Dr. Dan Patterson PMP, Acumen CEO Improving Schedule
Quality with Acumen Fuse
//
//
Agenda
! Overview of Acumen Fuse ! Schedule diagnostics ! Advanced logic analysis ! Project forensics ! Q&A
February 4, 2013 2
//
// Acumen
! Project Management Software ! Focus on analytics
! Core Concepts ◦ Project success requires a sound plan ◦ Forecasting requires risk consideration
! Recognition ◦ 2012 Planning Innovation of the Year
◦ 2012 Inc.500 Award
Proven Project Analytics
Product Offerings
Risk Workshops
Acumen Platform
Software Training
Realistic Scheduling
Critiqued
The Base
Risk-Adjusted
Optimized
Team-Aligned // S5
// S4
// S3
// S2
// S1
February 4, 2013 3
//
//
Build Schedule Basis
Acumen Fuse®: Project Diagnostics
Acumen Risk™: Risk Analysis & Register
Acumen 360™: Project Optimization
Team Validation and Buy In
S1 // Schedule Basis
S2 // Critiqued
S3 // Risk-Adjusted
S4 // Optimized
S5 // Team Approved
Acumen Fuse Diagnostics ! Improved Schedule Quality
Acumen 360 Scenario Generation ! Acceleration/Deceleration
Acumen Risk Risk Analysis ! Simplified Cost/Schedule
Acumen Software Summary
February 4, 2013 4
//
//
//
Better Planning = Project Success
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Prob
ability of O
n-‐Time Co
mple4
on
Fuse Schedule Index™
Proven Correlation
4 February 2013 6
//
//
! Benefit: ◦ Insight into shortcomings ◦ Improved project quality ◦ Reliable project plans
! Audience: ◦ Schedulers / Planners ◦ Project Controls ◦ Forensic Analyzers
! Features:
◦ Industry standard metrics ◦ Forensic analysis ◦ Dashboards & reports ◦ Industry Benchmarking
Acumen Fuse® Project Diagnostics
February 4, 2013 7
Acumen Fuse® pinpoints, and more importantly, resolves project shortcomings in a matter of minutes.
//
//
Types of Project Metrics
Schedule
• Logic • Float • Dura>on
Cost
• Overrun • Capacity • Burn rates
Performance
• Status • Completed • Delayed
Characteris>cs
• Level of detail • Constrained • Riding Data Date
Earned Value
• CPI/SPI • Trending • Earned schedule
Risk
• Exposure • Hot spots • Hidden paths
Fuse Metric Libraries
• Project management best practices • Industry/corporate standards: PMI, AACE, NDIA
• Fuse-specific: Logic Density™, Hotspot, Redundancy
• Compliance: DCMA 14 Point, DoD
• Create your own!
4 February 2013 8
//
//
Customizable Metrics Fuse Metric Editor
4 February 2013 9
//
//
Acumen-Specific Metrics
Logic Density™ • Measure of complexity/completeness
Logic Hotspot™ • Timely start?
Float Ra>o™ • Degree of flexibility per day of work
Redundancy Index™ • Non-‐needed logic
Advanced Project Insight
Finish Compliance™ • Accurate measure of performance
Insufficient Detail™ • Ac>vity V project dura>on
Milestone Ra>o™ • Detail V repor>ng
Broad Risk Range • Check for erroneous risk input
4 February 2013 10
//
//
Baseline Compliance Index™ Performance Analysis
4 February 2013 11
//
//
Finish Compliance Index™
0% 20% 40%
60%
80%
100%
Execution Performance
4 February 2013 12
//
//
! Circular logic ! Logic Density™ ! Redundancy Index™ ! Logic Sensitivity™ ! Out of sequence ! Dangling activities
Advanced Logic Analysis
February 4, 2013 13
//
//
Logic Sensitivity™
! Validation of logic ! Delay analysis
The Nudge Test
February 4, 2013 14
//
//
! Pinpoint changes ! Contractor updates ! Determine trends ! Calendar manipulation ! New Window
Analysis™
Project Forensics
February 4, 2013 15
//
//
! Review & address issues directly in Fuse
! Push updates directly back to P6 and MS Project
! Analyze impact of cleanse using Fuse metrics!
Schedule Cleansing
February 4, 2013 16