April 3, 2001 Washington, DC 2001 EMS Users Group

Preview:

Citation preview

April 3, 2001 Washington, DC

2001 EMS Users Group

Manley Higgins PEPCO

Project Manager

Mark BruenKEMA Consulting

Principal Consultant

PEPCO EMS Migration

EMS Migration

• Migration Philosophy

• Overview of EMS

• Migration Phases

• Related Enhancement Efforts

• Future Phases

• Long Range Plan & Update Process

• Challenges for the Future

EMS Migration

Migration Philosophy

Migration Philosophy

• In 1995, PEPCO Adopted a Long-Term EMS Migration Philosophy to Keep the EMS “Ever-green”.

Migration Philosophy

• Migration Rationale:

• Keep the system technologically current to meet the terms of the financial lease

• To protect the investment in the operational procedures, EMS software, system design, & database.

• To avoid obsolescence of hardware

Migration Philosophy

• Migration Rationale (cont.):

• To support increased performance and capacity requirements

• To allow for the addition and enhancement of system functions as business requirements change

• Enhance the EMS to accommodate the implementation of large-scale Distribution Automation and Substation Automation projects

Migration Philosophy

• Migration Rationale (cont.)

• And, to avoid the extreme and expensive effort of another EMS “forklift” replacement, including:• Procurement costs• System Testing• Cutover• Software Quality Control• Staff time commitment

EMS Migration

Overview of the PEPCO EMS

Overview of the Original PEPCO EMS

• EMS is “Consolidated Control System”• Designed to support Transmission,

Distribution, and Generation Operations • (Generation sold December

2000)

Overview of the Original PEPCO EMS

• Interfaces with other critical PEPCO and external systems including:• New Outage Management

System• Corporate Systems• PJM

Overview of the Original PEPCO EMS

• Procured from ABB Network Management (formerly NMTI)

• Delivered in 1993

• Initially commissioned in 1994

Overview of the Original PEPCO EMS

• Full featured EMS including:

• SCADA• Graphical User Interface (not

workstation based Full Graphics)• Distributed System w/ Proprietary

Hardware Front-ends• Full Advanced Applications Suite

• Real-time and Study• PEPCO Specific Applications

Overview of the Original PEPCO EMS

• Dispatcher Consoles• Transmission Dispatchers• Load Dispatchers• Transmission Shift Supervisors• Distribution Shift Supervisors

• System Support Consoles

• Development and Testing Facility• Dispatcher Training Simulator

EMS Migration

PEPCO Migration Phases

Migration Phases

• PEPCO established a multi-year migration program:• To fully migrate the EMS every

seven years.

• PEPCO’s management committed to to fund the effort to avoid the high costs of another procurement.

Migration Phases

• Migration Phase I – 1995 – 1996

• Open Systems Platform Enhancements including:

• Introduction of Dec Alpha Hardware Platform

• Operating System Upgrades• VAX VMX to UNIX• Intel RMX to UNIX

Migration Phases

• Migration Phase I (cont.)

• Conversion of Code to C• (from less common/difficult

languages – PLM, Assembly)• FORTRAN not converted

Migration Phases• Migration Phase II – 1997-1998

• ICCP for standards-based communications with:• PJM• PEPCO to BGE (planned

merger)• Ranger Data Acquisition Server

• Compaq Alpha hardware and Unix operating system

• Bow Software Protocol Emulations

Migration Phases• Migration Phase II – (cont.)

• Addition of PI Historian Data Repositories

• Upgraded DTS• Increased Database Sizing

• Via System Master Parameters

Migration Phases• Migration Phase III – 1999 – 2000

• Workstation Based Graphical User Interface

• ODBC Interface Into EMS• NT Based Historian• Study Mode State Estimator –

Uses Historian Data for Studies• DNP Protocol

Migration Phases• Migration Phase III (cont.)

• Event Storage and Retrieval

• Updated Software Tools to Improve Maintenance and Support Environment

Migration Phases

• Migration Phase IV – 2001-2002

(currently in progress)

• Increase DB Sizing (1.5 x current)• Naming size increases• DNP Protocol Converter (Rockwell

5020 to DNP)• Transfer Existing RTU to RDAS• Graphical Data Engineering Tool

• CIM Based

Migration Phases

• Migration Phase IV – (cont.)

• Facilities and Support Systems• Console Voice Equipment

(integrates PEPCO’s radio and telephone requirements)

• Upgrade/Life Extension for Critical Power (UPS) and HVAC

Migration Phases• More to Come?

• Phase V – Commercial Display Generation Software

• Phase VI – Upgrade EMS Application Processors, storage devices, printers, Bow-Tie Equipment, LAN I/F

• Phase VII – SCADA System• Phase VIII – Advanced Apps.

• These phases are currently under review

EMS Migration

Related EMS Enhancement Efforts

Related EMS Enhancement Efforts

• RTU Protocol Conversion for existing RTUs

• Outage Management System/EMS Interface – using ICCP

• Source Data Management System – to improve data management process

• System Security Enhancements

Related EMS Enhancement Efforts

• PEPCO Substation Automation Initiatives:

• Increased data from smart relays and Substation Automation systems (4 kV, 13 kV, 69 kV, 230 kV substations)

• VAR Dispatch – using feeder capacitors.

Related EMS Enhancement Efforts

• PEPCO Distribution Automation Initiatives:

• Feeder sectionalization using fault detectors and Motor Operated Disconnects

• 69 kV MODs• 13 kV MODs• Utilinet Spread Spectrum Radios

EMS Migration

Future Migration Phases

Future Migration Phases

• Migration of Advanced Applications to support:

• New Business Needs• New ISO Support Requirements• New Corporate Information Needs• Corporate Reorganizations and

Industry Restructuring

EMS Migration

Long-Range Plan & Update Process

Long-Range Plan and Update Process

• PEPCO is currently reviewing the Long-Range Migration Plan• Looking at current operational and

business needs• Investigating current technology• Assessing impacts of restructuring

• To properly align the next migration phases with the overall long-term direction

Long-Range Plan and Update Process

• Goal is to provide an updated 10 Year Forecast for planning purposes.

• Also to more clearly define the near-term needs and associated migration projects.

EMS Migration

Challenges for the Future

Challenges for the Future

• Distribution Operations Optimization• Fault detection and automated

feeder reconfiguration• Other distribution functions

• Additional Expansion of Distribution Functional and Data Requirements• Smart Relays, MODs, etc.

Challenges for the Future

• Integration with Corporate Systems

• Corporate-wide Data Availability• For Maintenance Monitoring

System• Enterprise Application Integration

(EAI) Environment

EMS Migration

Questions and Comments?

EMS Migration

Thank You!