George Russell IV Stormwater Program Manager

Environmental Complaints and Local Services

Stormwater Permitting

What do we do? Divide tasks between ECLS and WQD Paperwork! ~2000 facilities

NOIs, NECs, NOTs, ACSCERs, DMRs Invoicing

Annual fees and application fees Inspections

53 Environmental Specialists throughout the state 21 Field offices Complaints and NOTs

Notice of Intent NOI submitted via email, fax, mail, or in person Entered into our database and given a permit number Check for any past due fees on other permits Assigned to one of our technical reviewers or if SWP3

is required to be reviewed sent to WQD

Technical Review Review the NOI for accuracy

Latitude/Longitude Receiving waterbody SIC code

Create Maps Letters Permit Send for Supervisor Review

Finalization Permit is ready to be issued Verify fees have been paid Mail documentation Permit is now in effect

Timelines Entered into database within 24 hours Technical Review - 7 days Supervisor Review - 24-48 hours Finalization - 24 hours

Approximately 10 days until permit is issued if NOI is

correct and complete SWP3 review requires additional time

After the NOI While the permit is in effect Annual invoices Track payments Work complaints DMRs

Due Jan 15th - electronically ACSCERs

Due March 1st Enforcement referred to WQD

Termination When operations have ceased NOT is filed Verified with an inspection Check for any past due fees

Renewal Same process Submit NOI

Best way is through email at ecls-stormwaterpermitting@deq.ok.gov

Sector J and L or in an ARC will go to WQD for SWP3 review

Timelines could be longer based on high volume All fees must be paid before a new permit will be

issued

Contact Information George Russell IV 405-702-6100 george.g.russell@deq.ok.gov