Energy and Mineral Resources for Peolple’s Prosperity
DIRECTORATE GENERAL OF NEW, RENEWABLE ENERGY AND ENERGY CONSERVATION
MINISTRY OF ENERGY AND MINERAL RESOURCES
by :
Tisnaldi
Director of Geothermal
Presented at :
“The APEC Conference on Clean, Renewable and Sustainable Use of Energy”
Bali, October 1st 2013
Energy and Mineral Resources for Peolple’s Prosperity
Republic of Indonesia
Republik Indonesia
Flag National emblem
Motto: "Bhinneka Tunggal Ika" (Old Javanese)
"Unity in Diversity"
National ideology: Pancasila
Anthem: Indonesia Raya
Capital
and largest city
Jakarta
6°10.5′S 106°49.7′E
Official languages Indonesian
Area
- Land 1,904,569 km2 (15th)
735,358 sq mi
- Water (%) 4.85
Population
- 2011 census 237,424,363 (4th)
- Density 124.66/km2 (84th)
322.87/sq mi
GDP (nominal)
- Total $946.391 billion (16th)
- Per capita $3,816(105th)
INDONESIAN ARCHIPELAGO
Source : Wikipedia (2013)
Energy and Mineral Resources for Peolple’s Prosperity Energy and Mineral Resources for Peolple’s Prosperity
2011
Oil20 %
Gas30 %
Coal 33 %
NRE17 %
NEP : Gov. Reg. NO. 5/2006
Note:
NRE = New and Renewable Energy
NEP = National Energy Policy
Oil49,7 %
Gas 20,1 %
Coal 24,5 %
NRE5,7 %
2025
CURRENT ENERGY CONDITION
BACKGROUND
Energy and Mineral Resources for Peolple’s Prosperity
Source : Geological Survey, MEMR(2011)
Installed
Ready to develop
Preliminary survey
Early preliminary survey
Note:
Detailed survey
1 Sumatera 90 12,778 122
2 Java 71 9,717 1,134
3 Bali & Nusa Tenggara 28 1,805 5
4 Kalimantan 12 145
5 Sulawesi 65 3,044 80
6 Maluku 30 1,071
7 Papua 3 75
1,34128,635
Installed
Capacity
(MW)
Potential (MW)
Total 299
No. Island Number of Location
PLTP SIBAYAK: 12 MW
PLTP ULUBELU: 110MW
PLTP LAHENDONG: 80 MW
PLTP ULUMBU: 5 MW
PLTP DIENG: 60 MW PLTP DARAJAT: 270 MW
PLTP KAMOJANG: 200 MW
PLTP WAYANG WINDU: 227 MW PLTP GUNUNG SALAK: 377 MW
GEOTHERMAL POTENTIAL
Energy and Mineral Resources for Peolple’s Prosperity
5
ACEH 2 WKP
Jaboi: 70 MW
Seulawah Agam: 130 MW
NORTH SUMATERA 5 WKP
Sibayak – Sinabung: 130 MW
Sibual – Buali: 750 MW
Sipaholon Ria-ria: 75 MW
Sorik Marapi: 200 MW
Simbolon Samosir : 155 MW
JAMBI 1 WKP
Sungai Penuh: 70 MW
SOUTH SUMATERA 2 WKP
Lumut Balai: 250 MW
Rantau Dedap: 106 MW
BANTEN 2 WKP
Kaldera Danau Banten: 115 MW
G. Endut: 80 MW
WEST SUMATERA 4 WKP
Bukit Kili: 83 MW
Gn Talang: 35 MW
Liki Pinangawan: 400 MW
Bonjol: 200 MW
LAMPUNG 4 WKP
Gn.Rajabasa: 91 MW
Suoh Sekincau: 230 MW
Waypanas – Ulubelu: 556 MW
Way Ratai :105 MW
WEST JAVA 10 WKP
Ciater - Tgkban Perahu: 60 MW
Cibeureum–Parabakti: 485 MW
Cibuni: 140 MW
Cisolok Cisukarame: 45 MW
Gn. Tampomas: 50 MW
Gn. Tgkuban Perahu: 100 MW
Kamojang-Darajat: 1465 MW
Karaha Cakrabuana: 725 MW
Pangalengan: 1106 MW
G. Ciremai: 150 MW
CENTRAL JAVA 5 WKP
Baturaden: 175 MW
Dataran Tinggi Dieng: 780 MW
Guci: 79 MW
Gn. Ungaran: 100 MW
Umbul Telomoyo : 72 MW EAST JAVA 3 WKP
Blawan – Ijen: 270 MW
Gn. Iyang Argopuro: 295 MW
Telaga Ngebel: 120 MW
BALI 1 WKP
Tabanan: 276 MW
WEST NUSA
TENGGARA 2 WKP
Hu'u Daha: 65 MW
Sembalun : 100 MW
EAST NUSA TENGGARA 5 WKP
Atadei: 40 MW
Sokoria: 30 MW
Ulumbu: 199 MW
Mataloko: 63 MW
Oka Ile Ange : 40 MW
MALUKU 1 WKP
Tulehu: 100 MW
NORTH MALUKU 2 WKP
Jailolo: 75 MW
Songa Wayaua: 140 MW
NORTH SULAWESI 2 WKP
Kotamobagu: 410 MW
Lahendong-Tompaso: 358 MW
GORONTALO 1 WKP
Suwawa: 110 MW
CENTRAL SULAWESI 2 WKP
Marana: 35 MW
Bora Pulu : 152 MW
Total : 58 GWA
BENGKULU 2 WKP
Tmbg Sawah-Hululais: 873 MW
Kepahiyang : 180 MW
CENTRAL JAVA & EAST JAVA 1 WKP
Gunung Lawu : 195 MW
SOUTH SUMATERA & LAMPUNG 1 WKP
Danau Ranau: 210 MW
DISTRIBUTION OF GEOTHERMAL WORKING AREAS
Lisence – Issued : 38 GWAs
Tender on Progress : 2 GWAs
Tender Preparation : 13 GWAs
Tender – Failed : 5 GWAs
Energy and Mineral Resources for Peolple’s Prosperity
GEOTHERMAL BUSINESS STAGES
Energy and Mineral Resources for Peolple’s Prosperity
Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi Energi
Kementerian Energi dan Sumber Daya Mineral
• Law No. 27/2003 On Geothermal.
• Government Regulation No. 59/2007 on Geothermal Bussiness Activities.
• Presidential Regulation No. 04/2010 on Assignment to PT. PLN (Persero) to Accelerate The Development of Power Plant from Renewable Energy, Coal and Gas
• Ministry Regulation of Minister of Energy And Mineral Resources 1). MR No. 11/2008 on the Procedure for GWA Determination
2). MR No. 02/2009 on Guidelines for Geothermal Preliminary Survey Assignment (as amendment of MR. 05/2007)
3). MR No. 11/2009 on Guidelines for Implementation of Geothermal Business , jo. MR No. 18/2012
4). MR No. 21/2013 on Revision of MR No. 15/2010 on The List of Power Plant Acceleration Projects Using Renewable Energy, Coal, and Gas and Related
Transmission
LEGAL FRAMEWORK
Energy and Mineral Resources for Peolple’s Prosperity
1. Improving and harmonizing regulations in Geothermal Business;
2. Developing a comprehensive pricing structure;
3. Provide fiscal incentives for geothermal development;
4. MoU between Ministry of Energy and Mineral Resorces and Ministry of Forest;
5. Acceleration program in electricity generation; geothermal power is
expected to contributed 4,965 MW;
GEOTHERMAL POLICIES
Energy and Mineral Resources for Peolple’s Prosperity
Direktorat Jenderal Energi Baru, Terbarukan dan Konservasi Energi
Kementerian Energi dan Sumber Daya Mineral
GEOTHERMAL
DEVELOPMENT
INSTAL
LED
CAPACI
TY
(MW)
DEVELOPMENT (MW)
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
ADDED CAPACITY
(MW) 1226 115 5 58 135 715 1765 425 507 935 247 130 175 40 160
TOTAL
INSTALLED CAPACITY
(MW) 1226 1341 1346 1404 1539 2254 4019 4444 4951 5886 6133 6263 6438 6478 6638
Energy and Mineral Resources for Peolple’s Prosperity
Access to Potential Geothermal Resources for Investors:
• Preliminary Survey Assignment;
• Participate in the geothermal business through GWAs tendering mechanism.
Investment Opportunities:
3 new GWAs with total potential of 545 MW are going to be tendered in the near future:
Umbul Telomoyo : 120 MW
Danau Ranau : 210 MW
Gunung Lawu : 195 MW
Afterwards Government will tender another 10 GWAs
Currently 13 Preliminary Survey Assignment are carried out by Private Parties
7
INVESTMENT OPPORTUNITIES
Energy and Mineral Resources for Peolple’s Prosperity
Indonesia holds tremendous geothermal power potential;
Installed capacity of geothermal power plant is only1,341 MW;
Optimum utilization will significantly reduce dependence on fossil fuel and improve
national energy security;
Restructuring Geothermal Business to allow private participation in geothermal
development;
Whilst some supporting policies are in place, acceleration of geothermal
development in Indonesia needs international support in terms of finance,
technology, human resources as well as technical assistance.
7
CONCLUSION
Energy and Mineral Resources for Peolple’s Prosperity www.ebtke.esdm.go.id www.esdm.go.id