CITY OF PROSSER, WASHINGTON
AGENDA BILL
Agenda Title:
Approve Change Order No. 1 for the Wastewater Treatment Plant Improvements Project and Authorize the Mayor to Sign the Documents
Item Type:
Consent Agenda
Meeting Date:
February 9, 2016
Regular City Council Meeting
Department:
Public Works
Director:
LJ DaCorsi
Contact Person:
LJ DaCorsi
Phone Number:
509-786-2332
Cost of Proposal:
$6,764,694.00 Original & Current Construction Contract Price ($9,231.00) Credit to the City $6,755,463.00 Adjusted Contract Price Due to Change Order No. 1
Amount Budgeted:
$6,764,694.00 Original & Current Construction Contract Price
Account Number:
Name and Fund#:
Reviewed by Finance Department:
Attachments to Agenda Packet Item:
1. Letter from HLA, Inc., describing conditions that generated Change Order No. 1 2. Change Order No. 1 - dated January 18, 2016 (2 pages) 3. C/O No. 1 Drawing
Summary Statement:
During construction of the Geopier foundation for the new digester structure, the Contractor found large cobbles and boulders in some test piers. This did not allow the pier auger to reach required depths below the subgrade elevation for the new structure. Alternative options to complete the subgrade improvements were discussed with the geotechnical engineer. It was decided to delete the remaining geopiers and construct the foundation by open excavation with engineered aggregate base. This alternate method is less expensive than the Geopier method and results in a change in the original and current contract price. A change in conditions that affect the contract price generates the requirement for a Change Order.
Consistent with or Comparison to:
Recommended City Council Action/Suggested Motion:
Approve Change Order No. 1 for the Wastewater Treatment Plant Improvements Project and authorize the Mayor to sign the documents.
Reviewed by Department Director:
LJ DaCorsi
Date: Feb 4, 2016
Reviewed by City Attorney:
Howard Saxton
Date: Feb 5, 2016
Approved by Mayor:
Date:
Approved By: Department: Status:
~+..+HLA • Engineering and Land Surveying, Inc.
January 28, 2016
City of Prosser 601 Seventh Street Prosser, WA 99350
Attn: L.J. DaCorsi Public Works Director
Re: City of Prosser 2015 WASTEWATER TREATMENT PLANT IMPROVEMENTS PWTF No.: PC12-951-068 HLA Project No.: 14084 Change Order No. 1
Dear L.J.:
f I r (} ' iJ t; '.
cnv OF;: HLlSC)fR
Attached, please find three copies of Change Order No. 1 for the above referenced project.
During construction of the Geopier foundation, the Contractor found large cobbles and boulders in some test piers which did not allow the pier auger to reach depths below the subgrade elevation of the new digester structure. After consulting with the geotechnical engineer about suitable options to complete the subgrade improvements, it was decided to delete the remaining geopiers and construct the foundation by open excavation with an engineered aggregate base. The Contractor has also requested additional contract time due to downtime related to evaluating excavation conditions and to complete the proposed change order work. This change order will result in a credit to the City of $9,231.00. However, the credit may need to be offset by engineering expenses incurred in the additional construction time.
When all three copies of the Change Order have been signed by the City of Prosser, please retain one copy for your records, and return the remaining two copies to us for distribution.
Should you have any questions regarding this summary or Change Order No. 1, please contact me at (509) 966-7000.
Very truly yours,
Steven C. Sziebert
SCS/crf
Enclosures
Copy: Correspondence File
G:\PROJECTS\2014114084C PR 2015 V\W TREATMENT PLANT - APOLLO. INCICHANGE ORDERS\CHANGE ORDER NO 112016-01-28 CITY CO No. 1 Ltr.docx
2803 River Road •!• Yakima, WA 98902 •!• 509.966.7000 •!• FAX 509.965.3800 •!• www.hlacivil.com
January 18, 2016
CHANGE ORDER NO. 1
OWNER: City of Prosser
PROJECT NAME:
PWTF PROJECT NO.:
2015 WASTEWATER TREATMENT PLANT IMPROVEMENTS
PC12-951-068
HLA PROJECT NO.: 13109C
CONTRACTOR: Apollo, Inc.
THE FOLLOWING CHANGES ARE HEREBY MADE TO THE CONTRACT DOCUMENT:
·- - ------Original Contract Price (Including State Sales Tax):
Current Contract Price Adjusted by Previous Change Order(s) (Including State Sales Tax) :
Change in Contract Price Due to This Change Order (Including State Sales):
·- -·~
Adjusted Contract Price Due to This Change Order (Including State Sales Tax):
Original Contract Completion Date:
Current Contract Completion Date Adjusted by Non-Working Days and/or Previous Change Order:
Change in Contract Completion Date Due to This Change Order:
Revised Contract Completion Date:
CONTRACTOR:
ENGINEER:
OWNER:
~~-~ ,fa~-611( 7
uJ:~ ~ Huibregts , Louman Associates, Inc.
City of Prosser
G \PROJECTS\2014\14084C PR 2015 WW TREATMENT PLANT · APOLLO, INC\CHANGE ORDERS\CHANGE ORDER NO '"(l16-01-1e CHANGE ORDER 1 xtsx
- · -·---$6, 764,694.00
$6, 764,694.00
($9,231.00)
$6, 755,463.00
August 17,2016
Augst 19, 2016 (Additional one and one half days)
Five (5) Additional Working Days
August 26, 20"17
Date:
ITEM
NO.
1-1
City of Prosser
2015 WASTEWATER TREATMENT PLANT IMPROVEMENTS
PWTF Project No.: PC12-951-068
HLA Project No. : 14084C
CHANGE ORDER NO. 1
UNIT
DESCRIPTION UNIT QTY PRICE
. Eliminate the Geopier method of constructing the subgrade of the Primary Digester. Replace
LS 1 ($8,500.00) with site excavation and engineered aggregate base, per attached drawing.
CHANGE ORDER NO. 1 SUBTOTAL
SALES TAX @ 8.6%
CHANGE ORDER NO. 1 TOTAL
January 18, 2016
AMOUNT
($8,500.00)
($8,500.00)
($731 .00)
($9,231 .00)
REASON: During construction of the Geopier foundation, the Contractor found large cobbles and boulders in some test piers which did not allow the pier auger to reach depths below the subgrade elevation of the new digester structure. After consulting with the geotechnical engineer about suitable options to complete the subgrade improvements, it was decided to delete the remaining geopiers and construct the foundation by open excavation with an engineered aggregate base. The Contractor has also requested additional contract time due to downtime related to evaluating excavation conditions and to complete the proposed change order work. This change order will result in a credit to the City of $9,231.00.
G \PROJECTS\201"4\14084C PR 2015 WN TREATMENT PLANT · APOLLO, INC\CHANGE ORDERS\CHANGE ORDER NO 1\2016-01-18 CHANGE ORDER 1 xtsx
I· · I ..... 825'
• pl •• i 11hr111hed l'CICll •nd qiary apal1 ID be cllunMd Ind 18118<1 by. 11JP..anb11Mi af llw eER
Nd/9 IU---(veiy dei!R gnMll/ cclllll• lllllD). Ulgmd• Clllldllon 11111 i. conttmed by• nipn119n!lllM afthe
BER priOt 10 Fl~ &y.llflY tpillt
..... 8111.D'
N.T.S.
Northern. Inc. Primary Digester - Bearing Support Zone lmprovementl Detail Prosser Was~ Treatment Plant lmprovrmen18
Prosser, Washington 5
Consultlng Engineers Envirorunental Scientists Geologists Constru.ction lv[aterials Testing Geophysic.al Services
Job No. 214-551 Dat.e
1/18/2016 DrawnBy
MYM Reviewed By
IM Drawing
1 Revision
0
Recommended