Connor Creek Bridge Design and construct emergency vehicle/pedestrian bridge across Connor Creek....

Preview:

Citation preview

Connor Creek Bridge

Design and construct emergency vehicle/pedestrian bridge across

Connor Creek. Parks Development

Southwest Production Team

Connor Creek BridgeInitial Concept

Connor Creek BridgePhoto taken at high

tide on 12/29/05

Connor Creek BridgeDesign Concept

Connor Creek BridgeMed-Tracker

Connor Creek BridgeAmphibious All-Terrain Vehicles

Max IV

Argo Bigfoot

Connor Creek Bridge

Land Tamer

Amphibious All-Terrain Vehicles

Connor Creek Bridge

Permitting Process $5,000.00

Topographical Survey (Consultant) $2,400.00

Site Planning & Review $8,000.00

Geotechnical & Engineering (Consultant) $25,329.47

Construction Supervision $4,000.00

Emergency Vehicle (Vender) $20,000.00

Construction (Contractor) $180,000.00

Administration $1,000.00

TOTAL PROJECT COST $245,729.47

Budget of $250,000.00

Connor Creek BridgeSchedule

FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Project Description

Connor Creek Bridge

Environmental Review & Permits

Design

Bid & Award

Construction

Color Code

Environmental Review & Permits

Design

Bid & Award

Construction

Connor Creek Bridge

Southwest Region Capital Team

The bridge will carry pedestrians and a small emergency vehicle, with a maximum gross vehicle weight of 6000 pounds. The bridge will use timber planks, a timber rail system, and pressure treated glue laminated beams to span between timber pile caps over driven galvanized steel pipe piles. The length of the bridge is approximately 250' long. There will be four spans of 50' and two removable beach side spans of 25' each.

Recommended