Facilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT
Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
Jim Berg AIA DIRECTOR OF FACILITIES CONSTRUCTION
February 2019
1
ADDITIONS AND RENOVATION
PROJECTS IN CONSTRUCTION
2
OLIVER WENDELL HOLMES HS FINE ARTS NEW AUDITORIUM
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke Contract Amount - $32,014,460 Construction Period – June 2017 – January 2019 Construction Status – 97% Package 2 (Building) Project Scope – Fine Arts Building Replacement
Substantial Completion Interior January 11, 2019.
Rendering of New Auditorium 3
OLIVER WENDELL HOLMES HS FINE ARTS NEW AUDITORIUM
4
OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM
Bus Loop
Bandhall
Auditorium
Auditorium Lobby
5
SAM RAYBURN MIDDLE SCHOOL Building Replacement
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction
Superstructure work in progress.
GMP Amount – $13,900,000Tentative Construction Period - June 2018 - August 2019Construction Status - 40%Project Scope - Building Replacement (Gym, Band and Library)
6
SAM RAYBURN MIDDLE SCHOOL Building Replacement
New Library Location
Band Hall and Courtyard New Gym and Boys Lockers Location
7
SAM RAYBURN MIDDLE SCHOOL Building Replacement
Gym Building - Lower Level StairwellGym Building lower level
New Library - Foundation Band Hall
8
F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy
Architect – Chesney Morales Partners, Inc. Project Architect – Richard Morales NISD Project Manager – James Evans Contractor – Breda Construction, Inc. Contract Amount - $468,095 Construction Period – June 2018 – March 2019 Construction Status – 60% Project Scope – Additional Student Canopy
Steel framing install in progress.
Rendering of Student Canopy 9
F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy
FlatworkCanopy Steel
Canopy Steel Canopy Steel
10
BRAUN STATION ELEMENTARY SCHOOL Cafeteria/Kitchen Renovations & Window Upgrades
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Thomas Curiel Contractor – WR Griggs Construction Co. Contract Amount - $2,671,000 Construction Period – June 2018 – February 2019 Construction Status – 95% Project Scope – Cafeteria/Kitchen Renovations and Window Upgrades
Substantially Complete in February 4, 2019.
11
BRAUN STATION ELEMENTARY SCHOOL Cafeteria/Kitchen Renovations & Window Upgrades
Kitchen Equipment Kitchen Equipment
Cafeteria - Serving Line Gates Serving Line
12
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – CGC General Contractors, Inc. Contract Amount - $4,249,000 Construction Period – June 2018 – August 2019 Construction Status – 40% Project Scope – Cafeteria / Kitchen Renovation
Kitchen renovation work in progress. Underground utilities in progress.
Rendering of Caf eteria Interior 13
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation
Aerial of Site
NEW KITCHEN ADDITION
RENOVATED
CAFETERIA
14
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation
Kitchen Exterior Kitchen Exterior Kitchen Interior
15
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Thomas Curiel Contractor – Webber Commercial Construction Co. Contract Amount - $2,784,000 Construction Period – June 2018 – February 2019 Construction Status – 95% Project Scope – Fine Arts Addition, Bus Canopy & Drainage Upgrades
Fine Arts Classroom & Interior Substantial Completion Jan.15, 2019Exterior Canopies, landscape & irrigation underway.
Rendering of Band Room Addition at Fine Arts Classrooms 16
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades
Aerial Vi ew of Campus17
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades
Existing Front Entrance and Fine Arts Classrooms
Rendering of Band Room Addition at Fine Arts Classrooms
18
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades
Fine Arts Building - Exterior Canopies
CanopiesFine Arts Building - Exterior
19
TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Chris Parker Contractor – Central Builders, Inc. Contract Amount - $3,892,000 Construction Period – June 2018 – February 2019 Construction Status – 92% Project Scope – Cafeteria / Kitchen Renovation
Kitchen Renovation punch inspections in progress.Completion scheduled February 18, 2019.
Renovated Cafeteria 20
TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation
Kitchen Area - Equipment Kitchen Area - Serving Lines
Office Area Kitchen Equipment
21
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation
Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – WR Griggs Construction Contract Amount - $6,141,000 Construction Period – May 2018 – August 2019 Construction Status – 55% Project Scope – Science Classroom, Library Renovation and Classroom Addition
Plumbing, HVAC & Electrical in progress. Building Addition Framing & Masonry in progress.
22
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation
Site Plan23
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation
Classroom Addition Prep Room
Science Classroom Renovation Science Classroom Renovation
24
2014 BOND PROJECTS
IN
BID/DESIGN PHASE
SUMMER 2018
25
KALLISON RANCH AREA MIDDLE SCHOOL New Middle School
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke General Contractors, LLC Construction Budget - $48,000,000 Construction Period – July 2019 – May 2021 Status - Schematic Design in progress Project Scope – New Middle School
26
RANCHO DEL LAGO AREA ELEMENTARY SCHOOL New Elementary School
Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget – $23,000,000 Construction Period – March 2019 – May 2020 Status – Approval of Contractor to be recommended at February Board Project Scope – New Elementary School
Rendering of Rancho Del Lago Elementary School 27
NORTHSIDE NATATORIUM Pool Replacement
Architect – Nextgen Architects
Contractor – Henock Construction, LLCContract Amount - $2,430,000
Construction Period – March 2019 – July 2019Status – Demolition (March 15, 2019)
Existing Pool
Project Scope – Pool Replacement
NISD Project Manager – James Evans
28
NORTHSIDE SPORTS GYM PLAZA OF INFLUENCE PYLONS
Flanking Steel Pylons
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Thomas Curiel Contractor – Spaw Glass Contract Amount - $350,000 Construction Period – March 2019 – April 2019 Status – Construction Project Scope – Plaza Pylons
29
2014 BOND PROJECTS
IN
BID/DESIGN PHASE
SUMMER 2019
30
JOHN MARSHALL HIGH SCHOOL Library Upgrades
Architect – Garza Bomberger & Associates
Contractor – TBD Construction Budget - $3,000,000 Construction Period – Spring 2019 – Spring 2020 Status – Construction Drawings in Progress
Project Scope – Library Addition & Renovation
Interior View
NISD Project Manager – James Evans
31
NORTHSIDE ALTERNATIVE MIDDLE SCHOOL Science Classroom Addition
Architect – C.J. Lammers & Associates Project Architect – Chris Lammers NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $600,000 Construction Period – June 2019 – October 2019 Status - Bidding
Project Scope – Science Classroom Addition & Renovation
32
NEW CONSTRUCTION
PROJECTS IN DESIGN2018 BOND PROJECT
33
"GALM ROAD AREA" HIGH SCHOOL
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – James Berg Contractor – Joeris Contractors Construction Budget - $112,000,000 Construction Period – February 2020 – June 2022 Project Scope – New High School Schematic Design in progress
34
2018 BOND PROJECTS
ADDITIONS/RENOVATIONS
IN DESIGN
35
2019 SECURITY LOBBIES FOR 21 CAMPUSES
Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $2,980,000 Construction Period – June 2019 – December 2019 Status - Approval of Contractor to be recommended at February Board. Project Scope – Security Lobbies
Behlau ES Fisher ES Martin ESBurke ES Galm ES Murnin ESCarson ES Hatchett ES Oak Hills Terrace ESDriggers ES Langley ES Ott ESElrod ES Lewis ES Raba ESEvers ES Lieck ES Westwood ESFernandez ES Martin ES Northside Police Department
36
GLENOAKS ELEMENTARY SCHOOL Library and Classroom Building
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Contract Amount - $4,000,000 Construction Period – June 2019 – July 2020 Status – Bidding Project Scope – Library and Classroom Building
Library - Reading AreaFront Entry37
NORTHWEST CROSSING ELEMENTARY SCHOOL Cafeteria / Kitchen Renovation
Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $2,000,000 Construction Period – June 2019 – December 2019 Status - Bidding
Project Scope – Cafeteria / Kitchen Renovation
Cafeteria Proscenium - Prespective View 38
PAT NEFF MIDDLE SCHOOL Cafeteria Upgrades
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Thomas Curiel Contractor – TBD Construction Budget - $3,200,000 Construction Period – June 2019 – February 2020 Status - Master Plan and Schematic Design in progress
Project Scope – Cafeteria Upgrades
39
MEADOW VILLAGE ELEMENTARY SCHOOL ALE & Mechanical Upgrades
Architect – Chesney Morales Partners, Inc. Project Architect – Richard Morales NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $3,400,000 Construction Period – June 2019 – November 2019 Status - Approval of Contractor to be recommended at February Board.
Project Scope – ALE and Mechanical Upgrades
40
WILLIAM P. HOBBY MIDDLE SCHOOL Bus / Student Covered Walkway
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $2,800,000 Construction Period – June 2019 – December 2019 Status - Bidding
Project Scope – Bus / Student Covered Walkway and Front Entry
Canopy Rendering
41
SANDRA DAY O'CONNOR HIGH SCHOOL Agricultural Facility Upgrade
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $1,275,000 Construction Period – March 2019 – July 2019 Status - Approval of Contractor to be recommended at February Board.
Project Scope – Agricultural Facility Upgrade
New Configuration of Building P 42
SANDRA DAY O'CONNOR HIGH SCHOOL Flooring Replacement
Architect – Callins Watts Sendejo Architects Project Architect – Robert Watts NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $150,000 Construction Period – June 2019 – August 2019 Status - Approval of Contractor to be recommended at February Board.
Project Scope – Flooring Replacement
43
OLIVER WENDELL HOLMES HS & JOHN JAY HS Paint Booth Replacement
Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $300,000 Construction Period – June 2019 – August 2019 Status - Approval of Contractor to be recommended at February Board.
Project Scope – Paint Booth Replacement
44
2019 DOOR HARDWARE PROJECT Various Campuses
Architect – Huckabee Associates Project Architect – Jeff Rodriguez NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $461,000 Construction Period – June 2019 – August 2019 Status - Approval of Contractor to be recommended at February Board.
Project Scope – Door Hardware
R.R. Cable ES Leon Valley ES Northwest Crossing ES
William J. Thornton ES Eduardo Villarreal ES Anson Jones MS
45
ROOFING PROJECTS
46
2016 Hail Damage Roofing Projects
Phase IV - In Construction
Phase I - Complete
Beard Elementary School
Carnahan Elementary School
Clark High School
Stevenson Middle School
Carlos Coon Elementary School
Elrod Elementary School
Phase II – Complete
Esparza Elementary School (Closed out)
Nichols Elementary School (Closed out) Connally Middle School (Closed out)
Howsman Elementary School (2014 Bond) Leon Valley Elementary School (Closed out)
Scarborough Elementary School (Closed out)
Alternative ES & MS - North (Closed out)
Burke Elementary School (Closed out)
Brauchle Elementary School
Leon Springs Elementary School
Raba Elementary School
Phase III – In Construction
Burke Elementary School (2014 Bond)
Clark High School
Helotes Elementary School
O’Connor High School (1st Phase) Rhodes Elementary School
Sul Ross Middle School
Steubing Elementary School
Portable Roofs – Phase II (102)
Vale Middle School
Zachry Middle School Driggers Elementary School
Briscoe Middle School
Colonies North Elementary School Hoffmann Elementary School Scobee Elementary School Family Engagement Center
Northwest Crossing Elementary
Henderson Elementary School Knowlton Elementary School
Maintenance Building (2014 Bond)
LIST OF SC HOOLS
Portable Roofs -(Substantial Completion)
South Transportation Station Fernandez Elementary School
MEP Hail Damage -Various Campuses (54)
47
2016 Hail Damage Roofing Projects
Phase V - Design
O'Connor High School (2nd Phase)
Brandeis High School (1st Phase)
Stinson Middle School
Kuentz Elementary School
John Jay High School(2014/2018 Bond)
Hobby Middle School
Phase VI – Future
Support Services Center
Oak Hills Terrace Elementary School Kelly Smith Technology Center
Taft High School Northside Activity Center
North Transportation Station
Pease Middle School
Health Careers High School
Northside Tennis Center
Jefferson Middle School
John Glenn Elementary School(2014 Bond)
Mireles Elementary
Brennan High School Holmes High School
Rhodes Transportation Center Ward Elementary School
McDermott Elementary School
Mead Elementary School
Myers Elementary School
Adams Hill Elementary School(2018 Bond)