CUSTOMER DEPLOYMENT EXPERIENCE – NOKIA CABLE TAB
March 27, 2017
• 2014 – Rallying Cry to deliver Gigabit services and protect our backyard
• 10/2014 – Turned up first “G1GABLAST” service. With plan to build in greenfield forward and limited brownfield for strategic/competitive.
• 2015 – Biggest Challenges were in Operationalizing, Stabilizing, Standardizing and (Cabinet temp / cooling, Monitoring, Tshooting). Converged Edge for business services
• 2016 – Optimizing OLT deployment – Year of the R-OLT; 30k PON residential customers; 200k HHP FTTH
• 2017 – IPDR for LTOP; Outdoor ONT; “PON ready” fiber deep strategy with R-PHY N+0.
• 2018-19 – Drop the RFoG. IP Video; VoPON; 10G PON transition. We will likely move to 10G EPON.
WHEN AND WHAT
BROWNFIELD SFU ARCHITECTURE OVERVIEW
STB
ONT
Video & DOCSIS ServicesVia Traditional HFC Architecture
High Speed Data ServicesVia GPON Architecture
eMTA
• Video• Data• Phone
1Gbps Data
OLTActive Cabinet
ODNPassive Splitter Cabinet
Cross-ConnectEach Port is assigned to a specific address
4
CABINET BASED ARCHITECTURE – 2014 / 2015
MTC
ASR9K
ASR9K
ODNODN
ODN
ODN
ODN
ODN
ODN
ODN
ODN
ODN
ODNODNODNODNODNODN
OLT CABINET
5
NEW MICRO-OLT BASED ARCHITECTURE – 2016+
MTC
ASR9K
ASR9K
*OLM = Micro-OLT
ODNODN
ODN
ODN
ODN
ODN
ODN
ODN
ODN
ODN
ODNODNODNODNODNODN
Design Guidelines• Up to (8) R-OLT per
Ring• Up to 512 HP per R-
OLT• Up to 4096 HP per
Ring
Distance Guidelines• 40km BIDI Optics
(Standard)• 60km BIDI Optics
(Optional)• 10km Maximum
R-OLT to ONT
R-OLT-2R-OLT-1
R-OLT-3
R-OLT-4
R-OLT-5R-OLT-6
R-OLT-7R-OLT-8
• PON technology (2.5; 10). What provisioning methodologies would these lead to. Could DOCSIS back end be leveraged?
• Provisioning Methodology • Sigma Middleware, Push vs. Pull flow through.
• DPoX, Netconf Yang
• Serving overlay or Gfield alone? • RFOG
• Lower tier speeds over PON / Include Product parity with DOCSIS based services (i.e. bitcounting/CALEA).
• L3/L2 OLT
• Ringed Access for Cabinet OLT? Aggregation?
• OLT deployment model ; STC Facilities based, Cabinet Based; Strand Based or R-OLT
• Split Ratios
• Indoor/Outdoor ONT?
• Integrated Gateway vs. Stand Alone ONT
• How would we serve Business? MetroE, Backhaul, etc.
DESIGN CRITERIA TO PON-DER
OPERATIONAL LESSONS LEARNED
• Division of Labor… and RACIs are kind of a big deal. And FTTH challenges many existing models.
• Installation time 2-3 hrs per drop;
• Don’t get stuck on speed tests with customer.
• Mechanical engineering is critical component for reliability and success. Air flow matters, Cox and Nokia learned a lot. Dynamic temp range
OPERATIONAL LESSONS LEARNED – DIVISION OF LABOR / RACI
COX CONFIDENTIAL INFORMATION (FOR INTERNAL USE ONLY)
Q & A FOR COX TEAM
COX CONFIDENTIAL INFORMATION (FOR INTERNAL USE ONLY)
Key Take Aways:- R-Olt is the way to go and Critically important for Ftth in Cable Access- Converged Svc over PON will make FTTH a difficult business decision vs. DOCSIS - If your building fiber in greenfield… then that is the network you really want.
- so, let’s figure out how to do it well.- Division of Labor is critical in FTTH
Recommended