Document of The World...

Preview:

Citation preview

Document of 

The World Bank 

FOR OFFICIAL USE ONLY  

 Report No: ICR00004177 

  

 

IMPLEMENTATION COMPLETION AND RESULTS REPORT 

(IDA 58180, 52420, 43500)  

ON A 

CREDIT  

IN THE AMOUNT OF SDR 45.4 MILLION 

(US$ 68.1 MILLION EQUIVALENT) 

TO THE 

PEOPLE’S REPUBLIC OF BANGLADESH  

FOR A 

PUBLIC PROCUREMENT REFORM PROJECT II ( P098146 )  

December 19, 2017  

 

 

 

 

 

Governance Global Practice 

South Asia Region 

    

This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. 

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

 CURRENCY EQUIVALENTS  

 

(Exchange Rate Effective November 20, 16, 2017) 

 

Currency Unit =  =  Bangladesh Taka (BDT) BDT 78  =  US$1 

US$1.50  =  SDR 1  

 FISCAL YEAR 

July 1 ‐ June 30   

ABBREVIATIONS AND ACRONYMS 

AF  Additional Financing AF II BCCP 

Additional Financing II Bangladesh Center for Communication Programs 

BIM  Bangladesh Institute of Management BIGD  BRAC University Institute of Governance and Development BREB  Bangladesh Rural Electrification Board BWDB  Bangladesh Water Development Board CAS  Country Assistance Strategy CIPS CPF 

Chartered Institute of Procurement and Supply/ U.K. Country Partnership Framework 

CPI CPTU 

Corruption Perception Index Central Procurement Technical Unit 

CSM DLI 

Civil Society Members Disbursement‐Linked Indicator 

e‐GP  Electronic‐Government Procurement e‐PMIS  Electronic‐Procurement Management Information System ECoP  Environmental Code of Practice ESCB  Engineering Staff College Bangladesh FI FM 

Financial Institutions Financial Management 

GCF  Government Contractors Forum GOB  Government of Bangladesh HQ  Headquarters ICR  Implementation Completion and Results Report ICT  Information and Communication Technology IMED  Implementation, Monitoring, and Evaluation Division ISM  Implementation Support Mission ISR  Implementation Status and Results Report LGED  Local Government Engineering Department M&E  Monitoring and Evaluation MCIPS  Member of The Charted Institute of Procurement and Supply MIS  Management Information System 

NCB  National Competitive Bidding NSAPR  National Strategy for Accelerated Poverty Reduction PAD  Project Appraisal Document PDO  Project Development Objective PE PPA 

Procuring Entity Public Procurement Act  

PPR  Public Procurement Rules/Regulation PPRP  Public Procurement Reform Project PPRPII  Public Procurement Reform Project II PPSC  Public‐Private Stakeholders Committee PROMIS  Procurement Management Information System RHD  Roads and Highways Department SRGB  Survey Research Group Bangladesh 

              

 

Regional Vice President: Annette Dixon 

Country Director: Qimiao Fan 

Senior Global Practice Director: Deborah L. Wetzel 

Practice Manager: Felipe Goya 

Task Team Leader(s): Zafrul Islam 

ICR Main Contributor: Paul J. Kaiser  

  

TABLE OF CONTENTS  

DATA SHEET ............................................................................................................................ 1 

I.  PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES ........................................................ 6 

A. CONTEXT AT APPRAISAL ........................................................................................................... 6 

B. SIGNIFICANT CHANGES DURING IMPLEMENTATION ................................................................. 9 

II.  OUTCOME ...................................................................................................................... 12 

A. RELEVANCE OF PDOs .............................................................................................................. 12 

B. ACHIEVEMENT OF PDOs (EFFICACY) ........................................................................................ 13 

C. EFFICIENCY ............................................................................................................................. 19 

D. JUSTIFICATION OF OVERALL OUTCOME RATING ..................................................................... 20 

E. OTHER OUTCOMES AND IMPACTS .......................................................................................... 20 

III.  KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME ................................ 21 

A. KEY FACTORS DURING PREPARATION..................................................................................... 21 

B. KEY FACTORS DURING IMPLEMENTATION .............................................................................. 22 

IV.  BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME .. 23 

A. QUALITY OF MONITORING AND EVALUATION (M&E) ............................................................. 23 

B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE ..................................................... 25 

C. BANK PERFORMANCE ............................................................................................................. 26 

Bank Performance Rating: Satisfactory ....................................................................................... 28 

D. RISK TO DEVELOPMENT OUTCOME ........................................................................................ 28 

V.  LESSONS AND RECOMMENDATIONS .............................................................................. 28 

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS ............................................................ 33 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION ......................... 42 

ANNEX 3. PROJECT COST BY COMPONENT............................................................................. 44 

ANNEX 4. EFFICIENCY ANALYSIS ............................................................................................ 45 

ANNEX 5. DISBURSEMENT LINKED INDICATORS..................................................................... 47 

ANNEX 6. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS ... 50 

ANNEX 7. SUPPORTING DOCUMENTS .................................................................................... 52 

   

The World Bank Public Procurement Reform Project II ( P098146 )

Page 1 of 52

        

DATA SHEET 

  

BASIC INFORMATION  Product Information 

Project ID  Project Name 

P098146  PUBLIC PROCUREMENT REFORM PROJECT II ( P098146 ) 

Country  Financing Instrument 

Bangladesh  Technical Assistance Loan 

Original EA Category  Revised EA Category 

Not Required (C)  Not Required (C) 

Related Projects            

Relationship  Project  Approval  Product Line 

Additional Financing  P132743‐Additional Finaning of Public Procurement Reform Project II 

09‐May‐2013  IBRD/IDA 

Additional Financing  P158783‐Second Additional Financing to Public Procurement Reform Project II 

06‐Jun‐2016  IBRD/IDA 

Organizations 

Borrower  Implementing Agency 

People's Republic of Bangladesh, Economic Relations 

Division (ERD) 

Implementation Monitoring and Evaluation Division 

(IMED), Central Procurement Technical Unit (CPTU) 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 2 of 52

Project Development Objective (PDO)  Original PDO 

The Project Development Objective (PDO) is to improve performance of the public procurement system progressively in Bangladesh, focusing largely on the target agencies.  The PDO would be achieved by strengthening the ongoing reform process and moving it further along with the following outputs: (i) enhanced capacity in creating a sustained program to develop skilled procurement professionals, (ii) strengthened management and monitoring of procurement in target agencies, (iii) introduction of e‐government procurement in CPTU and the target agencies on a pilot basis, and (iv) creation of greater public awareness of a well functioning public procurement system by engaging civil society, think tanks, beneficiaries, and the private sector.  All these actions are key elements in effective implementation of the procurement law/ regulations.   

FINANCING 

 

  Original Amount (US$)   Revised Amount (US$)  Actual Disbursed (US$) 

World Bank Financing        IDA‐43500 

23,600,000  23,600,000  24,041,237 

 IDA‐52420 

34,500,000  34,500,000  32,446,437 

 IDA‐58180 

10,000,000  10,000,000  9,638,638 

Total    68,100,000  68,100,000  66,126,312 

Non‐World Bank Financing       

Borrower  1,300,000  4,800,000  3,610,000 

Total  1,300,000  4,800,000  3,610,000 

Total Project Cost  69,400,000  72,900,000  69,736,312  

  KEY DATES 

   

Approval  Effectiveness  MTR Review  Original Closing  Actual Closing 

05‐Jul‐2007  12‐Sep‐2007  09‐Dec‐2010  31‐Mar‐2013  30‐Jun‐2017 

  

The World Bank Public Procurement Reform Project II ( P098146 )

Page 3 of 52

 RESTRUCTURING AND/OR ADDITIONAL FINANCING 

 

 

Date(s)  Amount Disbursed (US$M)  Key Revisions 

09‐May‐2013  23.62  Additional Financing 

29‐Sep‐2015  39.94  Change in Disbursements Arrangements Other Change(s) 

06‐Jun‐2016  45.26  Additional Financing 

  

KEY RATINGS  

 

Outcome  Bank Performance  M&E Quality 

Satisfactory  Satisfactory  Substantial 

 

RATINGS OF PROJECT PERFORMANCE IN ISRs  

 

No.  Date ISR Archived  DO Rating  IP Rating Actual 

Disbursements (US$M) 

01  28‐Mar‐2008 Moderately 

Unsatisfactory Moderately Unsatisfactory  0 

02  30‐Sep‐2008  Moderately Satisfactory  Moderately Satisfactory  1.67 

03  26‐Mar‐2009  Moderately Satisfactory  Moderately Satisfactory  2.11 

04  01‐Oct‐2009  Moderately Satisfactory  Moderately Satisfactory  3.46 

05  23‐Dec‐2009  Moderately Satisfactory  Satisfactory  3.69 

06  14‐Jun‐2010  Moderately Satisfactory  Moderately Satisfactory  4.73 

07  30‐Apr‐2011  Satisfactory  Satisfactory  8.43 

08  20‐Aug‐2011  Satisfactory  Satisfactory  9.61 

09  07‐Jan‐2012  Satisfactory  Satisfactory  10.51 

10  07‐Jul‐2012  Satisfactory  Satisfactory  12.49 

11  18‐Jun‐2013  Satisfactory  Satisfactory  15.22 

12  29‐Dec‐2013  Satisfactory  Satisfactory  18.10 

13  27‐Jun‐2014  Moderately Satisfactory  Moderately Satisfactory  19.66 

14  22‐Dec‐2014  Moderately Satisfactory  Moderately Satisfactory  22.10 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 4 of 52

15  22‐Jun‐2015  Satisfactory  Satisfactory  23.36 

16  01‐Feb‐2016  Satisfactory  Satisfactory  26.77 

17  06‐Jul‐2016  Satisfactory  Satisfactory  31.77 

18  30‐Dec‐2016  Satisfactory  Satisfactory  39.63 

 

SECTORS AND THEMES  

 Sectors 

Major Sector/Sector  (%) 

 

Public Administration  100 

Central Government (Central Agencies)  80 

Sub‐National Government  10 

  

Information and Communications Technologies  100 

Other Information and Communications Technologies  5 

  

Social Protection  100 

Social Protection  5 

  Themes   

Major Theme/ Theme (Level 2)/ Theme (Level 3)  (%)  Private Sector Development  10  

Public Private Partnerships  10  

   Public Sector Management  87  

Public Finance Management  15  

Public Expenditure Management  15    

Public Administration  72  

Administrative and Civil Service Reform  14   

Transparency, Accountability and Good Governance 

58  

   

The World Bank Public Procurement Reform Project II ( P098146 )

Page 5 of 52

Social Development and Protection  14  

Social Inclusion  14  

Participation and Civic Engagement  14  

   

ADM STAFF  

Role  At Approval  At ICR 

Regional Vice President:  Annette Dixon  Annette Dixon 

Country Director:  Johannes C.M. Zutt  Qimiao Fan 

Senior Global Practice Director:  Deborah L. Wetzel  Deborah L. Wetzel 

Practice Manager:  Felipe Goya  Felipe Goya 

Task Team Leader(s):  Zafrul Islam  Zafrul Islam 

ICR Contributing Author:    Paul J. Kaiser 

         

The World Bank Public Procurement Reform Project II ( P098146 )

Page 6 of 52

 

I. PROJECT CONTEXT AND DEVELOPMENT OBJECTIVES 

A. CONTEXT AT APPRAISAL 

Context 

1. At the time of appraisal of the Public Procurement Reform Project II (PPRPII) in 2007, Bangladesh was one of the least developed countries in the world, with 40 percent of the population living below the national  poverty  line.1  Despite  considerable  progress  in  reducing  poverty  since  the  country  became independent  in  1971,  inefficient  and  ineffective  governance  practices  prevented  Bangladesh  from achieving its full economic potential and accelerating the pace of poverty reduction. Inefficiencies in public procurement practices, poor  financial management  (FM), and corrupt practices were  identified as key challenges that undermined good governance in the country. Vested interests in maintaining the status quo were strong, and there was initial reluctance by the political leadership to address these issues. 

2. The World Bank 2002 Country Procurement Assessment Report, which was broadly endorsed by the Government of Bangladesh  (GOB),  identified  several deficiencies  in public procurement practices. They included the absence of a sound legal framework governing public sector procurement, protracted bureaucratic  procedures,  a  lack  of  professionals  to manage  public  procurement,  and  the  absence  of transparency  and  accountability  mechanisms.  With  World  Bank  support  through  a  credit  Public Procurement Reform Project (PPRP), the GOB began addressing these issues in 2002 by establishing the Central  Procurement  Technical Unit  (CPTU),  issuing new public  procurement  regulations  in  2003,  and enacting a Public Procurement Law in 2006 based on international best practices. Despite these initial accomplishments,  there was  limited progress  in  achieving  improved procurement outcomes. Ongoing challenges  included  inconsistent  implementation  of  procurement  regulations  across  government agencies, substantial delays in the issuance of contracts, and inappropriate bidding practices. 

3. The World Bank’s 2006 Country Assistance Strategy (CAS), which was aligned with the GOB’s 2005 National  Strategy  for  Accelerated  Poverty  Reduction  (NSAPR),  identified  governance  as  the  major constraint preventing Bangladesh from improving its investment climate and empowering the poor. The NSAPR  specifically  highlighted  the  need  for  enhancing  the  efficient  use  of  resources,  promoting transparency and accountability in resource use, and tackling corruption. PPRPII was designed to address these  issues,  specifically  focusing  on  strengthening  the  public  procurement  system  at  the  key  sector ministries/agencies, a key element of good governance. 

Theory of Change (Results Chain) 

4. The four clusters of activities and outputs in figure 1 correspond to the four project components described in the original PPRPII, Additional Financing (AF), and AF II Project Appraisal Documents (PADs), including the intermediate results/outcomes presented in the Results Frameworks and Monitoring Plans. The project focuses mainly on the four target agencies of the key ministries that spend about 50 percent of  the  annual  development  program  of  the  GOB:  Roads  and  Highways  Department  (RHD),  Local Government  Engineering  Department  (LGED),  Bangladesh  Water  Development  Board  (BWDB),  and 

1 See: https://data.worldbank.org/indicator/SI.POV.NAHC?locations=BD. 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 7 of 52

Bangladesh  Rural  Electrification  Board  (BREB).  The  theory  of  change  in  the  original  and  subsequent projects  identified  the  following  assumptions  for  project  success:  (a)  capacity  of  the  CPTU,  the implementing  agency,  to  implement  this  operationally  complex  and politically  challenging project;  (b) sufficient Internet connectivity across the country to ensure fair and equal access by bidders/contractors to  electronic‐government  Procurement  (e‐GP);  and  (c)  political will  of GOB  leadership  to  support  the public procurement reforms required for improving the use of public resources with greater efficiency, transparency, and accountability.  

5. During  implementation,  the  CPTU  continually  enhanced  its  operational  capacity,  the  GOB effectively rolled out Internet connectivity across the country, and the highest levels of GOB leadership supported the reform agenda associated with PPRPII after initial reluctance. This was the evolving context for the theory of change described in Figure 1.  

Figure 1. PPRPII Theory of Change/Results Chain at Appraisal 

Note: BIM = Bangladesh Institute of Management; CIPS = Chartered Institute of Procurement and Supply; ESCB = Engineering Staff College Bangladesh; GCF = Government Contractors’ Firm; PDO = Project Development Objective; PROMIS = Procurement Management Information System. 

Project Development Objectives (PDOs) 

6. The original PDO, as  stated  in  the Legal Agreement, was “to strengthen  the Recipient’s public procurement system, with a particular focus on improving the performance of Target Agencies, through 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 8 of 52

(a) enhancing capacity by creating a sustained program to develop skilled procurement professionals; (b) strengthening  management  and  monitoring  of  the  procurement  process;  (c)  introducing  electronic government  procurement;  and  (d)  creating  greater  public  awareness  of  a  well‐functioning  public procurement  system  through  mobilization  of  civil  society,  think  tanks,  beneficiaries,  and  the  private sector.  All  these  actions  are  key  elements  in  effective  implementation  of  the  procurement law/regulations.” The PDO, as  stated  in  the PAD, was much shorter and  included  the  first part of  the original PDO in the Legal Agreement, that is, “to improve performance of the public procurement system progressively  in  Bangladesh,  focusing  largely  on  the  key  sectoral  ministries  and  targeting  their implementing agencies.” 

Key Expected Outcomes and Outcome Indicators 

7. There were three expected outcomes, based on the original PDO (see Components 1–4 below derived from the PDO) and reflected in the original PDO indicators: (a) about 60 percent contracts in at least three target agencies reduce delays by making contract awards within the initial bid validity period, (b)  e‐GP  introduced  in  at  least  two  target  agencies  at  the  headquarter  (HQ)  level  for  international procurement, and (c) increased stakeholder engagement in following procurement issues in at least two target agencies. The project  identified four agencies of the key sectoral ministries as  ‘target agencies’: RHD; LGED; BREB; and the BWDB. The CPTU, housed  in  the Ministry of Planning and under the direct authority  of  the  Implementation, Monitoring,  and  Evaluation  Division  (IMED),  was  designated  as  the primary implementing agency. 

Components 

8. The  project  comprised  four  interrelated  components  that  are  summarized  below,  including resource allocations and actual costs. Also, project financing is provided in Figure 2. 

(a) Component 1: Furthering Policy Reform and Institutionalizing Capacity Development (Total estimated cost: US$21.4 million; Actual cost: US$21.4 million) 

Support  the  public  procurement  reform  legal  framework  based  on  the  2003 Public Procurement Regulations and the 2006 Public Procurement Act (PPA)  

Enhance  the  capacity  development  program  that  provides  core  procurement skills required to institutionalize procurement capacity 

(b) Component 2: Strengthening Procurement Management at Sectoral Level and CPTU/IMED (Total estimated cost: US$15.9 million; Actual cost: US$10.35 million)  

Strengthen  the  four  key  sectoral  target  agencies,  along  with  20  additional agencies  in  seven  different  ministries  (added  in  the  AF),2  for  improved management and monitoring of procurement 

2 The seven ministries/divisions were Ministry of Education, Power Division, Ministry of Primary and Mass Education, Energy and Mineral Resources Divisions, Ministry of Health and Family Welfare, Local Government Division, and the Ministry of Housing and Public Works. 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 9 of 52

(c) Component 3: Introducing e‐Government Procurement (e‐GP) (Total estimated cost: US$30.2 million; Actual cost: US$33.1 million)  

Pilot  e‐GP  on  a  phased  approach  in  the  targeted  agencies  to  increase procurement  transparency and  lower  transaction  costs  and build  the physical capacity of the e‐GP system to sustain a countrywide rollout (added  in the AF and AF II)  

(d) Component 4: Communication, Behavioral Change, and Social Accountability (Total estimated cost: US$5.4 million; Actual cost: US$4.87 million)  

Create greater public awareness of the public procurement system and e‐GP by engaging civil society, think tanks, beneficiaries, and the private sector with the expectation of initiating a long‐term process of procurement monitoring. 

 Figure 2: Project Financing (US$ Million) 

 B. SIGNIFICANT CHANGES DURING IMPLEMENTATION 

Revised PDOs and Outcome Targets  

9. Original PDO revisions. The original PDO was clarified in 2013, but the intent of the original PDO remained  unchanged.  The  AF  PDO was  to  “improve  performance  of  the  public  procurement  system progressively  in Bangladesh,  largely  focusing on  the Target Agencies.” This adjusted PDO was shorter, similar to the original PAD, and focused to reinforce the project ‘s four target agencies (RHD, LGED, BREB, and  BWDB)  while  expanding  the  scope  to  provide  capacity  development  assistance  to  20  additional agencies  in  several  sectors,  including  health,  education,  power,  and  public  works.  The more  detailed content of the longer PDO at appraisal was further refined in the AF and AF II as project components and intermediate results  in  the Results Frameworks and Monitoring Plans but not formally  included  in the PDOs in the AF and AF II Legal Agreements. 

10. Outcome revisions. In the AF, PDO indicator targets (related to the reduction in delays in making contract  awards,  the  rollout  of  e‐GP,  and  expanded  capacity  development) were  scaled  up  to  reflect expanded scope, additional  funds, and  the extended closing date. Two new  indicators were added  to reflect assistance  to  the 20 additional agencies and  the publication of quarterly  reports by  the  target 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 10 of 52

agencies for monitoring of procurement performance. In AF II in 2016, AF PDO targets were again scaled up to reflect expanded scope, additional funds, and the extended closing date, and a new indicator related to the rollout of e‐GP was added. 

Revised PDO Indicators 

11. PDO  indicators were  revised  and  added  to  reflect  the  expanded  scope,  additional  funds,  and extended closing dates of the AF and AF II. Table 1 summarizes the PDO revisions in the AF and AF II. 

Table 1. Revised PDO Indicators 

Original  Additional Finance  Additional Finance II  Comments 

About 60% contracts in at least 3 target agencies reduce delays by making contract awards within the initial bid validity period 

About 80% contracts awarded within the initial bid validity period by the 4 target agencies 

About 82% contracts awarded within the initial bid validity period by the 4 target agencies 

AF: Number of target agencies for PDO measurement increased from 3 to 4 and end target increased;  AF II: End target increased 

—  4 target agencies publish PROMIS quarterly report for monitoring of procurement performance covering 90% of bids/invited contracts awarded 

4 target agencies publish PROMIS quarterly report for monitoring of procurement performance covering 95% of bids/invited contracts awarded 

AF: Number of target agencies for PDO measurement increased from 3 to 4 and end target increased;  AF II: End target increased 

e‐GP introduced in at least 2 target agencies at their HQ level for international procurement (80% in 2016) 

4 target agencies expand e‐GP to all 64 districts using National Competitive Bidding (NCB) procurement (80% in 2016) 

4 target agencies expand e‐GP to all 64 districts using NCB procurement (83% in 2017) 

AF: Number of target agencies increased and expansion from HQ to districts;  AF II: End target increased 

Increased stakeholder engagement following procurement issues in at least 2 target agencies 

Dropped  —  Target achieved during original project 

—  Procuring entities of 20 additional agencies with one trained/certified procurement staff (70% in 2016) 

Procuring entities of 20 additional agencies with one trained/certified procurement staff (78% in 2016) 

AF: Introduced to reflect measurement of new outcome;  AF II: End target increased 

—  —  Number of public sector organizations registered in the e‐GP system 

AF II: Introduced to reflect measurement of new outcome in the e‐GP system with enhanced capacity 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 11 of 52

Revised Components 

12. All four components were revised in the AF, and two components were revised in AF II. These revisions focused on adding new and enhancing existing activities with additional funds and an extended closing date. Table 2 summarizes project component revisions in the AF and AF II. 

Table 2. Project Component Changes 

Original Component  Additional Finance  Additional Finance II 

1: Furthering Policy Reform and Institutionalizing Capacity Development 

Scope of the capacity development program expanded to 20 additional agencies beyond the 4 target agencies, with further targeting and refinement of training programs that include procurement compliance and core competence training, along with master’s level training in procurement.  

Additional training provided for bidders and master's students 

2: Strengthening Procurement Management 

The organizational capacity for procurement performance management further strengthened at CPTU and the four target agencies, with full implementation of online performance monitoring (PROMIS) using indicators and an M&E framework.    

3: Introducing e‐Government Procurement (e‐GP)  

The transaction levels of the four target agencies substantially increased and the e‐GP network was initiated in 20 additional agencies. 

Expansion of CPTU data center to manage e‐GP growth 

4: Communication, Behavioral Change, and Social Accountability 

Efforts to raise awareness regarding public procurement reform and e‐GP through behavior change communications and social accountability mechanisms strengthened    

Other Changes 

13. Revised closing dates. At the request of the GOB, the original closing date of March 31, 2013, was extended by six months to September 30, 2013, to ensure implementation continuity and enable timely processing of the AF, including its effectiveness within the project’s implementation time frame. 

14. Additional Financing. There were also two AF agreements that expanded the scope, extended closing  dates,  and  added  funds  to  the  project.  The  original  total  estimated  project  cost was US$24.9 million,  of which  the  IDA  contribution was US$23.6 million.  In  the AF,  this was  increased  to US$60.9 million,  with  an  added  financing  of  US$34.5  million  from  IDA.  The  closing  date  was  extended  from September 30, 2013, to December 31, 2016 (for both the original project and the AF). In AF II, the total added project cost was US$12 million, with IDA financing of US$10 million. With AF II, the total project cost  increased to US$72.9 million, with IDA financing of US$68.1 million. The closing date for all three credits was extended six additional months from December 31, 2016, to June 30, 2017. 

Rationale for Changes and Implications for the Original Theory of Change 

15. Rationale for changes. The changes to the project reflected in the AF and AF II were in response to  the  achievement  of  targets  in  the  original  project,  as  political  will  began  to  evolve  in  support  of 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 12 of 52

procurement reform, target agencies were beginning to see improved results, and the bidding community increasingly  supported World Bank‐supported procurement  reform efforts. At  the  time of  the original project appraisal, the GOB and the World Bank established modest and realistic project expectations in specific reference to e‐GP, recognizing the sensitive nature of procurement reform, specifically the vested interests  that needed  to be overcome  to  improve  the use of public  resources with greater efficiency, transparency, and accountability. Over time, the CPTU successfully built on the stakeholders’ ownership, both public and private, by extensive consultations and ground‐level engagements with behavioral change communication program, followed by political support at a later stage for procurement reform to achieve the targets set in the original, AF, and AF II projects. The key rationale for AF was to introduce e‐GP with an adjustment in the financing arrangement (DLI‐based financing) and expand the capacity development program to additional 20 agencies. Subsequently, due to the quicker‐than‐expected rollout of e‐GP, AF II supported the development of enhanced capacity data center to accommodate increased demand across the country so that all public‐sector organizations are covered.  

16. Impact on theory of change. The original theory of change remained relevant throughout the life of the project. The slight adjustments to the PDO, PDO indicators and targets, and project components in the  AF  and  AF  II  further  refined  project  activities,  outputs,  and  outcomes  and  strengthened  their relationship  to  the  PDO.  Providing  additional,  targeted  training  for  key  procurement  stakeholders (including procurement entities and  the bidder/contractor  communities),  adding 20 additional agency beneficiaries  across  a  wide  range  of  sectors,  and  further  refining  communication  and  stakeholder engagement were three concrete changes to the project that contributed to the PDO by strengthening the public procurement system while specifically improving the performance of the 4 target agencies. 

II. OUTCOME 

A. RELEVANCE OF PDOs 

Assessment of Relevance of PDOs and Rating  17. The  current  Country  Partnership  Framework  (CPF)  for  Bangladesh  (FY16–20)  “identifies governance reforms as a  long‐term agenda that demands sustained effort as well as downstream and upstream interventions” by supporting policies and systems that improve transparency and efficiency in service delivery. The current CPF specifically states the World Bank’s commitment to support Bangladesh’s efforts to strengthen its public procurement system, including e‐GP. 

18. Throughout the project appraisal process and implementation (2007–2017), the PDO’s focus on strengthening the public procurement system and improving the performance of the four target agencies, remained relevant to, and clearly supported, the World Bank’s objectives in Bangladesh. In addition to the current CPF, there are also references to the preceding Country Assistance Strategies (FY06–09; FY11–14) since the project was originally developed in 2007. The CAS FY11–14 specifically had a core governance pillar  (enhance  accountability  and  promote  inclusion)  under  which  enhanced  transparency  and accessibility of public services through information technology came in prominently. 

Relevance Rating: Substantial

The World Bank Public Procurement Reform Project II ( P098146 )

Page 13 of 52

B. ACHIEVEMENT OF PDOs (EFFICACY)  Assessment of Achievement of Each Objective/Outcome  19. The achievement of the PDO is assessed by reviewing the achievement of the activities, outputs, and outcomes associated with the four project components, which are reflected as intermediate results in the Results Framework. Throughout implementation, the GOB and the World Bank worked together closely to assess the relevance of Intermediate Results Indicators used to monitor key activities and assess the achievement of results associated with each component, along with the higher‐level PDO indicators’ relevance to the PDO. There were slight adjustments to the PDO and Intermediate Outcome Indicators at the time of the AF and AF II, with some dropped, added, and revised, retaining the main objective. Several also remained unchanged for AF II. 

20. All PDO indicators were achieved fully, with some of them substantially exceeding the targets (for example,  e‐GP).  This  has  contributed  to  bringing  about  a  systemic  change  in  the  public  procurement environment  (see  annex  1  for  a  complete  list  of  indicators).  One  PDO  and  10  Intermediate  Results Indicators were dropped in the AF because the targets were met in the original project. The indicators that were revised in the AF (two PDO and four Intermediate Results Indicators) and AF II (four PDO and six  Intermediate Results  Indicators) also achieved  indicator  targets  fully and were adjusted upward  to reflect this progress. The original PDO and Intermediate Results Indicator targets of e‐GP were modest given  the prevailing  challenging  environment  at  that  time with  inadequate  infrastructure,  inadequate knowledge of e‐GP, limited willingness of implementing agencies, and unsure political commitment. Also, it was not possible to accurately measure the political will of key decision makers, whose proactive and public support for public procurement reform came at a later stage and their support of the rollout of e‐GP was essential to project success. Extensive stakeholders’ consultation and broad ownership of both the  procuring  organizations  and  the  bidding  community  helped  substantially  in  the  successful implementation  of  e‐GP  because  improved  transparency  in  e‐GP  attracted  large  numbers  of  the beneficiaries. This was reflected in the original theory of change for the project. The improvements to the overall  public  procurement  system,  resulting  from  the  capacity  development  and  e‐GP  initiatives,  are summarized in Figure 3 in terms of efficiency, transparency, and competitiveness.3 Similarly, Bangladesh improved its ranking in the Corruption Perception Index (CPI). In 2007, the CPI ranking was 162 out of 179 countries, with a score of 2 (out of 10), while in 2016 it ranked 145 out of 176 countries, with a score of 26 (out of 100). 

Figure 3. System Improvements Indicator Results 

 

3 Efficiency is measured in terms of timeliness of awarding tenders, transparency is related to the publication of awards, and competition is based on the average number of bidders. Improvement in these three measures correlated with the rollout of e‐GP. 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 14 of 52

21. Over time, the Prime Minister, Minister of Finance, and the Minister for Planning became strong supporters of the project by observing its contribution to improving the procurement environment with drastically reduced inappropriate and/or coercive bidding practices at the decentralized level. They clearly communicated  this  support  publicly  and  to  key  project  stakeholders.  In  addition,  IMED  also  strongly supported  the  project  and  the  CPTU’s  status  as  implementing  agency.  CPTU  leadership  managed  to capitalize on this political  support while effectively managing the project, despite  the ongoing staffing challenges described in section IIIB.  

22. While the PDO and Intermediate Results Indicators were organized in accordance with the four project  components  that  guided  implementation,  many  of  them  were  cross‐cutting  and  mutually reinforcing across components/Intermediate Results. This contributed to the achievement of the PDO and supported  the  longer‐term  goal  of  improving  the  use  of  public  resources  with  greater  efficiency, transparency, and accountability. 

23. A brief analysis of relevant project data, including Results Framework Indicator results (both at the PDO and Intermediate Results levels), provides further empirical basis for an accurate assessment of project efficacy.  

Intermediate Result/Component 1: Furthering Policy Reform and Institutionalizing Capacity Development  

24. The  project’s  comprehensive  capacity  development  program  effectively  provided  core procurement  skills  required  to  institutionalize procurement capacity at  the 4  target and 20 additional public agencies. There were five categories of training offered by the project: (a) 1–5‐day short courses for 17 different types of audiences covering policy makers to journalists; (b) three ‐week training sessions on the procurement of goods, works, and consultant services along with e‐GP training for five days; (c) a Procurement Core Competence Program offered by the  Chartered Institute of Procurement and Supply, U.K. (CIPS) in collaboration with BRAC University Institute of Governance and Development (BIGD) for top performers of the three‐week training sessions; (d) a top‐up Master’s Program in Procurement and Supply Management offered by BIGD; and (e) a one‐year Master’s Program in Public Procurement Management for Sustainable Development in the Turin School of Development at the University of Turin in Italy.  

25. The establishment of this comprehensive capacity development program, with five discrete but interrelated training opportunities (from one‐day courses to master’s level study), provided much‐needed capacity for a wide array of procurement professionals. By focusing on building the procurement training capacity  of  two  local  training  institutes  (the  ESCB  and  BIM)  and  BRAC  University,  the  project  also developed a sustainable approach to training procurement professionals. Table 3 provides a final tally of capacity development project beneficiaries.  

Table 3. Capacity Development Program Beneficiaries 

Capacity Development Program  Number of Beneficiaries  Comments 

Short courses (1–5 days)  14,083  17 topics, multiple stakeholders 

3‐week training sessions  6,414  4 target agencies, 20 additional agencies 

MCIPS (CIPS‐UK and BRAC‐IGD)  143  Top performers in 3‐week training 

Top‐up Master's Program (BRAC‐IGS)  107  Potential MCIPS participants 

Master's (University of Turin)  25  Potential participants from target agencies Note: MCIPS = Master’s Charted Institute of Purchasing and Supply. 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 15 of 52

26. There were two indicators directly related to capacity development when the project closed: (a) building  procurement  expertise  in  the  procurement  entities  of  the  20  additional  agencies  (PDO  and Intermediate  Results)  and  (b)  building  the  capacity  of  the  ESCB  to  deliver  procurement  training (Intermediate Results) from its own resources beyond PPRPII. Both were added in the AF.  

27. Three additional Intermediate Results Indicators focusing on capacity development were dropped in the AF because targets were already achieved: (a) curriculum and training materials, (b) faculty capacity at a local training institute, and (c) institutional capacity at a local training institute or university to deliver core competence skill certification and accreditation in procurement.  

28. There  were  indicators  fully  achieved  in  the  Results  Framework  for  the  second  part  of  this component, which focused on furthering policy reform, along with one indicator in the Monitoring Plan. In the original and AF PADs, reference is made to supporting secondary legislation resulting from the 2003 Public Procurement Regulations and the Public Procurement Act (PPA). Policy reform activities focused on preparing and updating policy documents,  standard bidding documents,  request  for proposals, bid evaluation  and  post  review  guidelines,  and  ensuring  for  transparency  and  accountability  by  posting relevant public procurement information on appropriate GOB websites. This work was done by the CPTU, with the assistance of FINEUROP and ESCB. 

Intermediate Result/Component 2: Strengthening Procurement Management 

29. The original project  focused on  improving procurement management and monitoring  in  the 4 target agencies, with an additional 20 agencies receiving procurement management support in the AF and AF II. Additional Component 2 activities included (a) initial development of M&E frameworks for the four target agencies, (b) implementation of an online procurement performance monitoring system as part of e‐GP, and (c) provision of additional space for the CPTU with the vertical extension of a third floor in its building. AF II enabled the CPTU to meet the unexpected rapid growth in e‐GP demand across the country, with resources for additional processing and storage capacity of the e‐GP system. 

30. There were four indicators that focused on strengthening procurement management when the project closed: (a) reducing delays by making contract awards within initial bid validity period (PDO), (b) publishing  online  PROMIS  quarterly  reports  for  monitoring  of  procurement  performance  (PDO  and Intermediate  Results),  (c)  publishing  all  contract  awards  above  Public  Procurement  Regulation  (PPR) thresholds on the CPTU website (Intermediate Results), and (d) the satisfactory handling of complaints (Intermediate Results).  

31. Two additional  Intermediate Results  Indicators were dropped  in  the AF because  targets were already  achieved  in  the  original  project:  (a)  procuring  computer  hardware  and  software  and  (b)  the submission of annual implementation plans. 

32. Because the four target agencies embraced and implemented original project activities, indicators were added and targets expanded in the AF and AF II to reflect this progress. In addition, indicators were also dropped that were achieved before the AF Agreement in June 2013. When PPRPII ended on June 30, 2017,  all  indicator  targets  were  fully  achieved,  with  some  substantially  exceeding  these  targets.  For example, e‐GP achievements far exceeded the target, which contributed to transform the procurement environment,  and  PROMIS,  which  tracked  procurement  entity  performance  related  to  efficiency, 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 16 of 52

transparency, and competitiveness, was effectively rolled out by the CPTU and implemented by all four target agencies, eventually producing quarterly reports on a regular basis. This system was integrated into e‐GP as the e‐Procurement Management Information System (e‐PMIS) module, with the CPTU and the four target agencies publishing quarterly procurement performance reports on their respective websites.  

33. To create incentives for the target agencies to implement e‐GP and publish quarterly procurement performance  reports  on  a  regular  basis,  Disbursement‐Linked  Indicator  (DLI) with  performance‐based financing, approximately valued at US$7.5 million, was introduced in the AF. There were two DLIs relating to  e‐GP  introduction  and  procurement  performance  measurement  of  the  four  target  agencies. Disbursement was contingent on each of the four agencies meeting the above two DLIs. Three of the four target agencies spent 100 percent of  their available DLI  funds with  the  fourth,  the BREB, spending 87 percent. 

Intermediate Result/Component 3: Introducing e‐Government Procurement (e‐GP) 

34. The project initially, and realistically, piloted e‐GP in the four target agencies but subsequently supported the rollout of this platform nationally for these four target agencies in the AF and AF II, once initial targets were achieved. It started with a pilot in four PEs only, then to 50 PEs, followed by 308 PEs, and eventually 1000s of PEs in four target agencies. The broadening of the scope of the e‐GP rollout in the AF and AF II reflect the rapid and growing acceptance and use of e‐GP by procuring entities and the bidding community, with the support of national‐level stakeholders and political leaders. Currently, over 1,000 other implementing agencies are registered in the e‐GP system and many of them are using it. Figure 4 elucidates the expanded rollout and use of e‐GP across Bangladesh by tracking the number of registered bidders/suppliers,  the  number  of  bid  invitations,  and  the  value  of  these  bid  invitations  from  e‐GP’s launching in 2011 until the end of PPRPII in June 2017. 

Figure 4. Implementation of e‐GP Status 

 

35. The milestone of exceeding 100,000 e‐GP tenders by nearly 34,000 registered bidders over the past  five  years  demonstrates  the  widespread  acceptance  and  sustainability  of  electronic  public procurement throughout Bangladesh.  

36. There were two indicators focusing on e‐GP when the project closed: (a) rollout of e‐GP in all 64 districts using NCB procurement by four target agencies (PDO and Intermediate Results) and (b) number of public sector organizations registered in the e‐GP system (PDO). 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 17 of 52

37. Two indicators were dropped in AF because targets were already achieved in the original project: (a) establishment of network and connectivity for management information systems (MIS) at the district level at two target agencies and (b) development and installation of e‐GP at the CPTU and all four target agency HQs.  

38. In  a  survey  that  analyzed  the  impact  of  e‐GP  implementation  in  cost  savings  for  agencies  in Bangladesh,  the  World  Bank  collected  comprehensive  procurement  contract‐level  data  from implementing agencies. Based on an analysis of this data, e‐GP reduced the cost ratio between 13 percent and 20 percent, resulting  in cost savings of more than US$ 446 million that  includes transaction costs, advertising cost, and record‐keeping costs. There was also evidence that e‐GP improved competition by limiting political influence, because the e‐GP system allowed bidders to place bids from anywhere there was Internet access. This limited rent‐seeking opportunity at various stages of the procurement process that migrated to a more insulated, online environment in e‐GP. Overall, e‐GP promoted more competition among bidders, resulting in more competitive pricing and lowered transaction costs through improved access for bidders across the country. This resulted in cost savings, as shown in Figure 5. 

Figure 5. Cost Savings in e‐GP 

 

Intermediate Result/Component 4: Communication, Behavioral Change, and Social Accountability 

39. While  the  first  three  components  built  government  capacity,  this  supply‐side  approach  was complemented by the fourth component’s attention to the demand for public procurement reform.  It created  greater  public  awareness  of  the  importance  of  public  procurement  to  local  development  by engaging civil society, think tanks, beneficiaries, and the private sector, along with key public officials at the local and national levels. 

40. The CPTU undertook a massive behavioral  change and communication  campaign  to demystify procurement  at  the  grassroots  level  and build  ownership  of  stakeholders.  The Bangladesh Center  for Communication Programs (BCCP) assisted the CPTU on promoting behavior change communication by developing  and  implementing  a  multi‐faceted  communications  strategy.  The  key  activities  included: conducting 99 events on procurement reforms covering over 5,700 participants that includes future 64 search conference and e‐GP launching; convening 64 e‐GP awareness workshops at the district level with over 2,400 participants; establishing 64 GCFs covering over 3,300 Pes and tenderers; and organizing four e‐GP workshops including one at the national level for 44 registered banks in the e‐GP system. The GCF provided  an  informal  platform  for  GOB  officials  and  bidders  to  share  information  and  experience, 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 18 of 52

including  issues and  resolutions about procurement and  the e‐GP system. The BCCP also developed a mobile  app;  produced  an  e‐GP  theme  song,  videos,  radio  and  television  commercials,  TV  talk  shows, success  story  videos,  infographics,  email  and  on‐line marketing;  and  created  two  digital  billboards  in Dhaka that display online live procurement data with a direct feed from the e‐GP platform. CPTU produced newsletters, leading articles in media. 

41. The CPTU pursued citizen engagement at the policy level by creating a Public Private Stakeholders Committee (PPSC), headed by the Planning Minister, and comprising representatives of key GOB agencies, leading think tanks, civil society, and business apex bodies. The PPSC was designed as a platform to discuss procurement policy guidance and provide opportunity for the public and private sector to share updates and focus on challenges and opportunities associated with ongoing procurement reforms, including the e‐GP rollout across the country. The BIGD under BRAC University provided technical support to the CPTU for the PPSC. Concurrently, the BIGD also piloted citizens’ monitoring of procurement contracts at the decentralized level through the establishment of citizens’ committees in four sub‐districts in two northern districts.  This  pilot  program  brought  together  community  members,  private  contractors,  and  local procurement entities around a specific public works project, providing opportunities for joint oversight and  problem  solving.  The  BIGD  held  four  divisional  workshops,  produced  a  documentary  of  social accountability, and shared its findings in a national citizens’ engagement forum. Three case studies on school construction and textbook delivery and three policy notes on citizen engagement and e‐GP were also produced.  

42. These activities demonstrated a clear recognition by the GOB and the World Bank that successful procurement reform requires improved supply and informed demand by key stakeholders at the local and national  levels.  The  BCCP  and  BIGD  proactively  reached  out  to  key  stakeholders  across  the  country, sensitizing them to the ongoing procurement reform process with a range of activities at the community, district, and national levels. Many of these activities were attended by CPTU officials and World Bank staff, strengthening  relationships  and  increasing  communications  between  stakeholders  regarding procurement  reforms  implemented  by  the  CPTU.  Toward  the  end  of  the  project,  BCCP  conducted  a qualitative perception opinion research (end‐line evaluation) of procurement reforms covering a target group of tenderers, procuring entities, civil society members, media, and financial institutions. Overall, 79.3 percent of  respondents were positive  about  improved  transparency  in public  procurement;  76.6 percent expressed procurement reforms as effective; 72.3 percent recognized the system as efficient; and 81.9 percent mentioned improved accountability. Variations among audiences are summarized in Figures 6 to 9.  

                   Figure 6: Opinion on Transparency of Procurement Reforms      Figure 7: Opinion on Effectiveness of Procurement Reforms 

  

The World Bank Public Procurement Reform Project II ( P098146 )

Page 19 of 52

   Figure 8: Opinion on Efficiency of Procurement Reforms             Figure 9: Opinion on Accountability of Procurement Reforms 

 

43. There were three Intermediate Results Indicators focusing on behavioral change communication, and social accountability when the project closed:  (a) GCFs held  in all 64 districts, holding semiannual meetings;  (b)  e‐GP  awareness  workshops  held  in  all  64  districts;  and  (c)  public‐private  stakeholders committee workshops held. There were no PDO Indicators. 

44. Four  indicators were dropped  in  the AF because  targets were already achieved:  (a)  increasing stakeholder engagement on procurement issues in at least two target agencies (PDO), (b) developing a government  communications  strategy  (Intermediate  Results),  (c)  organizing  communications  and advocacy workshops  in  all  64  districts  (Intermediate Results),  and  (d)  convening workshops on public procurement and social accountability for key stakeholders (Intermediate Results).  

Justification of Overall Efficacy Rating  45. The project strengthened the public procurement system and improved the performance of the four target agencies based on the achievement of PDO and Intermediate Results Indicator targets and the project data presented earlier. Both parts of the PDO were weighted equally in the original, AF, and AF II PADs, and indicators and targets used were appropriate measures of project efficacy. 

Efficacy Rating: Substantial 

 C. EFFICIENCY 

Assessment of Efficiency and Rating  46. The  project  was  designed  to  strengthen  the  public  procurement  system  and  improve  the performance  of  the  four  target  agencies  by  supporting  sustainable  procurement  reforms  to  improve competition in the competitive bidding process, reduce procurement delays, and improve procurement quality through better management and monitoring at the target agencies. To gauge the impact of project activities, a set of well‐defined procurement performance indicators was developed and improved in the AF and AF II. The existing procurement management information systems at the CPTU and the four target agencies were enhanced and expanded to monitor  their performance against established benchmarks 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 20 of 52

throughout  implementation. Because project  results  could  not  be  fully  quantified  in monetary  terms, there was no calculation of an economic rate of return. 

47. The business model that was developed for the e‐GP system included revenue generation from end‐user  fees  (bidders’  registration  fee,  renewal of  registration,  and  sale of  bidding documents).  This model was designed to ensure the sustainability of the e‐GP system beyond the life of PPRPII. At the end of  the  project,  the  e‐GP  system  was  generating  revenues  that  exceeded  initial  targets.  Earnings forecasts/actuals  are  as  follows:  FY14‐  US$0.55  million/US$1.8  million;  FY15‐  US$0.95  million/US$4 million; FY16‐ US$1.25 million/US$5 million; and FY17‐ US$2 million/US$ US$8.8 million. As opposed to these earnings, on average,  the annual operation and maintenance cost of  the e‐GP system  is US$2.5 million.  This  exemplifies  that  the  system  is  already  generating  higher  revenues  than  expenses  and  is becoming  self‐sustainable.  The  CPTU  also  fully  funded  all  staff  salaries  throughout  the  project  and implemented the e‐GP operation and management (O&M) contract  including 24 x 7 helpdesk services with substantial financing (60 percent) from the GOB. 

48. Overall, the project costs incurred to achieve its broader objectives were reasonable in terms of the  tangible  benefits  achieved  (as  described  in  the  last  section)  and  ‘value  for  money’  given  the sustainability of these benefits. 

 Efficiency Rating: Substantial  D. JUSTIFICATION OF OVERALL OUTCOME RATING  

49. The PDO remained relevant to the GOB’s and the World Bank’s plans and priorities throughout implementation. Project objectives measured by PDO and  Intermediate Results  Indicators and  related project  data  were  consistently  achieved  or  exceeded,  and  project  resources  were  efficiently  used  to achieve sustainable results.   Overall Outcome Rating: Satisfactory  E. OTHER OUTCOMES AND IMPACTS  

Gender 

50. AF II specifically addressed the impact of Components/Intermediate Results 1 and 3 on closing the gender gap in public procurement. The e‐GP created more professional opportunities for computer‐literate women, particularly working in computer cafes given the increased Internet access demands by the bidding community across the country and at procuring entities. Women also participated in training programs,  providing  them  with  opportunities  for  professional  advancement.  Furthermore,  women participated  effectively  in  the  citizen  engagement  component  with  specific  reference  to  contract monitoring and e‐GP workshops at the decentralized level.  

Institutional Strengthening 

51. The project contributed to institutional strengthening of the public procuring entities, civil society organizations, and associations along with the public and private sectors, through the training, technical 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 21 of 52

assistance,  and  outreach  initiatives  described.  Key  public  sector  beneficiaries  included  the  focal implementing agency, CPTU, along with the 4 target and additional 20 agencies. Representatives from the bidding community also received various levels of procurement training—in Dhaka and at the district and sub‐district levels. Civil society and educational organizations were also beneficiaries, including the BCCP, BIDG, BIM, and ESCB. 

Mobilizing Private Sector Financing 

52. Not applicable. 

Poverty Reduction and Shared Prosperity 

53. Throughout  implementation,  there  was  a  growing  recognition  by  the  GOB  regarding  the importance of  enhanced accountability  and  improved governance  to  reducing poverty,  improving  the investment  climate,  and  accelerating  private  sector‐led  growth.  Because  the  annual  government expenditure on the procurement of goods, works, and services accounted for 20 to  40 percent of the annual national budget and 60 to 80 percent of the annual development budget at appraisal, improving procurement  was—and  continues  to  be—a  foundational  aspect  of  good  governance  and  enhanced accountability. 

54. PPRPII  addressed  accountability  and  governance  issues  directly,  improving  the  public procurement  system  by  developing  and  successfully  rolling  out  e‐GP.  During  consultations  by  the Implementation  Completion  and  Results  Report  (ICR)  Team  with  key  GOB  stakeholders  and representatives of the bidding community, there was a clear consensus among public and private sector beneficiaries that the project improved accountability and governance in public procurement by limiting opportunities for corrupt practices when e‐GP became operational.4 

55. The e‐GP also leveled the playing field in the procurement process for the bidding community by limiting the impact of personal connections, informal relationships, and rent‐seeking behaviors of public officials at the national and local levels. This contributed to a broader, shared prosperity in the bidding community, empowering contractors previously unable to successfully navigate the daunting challenges of the pre‐e‐GP paper‐based procurement process. 

Other Unintended Outcomes and Impacts 

56. Not applicable. 

III. KEY FACTORS THAT AFFECTED IMPLEMENTATION AND OUTCOME 

A. KEY FACTORS DURING PREPARATION 

57. Project design. The project was well designed at the outset, aligning the original PDO with the GOB’s and World Bank’s priorities (see section IA and IB), identifying appropriate activities relevant to the PDO (see section IIB), and applying lessons learned from the PPRP, specifically regarding the importance 

4 The ICR team conducted two missions to Dhaka in June and July 2017, meeting with the World Bank and CPTU teams, along with a wide range of project stakeholders.  

The World Bank Public Procurement Reform Project II ( P098146 )

Page 22 of 52

of including the supply and demand dimensions of procurement policy reform. There were four clearly structured and sequenced components with an appropriate array of interrelated activities.  In addition, there  was  a  clear  operational  logic  with  a  motivated  focal  implementing  agency  (CPTU),  4  targeted agencies,  and  in  the  AF,  an  additional  20  agencies.  There  were  also  19  legal  covenants  that  were established for the project focusing on a range of operational issues related to the CPTU and target agency staffing, installation of e‐GP systems, and performance and financial reporting. Most covenants were fully in compliance, with a few partially, at the end of the project. Compliance was delayed for nine of these covenants.  

58. Results  Framework.  There  were  five  PDO  and  nine  Intermediate  Results  Indicators  well distributed across components when the project closed. This included three indicators that were common as PDO and Intermediate Results Indicators. Eleven additional indicators were dropped in the AF because targets were already achieved in the original project.  

59. Monitoring Plan. The project’s Monitoring Plan placed the responsibility for data collection on the CPTU and the four target agencies, with the assistance of the firm, Survey Research Group Bangladesh (SRGB), which reported to the CPTU. For the indicators that monitored incremental progress in achieving specific results, target values were set annually for the anticipated five‐year duration. Overall, appropriate baselines and target were set, given the working assumptions of the GOB and the World Bank at the time of appraisal, as reflected in the theory of change described in Section IA. 

60. Stakeholder  selection. The  project  identified  a  subset  of  public  procurement  stakeholders  to serve as implementers and beneficiaries. This included the CPTU, the four target agencies, BIM, and ESCB. The CPTU and the four target agencies were the key drivers for developing and rolling out e‐GP, with BIM and  ESCB  contributing  to  capacity  building.  Additional  project  beneficiaries  included  the  bidding community (including banks), along with civil society organizations,  institutions of higher  learning, and professional associations representing bidders with common expertise and focus.  

61. Risk mitigation measures. There were three risks to the PDO and six risks to component‐level results identified at preparation, all rated Modest or Substantial. The overall risk to project completion was rated Substantial. Lack of capacity, political will for reform, and willingness to embrace change were three main drivers for these risks. Project approach and planned activities were designed to mitigate these risks  when  feasible.  Component/Intermediate  Result  1  focused  on  capacity,  while  political  will  and willingness  to  change  were  addressed  by  empowering  and  equipping  motivated  change  agents  in implementer and beneficiary agencies. A comprehensive stakeholder engagement and strategic behavior change communication program was integrated throughout the life of the project to neutralize and/or reduce the possibility of perceived risks from non‐PE and bidding community stakeholders such as civil society organizations (CSOs), media, and other advocacy groups. 

B. KEY FACTORS DURING IMPLEMENTATION 

62. GOB/implementing agency. With the initial encouraging results on the ground, the GOB strongly supported the rollout and increased use of e‐GP by government procurement entities and the bidding community. This was conveyed by the highest levels of political leadership (see section IIB). There were, however, issues related to human resources and the organizational capacity of the CPTU during the early stages of implementation. A few positions were not filled, with this challenge compounded by periodic 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 23 of 52

staff transfers. This contributed to the slow mobilization of project activities, but this was subsequently resolved when the positions were eventually filled.  

63. PPR 2008 and PPA 2006 served as the legal and regulatory foundation for project activities. There were—and continue to be—challenges associated with subsequent amendments to the PPA that were not favored by some bidders and development partners,  including the World Bank. Some amendment requirements  also  did  not  conform  with  international  best  practices  and  World  Bank  procurement requirements.  This  included  the  following  changes  to  provisions  for  contracts  valued  at  US$300,000: lottery  for  works  contracts  in  case  there  was  a  tie  in  price  because  of  an  artificial  price  cap,  no experience/qualification requirement for small‐value works contracts, and the rejection of bids above or below a  fixed percent of  the estimate  for small works contracts. None of  these amendments were or continue to be acceptable for World Bank‐financed contracts.  

64. There were no major issues related to basic logistics, M&E, or fiduciary, social, and environmental practices. 

65. World  Bank  PPRPII  team.  The  World  Bank  Team  proactively  supervised  all  four  project components and worked closely and collaboratively with the primary implementers of the project: CPTU, the four target agencies, FINEUROP, ESCB, BCCP, and BIGD. Continuity of project leadership (there was one  Task  Team  Leader  throughout  appraisal  and  implementation)  contributed  to  building  strong relationships with stakeholders and facilitating open and constructive dialogue that focused on resolving issues as they arose.  

66. Project  reporting  was  conducted  regularly  and  predictably,  ensuring  that  project  data  were routinely collected and analyzed by the GOB and used to effectively monitor implementation progress. There were some challenges with the collection and analysis of data for the project, but the team carefully monitored this and worked closely with the CPTU and SRGB to resolve these challenges.  

67. There were 18 implementation supervision missions that were conducted on a regular basis, with detailed and well‐documented Aide Memoires. In addition, 17 Implementation Status and Results Reports (ISRs) documented implementation progress according to the Results Framework and Monitoring Plan up to December 2016. The 18th and final Implementation Support Mission (ISM) findings and conclusions are recorded in the ICR.  

Outside Project’s Manageable Control: Not applicable 

IV. BANK PERFORMANCE, COMPLIANCE ISSUES, AND RISK TO DEVELOPMENT OUTCOME 

A. QUALITY OF MONITORING AND EVALUATION (M&E) 

M&E Design 

68. Project M&E was conducted by the CPTU and target agencies. The SRGB assisted the CPTU by preparing semiannual reports on the overall project M&E, including progress on the Results Frameworks, for review by the World Bank.  

The World Bank Public Procurement Reform Project II ( P098146 )

Page 24 of 52

69. Results  monitoring  for  the  original  project  covered  (a)  procurement  activities  by  the  target agencies to determine compliance with the PPR, (b) procurement performance by the target agencies, (c) a  capacity  development  program  and  its  impact,  (d)  behavioral  change  communication  and  social accountability subcomponents, (e) the status of procurement and FM, and (f) overall project performance and its impact. For each component, a separate monitoring system was developed.  

70. AF results monitoring was enhanced by addressing (a) procurement performance by the target agencies, (b) capacity development by the additional agencies, (3) procurement monitoring by the target agencies using PROMIS, and (d) conducting of procurement using e‐GP. 

71. Due to quicker‐than‐expected progress in developing and rolling out e‐GP in the AF and AF II, and strengthening civic engagement during the original and AF projects, the M&E design in AF II was further refined. The GOB established e‐PMIS for tracking procurement performance with a set of  indicators to measure  efficiency,  transparency,  and  competitiveness  of  the  system,  with  all  four  target  agencies publishing e‐PMIS indicator reports on their respective organization websites and on the CPTU website. During AF, e‐GP system  information became available  to  the public,  including bid  invitations, contract awards, and quarterly online procurement performance monitoring reports with 45 system‐generated indicators. 

72. To meet  the  demand  side  of  governance with  civic  engagement  as  the  ‘third  eye’  on  overall procurement,  the  model  of  third‐party  monitoring  was  piloted  by  the  BIGD,  with  two  field‐level nongovernmental organizations using feedback from the citizen committee at the subdistrict level. The PPSC,  which  included  high‐level  representatives  of  different  key  stakeholders  including  leading  think tanks, regularly convened to provide strategic support. 

73. Overall, project M&E covered all components and subcomponents of the project, with M&E data used to evaluate the project in three stages: baseline at preparation and progress made at midterm and end of project  implementation. The  indicators  selected  for all  the  three projects adequately  reflected PPRPII’s theory of change, tracking progress made for all four project components and, more generally, for the PDO. Two project indicators were repeated as PDO and Intermediate Results Indicators without any explanation in the AF II PAD. 

M&E Implementation 

74. During  implementation  of  the  original,  AF,  and AF  II  projects, M&E  implementation  gradually improved after a challenging start. The SRGB initially did not collect, analyze, and report the data needed for  the  Results  Frameworks  and  Monitoring  Plans,  requiring  the  World  Bank  and  CPTU  to  clarify expectations. This was well documented in many Aide Memoires, proactively addressed by the Task Team Leader  and  the  team,  and  further  discussed  during  ISMs.  The  e‐GP  system  offered  systematic  data collection which enabled the SRGB, along with the World Bank and CPTU, to access much of  the data required for the Results Framework and Monitoring Plan regularly during the AF and AF II. 

75. The target agencies and the CPTU provided required information to the SRGB,  including direct data  from  the  agencies;  published  data  in  the  MIS  of  the  target  agencies’  and  CPTU  (e‐PMIS);  and documentation of field visits, consultations with official sources (including the bidding community, civil society, and beneficiary groups), and interviews with key informants. 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 25 of 52

M&E Utilization 

76. The  project  effectively  used  the  original  and AF  Results  Frameworks  and Monitoring  Plans  to update and improve subsequent iterations for both AF agreements. Both PDO and Intermediate Results Indicators were dropped and added based on progress achieving indicator targets, with some indicator targets increased to reflect strong progress in implementation. The methodology for one indicator was revised to improve accuracy based on available data. No targets were lowered in the original, AF, and AF II projects. 

Justification of Overall Rating of Quality of M&E  77. Despite initial challenges with the M&E firm (SRGB) and the unexplained repetition of indicators in the PDO and Intermediate Results categories, overall the project Results Framework and Monitoring Plan did a commendable  job capturing results, adapting to the rapid acceptance of e‐GP by procuring entities and the bidder community. The original and AF indicators also appropriately informed the content and form of both AF agreements.   M&E Quality Rating: Substantial  B. ENVIRONMENTAL, SOCIAL, AND FIDUCIARY COMPLIANCE 

78. Environmental  compliance.  The  project  was  assigned  Category  ‘C’  at  preparation,  since  no environmental impacts were expected to arise due to project implementation. This designation remained for  the AF  and AF  II. Overall,  the project did not  involve  any  acquisition of  land and displacement of population,  and  there were  no  project‐affected  persons  issue  on  this  account.  The AF  supported  the vertical extension of  the CPTU building  (from two  to  three stories), but no significant and  irreversible environmental  impacts  arose  during  implementation,  and  the  construction  was  subject  to  proper adoption of an Environmental Code of Practice (ECoP), including occupational health and safety issues. The bidding document included environmental clauses and kept provisions for better occupational health and safety for the workers. The Public Works Department supervised and ensured proper implementation of the ECoP.  

79. Social compliance. Extensive efforts under PPRPII contributed positively to changing the ‘mindset’ of stakeholders,  including public procurement officials and the bidding community. Under  the AF,  the involvement of civil society organizations and project beneficiaries further contributed to procurement monitoring, with specific reference to e‐GP awareness and bringing the reform agenda at the grassroots. The  framework  for  stakeholder participation  (a)  initiated a  gradual  approach  to  the  concept of  social accountability  in  procurement,  (b)  conducted  public  awareness  campaigns  in  the  beneficiary/user communities, and (c) instituted a communications strategy to build support procurement reform. 

80. The social accountability and citizen engagement subcomponent of the project included PPSCs, GCFs, and third‐party monitoring by citizen/beneficiary groups on a pilot basis in two districts covering four sub‐districts. This approach generated deep interest  in the community to take the reforms to the grassroots and is concurrently making the public procurement officials more accountable to the citizens. 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 26 of 52

81. The  project  also  contributed  positively  to  improved  gender  inclusion.  The  e‐GP  initiative (Component  3)  specially  created  more  opportunities  for  the  computer‐literate  female  workforce  at computer cafes and in data processing specifically in the bidding community and procurement entities. Furthermore, women benefitted from capacity development (Component 1), and increased participation in the monitoring of procurement contracts through citizen engagement.  

82. Fiduciary compliance. The CPTU, with the assistance of two FM consultants, implemented PPRPII in the absence of its own FM organization. The target agencies received project funds through the CPTU in  their  dedicated  project  bank  accounts.  In  the  AF,  funds were  disbursed  to  the  agencies  based  on achievement of  targeted  results  related  to DLIs. After  initial  challenges establishing  the disbursement modalities related to DLIs, they served their purpose and three of the four target agencies received 100 percent of available DLI funds, with the BREB receiving 87 percent. 

C. BANK PERFORMANCE 

Quality at Entry 

83. Strategic relevance and approach. The World Bank leveraged the GOB’s evolving understanding of the importance of procurement reform to good governance at entry, building on, and learning from the PPRP, the previous operation. The 2003 PPR, followed by subsequent passage of the PPA 2006 and issuing  the  PPR  2008,  provided  the  legal  framework  for  developing  a  strategic  approach  to  public procurement reform in Bangladesh.  

84. Technical,  financial,  and  economic  aspects.  The  World  Bank  team  that  prepared  PPRPII adequately considered the technical, financial, and economic aspects of the proposed project. The PPRP provided  some  helpful  lessons  learned,  including  nontechnical  elements  such  as  political  economy analyses  to  inform  and  improve  implementation  and  operationalizing  technical  insights  regarding  the importance  of  addressing  both  the  supply  and  demand  aspects  of  supporting  and  institutionalizing sustainable  reform.  The  IDA  funds  allocated  for  the  original  and  two  AF  projects  correctly  reflected absorption capacity for the implementing agency and four target agencies.  

85. Poverty,  gender,  and  social  development  aspects.  The  World  Bank  team  focused  on  the importance of good governance to economic growth and poverty reduction, based in part on the GOB and World Bank strategic planning documents. While gender was not an explicit focus of the original, AF, and  AF  II  projects,  there was  a  recognition  that  the  project  could  promote  gender  inclusion,  even  if indirectly. Social development was directly related to Component 4 activities related to behavior change communication and stakeholder engagement (see section IVB). 

86. Environmental and fiduciary aspects. The World Bank assessed that the project was a Category ‘C’ at entry, because no environmental impacts were expected during implementation. Category ‘C’ status remained for the AF and AF II as well. Given limited FM capacity of the CPTU at entry (see section IIIB), the World Bank supported hiring of two FM consultants to address fiduciary requirements and build the CPTU’s capacity in this area.  

87. Policy and institutional aspects. The World Bank Team and GOB recognized at preparation that the  2003  PPR  along  with  the  PPA  required  follow‐up  assistance,  including  the  revision  of  bidding 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 27 of 52

documents and English language translations of key documents. Component 1 specifically addressed this requirement.  

88. Implementation arrangements. The CPTU was identified as the lead implementing agency, given its prominent  role as  the public procurement  focal  point  for  the GOB, and  to ensure  implementation continuity  from  the  PPRP  to  PPRPII.  The  four  target  agencies  were  also  identified  as  important implementing  partners  given  the  project’s  focus  in  building  the  capacity  of  procurement  entities  to improve public procurement across sectors and throughout the country. Three of the four target agencies had a physical presence outside Dhaka. 

89. M&E arrangements. The M&E framework at entry for the original, AF, and AF II projects evolved to  reflect  implementation  progress,  additional  funds,  and  expanded  scope.  This  was  done  by  adding indicators, increasing targets for existing indicators, and dropping indicators when targets were met. The GOB and the World Bank recognized the needed for additional M&E support at preparation and hired a consultant  to  assist  the  CPTU  with  data  collection  and  analysis  required  for  the  project’s  Results Frameworks and Monitoring Plans.  

90. Risk assessment. The Bank Team assessed the overall risk to PDO achievement and component results  as  substantial.  The main  assessed  risk  to PDO was  inadequate  support  and  commitment  from target agency upper management at the initial phases due to the sensitive nature of procurement reform, and  the  important  role  they  needed  to  play  in  initially  piloting,  and  subsequently  rolling  out  e‐GP. Component #4 activities related to civil society monitoring of procurement processes were assessed as the most  controversial  and  highest  risk  to  achieving  results  due  to  the  politically  sensitive  nature  of monitoring in sub‐districts outside of Dhaka. 

Quality of Supervision 

91. The World  Bank  conducted  18  ISMs which  carefully monitored  implementation  progress  and identified key challenges to development impact that required additional attention by the GOB and the World Bank.  The World Bank  team was a multi‐sectoral  team with  fiduciary,  urban, water,  transport, energy, communication, and information and communication technology (ICT) expertise. Key staff and consultants  with  required  technical  expertise  at  the  component  level  participated  in  these  missions regularly.  The  project  Task  Team  Leader  and most  team members were  based  in  Dhaka, with  a  few international consultants hired on an as‐needed basis. The team developed an intimate knowledge of the project and maintained a strong working relationship with the GOB.  

92. The PDO and longer‐term outcomes in the theory of change informed the prioritization of the challenges  identified during  ISMs and routine oversight protocols. The Aide Memoires for  ISMs clearly identified  these  challenges  and  documented  general  recommendations  for  the  GOB,  along  with  key stakeholders including the CPTU, the four target agencies, and others involved in implementing activities for each component. The ISR also documented progress against Results Framework indicators and legal covenants.  

93. The World Bank team prioritized sustainable project outcomes for all four components and for the PDO more generally. Building the capacity of the ESCB to deliver procurement training without project funds and developing a business model for e‐GP that prioritized cost‐recovery from user fees were two 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 28 of 52

innovative approaches used by the GOB and the World Bank to prepare for project sustainability after the project closes. 

Justification of Overall Rating of Bank Performance 

94. Despite the highly challenging environment, the World Bank team’s continuous efforts to pursue the  reform  agenda,  by  consistently  maneuvering  and  adjusting  its  approach  to  implementation,  is commendable. Most  ISMs were held on time, fully and transparently recorded  in Aide Memoires, and followed  by  quality  ISRs.  This  formal  ISM  is  beyond  the  day‐to‐day  field‐based  supervision  of  project implementation by the World Bank team. Generally, the team was realistic and, at times, conservative in the ratings included in the ISRs. Overall, the team demonstrated its passion for reform and was able to form a critical mass within the GOB’s leading agencies who themselves now own the agenda. It is rare for politically  sensitive  and  challenging  reforms  to  be  supported  and  institutionalized  by  governments, especially when they go against vested interests in the system. This took several years to be accomplished, but the World Bank’s perseverance and partnership with the GOB was well worth the effort. 

 

Bank Performance Rating: Satisfactory 

 

D. RISK TO DEVELOPMENT OUTCOME  95. There  are  two  primary  risks  to  the  development  outcome,  specifically  related  to  financial sustainability and government/stakeholder ownership of, and commitment to, the continued rollout and institutionalization  of  e‐GP  across  the  country.  This  requires  continued  political  support  for  public procurement reforms that facilitate greater efficiency, transparency, and accountability.  

96. Regarding financial sustainability, the GOB needs to remain committed to restructuring the CPTU to (a) enhance its authority to recruit high‐performing information technology professionals, (b) further refine its current business model that generates revenues from user fees to cover operational costs, and (c) continually upgrade the e‐GP system to meet the increasing demand and improve existing services.  

97. As described  in section IIIB, the GOB made some PPA amendments, of which couple were not consistent with international best practices or with World Bank procurement requirements. To ensure the continued  development  of  a  transparent  and  accountable  e‐GP  system,  the GOB will  need  to  remain committed to public procurement reforms that ensure the integrity of e‐GP, and public procurement more generally, even when there are political pressures against this. 

V. LESSONS AND RECOMMENDATIONS 

98. The following lessons learned and recommendations from PPRPII can inform future World Bank‐funded  governance,  and  more  specifically,  procurement  reform‐related  projects  focusing  on  policy reform, e‐GP, and capacity development. Given the success of this operation, which is the World Bank’s single  largest  operation  in  procurement  reform  under  credit  financing,  these  lessons  and recommendations offer tangible and practical insights transforming global knowledge into ‘good local fit’ practices that may help in undertaking procurement reforms in other countries and regions.  

The World Bank Public Procurement Reform Project II ( P098146 )

Page 29 of 52

99. Challenges  and  enabling  conditions  for  a  sustainable  reform.  Enabling  conditions  for  a sustainable reform are not straightforward in a challenging environment like Bangladesh and often follows a complex trajectory, affected by numerous factors such as external  influence, vested  interest groups, political backlash, conflicting interest of stakeholders, corrupt practices, lack of appreciation to pursue a good  governance  agenda,  and  reluctance  to  change. Despite  this,  the  factor  that  remained  as  crucial enabler  was  the  appropriate  recognition/understanding  of  the  country’s  operating  context  and  its inherent political economy. Other key supporting enablers include—recognizing the Government as the driver  of  reforms;  identifying  a  political  leader  to manage  the  political  pathway; working with  a  few reform‐minded public officials both at the core ministry and the implementing agency level to design and implement  the  actual  reform  actions;  and  coordinating  with  influential  stakeholders  outside  the Government  (bidding  community/civil  society).  In  that  regard,  the  development  partner’s  role  was instrumental in terms of providing the required global knowledge and technical support with funding. 

100. Commitment and ownership. Successful and sustainable procurement reforms require ongoing high‐level commitment and ownership of the key stakeholders, especially the implementing agencies and the bidding community, as well as high‐level political commitment from the government. Such combined ownership enhances the probability of sustainable reform. Although both operations enjoyed support of the two governments in power that came successively from two opposition parties, such backing was not high at the initial phase of reforms. Instead, the actual implementation of crucial reforms like e‐GP was a bottom‐up approach, mainly owned by the mid‐level public officials of a few key agencies (who wanted to see changes) and a relatively young bidding community, both with knowledge of computers. Initially, it was  a  slow growing ownership  of  the  e‐GP  system by  those  stakeholders.  The project  implementers, including the key officials of the CPTU and the four target agencies key officials, leveraged the support of enthusiastic mid‐level officers and the young community of bidders and banks by widening the ownership circle. When political leaders saw that e‐GP was becoming popular at the field level because it reduced rampant  bid‐rigging/coercion/collusion,  and  thus  directly  contributing  to  containing  unruly  elements, then they started to support e‐GP. Within a short time, e‐GP became one of the most prominent political commitments  of  the  Bangladesh  Prime  Minister,  along  with  key  members  of  the  Cabinet  (Finance, Planning) who supported and mandated its rollout in all of the nation’s 64 districts. This was evidenced by the successful development and exponential rollout of e‐GP.  

101. Sustainable  institutional  mechanism.  Having  in‐built  institutional  mechanism  within  the Government’s existing framework makes the reform more sustainable in the longer term, although the pace of reform initially may be slow. An example of such sustainable mechanisms is how the CPTU has been fully funded by the Government, as opposed to creating a Project Implementation Unit with project funds.  Over  time,  the  CPTU’s  visibility  within  the  Government  has  become  highly  prominent,  with credibility ratings of the implementers and the bidding community.  

102. Self‐sustainable e‐GP business model. Early attention to developing a locally relevant, revenue generating e‐GP business model  can help  instill  long‐term sustainability  that  is not dependent on  the government  or  development  partner  resources.  Generated  revenue  can  cover  e‐GP  operation  and maintenance costs, along with new investments in the system, and also can strengthen and accelerate the e‐GP roll‐out while increasing revenue over the long‐term. Despite initial concerns over such a model and its feasibility, it eventually worked very well in Bangladesh. PPRPII’s revenue generation model has resulted in the establishment of a sustainable e‐GP system and also contributed to its accelerated roll‐out.  

The World Bank Public Procurement Reform Project II ( P098146 )

Page 30 of 52

103. Continuity  of  engagement.  The  slow  process  of  procurement  reform  needs  sustained engagement  by  the  government  as  the  leading  agent,  along  with  other  stakeholders  including  the development partners (if applicable), to bring about desired changes in institutions and systems. Tangible outcomes on the ground resulted from a sustained effort over time through two successive interventions to granulate and institutionalize policy changes and capacity development within the government system.  

104. Leadership continuity. Longer‐term and comprehensive reform initiatives require continuous and uninterrupted knowledge of, and commitment to, the sequential and inter‐related activities that achieve sustainable  results.  The  GOB  successfully  managed  changes  in  the  CPTU  with  minimal  disruption  to implementation  by  appointing  two  successive  qualified  and  experienced  Project  Directors  with  deep interest in reforms. In addition, there was only one PPRPII Task Team Leader throughout the project life cycle, from conception to completion. The continuity in leadership facilitated progressive implementation and ensured progression of the thought process, with the focus on the implementation of activities and achievement of sustainable results on the ground.  

105. Change management and client‐Bank relationship. The Bank team and the key government team at the CPTU worked like one unit for the same goal, without a hierarchical regime. Building an informal relationship of collaboration created huge momentum within this core group to collectively pursue the arduous reform agenda. The CPTU Head and Bank Task Team Leader worked hand‐in‐hand at all times, while maintaining their own institutional boundaries. At the implementation level, members of technical working groups at the four target agencies implemented the critical tasks of actual reform actions at the head office and decentralized level. 

106. Sequencing  of  reform  activities.  Proper  sequencing  of  actions  over  a  longer‐term  horizon  is critical, most likely through a series of successive interventions/operations that have specific objectives within  the  overall  reform  framework.  Lessons  learned  from PPRP were  incorporated  in  the  design  of PPRPII, and internal learning from the second operation was incorporated in the two subsequent PPRPII additional  financing mechanisms. Based on PPRPII  learning,  recently another new operation has been approved with US$55 million credit financing for digital project implementation monitoring at national level and e‐GP enhancement across the entire country. 

107. Supply  and  demand  of  reform.  Implementation  of  politically  sensitive  and  challenging  public procurement reform requires attention to the supply and demand sides of the procurement life cycle. Supply‐side  issues related to developing an efficient and effective  legal and regulatory framework and enhancing  the  service  delivery  capacity  of  key  implementers  need  to  be  complemented  by  nurturing informed demand for such reforms. PPRPII supported ongoing procurement reform, developed and rolled out e‐GP, and built the capacity of key implementers to effectively use this system while also focusing on educating potential users and beneficiaries about the benefits of PPR and, more specifically, e‐GP. The communications and behavior change components of the project specifically focused on the demand side.  

108. Communication  and  behavior  change  of  stakeholders.  Sustainable  and  transformative  policy reform needs an integrated suite of interventions that move beyond the actions of passing new laws and providing  specialized,  targeted  training  and  technical  assistance.  Beyond  technical  contents  of  laws, capacity development and e‐GP, PPRPII undertook a massive  stakeholders’ engagement program that supported a  range of activities  in engaging and sensitizing key stakeholders across the country on the importance of procurement reform and the benefits of e‐GP. The program involved different strata of 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 31 of 52

communities,  including  political  leaders,  implementers,  bidders,  bankers,  civil  societies,  academia, journalists, and, most importantly, common citizens and project beneficiaries. The PPSC and GCF played an important role, combined with numerous workshops and deeper dialogues directly with the field level officials,  bidding  community,  and  journalists  across  the  country  that  created  visible  momentum. Partnerships with BCCP and BIGD represented the recognition by the Bank and the CPTU that directly engaging stakeholders was essential to project success, in terms of communicating the content and form of  reforms  on  a  regular  basis,  and  changing  behavior  based  on  the  reforms.  Taken  together,  these activities effectively moved beyond simplistic technical “solutions,” reflecting an integrated approach to reform that explicitly addressed both supply and demand issues. 

109. Staffing at nodal agency (CPTU). The project suffered at times from the inadequacy of staff or non‐availability  of  skilled  staff,  in  particular  IT‐based  technical  staffing. Market  constraints  to  identify properly skilled staff added to delays in implementation. Appropriate staffing, both in terms of numbers and skills, is important for timely implementation of the reform agenda. 

110. Target‐setting  for  DLIs  ‐  Government  buy‐in  and  political  economy  considerations.  During project development, the Government and the World Bank agreed on DLI targets that reflect the political economy risks related to challenging procurement reform while developing targets that challenge and incentivize  government  partners  to  proactively  support  difficult  reform.  During  the  development  of PPRPII, the Government and the World Bank recognized the political economy and technical challenges associated with an effective and accelerated development and rollout of e‐GP,  including inadequate IT infrastructure,  limited capacity of key partners, a recalcitrant mindset to maintain the status quo, and reluctant  political  will.  This  influenced  the  establishment  of  DLI  targets  that  were  eventually  mostly exceeded by three of the four target agencies. 

111. Disbursement  versus  DLI  targets  and  project  restructuring.  The  project  faced  serious  fund flow/disbursement issues for several months because the DLI values set against each DLI period did not match the actual expenses  incurred for that corresponding period, although the  implementing agency fully achieved DLI targets ahead of time in most cases. This required restructuring of the project to amend the specific provision of disbursement, allowing a more flexible approach of cumulative expenses over period(s)  as  against  expenses  of  each  DLI  period.  The  lesson  learned  is  that,  in  Investment  Project Financing with DLIs, disbursement provisions should be made flexible enough in the Financing Agreement, allowing disbursement  against DLI  values upon  cumulative expenses,  instead of matching  values with expenses in each DLI period.  

112. Integrated,  incentive‐based  capacity  development.  Clear  incentives  for  beneficiaries  to participate  in multiple  professional  development  opportunities,  improves  the  efficacy  of  training  and technical assistance. PPRPII’s capacity development program comprised an integrated set of trainings with increasingly  higher  order  levels,  ranging  from  one‐day  sessions  to  master’s  level  study  abroad. Procurement professionals that excelled in specific programs could ‘graduate’ to the next level of training. Top performers went on to earn international procurement accreditation such as MCIPS/UK or master’s degrees at the University of Turin in Italy.  

113. Country system and integration with associated fields. With this procurement reform, now all World Bank‐funded projects in Bangladesh have been largely using the country systems for all national procurement. Work is going on to adopt the country systems for international procurement as well. As 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 32 of 52

part of the overall improvement of the public‐sector institutions and public financial management system, an integrated approach is under way to link e‐GP with the budgetary system and national identification system  of  the  Government  for  effective  public  service  delivery.  Also,  the  procurement  review/audit function is being linked to e‐GP using a separate module.  

114. Theory  of  change,  PDO,  and  indicators.  Focused  PDO  with  measurable  result  indicators, complemented by measurable Intermediate Outcome Indicators, make the project design robust. PPRPII was  designed with  clearly measurable  indicators,  and  the  same  approach  has  been  continued  in  the follow‐on  project  that  recently  become  effective.  The  theory  of  change  provided  the  framework  for effective  change  management  throughout  implementation,  accommodating  the  evolving  drivers  for political reform to ensure that results were effectively captured by refining the PDO and indicators in the AF and AF II. This was implemented by adopting a combined approach of political economy, relationship management, technical solutions, stakeholder management, and behavioral change communications to the grassroots level. 

115. Skill mix in the World Bank’s team. More diversified skills in the World Bank’s project team, with greater intensity of continuous field‐based supervision and adequate budget provision, results in better project design and implementation. The PPRPII World Bank team includes a broad array of multi‐sectoral skills (including fiduciary, transport, power, water resources, communication, social, and ICT). This lesson has now been duly  incorporated in the follow‐on new project, with even more diversified skills on the team, including skills in cutting‐edge technology such as Big Data, Open Contracting, and IT‐based social media. 

116. Capitalize  on  enabling  policy  environment.  When  developing  the  technical  approach  to procurement reform in partner countries, the World Bank needs to leverage the enabling environment for reform in addition to identifying the challenges and roadblocks. From the outset of PPRPII, the World Bank recognized that the national procurement laws in Bangladesh allowed foreign bidders to participate in procurements without restriction regardless of national or international competitive bidding. Thus, the project did not need to address the issue of eligibility and fairness for foreign bidders separately, instead focusing  on  the  reforms  required  for  its  development,  capacity  development,  and  rollout  and sustainability of e‐GP with performance measurement. 

   . 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 33 of 52

ANNEX 1. RESULTS FRAMEWORK AND KEY OUTPUTS 

       A. RESULTS INDICATORS  A.1 PDO Indicators       

 Objective/Outcome: Four target agencies fully introduce e‐GP in national competitive bidding 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Four target agencies publish PROMIS quarterly report for monitoring of procurement performance covering 90% of bids invited/ contracts awarded annually (2013‐ 20%, 2014‐ 50%, 2015‐ 70%, 2016‐ 90%) 

Percentage  0.00  5.00  95.00  100.00 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

     

 Unlinked Indicators 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of contracts  Percentage  10.00  60.00  82.00  85.00 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 34 of 52

 

awarded within initial bid validity period by the 4 target agencies (2013‐ 68%, 2014‐ 73%, 2015‐ 78%, 2016‐80%, 2017‐82%) 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Four target agencies expand electronic government procurement (e‐GP) to all 64 districts using national competitive bidding procurem ent (2013‐ 10%, 2014‐ 35%, 2014‐ 60%, 2016‐ 80%, 2017‐ 83%)) 

Percentage  0.00  3.00  83.00  95.00 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of procuring entities of 20 additional agencies with one trained/ certified procurement staff (2013‐ 10%, 2014‐ 30%, 2015 

Percentage  0.00  70.00  78.00  80.00 

  31‐Dec‐2012  29‐Dec‐2016  30‐Jun‐2017  30‐Jun‐2017 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 35 of 52

 

‐ 50%, 2016‐ 70%, 2017‐ 78%)  

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of public sector agencies registered in the e‐GP system 

Number  0.00  130.00  200.00  800.00 

  31‐Dec‐2012  29‐Dec‐2016  30‐Jun‐2017  30‐Jun‐2017  

Comments (achievements against targets):  

  

 A.2 Intermediate Results Indicators      

 Component: Capacity development program institutionalized locally and develop skilled professionals 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of procuring entities of 20 additional agencies with one trained/ certified procurement staff (2013‐ 10%, 2014‐ 30%, 2015‐ 50%, 2016‐ 70%, 2017‐ 78%)) 

Percentage  0.00  70.00  78.00  80.00 

  31‐Dec‐2012  29‐Dec‐2016  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

The World Bank Public Procurement Reform Project II ( P098146 )

Page 36 of 52

      

 Unlinked Indicators 

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of weeks of procurement training delivered by local training institute (ESCB) with its own fund/ resources outside of PPRPIIAF (2013‐ 5, 2014‐ 25, 2015‐ 45, 2016‐ 55, 2017‐ 55)) 

Number  0.00  2.00  55.00  150.00 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of contract awards published by four target agencies in CPTU's website for awards above PPR specified threshold (2013‐ 75%, 2014‐ 80%, 2015‐ 85%, 2016‐ 90%, 2017‐ 91%)) 

Percentage  10.00  70.00  91.00  100.00 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

The World Bank Public Procurement Reform Project II ( P098146 )

Page 37 of 52

    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of complaints handled satisfactorily by four target agencies (2013‐ 35%, 2014‐ 45%, 2015‐ 55%, 2016‐ 70%, 2017‐ 72%) 

Percentage  5.00  25.00  72.00  74.00 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Four target agencies publish PROMIS quarterly report covering 90% of bids invited/ contracts awarded (2013‐ 20%, 2014‐ 50%, 2015‐ 70%, 2016‐ 90%, 2017‐ 95%) 

Percentage  0.00  5.00  95.00  100.00 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Percentage of contract/ bid  Percentage  0.00  3.00  83.00  95.00 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 38 of 52

 invited through e‐GP by four target agencies using NCB in 64 districts (2013‐ 10%, 2014‐ 35%, 2015‐ 60%, 2016‐ 80%, 2017‐ 83%) 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Expanding Government‐contractors forum to all disitricts and holding semi‐annual meetings (2013‐ 10, 2014‐ 20, 2015‐ 40, 2016‐ 64, 2017‐ 64)) 

Number  0.00  4.00  64.00  64.00 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

   

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of e‐GP awareness workshops in all districts (2013‐ 10, 2014‐ 20, 2015‐ 45, 2016‐ 64, 2017‐ 64)) 

Number  0.00  64.00  64.00  64.00 

  31‐Dec‐2012  29‐Dec‐2016  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

The World Bank Public Procurement Reform Project II ( P098146 )

Page 39 of 52

    

Indicator Name  Unit of Measure  Baseline  Original Target Formally Revised  

Target 

Actual Achieved at Completion 

Number of Public‐Private Stakeholders Committee (PPSC) workshops/ meetings held (2013‐ 7, 2014‐ 10, 2015‐ 12, 2016‐ 14, 2017‐ 14)) 

Number  0.00  6.00  14.00  12.00 

  23‐May‐2007  31‐Dec‐2012  30‐Jun‐2017  30‐Jun‐2017 

 

Comments (achievements against targets):  

   

         

The World Bank Public Procurement Reform Project II ( P098146 )

Page 40 of 52

B. KEY OUTPUTS BY COMPONENT  

Objective/Outcome 1: Strengthened Public Procurement System 

 Results/Outcome Indicators 1. Percentage of procuring entities of 20 additional agencies with one trained/certified procurement staff  2. Number of public sector organizations registered in the e‐GP system 

Intermediate Results/Outcome Indicators 

1. Expand GCF to all districts and holding semiannual meetings 2. Number of weeks of procurement training delivered by a local institute (ESCB and BIM) funds/resources outside of PPRPII AF  3. Percentage of contracts/bids through e‐GP by four target agencies using NCB in 64 districts 4. Number of e‐GP awareness workshops in all districts 5. Number of PPSC workshops/meetings held 6. Percentage of procurement entities of 20 additional agencies with one trained/certified procurement staff (also Outcome Indicators) 

Key Outputs  (linked to the achievement of the Objective/Outcome 1) 

1. Public sector organizations registered in e‐GP 2. GCF established in all 64 districts and GCF meetings held 3. Procurement trainings delivered by ESCB and BIM 4. On‐line e‐GP system developed (procurement planning to contract completion 5. e‐GP awareness workshop held in all 64 districts 6. PPSC formed and workshops/meetings held 

Objective/Outcome 2: Improved Performance of Four Target Agencies 

 Result/Outcome Indicators 

1. Percentage of contracts awarded within initial bid validity period by 4 target agencies 2. Four target agencies publish PROMIS quarterly report for monitoring of procurement 3. Four target agencies expand e‐GP to all 64 districts using NCB procurement 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 41 of 52

Intermediate Results/Outcome Indicators 

1. Percentage of contract awards published by 4 target agencies in CPTU’s website for awards above PPR specified threshold 2. Percentage of complaints handled satisfactorily by 4 target agencies 3. Four target agencies publish PROMIS quarterly report covering 90% of bids/invited contracts awarded (also Outcome Indicator) 

Key Outputs  (linked to the achievement of the Objective/Outcome 2) 

1. On‐line system developed in e‐GP to calculate procurement contract performance  2. PROMIS system made operational 3. CPTU’s website published contract award information as per the PPR threshold 4. Complaint handling system introduced in e‐GP 

 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 42 of 52

 

ANNEX 2. BANK LENDING AND IMPLEMENTATION SUPPORT/SUPERVISION 

 

A. TASK TEAM MEMBERS 

Name  Role 

Preparation/Supervision/ICR 

Zafrul Islam  Task Team Leader 

Ishtiak Siddique  Procurement Specialist 

Mohammad Reaz Uddin Chowdhury  Financial Management Specialist 

Zahed Hossain Khan  Team Member 

Shakil Ahmed Ferdausi  Environmental Safeguards Specialist 

Zubair K.M. Sadeque  Team Member 

Masud Mozammel  Team Member 

Marghoob Bin Hussein  Team Member 

Tanvir Hossain  Team Member 

Sabah Moyeen  Social Safeguards Specialist 

Jorge Luis Alva‐Luperdi  Legal 

Satish Kumar Shivakumar  Disbursement 

Srivathsan Sridharan   Disbursement 

Mehrin Ahmed Mahbub  Team Member 

Dipanwita Chakraborty  Team Member 

Nadia Sharmin  Environmental Safeguards Specialist 

Nafisa Rusmila  Team Member 

Mahmuda Nusrat Hussain  Team Member 

Paul Schapper  Team Member (Consultant) 

Peter‐Armin Trepte  Team Member (Consultant) 

Joseph Fagan  Team Member (Consultant) 

Omar Khandaker   Team Member (Consultant) 

Md. Rafiqul Islam  Team Member (Consultant) 

A.N.M. Mustafizur Rahman  Team Member (Consultant) 

S M Hafiz Al Mamun  Team Member (Consultant) 

The World Bank Public Procurement Reform Project II ( P098146 )

Page 43 of 52

 

       

B. STAFF TIME AND COST 

Stage of Project Cycle Staff Time and Cost 

No. of staff weeks  US$ (including travel and consultant costs) 

Preparation 

FY06  2.273  10,213.96 

FY07  21.345  159,117.93 

FY08  0    34.41 

Total  23.62  169,366.30  Supervision/ICR 

FY08  21.954  94,351.73 

FY09  29.127  110,014.91 

FY10  31.772  91,176.86 

FY11  33.714  103,110.60 

FY12  26.115  103,030.96 

FY13  20.782  122,950.69 

FY14  10.763  32,582.22 

FY15  9.506  25,472.67 

FY16  28.106  207,418.49 

FY17  13.216  113,733.66 

FY18  3.634  68,639.56 

Total  228.69  1,072,482.35    

   

   

Page 44 of 52

ANNEX 3. PROJECT COST BY COMPONENT 

   

Components Amount at Approval 

(US$M) Actual at Project Closing (US$M) 

Percentage of Approval 

Component 1: Furthering Policy Reform and Institutionalizing Capacity Development 

21.40  21.40  100.00 

Component 2: Strengthening Procurement Management at Sector Level and CPTU/IMED 

15.90  10.35  65.09 

Component 3: Introducing e‐Government Procurement (e‐GP) 

30.20  33.12  109.67 

Component 4: Communication, Behavioral Change, and Social Accountability 

5.40  4.87  90.19 

Total   72.90   69.74  95.66 

  

   

Page 45 of 52

ANNEX 4. EFFICIENCY ANALYSIS 

 1. The costs incurred to achieve project objectives were reasonable in terms of the benefits achieved (as described in sections I–V), and the ‘value for money’ given the high probability of sustaining and building on the project outcomes of strengthening the public procurement system and improving the performance of the four target agencies (see section IIC). Because the project results could not be fully quantified in monetary terms, there was no calculation of an economic rate of return. Nevertheless, beyond the achievements made in terms of efficiency, transparency, and competitiveness, the other major benefits of the project is the sustainability of major interventions, that is, building the institution for regulating public procurement that is fully funded from the Government’s  own  resources  (CPTU);  establishing  the  e‐GP  system  that  is  becoming  self‐sustainable  by generating  its own revenues greater than expense; and institutionalizing procurement management capacity within the country using collaboration of local institutes with the internationally reputed organizations. Despite such achievements, there are still areas that need improvements, as summarized in the following paragraphs. 

2.  Overall  system efficiency  in  public  procurement  had  improved with  this  intervention  of  PPRPII.  The country has one uniform system for all its public procurement organizations regardless of the sector, resulting in  consistency  of  documentation  throughout  the  entire  procurement  cycle.  This  streamlined  process  and uniformity  of  documents  also  helped  the  bidding  community  in  reducing  bid  preparation  time  for  different organizations. The end‐line evaluation shows an overall satisfaction level of about 69 percent in the use of public funds with  variations  as  follows  in  the  type of  stakeholders:  bidding  community  ‐  76 percent,  procurement officials ‐ 78 percent, civil society ‐ 48 percent, and media professionals ‐ 30 percent.  

3.  Respondents agreed that the improved delegation of approving authority in the later part of the project, and the sub‐delegation of that authority within organizations, speeded up the approval process in general, in particular, reference to the contract decisions made at decentralized levels or within the agency level. Also, this has  been  clearly  demonstrated  through  reduction  of  procurement  processing  time  in  the  results  indicators. Nevertheless, still there are major issues of procurement delays, especially in the large‐value contracts requiring approval of the ministry and/or cabinet. Also, the propensity to push decisions to higher‐than‐necessary levels continues, thus increasing the time taken for approval.  

4.  Introduction of e‐GP has contributed to substantial improvements in improving the overall efficiency of the system, with specific  reference to reducing  inappropriate/coercive/collusive bidding practices,  improving speed  of  the  procurement  process,  significantly  reducing  the  number  of  complaints,  and  reducing  overall transaction costs. An analysis done for the four key agencies shows a savings range between 13 percent and 20 percent compared with the traditional tendering practices. 

5.  Overall, the complaints handling mechanism has built confidence levels, especially with the independent review panel mechanism. Review shows that in about 45 percent cases, the decision of this review panel was in favor of the bidders while about 55 percent was in favor of the procuring entities. This is a reasonable signal that the system is functioning well. Nevertheless, results also show that there are issues in dealing with complaints at some of the implementation agencies’ level, particularly in reference to the soft sectors, with some variations for the other sectors. The mechanism needs improvement for those agencies. 

6.  Self‐sustainability of the e‐GP system has increased substantially over time. The e‐GP system‐generated revenues have been exceeding the expenses being incurred by the system. Earnings are as follows: FY14: US$1.8 million;  FY15:  US$4 million;  FY16:  US$5 million;  FY17:  US$8.8  million  (sale  of  bidding  documents:  US$7.67 million; registration of bidders: US$0.75 million; and renewal registration: US$0.38 million). Average annual cost 

Page 46 of 52

of operating and managing the system is about US$2.5 million. This clearly demonstrates that the system is self‐sustaining. 

7.  In  conclusion,  it may be  said  that  though PPRPII made  substantial  contributions  in bringing  about  a systemic change in the public procurement environment of the country, there are still systemic issues that affect the efficiency gains. It has been demonstrated that some of the problems can be effectively addressed by the procuring entities themselves, or by their controlling ministries, simply through greater respect for and sincerity toward current procurement laws/rules.  

 

Page 47 of 52

 

ANNEX 5. DISBURSEMENT LINKED INDICATORS 

I: Improving procurement performance by using e‐GP in the Target Agencies 

DLI  DLI Target (Number of bids)/DLI Value (US$, millions) per Target Agency DLI Verification 

Protocol 

DLI Period Period 0 

(July 1, 2012–June 30, 2013) 

Period 1 (July 1, 2013–December 31, 

2013) 

Period 2 (January 1, 2014 –June 30, 2014 

Period 3 (July 1, 2014–June 30, 2015) 

Period 4 (July 1, 2015–June 30, 2016) 

 

DLI 1: Minimum number of bids invited in NCB using e‐GP by each of the Target Agencies 

          Definition: All bids invited under NCB across the target agency regardless of location of its procuring entities (HQ, districts, and sub‐districts) will be eligible.   Source/Verification: The target agency’s e‐GP/PROMIS cell reconciled data/reports based on actual invitations of bids by various procuring entities. The procurement monitoring coordinator of the target agency will report the DLIs achievement to the 

RHD  100/ 0.20  400/0.20  1,000/0.20  2,400/0.20  3,200/0.20 

LGED  100/0.30  400/0.30  1,000/0.30  2,400/0.40  3,200/0.40 

BWDB  60/0.19  120/0.19  300/0.19  720/0.19  960/0.19 

REB  8/$0.06  15/0.06  40/0.06  96/0.06  128/0.06 

           

Page 48 of 52

CPTU for validation by the Association. The DLIs will also be verified by an independent consultant contracted by the recipient. 

II: Improving procurement performance monitoring using PROMIS by the Target Agencies 

DLI  DLI Target (Number of bids) and DLI Value (US$, millions) for Each Target Agency DLI Verification 

Protocol 

DLI Period Period 0 

(July 1, 2012 – June 30, 2013) 

Period 1 (July 1, 2013 – December 31, 

2013) 

Period 2 (January 1, 2014 – June 30, 2014 

Period 3 (July 1, 2014 – June 30, 2015) 

Period 4 (July 1, 2015 – June 30, 2016) 

 

DLI 2: Minimum number of tenders entered into published PROMIS report, with procurement performance indicators covering various stages from bid invitations to award of contracts 

          Definition: Monitoring of procurement steps forward for all bids invited under NCB during the corresponding period of the respective DLIs across the target agency regardless of location of its procuring entities (HQ, districts, sub‐districts). Source/Verification: The target agency’s e‐GP/PROMIS cell reconciled data/reports based on actual invitations of bids by various procuring entities. The procurement 

RHD  200/0.20  800/0.20  1,200/0.20  2,800/0.20  3,600/0.20 

LGED  200/0.30  800/0.30  1,200/0.30  2,800/0.30  3,600/0.30 

BWDB  120/0.19  240/0.19  360/0.19  840/0.19  1,080/0.19 

REB  16/0.06  30/0.06  45/0.06  112/0.06  144/0.06 

Page 49 of 52

DLI  DLI Target (Number of bids) and DLI Value (US$, millions) for Each Target Agency DLI Verification 

Protocol 

monitoring coordinator of the target agency will report DLIs to the CPTU for validation by the Association. The DLIs will also be verified by an independent consultant contracted by the recipient. 

 

Page 50 of 52

ANNEX 6. BORROWER, CO‐FINANCIER AND OTHER PARTNER/STAKEHOLDER COMMENTS 

  

Government of the People's Republic of Bangladesh Ministry of Planning 

Implementation Monitoring & Evaluation Division (IMED) Central Procurement Technical Unit (CPTU) 

Sher‐e‐Bangla Nagar, Dhaka‐1207 Tel: 9144252‐3, Fax: 9180968, E‐mail: info@cptu.gov.bd; Website: www.cptu.gov.bd

 21.00.0000.367.14.981.17.425                       17 December 2017  Subject: Comments on Implementation Completion and Result Report (ICR): Public Procurement Reform Project II (P098146) [PPRP II: Cr. 58180, 52420 and 43500‐BD]  The undersigned is directed to inform you that the draft ICR on PPRP II project has been reviewed by the CPTU. The CPTU has agreed almost on all assessment on implementation. However, the followings are the observations on the ICR:  (1) In paragraph 24, line 4, Clause (i): the word eighteen will be replaced by seventeen. Line 5, Clause (ii): the words training for 5 days will be added after e‐GP. In line 8, first word Government will be replaced by Governance.  (2) In Table 3, after paragraph 25, Figures put in Column 2 and 3 will be replaced as under:  

Capacity Development Programme Type  # of Beneficiaries  Comments 

  14083  17 topics…. 

  6414   

  143   

  103   

  No Change  The following words will be deleted “3 Week Training top performer &” 

 (3) In paragraph 34, line 8: 2012 will be replaced by 2011;  (4)  In  paragraph  40,  from  line  4  onward  the  paragraph  will  be  reconstituted  as:  “The  key  activities included: conducting 99 events on procurement reforms including 64 Future Search Conference at District level,  National  Level  Launching event of  Social  awareness program, National  Level  Launching of  e‐GP having Prime Minister  as  Chief  guest  covering over 5,700 participants;   convening 64 e‐GP awareness workshops at district  level with over 2,400 participants, establishing 64 Government and Contractor’s Forums (GCF) covering over 3391 PEs and tenderers, and organizing four e‐GP workshops for 44 registered Bank’s in the e‐GP system, one at the national level in Dhaka and three in three were held in the Divisional Headquarters e.g. Sylhet, Rajshahi and Khulna. The GCF provided an informal platform for GOB officials and bidders to share information and experience including issues and resolutions about procurement and e‐GP  system.  BCCP  also  developed  a  mobile  app,  produced  an  e‐GP  theme  song,  videos,  radio  and 

Page 51 of 52

television commercials, TV talk shows, success story videos, info graphics; disseminated mobile SMS, TV scrolling messages, email and on line marketing and created two digital billboards in Dhaka that displays on‐line  live  procurement  data with  a  direct  feed  from  the  e‐GP  platform  and  conducted  opinion  and satisfaction  surveys.  CPTU  produced  newsletters, managed  social media,  arranged  TV  talk‐shows  and numerous news, articles in media on public procurement issues.” (5)  In  paragraph  41,  the  second  last  sentence  will  be  reconstituted  as:  “BIGD  held  four  divisional workshops, produced two documentaries on citizen engagement, formed and trained citizen committees and got monitored a number of public works projects and distribution of school text books.”  (6) In paragraph 42, line 5: the word attend will be replaced by attended by CPTU and Bank officials.   You are kindly requested to instruct the concerned wing to forward these comments to the World Bank for incorporating into the ICR for finalizing the same.  

              Shish Haider Chowdhury 

Director (Coordination and Training) Tel: 9144232 

Secretary Economic Relations Division Ministry of Finance Block No. 8, Room No. 3 Sher‐e‐Bangla Nagar Dhaka   Copy to:  

1. Ms. Mahmuda Begum, Additional Secretary, ERD; 2. Dr. Zafrul Islam, Lead Procurement Specialist and Task Team Leader, DIMAPPP; 3. PS to Secretary, IMED, Ministry of Planning 

         

Page 52 of 52

ANNEX 7. SUPPORTING DOCUMENTS 

 2002: The World Bank: Bangladesh Country Procurement Assessment Report 

2005: BD National Strategy for Accelerated Poverty Reduction  

2006: The World Bank BD: Country Assistance Strategy 

2006: BD Assessment of Readiness for Introduction of Electronic Bidding 

2007: Public Procurement Reform Project II‐ PPRPII (P098146)‐ Project Appraisal Document 

2007–2012: Procurement Management Information System Reports 

2007–2017:  The World Bank Project Implementation Status Reports 

2007–2017: Capacity Development Consultants Progress Reports 

2007–2017: M&E Consultants Semi‐Annual Reports 

2007–2017: Behavioral Change Communication Consultant’s Reports 

2011: BD Sixth Five‐Year Plan‐ Accelerating Growth and Reducing Poverty 

2011: The World Bank BD: Country Assistance Strategy 

2013: PPRPII Additional Financing (P132743)‐ Project Appraisal Document 

2013–2017‐ Quarterly e‐Procurement Management Information System (e‐PMIS) Reports  

2013: PPRPII Additional Financing (P132743)‐ Project Appraisal Document 

2016: BD Seventh Five‐Year Plan‐ Accelerating Growth and Empowering Citizens  

2016: The World Bank BD: Country Partnership Framework 

2016: PPRPII Second Additional Financing (P158783)‐ Project Appraisal Document 

2016: CPTU restructuring and e‐GP Study Report 

2017: Consultant’s Citizen Engagement Report 

2017: Consultant’s End‐Line Evaluation Report 

 

Recommended