ELI-NP Conceptual Design Report
Daniel Ursescu,Coordinator for Research Activities 1: ELI-NP Laser
INFLPR, Romania
Conceptual Design Report:Ti:Sa Solution
Multi-PWlaser
Technical areas
Laser experimenta area
Solution based on Apollon design
Goals for this workshop
1) analyze the bottlenecks and associated risks, knowing that: - the timeline for the project is January 2012 - August
2015,
- we prefer a turn-key laser system, due to commercial conditions such as guarantees
- UE offset conditions might apply
2) initialize a review of the cost evaluation (80 Meuro)
3) to confirm the existing solutions (and identify new technological oportunities)
Bottle-necks
List of botlenecks
a)
b)
c)
...
Bottle-neck ................. risks:
- present technology limit:
- time-line development:
- design:
- demonstrator:
- provider:
- budget:
- back-up:
ProgramDANIEL URSESCU INFLPR ELI-NP laser conceptual design report
RAZVAN DABU INFLPR About the possibility to build a 10-PW laser for ELI-NP until 2015
JEAN PAUL CHAMBARET (30 min) ILE Overview of the Apollon project
CHRISTOPHE SIMON-BOISSON Thales Optronique Technologies for multi-PW laser systems
TODD DITMIRE (30 min) National Energetics High energy pump laser development for 10 PW beamlines
TAE MOON JEONG APRI, GIST 0.1 Hz 1 PW Ti:sapphire Laser System
CONSTANTIN HAEFNER LLNL High Peak power short pulse laser technologies for ELI-NP
FRANCK FALCOZ Amplitude Technologies
Industrial approach and identification of risks for multi-PW laser systems
CURTIS DALE FREDERICKSON Continuum OPCPA pump source
CHRISTOPHER EBBERS LLNL Advanced pump laser technologies for high repetition rate Petawatt lasers
NATHAN CARLIE SCHOTT North America Laser glass development at SCHOTT
CATALIN MIHAI TICOS INFLPR Beam transport in vacuum: main issues and possible solutions
VALER TOSA INCDTIM Cluj-Napoca Propagation effects of femtosecond laser pulses in ionizing gas media
Bottle-neck ...gratings... risks:
- present technology limit: 0.15 J/cm^2, 90 cm*70 cm
- needed: higher damage threshold
- time-line development: until Sept. 2013
- design: exists at ILE
- demonstrator: up to 50 mm
- provider: JY, LLNL, PGL
- budget: 150 Keuro each
- back-up: existing JY, LLNL or PGL, 2 times more expensive
Recommended