation Items
A. CRMC Reservoir Model Presentation by CRMC Consultant, Hydros (Christine Hawley)
Invoices < $5,000 and within Budget and Scope (Manager’s Approval)
TWS Financial Inc. January 2018 Invoice $1,000.00
Hughes & Stuart Marketing (Services for January – March 2018) Invoice $750.00
Invoices $5,000 - $15,000 and within Budget and Scope (TAC Approval*) Leonard Rice Engineers February 2018 Invoice $8,446.50
Invoices > $15,000 and/or any Amount not within Budget or Scope (Board Approval) None
*Also requires post-payment Board ratification at next quarterly Board Meeting
Authority Board Chair: Lora Thomas Authority Board Vice-Chair: George Teal
TAC Chair: Patrick O’Connell TAC Vice-Chair: Mary Kay Provaznik
Technical Updates
A. Technical Member Updates (Members) a) CRMC b) Public Outreach Committee (Patrick O’Connell & David Van Dellen) c) Other Member
B. Manager’s Update
a) March 12th, 2018 Triennial Review Information Hearing (TRIH) (Katie Fendel & Kate Moran) i) Board Approved and Signed Letter Sent February 27th, 2018 to WQCC (Attachment 5)
b) 2017 Annual Report (Kate Moran) c) Regulation 85 Incentive Program (Katie Fendel) d) EPA Proposal Use of Orthophosphate-Based Corrosion Control Treatment (Katie Fendel) e) Site Applications and Land Use Referrals (Attachments 6 & 7, Kate Moran) f) Inquiry to Authority Plum Creek Watershed Education (Kate Moran)
C. Financial Recap (Attachments 8 & 9, Ted Snailum)
a) January – December 2017 b) January 2018
Upcoming Meetings
A. Next Scheduled TAC Meetings: a) Tuesday, April 3rd, 2018: 2:00 – 4:00 p. m., Castle Rock Water, 175 Kellogg Court,
Castle Rock, CO 80109 [NOTE: Meeting Date to be Discussed at March 6th TAC] b) Tuesday, May 1st, 2018: 2:00 – 4:00 p. m., Castle Rock Water, 175 Kellogg Court,
Castle Rock, CO 80109
B. Next Scheduled Board Meeting: a) Monday, May 21st, 2018: 3:00 – 5:00 p. m., Castle Rock Water, 175 Kellogg Court,
Castle Rock, CO 80109
C. Public Outreach Committee Meeting: TBD
4:00 p.m. Adjournment of Regular Meeting Attachments
Attachment 1 - February 6th, 2018 TAC Meeting Minutes Attachment 2 - TWS Financial Invoice - January 2018 Attachment 3 - Hughes & Stuart Invoice - (January – March) Marketing Services Attachment 4 - Leonard Rice Engineers Invoice - February 2018 Attachment 5 - Regulation 73 TRIH Letter to WQCC Attachment 6 - Site Applications Attachment 7 - Land Use Referrals Attachment 8 - TWS Financial Recap January – December 2017 Attachment 9 - TWS Financial Recap January 2018
Attachment – 1
February 6th, 2018 TAC Meeting Minutes
Page 1 of 4
TAC Meeting Minutes
February 6, 2018 Castle Rock Water 175 Kellogg Court
Castle Rock, CO 80109
Member Attendees:
David Van Dellen (Castle Rock) Jim Dederick (Douglas County) Mary Kay Provaznik (Dominion W&SD) Patrick O’Connell (Jefferson County) Ron Beane (Louviers W&SD) Weston Martin (Plum Creek WRA)
Alternate Members, Other Associate Agencies, and Attendees: Barbara Biggs (Roxborough W&SD) Bill Ruzzo (Chatfield Reservoir Mitigation Company) Cathy Begej (Jefferson Conservation District) Elaine Hassinger (Tri County Health Department) Ronda Sandquist (Roxborough W&S) Kate Moran (Authority Manager) Katie Fendel (Authority Manager) Patrick O’Brien (Authority Manager)
Call to Order
• Meeting called to order at 2:10 p.m. by Vice Chair, Mary Kay Provaznik • No disclosures
Action Items 1) January 9, 2018 TAC Meeting Minutes
• Discussion Included: No change to January 9, 2018 TAC Meeting Minutes
• Jim Dederick moved, Ronda Sandquist seconded approval of the minutes; motion carried
2) Invoices • Discussion Included: All invoices within scope and budget Manager shared an updated invoice table to include two additional invoices:
o Hughes and Stuart Public Outreach 2017 invoice for $1,000.00 is within scope and budget
Chatfield Watershed Authority
Page 2 of 4
o TWS Financial Inc. November 2017 invoice for $1,000.00 is within scope and budget
• Jim Dederick moved, Ronda Sandquist seconded approval of all invoices; motion carried
3) Recommended New Policy for Site Location Approvals Review Requirements
• Discussion Included: Clarify process and Authority roles in new policy Manager will make changes to new policy based on TAC recommendations Manager will provide updated version at the next TAC meeting to change
• No action
Discussion Items 1) Water Quality Report
• Discussion Included: PCWRA data will be utilized, with other monitoring partners’ (Centennial W&SD,
Denver Water, Colorado Parks and Wildlife) in Water Quality Reports o PCWRA data will provide additional upstream to downstream look at water
quality parameters within watershed E. coli increases in lower portion of the Plum Creek mainstem could potentially be a
result of aging septic tanks o Portion of Plum Creek mainstem has high-priority 303(d) listing for E. coli
Phosphorus and chlorophyll α in compliance for reservoir in 2017 (growing season) 2) Triennial Review Informational Hearing (TRIH)
• Discussion Included: Review of draft recommendation letter
o Ronda Sandquist provided a redlined version and TAC accepted these changes
o Manager will send out updated letter with Ronda’s edits incorporated with additional sentence about CRMC’s model consultant has been invited to present on model status TAC wants to provide Commission with notification Hydros has been
invited by Authority to present at TRIH o Manager will send out updated version for TAC to review and provide input
prior to next Board meeting February 26th, 2018 This includes two signing options for the Board, both option 1 and
option 2 will be sent to TAC for review Review of PowerPoint presentation for March 12th, 2018 TRIH
o CRMC confirmed Christine Hawley can attend TRIH o Christine will provide draft presentation at the March 6th, 2018 TAC meeting
prior to TRIH TAC Vice-Chair Mary Kay and Board Member will be invited to March 12th, 2018
TRIH Manager will send out updated PowerPoint based on TAC feedback
o Slides will include chlorophyll α and total phosphorus data, public outreach, policy updates, and monitoring program
Chatfield Watershed Authority
Page 3 of 4
o Manager will send out updated version of PowerPoint for TAC to review and provide input prior to next Board meeting February 26th, 2018
Technical Updates 1) Technical Member Updates (Members)
• CRMC Update from Bill Ruzzo: Currently no access from east to west side
o Closures: east side at Plum Creek area o West side only areas that are open include the dog off leash area and stables o Update on construction and procurement progress on-site and off-site o CRMC Reservoir Model is calibrated
Draft report due to CRMC mid-February 2018 Hydros to present at next Authority TAC March 6th, 2018 and TRIH
March 12th, 2018 o Monitoring
Contract with GEI for 2018 monitoring approved by CRMC Additional inflow monitoring at Plum Creek and South Platte River
Barbara Biggs will report back on model to TAC at next meeting • Other Member Updates: David Van Dellen noted on Saturday May 5th, 2018 Castle Rock has Spring Up the
Creek event 2) Manager’s Update
• Site Applications and Land Use Referrals: Received two new land use referrals and Manager will begin review
o Douglas County Mineral Extraction Plan Update o Douglas County Sterling Ranch LLC Preliminary Plan No. 3
Manager will invite Board members to attend the next TAC meeting March 6th, 2018
• Public Outreach Committee Meeting Update: Next meeting TBD
o Manager will follow-up with PEOs re: invite all Authority members to call into the next Public Outreach Committee meeting
PEOs preparing proposal for public outreach to bring to the Board TAC members David Van Dellen and Pat O’Connell will continue to attend Public
Outreach Committee meetings
3) Financial Recap • No comments
Reminders Next Scheduled TAC Meeting Tuesday, March 6th, 2018 2:00 – 4:00 p. m. Castle Rock Water, 175 Kellogg Court Castle Rock, CO 80109
Chatfield Watershed Authority
Page 4 of 4
Adjournment of Regular Meeting at 4:00 pm
Attachment – 2
TWS Financial Invoice - January 2018
InvoiceDate
2/13/2018
Invoice #
17229
Bill To
Chatfield Watershed Authority4255 N. US Highway 85Castle Rock, Co 80108
TWS FINANCIAL INC.
CERTIFIED PUBLIC ACCOUNTANTS7345 S. PIERCE ST. #205LITTLETON CO. 80128(303) 933-4207
P.O. No. Terms Project
Thank you for your business.Total
DescriptionQuantity Rate Amount
January 2018 Financial Statement Prep. 1,000.00 1,000.00
$1,000.00
Attachment – 3
Hughes & Stuart Invoice - (January – March) Marketing Services
DATE12/1/2017
INVOICE # 201465
ATTENTION:
Chatfield Watershed AuthorityAttention: Katie FendelLeonard Rice Engineers, Inc.1221 Auraria ParkwayDenver, CO 80204
7000 S. Yosemite Street, Ste 285Centennial, CO 80112Phone: 303.798.0601 Fax:303.798.1315www.HughesStuart.comP.O. NO.
TERMSNet 45 DUE DATE:1/15/2018
Thank You for Your Business!Please note balances over 45 days will be assessed a late fee of 18% Total
Balance DuePayments/Credits
DESCRIPTION AMOUNTQUANTITY RATEChatfield Watershed Authority Monthly Website Updates & Maintenance, January - March,2018 450.003 150.00Website Domain Security Monitoring 300.003 100.00
$750.00
$750.00$0.00
Attachment – 4
Leonard Rice Engineers Invoice - February 2018
Chatfield Watershed Authority Watershed Management Services Leonard Rice Engineers, Inc. Budget Status through February 25, 2018
Task Description Tasks Included 2018 Budget Previous Billed
Current Month* Total Billed % of
Budget
1 Board & TAC Management
Facilitate/participate at quarterly Board meetings, ten TAC meetings; prepare agendas and packet materials; prepare presentations for Board/TAC meetings; coordinate with other team consultants and other stakeholders; public outreach; complete assigned follow-up tasks
$58,140.00 $4,753.25 $5,165.50 $9,918.75 17%
2a Water Quality Data Management
Coordinate compilation of water quality data; provide monthly data assessments for Board/TAC meetings $4,719.00 $484.00 $484.00 $968.00 21%
2b
Site Application/ Land Use Referral Reviews
Review & comment on submitted site applications and land use referrals $12,885.00 $158.00 $790.00 $948.00 7%
2c Regulation 73 Tasks
Prepare Annual Report; Present report to Water Quality Control Commission; facilitate responses to Reg. 73-related requests; other tasks as assigned $7,031.00 $37.25 $1,027.00 $1,064.25 15%
2d Strategic Planning
Katie Fendel will take on a technical advisory role with a not to exceed 4 hours per month (billed). Katie will assist with strategic planning, technical input and facilitate discussions, as needed
$11,760.00 $980.00 $980.00 $1,960.00 17%
Total $94,535.00 $6,412.50 $8,446.50 $14,859.00 16% * Specific Tasks Included: • Preparation of agenda and packet materials for 2/26/2018 Board meeting, 2/6/2018 TAC meeting, and 3/6/2018 TAC meeting; • Attendance at 2/6/2018 TAC meeting and follow-up tasks from meeting; • Preparation of Triennial Review Informational Hearing (TRIH) materials for February TAC and Board meetings; • Completion of four land use referral projects, including review and submittal of comments and/or response letters; • Generation of graphs, charts, and figures for TAC, Board, and preparation of Control Regulation 73 Annual Report graphs; and • Project management tasks, including miscellaneous communications, requests from members for information, review of other consultants’ bills, and invoicing.
Attachment – 5
Regulation 73 TRIH Letter to WQCC
Attachment – 6
Site Applications
Last update: 2/23/2018AUTHORITY COMMENTS
From Proposed Project Engineer Submittal Type Type of Project Developer Owner Date ReceivedReview
Deadline (60-Days)
Comments Sent Comment/Response Tracking to Applicant and State
CHATFIELD WATERSHED AUTHORITYSTATUS OF SITE APPLICATION REVIEWS
LAND USE AGENCY INFORMATION
4 HDRPlum Creek Lift
Station (Shea Homes)
Jamie Eichenberger Site Application Lift Station
Centennial Water and Sanitation
District
Centennial Water and Sanitation
District
11/29/2017 1/28/2018 1/24/2018
On October 23, 2017, phone conversation with Jamie Eichenberger with HDR the Plum Creek LS and 10" Forcemain. At this time thdo not have an emergency plan included and will begin to draft plan in approx. 3 to 4 weeks. The Authority Manager sent an email on 10/26/2017 re-confirming the Authority will not review until a complete application is provided (i.e., emergency response plan). On November 29, 2017, received emergency response plan.
Response letter has been drafted and sent to TAC 1/9/2018. TAC approved.Response letter submitted to Division 1/24/2018.
5 Calibre Remuda Ranch Lift Station David Theisen Site Application Lift Station TBD TBD TBD TBD No application has been sent at this time. Pending application to start review.
6 HDR Swim Beach Lift Station Paul Perri Site Application Lift Station CRMC Colorado Parks
and Wildlife 10/13/2017 12/12/2017 12/11/2017
The Authority recommends Division approval of this site application, after consideration of the following comment. Although the Emergency Response Plan submitted by the Applicant does not include what the Authority typically requires in emergency response plans, we request that, as the Project is developed and implemented, additional emergency control measures as outlined in our ERP Criteria be included.
7 Kennedy/Jenks Consultants
Hunting Hill Filing 2 Wastewater Lift
StationGreg Sekera Site Application Lift Station
Richmond American Homes
Centennial Water and Sanitation
District
10/24/2017 12/23/2017 11/13/2017 The entire project occurs outside of the Chatfield Watershed; therefore, outside of the Authority's jurisdiction to review for compliance with Reg 73 and Emergency Response Plan Criteria.
8 Burns and McDonnell
Wastewater Utility Plan Update:
PCWRA WRF Capacity
Expansion
Brian Knadle Wastewater Utility Plan Update
WRF Capacity Expansion PCWRA PCWRA 11/14/2017 1/12/2018 1/11/2018
November 14, 2017 received from Burns and McDonnell a small packet re: Wastewater Utility Plan Update. In progress with review of material. Based on 1/9/2018 TAC meeting, Manager called Brian Knadle (1/11/2018) and left a voicemail stating the TAC does not plan to incorporate wastewater utility plan reviews into the updated policy for site applications; therefore, the Authority no longer will review these wastewater utility plans.
2/23/2018 Page 1
Attachment – 7
Land Use Referrals
Last update: 2/27/2018
Referral Agency
Proposed Development
Case Worker/Planner Email Submittal Type Type of Land
UseLUA
NumberDate
ReceivedReview
DeadlineSite Engineer or
Planner
Approx. Development Size
(acres)
Review Comments Sent Comments
AUTHORITY COMMENTSAPPLICANT INFORMATION
CHATFIELD WATERSHED AUTHORITYSTATUS OF LAND USE REFERRALS
LAND USE AGENCY INFORMATION
Douglas County
Mineral ExtractionPlan Update Joe Fowler jfowler@douglas.co.us MEP
Mineral Extraction Plan sub-element to Douglas County Comprehensive
Master Plan
DR2016-001 1/26/2018 3/2/2018 Douglas County N/A
Douglas County
Sterling Ranch Preliminary Plan
No. 3Brett Thomas bthomas@douglas.co.us Preliminary Plan residential SB2017-009 1/31/2018 2/21/2018 Douglas County 208 Yes
2/21/2018
Letter included comments on point source and non-point source for total phosphorus. The facility that will receive wastewater associated with the proposed planned development must have adequate design capacity to treat the additional wastewater, including adequate phosphorus treatment capacity to remain within its assigned wasteload and concentration limits. Dominion Water and Sanitation District demonstrated that it has adequate capacity to treat the wastewater that would be generated by the proposed preliminary plan as part of the Sterling Ranch Planned Development. The planned development includes stormwater drain systems, detention ponds, and open space areas. Regulation 73.6(2) states the Authority “members shall implement nonpoint source control programs for those areas within their jurisdictions”. The project will need to comply with the Douglas County’s non-point source control programs including stormwater. Based on the above, the Authority takes no exception to the proposed planned development, provided it complies with Control Regulation 73 as defined in above comments.
Douglas County
Proposed Amendments:
Douglas County Zoning Resolution
Jamie Hartig jhartig@douglas.co.us Zoning Resolution Referral Rezoning DR-2018-
001 2/1/2018 2/22/2018 Douglas County N/A Yes2/22/2018
No commentResolution is for proposed updates to Electric Message Signs (EMS) to Douglas County Zoning Resolution Section 29 - Sign Standards.
Douglas County
Lawrence Development Lot
3 RezoningDan Avery davery@douglas.co.us Rezoning Rezoning A1 to
GI ZR2018-003 2/6/2018 2/27/2018 Douglas County N/A Yes2/27/2018
Letter included comments on point source, including if septic tanks are needed, and non-point source for totaphosphorus. The Authority recently adopted the Commercial/Industrial Individual Sewage Disposal Systems Policy on November 20th, 2017. If the property requires a septic system which will generate 2,000 gallons per day (gpd) or more, the Authority requests the Applicant complies with the Commercial/Industrial Individual Sewage Disposal Systems Policy (this was attached to the response letter). Additionally, the Applicant would require submittal of a Colorado Discharge Permit System (CDPS) application if the Applicant needs a septic system greater than 2,000 gpd. Under Control Regulation 73, total phosphorus allocations are distributed among sources, including point sources (e.g., discharge permits). Therefore, if the Applicant requires a septic system greater than 2,000 gpd, a discharge permit is required and the point sourcedischarger shall show if phosphorus allocation are met. If total phosphorus allocation is in exceedance, the Division will not issue a discharge permit until phosphorus pounds are awarded from Reserve Pool, Trading Program, or by Temporary Transfers (Regulation 73.3(2)(a)). The Applicant stated “the current stormwater management plan will remain in effect to prevent all unlawful discharge into Plum Creek” on Lot 3. Regulation 73.6(2) states the Authority “members shall implement nonpoint source control programs for those areas within their jurisdictions”. The project will need to comply with the Douglas County’s non-point source control programs including stormwater. Based on the above, the Authority takes no exception to the proposed rezoning, provided it complies with Control Regulation 73 as defined in above comments
2/27/2018 Page 1
Attachment – 8
TWS Financial Recap January – December 2017
Attachment – 9
TWS Financial Recap January 2018