View
5
Download
0
Category
Preview:
Citation preview
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
1
Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public
Construction Projects
Jesper Kranker Larsen1, Geoffrey Qiping Shen2, Søren Munch Lindhard3, and Thomas Ditlev Brunø4
1 Ph.D. Fellow, Aalborg University, Department of Mechanical and Manufacturing Engineering, Aalborg East, 9220; jkl@m-tech.aau.dk. 2 Professor, The Hong Kong Polytechnic University, Department of Building and Real Estate, Hung Hom Kowloon, Hong Kong; bsqpshen@polyu.edu.hk. 3 Assistant Professor, Aalborg University, Department of Mechanical and Manufacturing Engineering, Aalborg East, 9220 Denmark; lindhard@m-tech.aau.dk. 4 Associate Professor, Aalborg University, Department of Mechanical and Manufacturing Engineering, Aalborg East, 9220 Denmark; tdp@m-tech.aau.dk.
Abstract Due to the loss of financial resources and the need to optimize projects, academics, politicians and the
construction industry have become increasingly aware of the challenges presented by the frequent time and
cost overruns and reduced quality level of construction projects. The purpose of this study is to analyse the
factors that project managers experience as having the greatest effect on time, cost and quality, and to
discover whether the factors’ effects are significantly different from each other. A questionnaire with 26
factors identified from interviews was sent to the full population of publicly employed project managers.
Factors were ranked by using the relative importance index and tested for significant differences by applying
the Friedman´s test with the Wilcoxon´s test as post-hoc analysis. From the analysis, the most affecting
factor associated with time was found to be unsettled or lack of project funding. For the cost related factor,
errors or omissions in the consultant material, was the most important. Finally, the quality related factor was
errors or omissions in construction work. The main conclusion of this research showed that the project
schedule, budget and quality level are significantly different affected. The project manager therefore cannot
handle such critical issues by only focusing at schedule or budget related complication, either can the project
manager assume that time, cost and quality are equally affected.
Keywords: Construction Management, Cost Overrun, Denmark, Quality Level, and Schedule Delay.
This is the Pre-Published Version.http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000391
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
2
Introduction Delay in construction projects, cost overrun and quality level have long been common problems in the
construction and engineering sector. In particular, time and cost increases in large public construction
projects seem to be a global phenomenon affecting five continents, with no reduction in the last 70 years and
an average cost overrun of 28 % (Flyvbjerg et al. 2002; Flyvbjerg et al. 2003). Optimistic expectations to
time and budget planning has as an consequence been found to decrease the level of quality and productivity
during the construction stage and in the final end-product (Park et al. 2010).
To reduce such overrun the existing body-of-knowledge tends to focus on critical success factors
associated to time and cost as individual concepts of different project types and geographical regions with
little frame of reference. Aibinu and Odeyinka (2006); Al‐Kharashi and Skitmore (2009); Kazaz et al. (2012)
all study causes of schedule delays and effects to the time concept. Iyer and Jha (2005); Shane et al. (2009)
study cost escalation factors in construction projects as the cost related concept. And finally Kaliba et al.
(2009); Koushki et al. (2005); Olawale and Sun (2010) study the cost and time concepts as interrelated,
which fits Hancher and Rowings (1981) definition of a successful project as the ability to meet both budget
and deadline according to the contract. However, in addition to previous conducted studies we need to
include quality into the debate of time and cost as interrelated concepts since all three concepts have been
central in the construction literature, also known as the “iron triangle”. Comprehensive studies focusing on
time, cost and quality as interrelated concepts are therefore essential to be able to demonstrate significant
differences between the three concepts in the “iron triangle” and to extend the existing body-of-knowledge.
A potential solution to the critical success factors effect on construction projects is increased pre-project
planning effort (Yang et al. 2012). The benefits of using pre-project planning is find to be increased profit, a
reduction of risk and an increased quality (Barker et al. 2004; González et al. 2008; Hanna and Skiffington
2010; Hwang and Ho 2011). The effort spent in this early project stage therefore affects the level of success
during the start-up, detailed design and construction stage (Chang et al. 2010; Yang and Wei 2010). These
results are further supported by Thomas and Ellis Jr (2007) who used simple pre-project planning methods to
reduce the preliminary construction duration by up to 30 %. Hanna and Skiffington (2010) argue for an
increased construction planning level allow the contractor to be more proactive to critical factors which
affect the project compared to a reactive approach. The positive effects of realistic planning of cost and time
before design, as well as its success during the construction stage is according to Gibson Jr et al. (2006)
improved project outcome, user satisfaction and reduced project cost and duration. Identifying and test for
significant differences of the impacts at time, cost and quality from the critical success factors are therefore
vital to deal with the factors in the pre-project planning process to secure the project outcome.
The aim of this paper is thus:
To present the factors that have the most negative effect on time, cost and quality
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
3
To test if a factor affects time, cost and quality significantly different from each other
If its affects significant different - to identify which of the elements in the “iron triangle” which
affect significantly different
The tested H0 hypothesis is thus based on the definition of a successful project: time, cost and quality
should be affected similar by any factor. HA hypothesis is that there is a significantly different impact. The
geographic context and empirical basis of the study is focusing at the Danish publicly funded construction
sector.
Literature review Despite several studies related to cost overrun since Arditi et al. (1985), the definition of cost escalation is
not always clearly defined. Flyvbjerg et al. (2002) define cost escalation as the gap between the actual cost
and the estimated cost. Actual cost is the actual accounted project cost after completion, and estimated cost is
the budgeted or forecasted project cost at the time of decision to start the project.
Contrary to cost overrun, the definition of time overrun is clearly articulated in literature. However, two
different definitions have been used. The most commonly used definition is presented by O’Brien (1976) as
the delay in time either beyond the agreed contract deadline or beyond the date the parties have agreed upon
for the delivery of a project. Among others, the studies conducted by Lo et al. (2006) and Assaf and Al-Hejji
(2006) use this definition. The second definition was proposed by Stumpf (2000), and states that a time
overrun is an act or event that extends the time to perform the task beyond the agreed contract deadline.
Sweis et al. (2008) use this definition.
Looking into how the literature defines quality provides answers that are less clear. According to Flynn et
al. (1994), quality is a distinction between input (the quality of management) and output (the quality of
performance). Fujimoto (1989) and Voss and Blackmon (1994) describe internal performance as the ability
to conform to required specifications, where Fynes and De Burca (2005) express external performance as the
level of quality-in-use of the end-product.
However, these definitions are debated in the construction sector due to difficulties in defining quality to
construction projects, based on lack of standardisation, size of projects and involved parties (Hoonakker et al.
2010). Loushine et al. (2006) reviewed 26 research papers associated to applied construction quality
definitions. The study provided five different definitions for quality: “meeting expectations of the customer”,
“reduced rework or defects”, “repeat business”, “conformance to ISO 9000 criteria” and finally “completion
on-time and within budget”. The definition of quality management is thus not a “controlling the construction
process”, but should be defined by the level of fulfilment of the project, according to the owner or end-user
expectations (Loushine et al. 2006).
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
4
This result is supported by Hoonakker et al. (2010) which state that a precise definition of quality
associated to the construction sector is difficult to define, and further point out that limited solid empirical
data on quality due to lack of an exact definition is to be found.
The level of success after project completion is thus not only based on time and cost based empirical
criteria, but is an individual weighing of time, cost and quality. Liu and Walker (1998) divide project success
definition into three categories: “project goals”, “satisfaction of the claimant(s)” and finally “perception and
awareness of different claimant(s)”. Project goals represent those regarding the contract agreed time, cost
and quality also known as the “iron triangle”. Long et al. (2004) define a successful project as one that is
completed within agreed contract budget and deadline, in accordance with required specifications, and to the
satisfaction of stakeholders. Similar related definition are also used by Avots (1969); Gaddis (1959); Handa
and Adas (1996); Kerzner (1998); Morris and Hough (1987); Olsen (1971); Trauner (1993); Tuman (1983);
Tuman (1986); Williams (1993).
However, the definition of project success is similar to quality challenging to define due to varying
opinions and requirements (Liu and Walker 1998).
Research method Quantitative surveys are designed to acquire information from individuals about themselves or about a
social unit to which they belong or with which they are involved (Rossi et al. 1983). In such processes, the
sampling method used, determines the level of information about the population, and its accuracy (Rea and
Parker 2012). To develop operational factors from the semi-structured interviews, each factor was
objectively evaluated into understanding, retention and application as suggested by Sekaran (1992).
Previously tested and used factor expressions from earlier published studies were also used to ensure clear
and comprehensible factor definitions (Forza 2002). To measure the impact of each factor on time, cost and
quality, all three elements were measured on an ordinal five point Likert scale (where 1 very low, 2 low, 3
medium, 4 high, 5 very high impact), similar to what is used by Doloi (2012), and a ‘don’t know’ option was
included to prevent respondent bias.
Data was collected using SurveyXact and sent by email in accordance with the ethical research standards
of the Danish Social Science Research Council (S.S.R.C. 2002). The data collection was based on the full
population of project managers employed by Danish public construction agencies, totalling four agencies.
Their educational backgrounds include architects, engineers and building surveyors. The chosen population
has both pros and cons, but was chosen since publicly funded construction projects represent some of the
most complex construction projects in Denmark which implies that a further generalization to less complex
public funded construction projects is possible. Further, the publicly employed project managers are the only
trade group which follow a public construction project from the beginning to the end.
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
5
The analysis was conducted using Statistical Package for the Social Sciences (SPSS), where a data review
was made to recode “don’t know” responses as “missing”. To check the reliability of the dataset, the
Cronbach alpha test was conducted. To be acceptable, values had to have a level of at least .7 (Kline 2013).
The Relative Importance Index (RII) was used to rank factors with an index range of 0.0 - 1.0 (see equation
1), the same method has been used by Aibinu and Odeyinka (2006) and Doloi et al. (2012).
(1) Relative Importance Index (RII) = ∑
∗
Total sum of each factor where 1 very low, 2 low, 3 medium, 4 high, 5 very high
Highest weight in this study 5 very high
Total number of respondents at each variable
To test for difference between time, cost and quality, a non-parametric approach was used. The strength
of such methods, is that they work by ranking data and then conducting the analysis on the ranks instead of
the actual data (Field 2009). Friedman´s test is applicable when ordinal scaled data contains more than two
related samples, as here where the same respondents have been used (Sekaran 1992). To follow up on
significant factors, a Wilcoxon signed-rank test was applied. To limit the number of follow-up tests and Type
I errors, the Bonferroni correction was used, where something was accepted as significant if its significance
level was less than α/the number of comparisons (Field 2009). To test the correlation between factors, the
Kendall tau test was used. This test is useful when small data sets with large numbers of tied ranks are
processed (Field 2009). According to Howell (1997), the Kendall tau test performs more accurate correlation
estimates than the Spearman test in these situations.
Identification of questionnaire factors To identify the applied factors that affect construction time, cost and quality a qualitative research
approach was initially adopted. An explorative semi-structured interview study was first conducted with in
total eight public agency employed project and property managers, where 20 factors were identified.
However, examination of an investigation of public construction projects overruns, carried out by the
National Audit Office of Denmark in 2009, led to the identification of six additional factors. A total of 26
factors were thus identified.
To support the 26 factors with existing research, a literature review was conducted to evaluate if previous
studies have used similar factor descriptions. The conducted review leads, to identification of 20 studies
which used similar factors as identified in the interview study (see Table 1). As great geographical
differences were expected regarding construction processes and complications we did not include further
factors from the literature. Furthermore the focus of the study was on the Danish public construction projects.
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
6
Why we did not consider factors from other geographical areas which are not represented in the Danish
construction industry.
Questionnaire categories External complications are conditions or circumstances that are beyond the control of the project
organization, such as delays or long process times by other public authorities, unpredictable soil conditions,
state of the market conditions, unpredictable project conditions and finally unpredictable weather conditions.
Complications related to contract are circumstances or inconsistencies in documentation shared by
partners. They include the use of selection and assignment criteria, errors or inconsistencies in project
documents, lack of requirement specifications in tender documents, lack of project structure or material and
unforeseeable authority requirements or restrictions.
Project management-related complications are human-related factors that the management manage to
secure a stable organization and process. Problems can include miscommunication between partners,
conflicts and disputes between partners, slow user decision making, change of partners in the project
organization, inexperienced or newly qualified construction supervisors, and inexperienced or newly
qualified consultants.
Project change-related complications are conditions or circumstances that derive from changing
requirements. They include errors or omissions in construction work, errors or omissions in the consultant
material, failure to identify needs, lack of preliminary examination before design or tendering, and late user
changes affecting the project or function.
Finance and scheduling complications are problems within project finance and scheduling. They include
optimistic expectations regarding time, cost, and quality, political focus on reduced project costs or time,
unsettled or lack of project funding, unsettled or lack of project planning, and the complexity or volume of
the project.
Results The questionnaire was sent to 111 potential respondents (see
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
7
Table 2), of whom 56 replied. This gives a response rate of 50.5 %. This is an acceptable response rate
according to Flynn et al. (1990), who argue for a minimum response rate of 50 % . The respondents’ mean
age was 51 (SD 11 years), where the oldest was 70 and the youngest 28 years old. Due to the high mean age,
the respondents’ experience is expected to be on a sufficiently high level to answer the questionnaire.
The general response frequency of such questionnaire studies in this research area is varying. For
example the response rate in Iyer and Jha (2005) study was 25 %; Al‐Kharashi and Skitmore (2009); Kaliba
et al. (2009) both experienced a response rate of 43 %; Olawale and Sun (2010) reported a response rate of
44 %; Kazaz et al. (2012) 47.7 % and Aibinu and Odeyinka (2006) 51 %. The response frequency of our
research (50.5 %) compared to previous studies presented above, is thus considered sufficient.
To validate the consistency of the questionnaire, each category was tested in relation to time, cost and quality (
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
8
Table 3). External cost was found to have a Cronbach alpha (α) less than .7, indicating questionable data
consistency and should then be cautiously considered. Four of the 15 tests were found to be acceptable (α
between .7 and .8) , and 10 of the 15 tests demonstrated a good level of consistency (α between .8 and .9)
(Kline 2013).
Ranking of factors Of the top five factors that affect time, FS3 (unsettled or lack of project funding) was found to be the
highest ranking (RII = .774). It was followed by EX1 (delayed or long process times by other authorities), FS4 (unsettled or lack of project planning), PC1 (errors or omissions in construction work) and PC3 (lack of identification of needs) indicated by their decreasing RII values (
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
9
Table 4 and Figure 1).
When it comes to factors that affect cost, PC2 (errors or omissions in the consultant material) is found to be the highest ranking (RII of .766). It is followed by CR2 (errors or inconsistencies in project documents), PC5 (late user changes affecting the project or function), PC4 (lack of preliminary examination before design or tendering) and PM6 (inexperienced or newly qualified consultants) indicated by their decreasing RII values (
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
10
Table 4 and Figure 1).
Of the factors affecting quality, PC1 (errors or omissions in construction work) was the highest ranked (RII of .688), followed by PM6 (inexperienced or newly qualified consultants), FS2 (political focus on reduced project costs or time) FS4 (unsettled or lack of project planning) and CR2 (errors or inconsistencies in project documents (
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
11
Table 4 and Figure 1).
Friedman´s test To test if the factors affect time, cost and quality to a significantly different degree, Friedman´s test was
conducted. Due to the definition of a successful project according to Long et al. (2004), we did not expect to find a significant difference in the impact of the various factors. To secure Friedman´s minimum sample size, 23 datasets with an α of .01 were required (Fahoome 2002), the smallest dataset in the test was 44 (see
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
12
Table 5). Out of 26 tests, 17 rejected the null hypothesis, and nine tests confirmed it (see
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
13
Table 5).
An examination of the survey categories reveals that the category “Project Management - PM” in five out
of six tests confirms the null hypothesis. The factors within this category thus affect time, cost and quality
differently from the other categories, as the factors within this category affect non-significantly different,
whereas the other categories factors affect to a significantly different extent, except factor CR1, CR4 and
FS2 which confirmed the null hypothesis.
Post-hoc analysis Following up on the factors rejecting the null hypothesis, a post-hoc analysis was conducted to find
patterns and connections within these factors that would otherwise remain undetected. The smallest data set in the tests was 44, why both the minimum requirement for the Wilcoxon test and the Kendall’s tau were obtained (20 and 15 α of .01 respectively) (see
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
14
Table 6) (Fahoome 2002; Sprent 1989).
33 of 51 tests found a significant difference and 18 tests found a non-significant difference. The effect size of all tests was positively correlated in the range from small to large effect size (.226 to .808). Ten of the 18 non-significant factor combinations in
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
15
Table 6 involve the combination time and cost, where factors EX2, EX4, EX5, CR5, PC3, PC4, PC5, FS1,
FS4 and FS5 demonstrate a non-significant difference of the impact on time and cost. These impacts were
further supported by the effect size (.569 to .808) for all of the ten combinations and thus represented a large
positive effect.
The second factor combination was between quality and time and was found in five out of the 18 non-
significant combinations EX3, CR2, CR3, PC2 and FS1. They had a medium to large positive effect (.407
to .588), thus a smaller degree of association than for time and cost.
The combination between quality and cost had the smallest degree of association found in the analyses. It
was only non-significant in three out of the 18 tests. The equal impact of quality and cost was found for
factors PM3, FS3 and FS4 with a large positive effect (.536 to .575).
Discussion Comparing these results with previous studies done byKaliba et al. (2009); Koushki et al. (2005);
Olawale and Sun (2010), time, cost and quality, which were not found related in any previous studies, have
been found of particular importance when a factor affects a construction project. As previously mentioned
several previous studies in the area of critical factors have mainly focused on factors affecting either project
time or cost by ranking them against one another by using the relative importance index. Their findings are
thus not associated with a successful project outcome according to for example the definition of project
success by Long et al. (2004).
To secure project success by using the results from the relative importance index is it in our research
demonstrated that all three elements (cost, time and quality) from the “iron triangle” should be considered
due to its significantly different impact on cost, time and quality. Measuring just one or two of the three “iron
triangle” elements will therefore not secure either project success, or success of the measured element due to
the demonstrated positive correlation between the three “iron triangle” elements. This result supports the
need for adequate pre-project planning activities to improve and secure project cost, time and quality before
the detailed design stage and construction stage starts (Gibson Jr et al. 2006).
The factors in the category “Project Management” indicate that when particular human project
management related factors affect time, cost and quality, they impact all three elements in the “iron triangle”
non-significantly different. This difference should be seen as the three elements time, cost and quality not
necessarily are independent of each other when they impact, but are conversely a cause for equal negative
impact (Haimes 2005). A similar result was made by Hwang and Lim (2013) who demonstrate that project
outcome is a result of owner activity in the project management and delivery. To reduce such project
management related impact Dvir et al. (2003) are arguing for the need to capitalise time in project
procedures due to the significant relationship between defining “project goals”, “functional requirements”,
“technical specifications” and the following project success defined by to the end-user.
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
16
Our study evaluated the effect of 26 factors on the time, cost and quality of public construction projects,
seen from the publicly employed project manager’s perspective. We found the five main causes of delay
were identified as unsettled or lack of project funding, delay or long process times caused by other
authorities, unsettled or lack of project planning, errors or omissions in construction work and lack of
identification of needs. Furthermore, the factors with the greatest effect on budget were identified as errors or
omissions in the consultant material, errors or inconsistencies in project documents, late user changes
affecting the project or function, lack of preliminary examination before design or tendering and
inexperienced or newly qualified consultants. In addition the quality related factors were errors or omissions
in construction work, inexperienced or newly qualified consultants, political focus on reduced project costs
or time, unsettled or lack of project planning and errors or inconsistencies in project documents. Comparing
these results with existing studies are mostly all identified factors found related to either the owner, end-users
and consulting task which should have been completed in either the initiation or planning phase of a project.
Dvir et al. (2003) suggestion by invest more time in project goals, functional and technical requirements
seems thus also highly relevant in the Danish construction industry to reduce the most affecting factors.
Further Kazaz et al. (2012) find that owner based project complication rank as some of the most affecting
reasons for delays in 16 different countries. The consultant’s ability to identify and fulfil owner and end-
users requirements during a construction projects seems thus vital to secure a successful project outcome.
When the Friedman´s test was applied, 17 of the 26 factors rejected the null hypothesis by demonstrating
significantly different impacts on time, cost and quality, and nine factors accepted the null hypothesis. In the
following post-hoc analysis 33 of 51 tests were further found significantly different in the combinations
between time, cost and quality, where 10 out of 18 the non-significant tests were between time and cost, five
test between quality and time and three between quality and cost. All 51 conducted post-hoc tests were found
positively correlated, meaning an effect in for example time also will increase the impact on cost and quality.
Linking these result with studies which have studied time and cost related factors, are Kaliba et al. (2009)
state that no straightforward solutions to these overruns and delays seems available. By looking at our results
is there clearly a too complex factor structure between time, cost and quality for a project manager to
comprehend. However, we do instead suggest that future construction project should focus at monitoring the
five identified critical time, cost and quality related courses, combined with an increased pre-planning effort
during the initiation and planning phase of a project to reduce and handle these critical project complications.
Conclusion The conclusion from our findings of this research showed that the project schedule, budget and quality
level are affected significantly different. The project manager therefore cannot handle such critical issues by
only focusing at schedule or budget related complication, either can the project manager assume that time,
cost and quality are affected equally. In addition, the project organization must manage the factors as early as
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
17
possible, since top five factors affecting time, cost and quality mainly were found to be consultant tasks,
which should have been completed in the design stage before either tendering or construction. The project
manager must therefore consider and adjust the handling of each factor impact individually.
By adding the quality perspective and test it for significant difference to the existing body-of-knowledge
the factor complexity is revealed, but demonstrates at the same time the need for increased pre-planning
effort within the project organizations respond to the factors. A project organization can for that reason
define a project success outcome, but cannot manage critical issues according to its defined project success.
Potential implication and outcome of this study is relevant to the challenges facing public funded
construction projects regarding time, cost and quality. Using these results, it is now possible to counter the
impact of a factor on time, cost and quality before it affects a project. Moreover, the results indicate how a
given factor will affect time, cost and quality. It is therefore our hope that these significant new results will
be used by public construction agencies to understand the challenges that their project managers are facing
and that the factors with the greatest effect thereby can be reduced.
Even though a significant effort has been invested in limiting bias and study limitations these results still
have some. Firstly, the study focuses on a limited small population and is thus more sensitive to bias due to a
low response rate. Secondly, the limitation of applying questionnaire research is that it reduces the ability for
extension and generalization of the results to other populations or areas due to findings are restricted to the
studied population (public funded construction projects).
Future research into the effect of factors on time, cost and quality of public funded construction projects
could be continued by conducting similar studies in other regions of the world. Further, it could be beneficial
if studies like this were followed up by for example factor analysis, regression analysis or case studies to
explain and demonstrate the effect of these factors at a higher level.
Acknowledgement Thanks to Associate Professor Derek Drew and M.Sc. Siff Dea Hjort Stöckel for review and comment
during the writing process, and a special thanks to the respondents for their involvement and honesty
throughout the research project. The Department of Mechanical and Manufacturing Engineering, Aalborg
University provided financial support for this article. The authors would like to thank the reviewers of this
paper for their constrictive comments.
References Abd El-Razek, M., Bassioni, H., and Mobarak, A. (2008). "Causes of delay in building construction projects
in Egypt." Journal of Construction Engineering and Management, 134(11), 831-841.
Aibinu, A. A., and Odeyinka, H. A. (2006). "Construction delays and their causative factors in Nigeria."
Journal of Construction Engineering and Management, 132(7), 667-677.
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
18
Al‐Kharashi, A., and Skitmore, M. (2009). "Causes of delays in Saudi Arabian public sector construction
projects." Construction Management and Economics, 27(1), 3-23.
Arditi, D., Akan, G. T., and Gurdamar, S. (1985). "Cost overruns in public projects." International Journal
of Project Management, 3(4), 218-224.
Assaf, S. A., and Al-Hejji, S. (2006). "Causes of delay in large construction projects." International Journal
of Project Management, 24(4), 349-357.
Avots, I. (1969). "Why does project management fail?(Project management systems failure analysis,
discussing cost, products quality and project objectives)." California management review, 12, 77-82.
Barker, R., Childerhouse, P., Naim, M., Masat, J., and Wilson, D. (2004). "Potential of total cycle time
compression in construction: Focus on program development and design." Journal of Construction
Engineering and Management, 130(2), 177-187.
Chang, A. S., Shen, F.-Y., and Ibbs, W. (2010). "Design and construction coordination problems and
planning for design-build project new users." Canadian Journal of Civil Engineering, 37(12), 1525-
1534.
Doloi, H. (2012). "Cost overruns and failure in project management: understanding the roles of key
stakeholders in construction projects." Journal of Construction Engineering and Management,
139(3), 267-279.
Doloi, H., Sawhney, A., Iyer, K., and Rentala, S. (2012). "Analysing factors affecting delays in Indian
construction projects." International Journal of Project Management, 30(4), 479-489.
Dvir, D., Raz, T., and Shenhar, A. J. (2003). "An empirical analysis of the relationship between project
planning and project success." International Journal of Project Management, 21(2), 89-95.
Fahoome, G. F. (2002). "Twenty nonparametric statistics and their large sample approximations." Journal of
Modern Applied Statistical Methods, 1(2), 35.
Faridi, A. S., and El‐Sayegh, S. M. (2006). "Significant factors causing delay in the UAE construction
industry." Construction Management and Economics, 24(11), 1167-1176.
Field, A. (2009). Discovering statistics using SPSS, Sage publications.
Flynn, B. B., Sakakibara, S., Schroeder, R. G., Bates, K. A., and Flynn, E. J. (1990). "Empirical research
methods in operations management." Journal of Operations Management, 9(2), 250-284.
Flynn, B. B., Schroeder, R. G., and Sakakibara, S. (1994). "A framework for quality management research
and an associated measurement instrument." Journal of Operations Management, 11(4), 339-366.
Flyvbjerg, B., Holm, M. S., and Buhl, S. (2002). "Underestimating costs in public works projects: Error or
lie?" Journal of the American Planning Association, 68(3), 279-295.
Flyvbjerg, B., Holm, M. S., and Buhl, S. (2003). "How common and how large are cost overruns in transport
infrastructure projects?" Transport Reviews, 23(1), 71-88.
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
19
Forza, C. (2002). "Survey research in operations management: a process-based perspective." International
Journal of Operations & Production Management, 22(2), 152-194.
Frimpong, Y., Oluwoye, J., and Crawford, L. (2003). "Causes of delay and cost overruns in construction of
groundwater projects in a developing countries; Ghana as a case study." International Journal of
Project Management, 21(5), 321-326.
Fugar, F. D., and Agyakwah-Baah, A. B. (2010). "Delays in building construction projects in Ghana."
Australasian Journal of Construction Economics and Building, 10(1/2), 103-116.
Fujimoto, T. (1989). Organizations for effective product development: The case of the global automobile
industry, Harvard University.
Fynes, B., and De Burca, S. (2005). "The effects of design quality on quality performance." International
Journal of Production Economics, 96(1), 1-14.
Gaddis, P. O. (1959). The project manager, Harvard University.
Gibson Jr, G. E., Wang, Y.-R., Cho, C.-S., and Pappas, M. P. (2006). "What is preproject planning,
anyway?" Journal of Management in Engineering, 22(1), 35-42.
González, V., Alarcón, L., and Mundaca, F. (2008). "Investigating the relationship between planning
reliability and project performance." Production Planning and Control, 19(5), 461-474.
Haimes, Y. Y. (2005). Risk modeling, assessment, and management, John Wiley & Sons.
Hancher, D. E., and Rowings, J. E. (1981). "Setting highway construction contract duration." Journal of the
Construction Division, 107(2).
Handa, V., and Adas, A. (1996). "Predicting the level of organizational effectiveness: a methodology for the
construction firm." Construction Management & Economics, 14(4), 341-352.
Hanna, A. S., and Skiffington, M. A. (2010). "Effect of preconstruction planning effort on sheet metal
project performance." Journal of Construction Engineering and Management, 136(2), 235-241.
Hoonakker, P., Carayon, P., and Loushine, T. (2010). "Barriers and benefits of quality management in the
construction industry: An empirical study." Total Quality Management, 21(9), 953-969.
Howell, D. (1997). "Statistical methods for psychology." Wadsworth, Belmont, CA.
Hwang, B.-G., and Ho, J. W. (2011). "Front-end planning implementation in Singapore: Status, importance,
and impact." Journal of Construction Engineering and Management, 138(4), 567-573.
Hwang, B.-G., and Lim, E. S. J. (2013). "Critical success factors for key project players and objectives: Case
study of Singapore." Journal of Construction Engineering and Management, 139(2), 204 - 215.
Iyer, K., and Jha, K. (2005). "Factors affecting cost performance: evidence from Indian construction
projects." International Journal of Project Management, 23(4), 283-295.
Kaliba, C., Muya, M., and Mumba, K. (2009). "Cost escalation and schedule delays in road construction
projects in Zambia." International Journal of Project Management, 27(5), 522-531.
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
20
Kazaz, A., Ulubeyli, S., and Tuncbilekli, N. A. (2012). "Causes of delays in construction projects in Turkey."
Journal of Civil Engineering and Management, 18(3), 426-435.
Kerzner, H. (1998). In search of excellence in project management, Van Nostrand Reinhold.
Kline, P. (2013). Handbook of psychological testing, Routledge.
Koushki, P., Al‐Rashid, K., and Kartam, N. (2005). "Delays and cost increases in the construction of private
residential projects in Kuwait." Construction Management and Economics, 23(3), 285-294.
Liu, A. M. M., and Walker, A. (1998). "Evaluation of project outcomes." Construction Management and
Economics, 16(2), 209 - 219.
Lo, T. Y., Fung, I. W., and Tung, K. C. (2006). "Construction delays in Hong Kong civil engineering
projects." Journal of Construction Engineering and Management, 132(6), 636-649.
Long, N. D., Ogunlana, S., Quang, T., and Lam, K. C. (2004). "Large construction projects in developing
countries: a case study from Vietnam." International Journal of Project Management, 22(7), 553-
561.
Loushine, T. W., Hoonakker, P. L., Carayon, P., and Smith, M. J. (2006). "Quality and safety management in
construction." Total Quality Management and Business Excellence, 17(9), 1171-1212.
Morris, P. W., and Hough, G. H. (1987). "The anatomy of major projects: A study of the reality of project
management."
O’Brien, J. J. (1976). "Construction Delay: Responsibilities, Risks, and Litigation." Boston: Cahners.
Odeh, A. M., and Battaineh, H. T. (2002). "Causes of construction delay: traditional contracts." International
Journal of Project Management, 20(1), 67-73.
Olawale, Y. A., and Sun, M. (2010). "Cost and time control of construction projects: inhibiting factors and
mitigating measures in practice." Construction Management and Economics, 28(5), 509-526.
Olsen, R. P. (1971). Can project management be defined?
Park, M., Kim, W., Yoon, Y., and Nepal, M. P. (2010). "Scheduling decisions and their dynamic
consequences on construction performance." KSCE Journal of Civil Engineering, 14(3), 251-259.
Rea, L. M., and Parker, R. A. (2012). Designing and conducting survey research: A comprehensive guide,
John Wiley & Sons.
Rossi, P. H., Wright, J. D., and Anderson, A. B. (1983). Handbook of survey research, Academic Press New
York.
S.S.R.C., D. (2002). "Vejledende retningslinier for forskningsetik i samfundsvidenskaberne." Danish Social
Science Research Council.
Sambasivan, M., and Soon, Y. W. (2007). "Causes and effects of delays in Malaysian construction industry."
International Journal of Project Management, 25(5), 517-526.
Sekaran, U. (1992). "Business Research Methods." McGraw-Hill.
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
21
Shane, J. S., Molenaar, K. R., Anderson, S., and Schexnayder, C. (2009). "Construction project cost
escalation factors." Journal of Management in Engineering, 25(4), 221-229.
Sprent, P. (1989). "Applied Nonparametric Statistical Methods." Chapman and Hall, London.
Stumpf, G. R. (2000). "Schedule delay analysis." Cost Engineering-Ann Arbor Then Morgantown, 42(7), 32-
32.
Sweis, G., Sweis, R., Abu Hammad, A., and Shboul, A. (2008). "Delays in construction projects: The case of
Jordan." International Journal of Project Management, 26(6), 665-674.
Thomas, H. R., and Ellis Jr, R. D. (2007). "Contractor prebid planning principles." Journal of Construction
Engineering and Management, 133(8), 542-552.
Toor, S. U. R., and Ogunlana, S. O. (2008). "Problems causing delays in major construction projects in
Thailand." Construction Management and Economics, 26(4), 395-408.
Trauner, T. J. (1993). Managing the construction project: a practical guide for the project manager, Wiley
New York, NY.
Tuman, G. (1983). "Development and implementation of effective project management information and
control systems." Cleland, DI & King, WR Project management handbook. New York, Van Nostrand
Reinhold Co, 495-529.
Tuman, J. "Success modeling: A technique for building a winning project team." Proc., Proceedings of
Project Management Institute, 29-34.
Voss, C., and Blackmon, K. (1994). "Total quality management and ISO 9000: A European study." Centre
for Operations Management, London Business School, London.
Wambeke, B. W., Hsiang, S. M., and Liu, M. (2011). "Causes of variation in construction project task
starting times and duration." Journal of Construction Engineering and Management, 137(9), 663-
677.
Williams, T. (1993). "Risk-management infrastructures." International Journal of Project Management,
11(1), 5-10.
Yang, J.-B., and Wei, P.-R. (2010). "Causes of delay in the planning and design phases for construction
projects." Journal of Architectural Engineering, 16(2), 80-83.
Yang, L.-R., Chen, J.-H., and Huang, C.-F. (2012). "Requirements definition and management practice to
improve project outcomes." Journal of Civil Engineering and Management, 18(1), 114-124.
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
22
Table 1: Category and factor description for the factors used in the questionnaire
Category Id. Factor description
Studies using comparable factors
Aib
inu
and
Ode
yink
a(2
006)
Abd
El-
Raz
eket
al.(
2008
)A
l‐K
hara
shia
ndSk
itm
ore
(200
9)A
ssaf
and
Al-
Hej
ji(2
006)
Dol
oiet
al.(
2012
)Fa
ridi
and
El‐
Saye
gh(2
006)
Frim
pong
etal
.(20
03)
Fuga
ran
dA
gyak
wah
-Baa
h(2
010)
Iyer
and
Jha
(200
5)K
alib
aet
al.(
2009
)K
azaz
etal
.(20
12)
Kou
shki
etal
.(20
05)
Lo
etal
.(20
06)
Lon
get
al.(
2004
)O
deh
and
Bat
tain
eh(2
002)
Ola
wal
ean
dSu
n(2
010)
Sam
basi
van
and
Soon
(200
7)Sh
ane
etal
.(20
09)
Too
ran
dO
gunl
ana
(200
8)W
ambe
keet
al.(
2011
)
External EX1
Delays or long process times by other authorities
● ● ● ● ● ●
EX2 Soil conditions ● ● ● ● ● ● ● ● ● ● ● ● ●
EX3 State of market conditions ● ● ● ● ● ● ● ● ● ●
EX4 Project conditions ● ● ● ● ●
EX5 Weather conditions ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ●
Contractual Relationship
CR1 Selection and assignment criteria ● ● ● ● ● ●
CR2 Errors or inconsistencies in project documents
● ● ● ● ● ● ● ● ● ● ● ● ●
CR3 Lack of requirement specifications in tender documents
● ● ● ● ● ● ●
CR4 Lack of project structure or material
● ● ● ● ● ● ● ● ● ● ● ●
CR5 Unforeseeable authority requirements or restrictions
● ● ● ● ● ● ●
Project Management
PM1 Miscommunication between project partners
● ● ● ● ● ● ● ● ● ● ● ● ● ●
PM2 Conflicts and disputes between project partners
● ● ● ● ● ● ● ● ● ● ● ●
PM3 Slow user decision making ● ● ● ● ● ● ● ● ● ● ●
PM4 Change of partners in the project organization
● ● ● ● ● ● ●
PM5 Inexperienced or newly qualified construction supervisors
● ● ● ● ● ● ● ● ● ● ● ● ●
PM6 Inexperienced or newly qualified consultants
● ● ● ● ●
Project Changes
PC1 Errors or omissions in construction work
● ● ● ● ● ● ● ● ● ●
PC2 Errors or omissions in the consultant material
● ● ● ● ● ● ● ●
PC3 Lack of identification of needs ● ● ● ● ● ● ● ● ●
PC4 Lack of preliminary examination before design or tendering
● ● ● ● ●
PC5 Late user changes affecting the project or function
● ● ● ● ● ● ● ● ● ● ● ● ● ● ●
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
23
Finance and Scheduling
FS1 Optimistic expectation regarding time, cost and quality
● ● ● ● ● ● ● ● ● ●
FS2 Political focus on reduced project costs or time
FS3 Unsettled or lack of project funding
● ● ● ● ● ● ● ● ● ● ● ● ● ● ● ●
FS4 Unsettled or lack of project planning
● ● ● ● ● ● ● ● ● ● ● ●
FS5 Complexity or volume of the project
● ● ● ● ● ●
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
24
Table 2: Response rate and agency distribution of the questionnaire
Agency Potential
respondents Response frequency
Respondent rate
Agency 1 5 2 40.0 % Agency 2 16 6 37.5 % Agency 3 52 24 46.2 % Agency 4 38 24 63.2 % Total 111 56 50.5 %
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
25
Table 3: Reliability values for each questionnaire category: time, cost and quality
Category N Time N Cost N Quality External 52 .708 52 .664 52 .725 Contractual Relationship 48 .773 48 .822 46 .845 Project Management 43 .776 43 .825 43 .848 Project Changes 46 .822 45 .849 46 .832 Finance and Scheduling 40 .856 40 .888 40 .856
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
26
Table 4: Relative importance index (RII) and rank (R), ranking is conducted by giving the lowest index value
one or A, the next lowest two or B, and so on
Id.
Time Cost Quality N RII R N RII R N RII R
EX1 56 .739 25 56 .529 4 56 .421 4 EX2 54 .511 4 54 .541 5 54 .344 1 EX3 55 .476 1 54 .570 8 54 .433 5 EX4 55 .629 11 55 .647 14 55 .476 7 EX5 55 .505 2 55 .491 2 55 .360 2 Average .572 A .556 A .407 A CR1 49 .510 3 49 .469 1 47 .438 6 CR2 54 .630 12 54 .726 25 54 .641 22 CR3 52 .573 6 52 .692 19 52 .631 20 CR4 53 .615 9 53 .645 13 53 .600 18 CR5 53 .589 8 53 .558 6 53 .408 3 Average .583 B .618 C .544 B PM1 51 .573 7 51 .592 9 51 .573 14 PM2 51 .659 16 50 .612 10 51 .588 16 PM3 53 .683 20 52 .558 7 52 .519 9 PM4 51 .537 5 50 .508 3 50 .556 12 PM5 49 .616 10 49 .624 11 49 .629 19 PM6 49 .645 14 49 .698 22 49 .678 25 Average .619 C .599 B .591 D PC1 49 .694 23 49 .661 18 48 .688 26 PC2 53 .649 15 53 .766 26 52 .631 21 PC3 51 .690 22 50 .696 20 50 .592 17 PC4 48 .679 19 48 .700 23 49 .567 13 PC5 53 .683 21 53 .717 24 52 .554 11 Average .679 D .708 E .606 E FS1 48 .671 18 48 .650 15 48 .579 15 FS2 49 .665 17 51 .651 16 50 .644 24 FS3 46 .774 26 44 .636 12 44 .545 10 FS4 50 .712 24 50 .696 21 48 .642 23 FS5 51 .639 13 51 .651 17 51 .506 8 Average .692 E .657 D .583 C
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
27
Table 5: Friedman´s test of time, cost and quality, * significant at the .01 level, two degrees freedom
Id. N
Chi- Square
Asymp. sig.
EX1 56 64.679 .000* EX2 54 48.620 .000* EX3 54 21.938 .000* EX4 55 35.724 .000* EX5 55 33.476 .000* CR1 47 8.719 .013 CR2 54 13.059 .001* CR3 52 23.138 .000* CR4 53 2.600 .273 CR5 53 42.471 .000* PM1 51 1.089 .580 PM2 50 6.258 .044 PM3 52 33.724 .000* PM4 50 4.541 .103 PM5 49 .338 .845 PM6 49 4.522 .104 PC1 48 1.339 .512 PC2 52 31.829 .000* PC3 50 17.845 .000* PC4 48 25.224 .000* PC5 52 33.787 .000* FS1 48 17.465 .000* FS2 49 .261 .878 FS3 44 28.474 .000* FS4 48 13.291 .001* FS5 51 31.196 .000*
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
28
Table 6: Wilcoxon´s test of T - time, C - cost and Q - quality, *significant at .003 level, sum of ranks is conducted
by giving the lowest value one, the next lowest two and so on **effect size is significant at .01 level
Id. N
Factor combination
Asymp. sig.
Sum of ranks
Effect size
EX1 56 EX1-T – EX1-C .000* 8.0 .522** 56 EX1-Q – EX1-T .000* 31.5 .300** 56 EX1-Q – EX1-C .000* 57.0 .440**
EX2 54 EX2-T – EX2-C .146 54.0 .695** 54 EX2-Q – EX2-T .000* 11.0 .614** 54 EX2-Q – EX2-C .000* 24.0 .466**
EX3 54 EX3-T – EX3-C .001* 22.5 .632** 54 EX3-Q – EX3-T .146 100.5 .407** 54 EX3-Q – EX3-C .000* 6.0 .565**
EX4 55 EX4-T – EX4-C .307 79.0 .596** 55 EX4-Q – EX4-T .000* 52.5 .299** 55 EX4-Q – EX4-C .000* 11.0 .407**
EX5 55 EX5-T – EX5-C .588 156.0 .569** 55 EX5-Q – EX5-T .000* 24.0 .420** 55 EX5-Q – EX5-C .000* 22.0 .425**
CR2 54 CR2-T – CR2-C .000* 46.0 .576** 54 CR2-Q – CR2-T .624 210.0 .456** 54 CR2-Q – CR2-C .003* 57.0 .519**
CR3 52 CR3-T – CR3-C .000* 22.0 .557** 52 CR3-Q – CR3-T .016 108.0 .588** 52 CR3-Q – CR3-C .003* 27.0 .675**
CR5 53 CR5-T – CR5-C .146 104.0 .728** 53 CR5-Q – CR5-T .000* .0 .494** 53 CR5-Q – CR5-C .000* 9.5 .561**
PM3 52 PM3-T – PM3-C .000* 43.5 .490** 52 PM3-Q – PM3-T .000* 8.5 .467** 52 PM3-Q – PM3-C .074 84.0 .575**
PC2 53 PC2-T – PC2-C .000* 40.5 .605** 52 PC2-Q – PC2-T .425 183.5 .554** 52 PC2-Q – PC2-C .000* 12.5 .654**
PC3 50 PC3-T – PC3-C 1.000 85.5 .646** 50 PC3-Q – PC3-T .001* 71.5 .462** 50 PC3-Q – PC3-C .000* 27.0 .584**
PC4 48 PC4-T – PC4-C .197 40.0 .808** 48 PC4-Q – PC4-T .000* 30.0 .593** 48 PC4-Q – PC4-C .000* 30.0 .544**
PC5 53 PC5-T – PC5-C .097 88.5 .714** 52 PC5-Q – PC5-T .000* 46.0 .523** 52 PC5-Q – PC5-C .000* 34.5 .432**
FS1 48 FS1-T – FS1-C .265 54.5 .660** 48 FS1-Q – FS1-T .005 56.0 .539** 48 FS1-Q – FS1-C .003* 26.0 .705**
FS3 44 FS3-T – FS3-C .001* 17.5 .527** 44 FS3-Q – FS3-T .000* 25.0 .226 44 FS3-Q – FS3-C .005 28.0 .591**
FS4 50 FS4-T – FS4-C .346 45.0 .779** 48 FS4-Q – FS4-T .001* 7.0 .632** 48 FS4-Q – FS4-C .010 51.0 .536**
FS5 51 FS5-T – FS5-C .623 45.0 .725**
Larsen J.K., Shen G.Q.P., Lindhard S.M. and Brunoe T.D. (2015). Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. Journal of Management in Engineering, 32(1), DOI 10.1061/(ASCE)ME.1943-5479.0000391, June. (SCI, among the Top Ten Article Download in 2016, 1431 times. Ranked 30/126 in Civil Engineering by JCR in 2015).
29
51 FS5-Q – FS5-T .000* 52.0 .422** 51 FS5-Q – FS5-C .000* 9.0 .516**
Figure captions list
Figure 1: Boxplot for the five highest ranked factors affecting T - time, C - cost and Q - quality
Recommended